Professional Documents
Culture Documents
• Note: The 9th Edn's “Contract Period” is simply the ‘contractual’ period within which the
Works must be commenced, carried out and completed.
• SIA BC 2016 now calls it: "Construction Period"
• It is NOT the period of ‘existence’ or ‘operation’ of the Contract per se.
• The Contract per se is made (starts) upon the Mutual Assent, ie agreement of the Parties (usually by a
communicated acceptance of offer)—unless the agreement includes a condition of ‘subject to contract’ (eg a
formal requirement of execution under signature).
• LOA can either effect the agreement, or record a prior agreement.
• The contract will start to ‘operate’ automatically upon the contract being made, unless there is a condition-
precedent.
(architect doesn’t have to be constantly on site, only there for impt duties, ensuring standard of works, verifying
materials, etc. – can hire site supervision staff, etc.)
(but many paper works. Contractor is not in control of bureaucratic control of the TOP
paper work. ) (physical readiness for TOP is ok)
NOTE:
• As Completion is important … it is important
that the Contractor is given the full period of
time and full access to achieve completion …
• Hence: Cl. 10 provides that:
1. “The Contractor shall commence Works on the Contract
Commencement date”.
2. “if the date … becomes invalidated … [it] shall be
appropriately modified or re-calculated”.
3. “the Contractor shall be entitled … to free and
uninterrupted possession of the whole of the area of the
Site”.
What is ‘handover?’
Handover is typically an event
... after completion
... where the Employer is provided with the
access & items required for occupancy.
Handover is often soon after actually getting TOP
(i.e. so the Employer can 'legally' occupy the
building).
(contractually separate)
Why Phases ?
Eg – Where a ‘part’ of the building can be occupied
earlier and thus
(i) operator’s commercial activities,
(ii) developer’s rental or property sales, etc,
can proceed (hence LD relates to loss of rental or sales)
Eg - Supermarket renovation in stages so only part is
closed down at any particular time (ie business
continuity).
... and so that any e.o.t. for a discrete part of the Works
doesn’t give e.o.t. for the whole of the works ...
... Further consider the essential contract requirement that the Contractor is to
always proceed with diligence and due expedition (see Cl. 21) ...
... It is so important that it is also a ground for ‘termination’ (see Cl. 32(3))!!
Also eg see CAA v HP [2015] SGHC 32 ... where progress of work is slow relative to
achieving completion by the [latest] date for completion [incl. e.o.t.] - eg measured
against ‘revised’ programme + key/milestone dates.
... THUS phasing arrangements should promote that ALL parts of the Works are
always needing to be proceeded with diligently and expeditiously – ie realistic
timeframes relative to a good rate of work!
Note: ‘slow’ rate of progress of the work might lead to unnecessary additional
preliminaries costs being incurred by the Employer!
Partial Re-occupation
Either:
(a) Cl. 26(1)&(2) - Occupation of Part with consent, or
(b) Cl. 26(3) - Occupation of Part without consent
1. Design Development:
Although Architects may have 'standard' specs & details ...
... the 'assembly' of the unique building is 'one-off', 'bespoke'
and 'un-tested‘ (ie without a full-scale 'prototype').
... they are applied by different builders for different
projects.
POINT_1.
Prevents the Contractor limiting liability for defects:
It is a provision through an expressed term of contract, therefore it
prevents the Contractor from having an ‘exclusion clause’ limiting
or avoiding liability for defects, ie
(i) it sets the allocation of liability and risk, and
(ii) the drafting protects the Employer’s commercial interests (as in
most ‘standard’ forms of building contract).
POINT_2.
For Convenience / benefit of the Employer:
2.(1) If there was no contractual provision, then; defects would
technically be a breach of contract to which Employer would have
to pursue legal rights for remedy (ie an action under breach of
contract), and each defect would need to be dealt with separately either:
(A) For rectifying the defect; either
(i) to order the Contractor to perform the rectification of defect, or
(ii) to recover costs of engaging another contractor to rectify, or.
(B) For diminution of value (ie reduced market value) of the development due
to defects (non-compliant work) that are retained without rectification.z
POINT_3.
‘Protects’ the Contractor by giving a ‘privilege’ to
return to the site to attend to his defective work:
The contractor’s liability does not end at the
POINT_4.
A practical mechanism; allows more economical and
practical arrangements for deployment of resources
to attend to defects, and to have insurance coverage,
etc.
4.(1)_Hence can rectify defects at own (usually lower) costs,
through (1) not being subject to recovery of (higher) costs of other
contractors, (2) Contractor can manage the arrangements /scheme
of rectification (contractors, scheduling, etc) so it can be done
effectively and efficiently.
