ADDITIONAL WORKS ON 9E&F FLAT

SI NO:- TYPE OF WORKS QUANTITY LABOUR CHARGE TOTAL CHARGE LABOUR MATERIAL CHARGE
ADDITIONAL PLUMBING WORKS:-
1 WORK AREA DISHWASHER POSITION CHANGING 1 LABOUR 800/LABOUR 800
2 TOILET ADDITIONAL FLOOR TRAPS (4 TRAPS) 2 LABOUR 800/LABOUR 1600 300/MULTI TRAP(4nos)

ADDITIONAL ELECTRICAL WORKS:-


1 EXTRA SWITCHBOARD FIXING AT LIVING AREA 2 LABOUR 700/LABOUR 1400 700
2 EXTRA POWER POINTS IN ALL BEDROOMS FOR CEILING LIGHTS 4 LABOUR 700/LABOUR 2800 1120
3 HOME THEATRE + SPEAKER LINE POINTS 3 LABOUR 700/LABOUR 2100 600
4 COMPUTER POINTS AT BEDROOMS 4 LABOUR 700/LABOUR 2800 1350
5 BAR COUNTER POWER POINTS & LIGHT POINTS 2 LABOUR 700/LABOUR 1400 680
6 4 BALCONIES PEBBLE COURT EXTRA LIGHT POINT FIXING 3 LABOUR 700/LABOUR 2100 800
7 WASH COUNTER AREA LIGHT POINT FIXING 1 LABOUR 700/LABOUR 700 350
8 KITCHEN ADDITIONAL POWER POINTS 2 LABOUR 700/LABOUR 1400 350
9 WORK AREA DISHWASHER ELECTRAL POINT POSITION CHANGING 1 LABOUR 700/LABOUR 700
10 TV POINTS POSITION CHANGING WORKS AT BEDROOMS 1 LABOUR 700/LABOUR 700
11 PRAYER ROOM ADDITIONAL POINT FIXING WORK 1 LABOUR 700/LABOUR 700 350
12 BALCONY AREA 4 MODULE SWITCHES FIXING WORK 3 LABOUR 700/LABOUR 2100 600

CORE CUTTING WORK:-


1 EXTRA CORE CUTTING FOR SPEAKER LINE POINT 3 HOLES 750/HOLE 2250

GRANITE SHIFTING CHARGES:-


1 COMPANY LABOUR TILE SHIFTING CHARGES (6DAYS) 36 LABOUR 600/LABOUR 21600

GRANITE CHEMICALLING WORK:-


1 CHEMICAL CHARGES (EUROBUILD) 20 LITTERS 496/LITTER
2 CHEMICL APPLYING CHARGES 8 LABOUR 700/LABOUR 5600

WHITE CEMENT:-
1 WHITE CEMENT FOR GRANITE LAYING 20 BAGS 860/BAG
TOTAL CHARGES
TOTAL AMOUNT

800
1900

2100
3920
2700
4150
2080
2900
1050
1750
700
700
1050
2700

2250

21600

9920
5600

17200
85070