Professional Documents
Culture Documents
Note: if an item of work is not mentioned & priced in the BQ (but is in, say, the
drawings) ...
... this is equivalent to the BQ stating a 'nil' quantity.
... but it does not mean the item of work is not in the contractual scope
... ie the item of work is allowed for in Contract Period/programming & planning,
preliminaries &
site management, etc.
... it is not a variation, and thus does not give grounds for EOT.
Interim Payment
As with most forms of building contract, the SIA form involves ‘interim
payments’ (aka
‘progress’ payments) - the payment of the Contract Sum in instalments
leading to a final
payment for payment in full.
(contractors need constant cashflow interim payments favourable.)
In general, contract law recognises a full & final (ie 'one-off) payment of a fixed sum upon
full completion of performance (ie completion of the Works).
Interim payments (as with variations) of the Contract Sum are by provision of contract
only.
» Contract Law has not traditionally required interim payment, nor any particular mode
thereof (as it is
essentially a matter for agreement between contracting parties),
» however recent legislation in some jurisdictions has lead to statutory rights to interim/
progress payments;
• eg UK's Housing Grants, Construction and Regeneration Act 1996 legislates that a
Contractor is entitled to payment by instalments, stage payments or periodic payment
unless the contract period is less than 45 days (in which case a single / one-off payment
may be made)
• However, Singapore's SOP Act does not give a minimum length of contract period that
such oneoff
payments must satisfy.
Interim payment (in the SIA form of Building Contract): – 2 forms of progress
payment
Article 2 provides for Interim Payment by either:
» Fixed instalments
- payable upon completion of defined 'milestones/stages' of the Works (to
be stated in Appendix), or
» Periodic valuation of the Works
- ie pay the value of the ‘works done’ (commensurate to the parts of the
Works that are completed) at regular times throughout the period of works
being carried out.
Notes:
• In the SIA forms of Building Contract: The 'mode' of interim payment (ie 'periodic' or
'milestone/stage'*
payment) is to be selected.
• *(There may be 'milestones/stages' for payment within a Phase or similarly a
'milestone/stage' for
payment may be one-and-the-same as a 'Stage'(/Phase) for completion).
Interim Payment
- the importance of Cashflow:
… because contractors are usually paid retrospectively, ie they pay for the
running expenses of a project up-front.*
Hence, for example, to minimise:
- project financing costs incurred by the Contractor (and passed on to the Employer
through the tendered sum)
- risk of financial default by the Contractor.
The Contractor’s financial capacity / capability and arrangements to meet the needs
of a construction project is reliant on the Employer honouring the contractually-
agreed scheme of progressive / interim payments.
* For example:
1. Site set-up & site-management costs
2. Preliminaries costs (eg insurance, security deposits, etc)
3. Procurement of building materials
4. Down-payments for materials and sub-contractors
5. Lines of credit & financing charges
6. Utilities & services connection fees
7. Permits and licenses applications, including professional fees
8. Business overheads
9. etc
10. [Often needed for 'next project ...]
Objectives:
» To assist and improve the realisation of ‘cashflow’ (otherwise hindered by late or non-payment to
construction related
Contractors / Suppliers / Service-providers by Employers or Main Contractors)
[ie to hold Employers / Main Contractors to the contractual ‘promises’ they make to Contractors /
Subcontractors to
provide progressive payment (i) fully & (ii) on time]
» To provide quick and cost-effective resolution of payment related disputes (through ‘Adjudication’)
which can be enforced in the Courts (Adjudication = to find if the contractor is entitled to the payment.
If yes, adjudicator can make an order for the employer to do the payment. If still no payment, can be
taken to the court -> order for payment to be made.)
» The SOP Act seeks to ‘promote’ cashflow throughout the contractual chain (ie
‘all the way
down the line’) …
» HENCE: payment from (applies to contractors, suppliers & consultants)
… ie in the Payment Response the Respondent must give reasons for stating a
payment amount less than that claimed in the Payment Claim.
eg if the Respondent thinks that the claimed amount for the ‘works done’ should be valued differently
to that claimed, or
eg if the Respondent wants to make a deduction from the payment
ADJUDICATION -- a fast mechanism to get a response -> to help the cashflow FAST enough.
