INVESTIGASI PERUNTUKKAN

(o dan p)
Prioritas
Kode
Elevasi (z) Crossing Monitoring Pelaksanaan

No. STA (BD) STA ( BD baru) Deviasi Deviasi


ID-Pengujian Koordinat UTM (x,y) Eksisting (Hasil Eksisting (3-4- Rencana FG Rencana FG (3-4- Crossing/ Mainroad Tipe Crossing
(FG 14-2-2020- (FG 3-4-2020- Uraian
Pengukuran Topo) 2020) (14-Feb 2020) 2020) (Basic Design)
Eksisting) Eksisting)

S 1 S-23 72+000 71+957 411283.114, 9608260.930 18.793 28.658 9.865 Mainroad - - -


S 2 S-24 72+140 72+097 411138.978, 9608263.038 22.721 21.118 24.940 26.122 2.219 5.004 Mainroad - - -
B2 3 B2-09 72+315 72+272 410974.376, 9608294.816 19.998 22.656 26.298 25.377 6.300 2.721 Mainroad, Crossing Box Culvert 2x2 - -
B2 o 4 B2-10 72+510 72+467 410778.239, 9608332.682 24.478 22.316 32.242 30.726 7.764 8.410 Mainroad - - Ongoing
S 5 S-25 72+635 72+592 410655.505, 9608366.970 30.154 26.252 35.982 34.476 5.828 8.224 Mainroad - - -
S p 6 S-26 72+750 72+707 410550.101, 9608378.041 33.687 32.995 38.438 37.655 4.751 4.660 Mainroad, Crossing Box Pedestrian Jalan Kebun V
B2 7 B2-11 72+925 72+882 410372.315, 9608411.048 29.978 30.568 40.559 40.466 10.581 9.898 Mainroad, Crossing Box Culvert 2x2 - -
S 8 S-27 73+110 73+067 410187.334, 9608444.943 37.000 36.367 40.471 40.662 3.471 4.295 Mainroad - - -
S p 9 S-28 73+280 73+237 410017.290, 9608469.423 35.312 36.649 37.049 38.327 1.737 1.678 Mainroad - - V
D D 10 D-13 73+340 73+297 409959.244, 9608489.054 32.986 35.051 36.673 36.932 3.687 1.881 Mainroad - - V
D D 11 D-14 73+365 73+322 409935.638, 9608496.625 32.503 33.649 34.940 36.260 2.437 2.611 Mainroad - - V
B2 12 B2-12 73+480 73+437 409827.510, 9608517.500 26.265 27.304 33.448 33.391 7.183 6.087 Mainroad - - -
B1 o 13 B1-21 73+680 73+637 409619.230, 9608511.399 42.000 38.572 34.388 33.426 -7.612 -5.146 Crossing Overpass Jalan Desa V
S p 14 S-28a 73+680 73+637 409619.230, 9608511.399 42.000 38.572 34.388 33.426 -7.612 -5.146 Crossing Overpass Jalan Desa V
B1 15 B1-21a 73+700 73+657 409609.284, 9608559.785 42.000 39.612 34.388 33.510 -7.612 -6.102 Crossing Overpass Jalan Desa -
B1 16 B1-22 73+712 73+669 409597.963, 9608600.171 42.000 41.967 34.434 33.545 -7.566 -8.422 Crossing Overpass Jalan Desa -
D D 17 D-15 73+845 73+802 409470.718, 9608585.709 33.010 38.494 33.884 33.125 0.874 -5.369 Mainroad - - V
D D 18 D-16 73+870 73+827 409443.384, 9608589.714 32.164 35.824 33.617 32.881 1.453 -2.943 Mainroad - - V
S 19 S-29 73+915 73+872 409402.818, 9608593.404 29.227 32.961 32.978 32.309 3.751 -0.652 Mainroad - - V
S 20 S-30 74+115 74+072 409204.835, 9608621.448 22.994 23.028 30.703 28.301 7.709 5.273 Mainroad - - -