4.(2)_Hence avoids having to go through lawsuits/ADR for breach of
contract.
POINT_5.
General Considerations:
5. (1)_Efficiency: (1) of Contractor's personnel who are familiar with
the ins-and-outs of the Works, (2) of resources, ie defect
rectification can use retained or left-over equipment and materials,
etc. Both are even more relevant where the Contractor is nearby for
subsequent phases of the Works.
5. (2)_Efficiency of Insurance coverage (rather than individual
insurances by other contractors).
POINT_6.
Contract Administrator:
6.(1)_Addressing defect rectification thru the Contract promotes the
role of a knowledgeable and impartial Contract Administrator:
6.(2)_ Promote an effective and efficient process.
6.(3)_ Advise on cost issues.
Collateral Warranties
A collateral warranty generally defines an agreement
ancillary [ie operating collaterally] to another principal
contract :
In construction the word “warranty” tends to be referred to as a
separate contract placing a party to an existing contract under
an independent obligation to another person. Such a warranty
may, for example, place an obligation on a sub-contractor to a
land owner or developer. Warranties may be used to protect a
purchaser against latent defects caused by a sub-contractor.
Without such a warranty, the purchaser may not have an action in
contract [as they are not privy to the Contract].
[A collateral warranty will also typically last longer than the DLP
under the Contract].
Also note;
Trebor Bassett Holdings Ltd and The Cadbury UK Partnership v ADT Fire
and Security plc [2012] EWCA Civ 1158
Statutory or Common Law implication of warranty of 'fitness for purpose'
on 'goods' (ie proprietary products sold for a purpose) does not include
'bespoke systems' (ie custom-made systems made-up of goods &
materials, such as under a design & construct arrangement), which are
considered the output of a 'service'.
HENCE, without ‘implied’ warranty of fitness …
… there is need for expressed 'contract' and/or
'collateral' warranty rights for defect repairs on bespoke
systems.
EXAMPLES:
• JCT standard forms – Collateral Warranties
• UK’s Property Care Association - Guarantees
• notes by ICE on collateral warranties
• compare with USA states’ schemes of warranties
• Note reference to “contractual warranties” in Woolcock Street
Investments Pty Ltd v. CDG Pty Ltd
Warranties
- vs Service Agreements
• Note the difference between Warranty / Guarantee vs
‘servicing’ agreements ...
• Supplementary requirements for servicing might be included in the
Contract Documents;
- typically known as service agreement, a service contract, or a
maintenance agreement (similar to ‘extended warranty’ for products)
- & might become a ‘term’ contract
- & might be integrated as part of Warranties (& vice versa)
- might cover faults in a product’s materials & workmanship
- may involve replenishment of consumables
- may address wear & tear / weathering
- may be at call or a regular / periodic servicing schedule
- may involve preventative inspections
- may involve re-tuning, re-balancing, etc
• Servicing air-conditioners, Lifts, other building services
• Watering and cutting / pruning planting
PART 5: EXTENSION OF TIME
In regard to completion ...
Extension of Time (EOT) and Delay occurs
when the Works …
… are not completed by the contractual Date of Completion
… ie not completed within the Contract Period;
Note:
IN_PRINCIPLE ENTITLEMENT:
1) Subject to the Contractor giving ‘notice’ [see Subclause
23(3)].
2) Only if delaying factors are within the grounds set-out
in Sub-clauses 23(2)(a)to(q).
3) Subject to the matters / events causing real delay to
the completion of the Works. (cannot be hypothetical)
Mitigation of Delay
• Subject to “due diligence and the taking of all
reasonable steps by the Contractor to avoid or
reduce [the delay in completion].”
» Similar in nature to Cl. 21 requiring that “the
Contractor shall proceed with the Works diligently and
with due expedition at all times until completion.”
» What are ‘reasonable steps’? Does this involve cost to
the Contractor? Eg can an Employer expect
‘acceleration’ in the progress of works, or just
(replanning, rescheduling, w/o extra cost)
(the architect cannot say I cannot assess because you haven’t given enough
information. But rather, if insufficient info given, that be a conclusion of the
assessment.)
Completion Certificate
• the liability of the Contractor to pay LD shall
cease upon the issue of the Completion
Certificate.
• [Although I would say ...
... the liability of the Contractor as to the accrual of LD
shall cease upon the date of Completion as certified by
the Architect in the Completion Certificate.]
PART 7: MISCELLANEOUS TOPICS ON EOT & DELAY
*Is just notes for reference
OTHER CONSIDERATIONS REGARDING
_EXTENSION OF TIME FOR COMPLETION
_DELAYS ….