Has to happen quickly. // 7 days to appoint ADJ. -> 7-14 days -> ADJ make decision.
- salient provisions:
Sn 5 - Entitlement to Progress Payment
» Any person who has carried out any construction works or supplied goods or services* is
entitled to a
progress payment.
• This is the basis to promoting good cashflow to contractors.
* Hence Architects and Engineers etc are also covered by the Act.
[Note: differs for • ‘Supply Contract’ that provides for a payment date [60d after ‘payment
claim’],
For Construction Contract that does not provide for a payment date:
» no greater than 14 days * check new revision after tax invoice (if GST taxable) or
otherwise the time by which a ‘payment response’ is required [see Sn 11].
[Note: differs for • ‘Supply Contract’ that does not provide for a payment date [30d after
‘payment claim’]
[Note: differs for Construction Contract that does not provide for a response date [ie 7d
max]
[Note: The intent of the SOP Act authors is to encourage parties to resolve and settle their disputes themselves,
without incurring extra
time and expense of formal dispute resolution processes, such as Arbitration and Litigation, and including
Adjudication]
Further to the SOP Act only applying where a ‘Construction Contract’ or ‘Supply Contract’
exists …
… the SOP Act gives opportunity for the particular Contract to make provisions
from which the SOP
Act provisions will operate.*
… and only if these provisions are not expressly made in the terms of
contract, then the SOP
Regulations ‘prescribe’ a default requirement.
*Note: SOPA respects contractual provisions /arrangements for progress payment in the first instance.
Ways in which the SIA forms (7th – 9th edn) of building contract have changed in light of
the SOP Act included:
» The Contractor’s serving of a ‘payment claim’ (as previously, up to the 6th Edn, the
Architect unilaterally issued an Interim / Final Certificate for payment based on the QS
valuation, without need for a 'claim').
» Payment made on Payment Response of the Employer, no longer the Interim Certificate
(although Summary
Judgment / Interim Award to enforce payment based on certificate is still provided).
» Termination of contract by Contractor now based on failure to pay an adjudicated
amount (rather than the
amount stated in the certificate)
» Introduction of Final Accounts (before the Final Certificate) – to deal with project cost
issues before the Final Claim can be submitted (considering the 21d max to respond to a
payment claim).
» Period following the Maintenance Period upon expiry of which the Architect must make
an allowance (deduction) for any defects remaining unresolved – to ensure the timeframe
by which a Contractor can make a Final Claim is not indeterminate.
Note the difference in approach to SOPA between the SIA A&CBC (7th – 9th edn)** and SIA
MWC:
eg – Interim Payment:
1. Contractor’s “Statement of Work Done” (not a ‘claim’).
2. Architect issues “Interim Certificate” within 14d.
3. Contractor’s Invoice
4. Employer to make payment within 14d
Payment Claims and Payment Responses and other SOPA provisions come under “Dispute
Resolution” in Cl. 25 of the SIA MWC ... eg if the Employer fails to pay at ‘4.’
Note the difference in approach to SOPA between the SIA A&CBC (7th – 9th edn)** and SIA
BC 2016:
STATUTORILY:
1. The SIA BC 2016 splits the 'contractual' provisions for payment from the 'statutory'
provisions:
2. The statutory provisions are in the new clause 40.
3. The contractual provisions are in clause 31.
4. Clause 40 provides timelines for payment claims, payment responses and payment, as
well as the basis
for the amount claimable under the Act.
CONTRACTUALLY:
1. The SIA BC 2016 reverts closer to pre-7th Editions ...
2. Contractor to submit 'adequate vouchers & information' to substantiate the work done
[albeit now in a "progress claim"].
3. Architect issues “Interim Certificate” on prescribed dates.
4. Employer to make payment within the stipulated "Period for Honouring Certificates" as
stated in the Appendix.