S p 21 S-31 74+315 74+272 409005.652, 9608626.952 21.005 21.456 27.779 25.405 6.774 3.949 Mainroad - - V
D D 22 D-17 74+440 74+397 408873.392, 9608648.568 24.899 23.965 26.154 25.029 1.255 1.064 Mainroad - - V
D D 23 D-18 74+465 74+422 408848.326, 9608648.283 25.000 24.241 25.829 24.954 0.829 0.713 Mainroad - - V
S p 24 S-32 74+490 74+447 408823.174 , 9608642.877 25.000 24.630 25.504 24.878 0.504 0.248 Mainroad - - V
D D 25 D-19 74+515 74+472 408798.469, 9608648.662 25.000 24.961 25.179 24.803 0.179 -0.158 Mainroad - - V
D D 26 D-20 74+540 74+497 408772.201, 9608651.813 24.157 25.000 24.854 24.727 0.697 -0.273 Mainroad - - V
D D 27 D-21 74+565 74+522 408748.244, 9608651.728 23.000 25.000 24.530 24.651 1.530 -0.349 Mainroad - - V
S 28 S-33 74+690 74+647 408623.362 , 9608657.944 26.541 23.816 24.886 24.273 -1.655 0.457 Mainroad - - V
S 29 S-34 74+890 74+847 408423.307 , 9608651.246 33.002 32.965 28.524 26.732 -4.478 -6.233 Mainroad - - -
S 30 S-35 75+080 75+037 408232.222, 9608627.838 30.491 33.617 32.258 30.700 1.767 -2.917 Mainroad - - -
B1 o 31 B1-23 75+228 75+185 408089.248, 9608623.288 22.330 23.605 33.153 32.908 10.823 9.303 Crossing Jembatan Underpass Jalan Operasional Blok Limau Barat (Pertamina) V
S p 32 S-35a 75+228 75+185 408089.248, 9608623.288 22.330 23.605 33.153 32.908 10.823 9.303 Crossing Jembatan Underpass Jalan Operasional Blok Limau Barat (Pertamina) V
B1 33 B1-24 75+278 75+235 408036.300, 9608616.602 22.504 22.188 33.035 33.082 10.531 10.894 Crossing Jembatan Underpass Jalan Operasional Blok Limau Barat (Pertamina) -
S 34 S-36 75+385 75+342 407932.076, 9608616.600 20.992 21.894 32.173 32.754 11.181 10.860 Mainroad - - -
S 35 S-37 75+585 75+542 407782.570, 9608595.240 21.007 21.000 29.924 29.582 8.917 8.582 Mainroad - - -
S 36 S-38 75+685 75+642 407634.298, 9608572.318 22.346 22.561 27.627 27.861 5.281 5.300 Mainroad - - -
B2 37 B2-13 75+815 75+772 407508.939, 9608573.353 22.451 22.635 29.601 28.553 7.150 5.918 Mainroad - - V
S p 38 S-39 75+990 75+947 407333.311, 9608567.186 30.004 28.674 34.644 33.458 4.640 4.784 Mainroad - - V
B2 39 B2-14 76+140 76+097 407185.188, 9608544.848 32.494 31.250 39.644 37.958 7.150 6.708 Mainroad - - -
S 40 S-40 76+240 76+197 407084.942, 9608546.472 34.634 33.931 42.341 40.958 7.707 7.027 Mainroad - - -
B1 o 41 B1-25 76+367 76+324 406953.895, 9608525.458 38.132 37.051 45.350 44.434 7.218 7.383 Crossing Box Traffic Jalan Kebun V
S 42 S-41 76+480 76+437 406836.473, 9608505.244 39.519 39.025 47.058 46.445 7.539 7.420 Mainroad - - -
B2 43 B2-15 76+580 76+537 406736.745, 9608507.449 40.403 39.962 47.486 47.341 7.083 7.379 Mainroad - - -
