VOLUME(m3)
COLUMN #1 7.25 x 0.3 x 0. 3 0.62525 21 13.7025
FOOTING #1 1 X 1 X 0.3 .3 21 6.3
BEAM #1 0.2 X 0.3 X .3325 0.01995 5 0.09975
BEAM #2 0.2 X 0.3 X .3050 0.0183 4 0.0732
BEAM #3 0.2 X 0.3 X .2850 0.0171 4 0.0684
BEAM #4 0.2 X 0.3 X .2700 0.0162 10 0.162
BEAM #5 0.2 X 0.3 X .2275 0.01365 5 0.06825
BEAM #6 0.2 X 0.3 X .1900 0.0114 5 0.057
BEAM #7 0.2 X 0.3 X .1200 0.0072 3 0.0216
TOTAL 20.5527 = 21
SLAB ESTIMATES
GROUND FLOOR
DESCRIPTION VOLUME CEMEN AREA PRICE TOTAL
(m3) T SAND GRAVEL SAND GRAVEL CEMENT
SLAB 12.25 110.25 6.125 12.25 P 700 P 700 P 255 P 40,976.25
SECOND FLOOR
SLAB 18.3375 159.23 9.14 18.3375 P 700 P 700 P 255 P 55,061
TOTAL P 96,037.25