** Note: SIA BC 2016 edn has revised the approach to SOP Act ....
The requirement for separately stating amounts due to NSC/S serves two purposes:
1. NSC/S still want more ‘protection’ from Contractors who may have taken the opportunity
to under-pay them, ie NSC/S want to know what value the QS/Architect has assessed for
their particular work done, so it is not under-valued by the Contractor.
2. NSC/S works are done under utilisation (by substitution) of PC Sums and Provisional
Sums. Having Interim [Payment] Certificates state separately the amounts due to each
individual NSC/S could be argued to be redundant under the current contract provisions as
–
– the Main Contractor is now required to take full responsibility for NSC/S, including for
payment, as if the NSC/S were his own domestic subcontractor/ supplier – ie the NSC/S has no
rights or benefits directly from the Main Contract.
– The SOP Act deals independently with each contractie the Main Contract has no bearing on
the Sub-Contract, except …
– Section 24 of the SOP Act allows all sub-contractors to seek ‘direct payment from principal’.
With this in mind, it is not unexpected that in many projects the Main Contractor asks the
Sub- Contractor to cooperate by giving a ‘draft’ claim which the Main Contractor can
include in the Payment Claim for the Main Contract - so it can be seen how much of the
Sub-Contractor’s ‘draft claim’ is accepted by the Architect / QS as basis for payment.
But – must be careful that the ‘draft’ is not able to be construed as a formal claim (especially as the
SOP Act does not require a payment claim to be identified / labeled as such).
The SIA Sub-Contract 2016 provides that the Subcontractor shall be paid within 14d of the
Period for Honouring Certificates in the SIA BC 2016 main contract.
The SIA Sub-Contract 2016 also separates 'contractual' from 'statutory' provisions: the
provisions for SOPA are in SIA S-C 2016 clause 17.
... stipulating timelines for payment claim, payment response and payment and stipulating
the basis for the amount payable (ie the interim certificates)
SIA A&CBC 9th Edn – Cl. 31(15)(a) – Payment Response to Interim Payment
Claim
» The Employer shall respond to the Payment Claim with a Payment Response within 21
days.
» The Contractor shall be entitled to payment of the amount/sum stated in the Payment
Response.
(archi interim cert – as benefit of architect & QS who valuates how much the interim
payment should be.)
» Sn 11 of SOP Act requires that a Payment Response;
• identifies the payment claim to which it relates
• state the response amount
• state any reasons where response amount is less than claimed, or where any payment is
withheld
[Typically done by making reference to such as provided in the QS’ breakdown of
‘valuation’ of work in the schedule to the Interim Certificate]
[Note: Sn 6 of SOP Regs further requires that ‘calculations’ how the differing or withheld amount is derived must be
stated in the Payment Response]
The Clause also allows the Architect to issue a ‘negative’ certificate , eg where previous
overpayment has occurred.
(Retention monies is unique to SIA form of contract. Whereby $ for security as employer
just in case the contractor does something wrong -> employer isable to hold back some $,
abit like a security deposit, but not a security deposit that is paid upfront.) (retains 10-20%
of the money for own security)
SIA A&CBC 9th Edn – Cl. 31(9) - First Release of Retention Monies
First half the Retention Monies to be released upon Completion (less a reasonable sum to
cover outstanding works).
The sum withheld shall be released to the Contractor as soon as such outstanding work is
completed.
Note that pursuant to Clause 25; Retention Monies shall apply to Phases/Stages of work “mutatis mutandis as if each
Phase or Stage was the subject of a separate and distinct contract…”
SIA A&CBC 9th Edn – Cl. 31(10) - Second Release of Retention Monies
Second half the Retention Monies to be released upon end of Maintenance Period or upon
issuance of Maintenance Certificate (whichever is later!). (1 year-ish)
[Typically the Maintenance Certificate will not be issued before the end of the Maintenance Period, even if all defects
had been rectified]
The released amount may be subject to deduction for ‘Allowance for Defect’ under Cl.
