Annex-II

Appendix B-I

Typical Cross Sections for the project highway to be followed are given below:-

In LHS In RHS
Design Chainage Design Chainage Length Length TCS Type
S.No. (LME) (RME) (LHS) (RHS) No. Remarks
m m (As attached)
From To From To

Type-A-3 Fig 2.4 of


1 2+500 2+600 2+505 2+595 100 90 TCS 9 (d)
Manual

Type-A-3 Fig 2.4 of


2 2+600 2+735 2+595 2+731 135 136 TCS 9 (c)
Manual

Fig 7.2A of Manual


3 2+735 2+746 2+731 2+742 11 11 TCS 4
(Minor Bridge)

Type-A-3 Fig 2.4 of


4 2+746 3+110 2+742 3+105 364 363 TCS 9 (c)
Manual
6 Lane divided
5 3+110 3+157 3+105 3+150 47 45 TCS 6 Highway for
approaches
6 Lane divided
6 3+157 3+163 3+150 3+156 6 6 TCS 4a Highway
(Minor Bridge)
In between approach
7 3+163 3+960 3+156 3+950 797 794 TCS 6 of Minor Bridge &
EUP
Fig 7.8 of Manual
8 3+960 4+250 3+950 4+240 290 290 TCS 5
(EUP)
In between approach
9 4+250 5+190 4+240 5+185 940 945 TCS 6 of EUP & Major
Bridge
Fig 7.4A of Manual
10 5+190 5+270 5+185 5+265 80 80 TCS 3
(Major Bridge)

Type-A-3 Fig 2.4 of


11 5+270 5+535 5+265 5+530 265 265 TCS 9 (c)
Manual

Type-B Fig 2.6 of


12 5+535 6+400 5+530 6+395 865 865 TCS 10
Manual

Type-A-3 Fig 2.4 of


13 6+400 7+224 6+395 7+219 824 824 TCS 9 (c)
Manual

Type-A-3 Fig 2.4 of


14 7+224 7+420 7+219 7+414 196 195 TCS 9 (a)
Manual

Type-A-3 Fig 2.4 of


15 7+420 7+500 7+414 7+493 80 79 TCS 9 (c)
Manual

Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
In LHS In RHS
Design Chainage Design Chainage Length Length TCS Type
S.No. (LME) (RME) (LHS) (RHS) No. Remarks
m m (As attached)
From To From To

Type-A-3 Fig 2.4 of


16 7+500 7+751 7+493 7+743 251 250 TCS 9 (a)
Manual

Type-A-3 Fig 2.4 of


17 7+751 7+938 7+743 7+930 187 187 TCS 9 (c)
Manual

Fig 7.4A of Manual


18 7+938 7+978 7+930 7+970 40 40 TCS 3
(Minor Bridge)

Type-A-3 Fig 2.4 of


19 7+978 8+055 7+970 8+048 77 78 TCS 9 (c)
Manual

Type-A-3 Fig 2.4 of


20 8+055 8+300 8+048 8+293 245 245 TCS 9 (a)
Manual

Type-A-3 Fig 2.4 of


21 8+300 8+990 8+293 8+981 690 688 TCS 9 (c)
Manual

Type-A-3 Fig 2.4 of


22 8+990 9+143 8+981 9+134 153 153 TCS 9 (a)
Manual

Type-A-1 Fig 2.2 of


23 9+143 9+184 9+134 9+172 41 38 TCS 7
Manual

Type-A-2 Fig 2.3 of


24 9+184 9+535 9+172 9+545 351 373 TCS 8
Manual

Type-A-1 Fig 2.2 of


25 9+535 9+576 9+545 9+620 41 75 TCS 7
Manual

Fig 7.4A of Manual


26 9+576 9+656 9+620 9+700 80 80 TCS 3
(Major Bridge)

Type-A-1 Fig 2.2 of


27 9+656 9+980 9+700 10+017 324 317 TCS 7
Manual

Type-A-2 Fig 2.3 of


28 9+980 10+300 10+017 10+315 320 298 TCS 8
Manual

Type-A-3 Fig 2.4 of


29 10+300 10+785 10+315 10+797 485 482 TCS 9 (a)
Manual

Fig 7.4A of Manual


30 10+785 10+845 10+797 10+857 60 60 TCS 3
(Major Bridge)

Type-A-3 Fig 2.4 of


31 10+845 11+500 10+857 11+511 655 654 TCS 9 (c)
Manual

Type-A-3 Fig 2.4 of


32 11+500 11+710 11+511 11+721 210 210 TCS 9 (a)
Manual

Type-A-3 Fig 2.4 of


33 11+710 11+965 11+721 11+980 255 259 TCS 9 (c)
Manual

Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
In LHS In RHS
Design Chainage Design Chainage Length Length TCS Type
S.No. (LME) (RME) (LHS) (RHS) No. Remarks
m m (As attached)
From To From To

Type-A-3 Fig 2.4 of


34 11+965 12+080 11+980 12+095 115 115 TCS 9 (a)
Manual

Type-A-3 Fig 2.4 of


35 12+080 12+577 12+095 12+594 497 499 TCS 9 (c)
Manual

Fig 7.4A of Manual


36 12+577 12+937 12+594 12+954 360 360 TCS 3
(Major Bridge)

Type-A-3 Fig 2.4 of


37 12+937 13+028 12+954 13+044 91 90 TCS 9 (c)
Manual

Fig 7.4A of Manual


38 13+028 13+088 13+044 13+104 60 60 TCS 3
(Major Bridge)

Type-A-3 Fig 2.4 of


39 13+088 13+765 13+104 13+798 677 694 TCS 9 (c)
Manual

Type-A-3 Fig 2.4 of


40 28+470 29+313 28+475 29+323 843 848 TCS 9 (a)
Manual

Fig 7.4A of Manual


41 29+313 29+593 29+323 29+603 280 280 TCS 3
(Major Bridge)

Type-A-3 Fig 2.4 of


42 29+593 29+990 29+603 30+000 397 397 TCS 9 (a)
Manual

Total Length (km) 12.785 12.818

NOTE :-
Median and carriageway width tapering shall be provided as per IRC-SP-84-2019
Section no. 2.5.4 and section 2.12.2.3.

Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to
Km 30/000)
Four laning of Haridwar Nagina section of NH-74 in the state of Uttrakhand on EPC mode (Package-III: From Design Chainage
LME (Km. 2/500 to Km 13/765 and Km 28/470 to km 29/990) & Design Chainage RME(Km 2/505 to Km 13/798 and Km 28/475 to