B2 44 B2-16 76+760 76+717 406562.350, 9608492.905 39.656 41.766 46.231 46.856 6.575 5.090 Mainroad - - -
B2 o 45 B2-17 76+980 76+937 406391.237, 9608478.361 29.745 28.717 42.423 42.595 12.678 13.878 Mainroad, Crossing Box Culvert 2x2 - -
B3 46 B3-01 77+140 77+097 406188.647, 9608461.739 45.000 43.689 37.719 37.814 -7.281 -5.875 Mainroad - - -
D D 47 D-22 77+245 77+202 406080.961, 9608455.903 38.552 38.437 33.475 34.664 -5.077 -3.773 Mainroad - - V
S p 48 S-42 77+270 77+227 406064.868, 9608450.899 35.329 37.008 35.377 33.915 0.048 -3.093 Mainroad - - V
D D 49 D-23 77+295 77+252 406032.026, 9608451.437 34.472 35.785 32.439 33.185 -2.033 -2.600 Mainroad - - V
D D 50 D-24 77+320 77+277 406006.430, 9608449.553 33.360 34.915 32.109 32.561 -1.251 -2.354 Mainroad - - V
S p 51 S-43 77+380 77+337 405938.367, 9608450.395 31.470 29.905 31.470 31.586 0.000 1.681 Mainroad, Crossing Box Culvert 2x2 - V
S 52 S-44 77+480 77+437 405839.783, 9608422.657 38.906 31.968 32.724 31.541 -6.182 -0.427 Mainroad - - -
B2 53 B2-18 77+610 77+567 405719.585, 9608422.263 27.999 33.271 35.113 34.176 7.114 0.905 Mainroad, Crossing Box Culvert 2x2 - -
S p 54 S-45 77+735 77+692 405590.056, 9608423.372 33.393 31.621 36.455 36.631 3.062 5.010 Mainroad - - V
B1 o 55 B1-26 77+865 77+822 405461.159, 9608401.591 29.535 33.525 36.719 37.811 7.184 4.286 Crossing Box Traffic Jalan Kabupaten V
B2 56 B2-19 78+025 77+982 405292.510, 9608386.946 23.001 23.864 35.278 37.322 12.277 13.458 Mainroad, Crossing Box Culvert 3x2 - -
S p 57 S-46 78+115 78+072 405214.509, 9608387.651 32.312 23.512 33.517 36.113 1.205 12.601 Mainroad - - V
B2 58 B2-20 78+295 78+252 405035.834, 9608357.692 24.844 25.627 31.017 31.981 6.173 6.354 Mainroad, Crossing Box Culvert 2x2 - -
D D 59 D-25 78+390 78+347 404936.585, 9608343.883 27.362 24.999 28.750 29.776 1.388 4.777 Mainroad - - V
D D 60 D-26 78+415 78+372 404911.506, 9608340.465 27.695 26.674 28.555 29.415 0.860 2.741 Mainroad - - V
D D 61 D-27 78+440 78+397 404886.601, 9608333.416 28.326 27.331 28.484 29.179 0.158 1.848 Mainroad - - V
D D 62 D-28 78+465 78+422 404862.429, 9608331.951 29.233 27.729 28.538 29.069 -0.695 1.340 Mainroad - - V
S p 63 S-47 78+490 78+447 404840.045, 9608323.834 30.651 28.395 28.717 29.083 -1.934 0.688 Mainroad - - V
S 64 S-48 78+690 78+647 404642.618, 9608284.768 36.420 33.984 33.130 32.874 -3.290 -1.110 Mainroad - - -
B3 65 B3-02 78+770 78+727 404572.489, 9608267.761 41.207 38.523 35.005 34.874 -6.202 -3.649 Mainroad - - -
S 66 S-49 78+895 78+852 404448.887, 9608235.157 35.780 39.032 37.713 37.853 1.933 -1.179 Mainroad - - -
S 67 S-50 79+093 79+050 404256.381, 9608181.322 34.762 39.380 4.618 Mainroad - - -