27(4).
Note that pursuant to Clause 25; Retention Monies shall apply to Phases/Stages of work “mutatis mutandis as if each
Phase or Stage was the subject of a separate and distinct contract…”
Further Notes on ‘Final Accounts’ (under the SIA A&CBC 9th Edn):
» Further to the notes above, the submission of Final Accounts Documents is intended to,
eg:
1. give the Architect and QS time to evaluate the potential final claim (typically a ‘bulk’ or
‘consolidated’ account of all items not claimed or settled for interim payment previously),
and
2. Allow for feedback to the Contractor, if necessary (eg if further, clearer or corrected
“supporting documents, vouchers and other documents” are required to facilitate the
assessment - which if missing from a final payment claim may mean that the Contractor
‘misses out’ on some payment for that item, ie where the QS’ assessment of the value of
work done is based only on the information available).
SIA A&CBC 9th Edn – Cl. 31(15)(b) – Payment Response to Final Payment
Claim
» Employer (the Respondent) shall respond to the Final Payment Claim with a Payment
Response within 21
days.
» The Contractor shall be entitled to payment of the amount/sum stated in the Payment
Response.
» [Note that 31(15)(b) states that the obligation for providing of Payment Response is
subject to the Final Payment Claim being served in accordance with Sub- Clause 31(11)(c) -
ie subject to the procedural requirement for Final Account Documents. Without such
compliance, any claim need not be accepted as the ‘final’ payment claim.]
Summary of Payment:
Salient differences regarding payment between SIA 9th edn and SIA BC
2016:
'Contractual' provisions (Cl. 31) are separated from 'statutory' provision [SOP Act] (Cl.
40).
Architect issues Interim/Final Certificate at the prescribed time (ie payment claim does
not trigger the payment process).
No Final Accounts Documents or Statement [so Arch/QS will need to deal with variations
progressively?*]
*How do milestone payments work against periodic entitlement to payment claim under Cl. 40?
Payment is made based on Interim/Final Certificate, no longer the Employer's Payment
Response.
Note: under SIA A&CBC 9th Edn Cl. 31(16), payment is made on the Payment
Response.
~ As such, one may question what is the purpose of the Interim Certificate?
Therefore, consider:
1. Provisions for ‘Temporary Finality’ (ie enforcement of certificates by Summary Judgment or Interim Award),
2. Despite an Arbitrator not being ‘bound’ by a certificate of the Architect, it presents an independent assessment of
the ‘amount due for payment’ – as ‘determined / valued in accordance with the terms of the Contract’ (especially as
the Architect certifies ‘completion’ of works when they appear to be complete and comply with the Contract in all
respects – which can be seen to applicable progressively on a periodic or stage basis)
3. Useful reference for Employer to prepare the Payment Response.
Interim & Final Certificates provide an independent certifier (Arch & QS) assessment of payment amounts entitled under the Contract.
• Deductions are not certified per se, they are ‘recorded (usually in a footnote) on the
certificate: Deductions are made from the amounts due for payment, so are not part of the
certified amount itself – but would be indicated in
the Payment Response.
• Thus Interim Certificates (per the SIA specimens) take the form of:
• Completed Work (minus _% retention)
• plus Unfixed Materials on Site (minus _% retention)
• minus Amounts previously certified.
Temporary Finality:
Clauses 31(11) [fmr 31(13)] and 37(4)(h) [fmr 37(3)(h)] of the SIA form expressly provide in
contract that Architect’s Certificates :
» shall have status of ‘temporary finality’ – i.e.: "full effect [enforcement] by way of
Summary Judgment or Interim Award shall be given to all decisions and certificates of the
Architect"
… ie such that any issues of set-off and cross-claim can only be settled later by the Courts and/or
Arbitrator in final judgement or final award in any dispute between the parties (and not thru
deductions from the interim payments).
… ie ‘pay first, argue later’
(if architect produces interim certificate, & employ or does not honour it
for payment, the contractor can take the interim cert to the courts & get
summoned the payment ; & the employer cannot deny it and is compelled
to pay.
.. adjudication & summary judgement both makes similar provisions,
binding the parties to their obligations for payment.)
Interestingly, the objectives of the SIA forms of contract were not totally inconsistent with
the objectives of the SOP Act:
» Such ‘deprivation of finance’ was ‘overcome’ in the earlier SIA forms of Building Contract
by the certificates of the Architect (eg Interim Certificates for payment), which were given
contractual effect to: “bind both the employer and contractor [ie requiring the Employer to
make payment], but only until final judgment or final award in any dispute between them
…
… both parties [could] therefore use the summary procedures* in the Courts (or interim
awards by arbitrators) in order to enforce the certificates [issued by the Architect for
payment]…”
» The contractual provision of 'contractual effect' to “bind both the employer and
contractor [ie requiring the Employer to make payment of the amount certified by the
Architect], but only until final judgment or final award in any dispute between them …” is
referred to as “temporary finality” of the certificates.
» The endeavours to promote ‘cashflow’ often bring up the notion of ‘pay first, argue later.’
» This is supported by the provision giving certification of interim / progress payment a status of ‘temporary finality’
» ie payment certificates ‘bind’ the parties temporarily (pending resolution of a dispute) so as to facilitate and
obligate timely payment.
» Also, it is noted that the contractual scheme of ‘finance regulation’ in the SIA forms of
building contract is in line with the SOP Act objectives to promote ‘cashflow’ - but was
more focused on Employer - Main Contractor contractual relationships rather than the
Main Contractor - Sub-Contractor relationships.
» Note that the provision for ‘summary judgment’ still remains in the SIA form of building
contract – but it’s applicability & status has not been ‘tested’ by the Courts post SOP Act.
In conclusion:
The contractual provision for payment certificates being given full effect by way of
Summary Judgement or Interim Award now ‘supplement’ rights to ‘Adjudication’ of
payment disputes under the provisions of the SOP Act.
1. Summary Judgement of the Court or Interim Award of an Arbitration Tribunal to expeditiously
establish / order a requirement for payment based on the Architect’s payment certificate, and
2. Adjudication to quickly resolve a payment dispute so the correct amount of payment is released
(with interest, to discourage frivolous adjudication applications).
Further Reading:
BCA’s notes on the SOP Act in their website at www.bca.gov.sg (under the “Procurement”
link).
Article: “Security of Payments in the Construction Industry: When is the Claim Triggered?”
at
www.bca.gov.sg/SecurityPayment/security_payment_relevantinfo.html
BCA’s preferred approach to questions such as;
- Whether the issuance of an Interim Certificate constitutes the ‘terms’ of contract that determine;
• when a payment claim can be served (eg is an Interim Certificate a ‘condition precedent’ to a payment claim being
served)?
• the amount that can be claimed? (and if so, whether this constitutes ‘contracting out’? eg - what if the Interim
Certificate is not issued on time or at all?)
PART 3: SECURITY – RETENTION & PERFORMANCE BONDS
Security:
Security for the performance of the Contractor under a building contract typically
take two form in Singapore:
(A) Security by ...
- cash deposit (ie “Security Deposit”)
- performance (surety) Bond
(A) Security by ...
- retention monies
Performance Bonds
see: http://www.singaporelaw.sg/sglaw/laws-of-singapore/commerciallaw/chapter-23
“23.8.1 A performance guarantee or performance bond ... is in essence an unconditional
undertaking by a third party to pay the beneficiary upon demand, independent and
irrespective of the underlying contract between the beneficiary and the principal.”
Performance Bonds are usually “on demand” – ie without conditions.
The Courts only recognize “fraud” or “unconscionability” as basis for injunction on
calling the bond.
(e.g. offer collateral to bank -> bank guarantee as form of security)
... but although the standard Conditions only provide for “retention
moooonies”
... often the Employer will require a Performance Bond too! (kiasu!)
PART 4: COMPENSATION OR ADDITIONAL PAYMENT
(FOR LOSSES & EXPENSES)
losses and expenses ....
The general sentiment in drafting standard form building contracts is to deal with
‘disputes’ within the contract as far as practical / possible...
... ie to avoid ‘litigation’ .... eg provisions for referring disputes to S.O. (or
Architect, in an SIA-MWC context), Mediation, Dispute Adj. Boards, etc, for
resolution;
... hence, also:
Provisions in contract for compensation and additional payment (in lieu of suing
for ‘damages’).
Grounds for compensation / additional payment (in lieu of damages) for losses &
expenses are typically:
(A) Where the Employer might be the 'cause' of the loss/expense (eg 'prevention'
or 'breach of contract' or 'variations'); or
(B) To relieve the Contractor of the 'risk' of financial burden, as a commercial
term of contract (eg adverse conditions of the site).
Examples of "additional payment or compensation" under SIA Conditions (9th Edn refers):
Cl. 1(2) & 1(4)(a) & 2(3) & 12(2)&(4), 12(4)(c) – regarding an Instruction ordering a
'variation' to the permanent works (where "additional payment or compensation" can apply
over-and-above any "increase in the Contract Sum").
Cl. 1(2) & 1(4)(b) & 2(2) & 12(2)&(4) – regarding an Instruction ordering a 'variation' to the
temporary works or methods of working (where "additional payment or compensation" can
apply over-and-above any "increase in
the Contract Sum").
Cl. 1(2) & 1(4)(c) & 12(2)&(4) – regarding an Instruction ordering a 'variation' comprising
postponement or suspension of work (where "additional payment or compensation" for
prolongation / disruption would be most applicable, and would apply over-and-above the
"increase in the Contract Sum", if any) .
Cl. 1(2) & 1(4) & 1(8) & 12(2)&(4) – regarding an Instruction for which the Architect has no
power or justification
(where "compensation" can apply).
Note that under Cl. 12(6), "additional payment" and "compensation" is described as:
"equivalent to the increase … in the cost, or the decrease … in the profitability of the
contract work"
Further note that under Cl. 12(6), in regard to "additional payment" and "compensation" :
"Loss of profit on
[i] omitted work or
[ii] on other business or contracts by reason of prolongation of the contract period shall be
[a] recoverable only in accordance with the general law
[b] where the Employer is in breach of contract, or
[c] in cases where … the Employer gives an indemnity ".
ie such 'loss of profit' on omitted work is not permitted by contract to be
recoverable as "additional payment" or "compensation" under contract.
Note on 'variations':
'Variation cost' includes:
(A) The increase in Contract Sum – i.e. labour, materials, etc plus preliminaries ...AND
(B) Any other losses/expenses incurred.
Any 'increase in Contract Sum' would normally be based on contract rates/prices ...
e.g. consider valuing variations under Cl. 5:
(1) S.O.R. or BQ + 'breakdown'/make-up of rates/prices.
(2) Prelims subject to Q. F & T.
To illustrate further: Variation cost includes preliminaries (in addition to labour, materials,
etc costs):
• Typically, variations are ordered through instructions, and instructions "will in principle entitle the
Contractor … to additional payment or compensation or to an increase in the Contract Sum" (see SIA
1(2)&(4)) – including an increase equivalent to the value of additional preliminaries arising from the variation
(see Cl. 12(4)).
• This relates to SIA Cl. 5(2) under which prices for preliminaries can be adjusted if indicated with "T" for time
and "Q" for quantity (as
opposed to "F" for fixed).
• Preliminaries' pricing adjusted on basis of "T" (time) is, in effect, payment for prolongation (of the
preliminary item of work) caused by
the variation.
1. Variations are valued based on (i) SOR; (ii) */ Market Rates; (iii) daywork (time-charged) rates [or in
PSSCOC: under ‘Quotation'].
2. Variation cost includes Preliminaries (in addition to labour, materials, etc, costs) – eg see 12(4)(a).
3. Variation costs either ‘increase’ or ‘decrease’ the Contract Sum (ie change the ‘value’ of the Works done by
the Contractor).
Note that there are also other ways the Contract Sum (ie value of Works) is reduced, eg 11(3).
4. Variation cost does not include L&E / Compensation or Additional Payments – see 31(4)(b) v. 31(4)(f) – nor
Set-offs and Compensation Damages (deducted from sums due, or otherwise recovered) from the Contractor
by Employer – see 31(4)(b) v. 31(4)(h).
5. L&E / Compensation or Additional Payments do not ‘increase’ or ‘decrease’ the Contract Sum (ie change
the ‘value’ of the Works).
6. L&E / Compensation or Additional Payments paid by the Employer to Contractor are --vis-à-vis Set-offs and
Compensation Damages (deducted from sums due, or otherwise recovered) from the Contractor by Employer.
7. L&E / Compensation or Additional Payments are usually on an ‘indemnity’ basis; ie based on the actual
cost/losses incurred (although rates/prices captured in contract may be evidence to determining the actual
cost/losses incurred, eg salary rates).
NOTE
Under Cl. 4,4(3) of PSSCOC:
"Loss and Expense" is distinguished from "any other compensation or remedy whatsoever (whether pursuant to the
Contract or as damages or
otherwise in law)".
Under Cl. 19.3 of PSSCOC:
"Loss and Expense" is distinguished from "any other compensation, damages or other amount".
Under Cl. 4,4(3) of PSSCOC:
"Loss and Expense ... including any loss, expenses, costs or damages".
Hence indicating that L&E in the mode of "damages" (or "compensation") would only include the "damages" (or
"compensation") of the kind described in the definition of L&E under Cl. 1.1(q).
PSSCOC 's 'Loss & Expense' includes "other costs, loss or expense of whatsoever nature
and howsoever arising."
The PSSCOC appears to seek resolution of claims / potential disputes at the contract level
rather than encouraging such matters to go to arbitration or the Courts (eg to seek
damages).
Comparatively; note that under Cl. 16(6) of the SIA Conditions (limiting the
attempt to avoid litigation):
"Where additional payment or compensation is due to the Contractor for compliance with
an Architect's instruction [eg order for variation] ...
... such [additional] payment or compensation shall be ...
equivalent to the increase ... in cost, or the decrease ... in
profitability [of the work still to be done] ...
... [but] loss of profit
[i] on omitted work, or
[ii] on other business or contracts by reason of prolongation
... shall be recoverable only in accordance with the general law".
In summary,
1. SIA provides for "additional payment" and "compensation", and PSSCOC
provides for "Loss and Expense", for losses and expenses arising from
specific circumstances.
2. Both SIA and PSSCOC provide for recovery of losses and expenses
(particularly preliminaries) arising from prolongation of the contract
period due to variations ordered by, or on behalf, of the Employer.
3. SIA recognises/permits that loss of profit arising from prolongation can be
claimed in legal action under general law under certain conditions.
4. PSSCOC would only allow claims for L&E (including loss of profit) arising
from prolongation if the contractual rates don't already provide for such
costs and damages.
5. Neither SIA nor PSSCOC include EOT as a direct basis for entitlement to
recover losses and expenses (including for preliminaries).
http://www.singaporelaw.sg/sglaw/laws-of-singapore/commercial-law/chapter-26
26.6.14 Most standard forms of contract provide for loss and
expense to be certified by the architect where the contractor has
been delayed by breaches or acts of prevention by the employer or
his agent. However, none of the SIA forms after 1980 has a loss and
expense clause for prolongation. In fact, Clause 31(14) expressly
provides that the architect has no power to decide or certify any
claim for breach of contract made against the Employer by the
Contractor. However, one might consider that Clause 12(4)
[Valuation of Variations] does provide a limited express entitlement
under the contract to additional `preliminaries´ costs which are
associated with variations, which in themselves do not amount to a
breach of contract.