You are on page 1of 2

List for Amount Deduction from M/s.

Front Line Construction ( Kalarikkal ) at Mystic Rose site

SL. WORK DESCIPTION TOTAL LABOURS AMOUNT REMARKS


NO: (INR)
1. Tank inside cleaning & waste 12 Labours X 800= 9,600/- 9,600/-
removal work inside Rain water
harvesting tanks at Ground.
2. Water proofing work inside Rain Total Amount – 65,000/- 65,000/-
water harvesting tanks at Ground.
3. Ventilation duct top portion bad 6 Labours X 800= 4,800/- 33,200/-
quality block work, plastering and Scaffolding- 1,500/-
concreting works. Surface Materials – 2,000/-
repairing works done (4 Nos.) Total – 8,300/- X 4 Nos=
33,200/-
4. Ventilation duct top portion broken 175sqft X 275= 48,125/- 48,125/-
glass replacement charge ( The top
surface was not good ).
5. Water leakage rectification work at4 Labours X 800= 3,200/- 5,200/-
8A pebble court. Water proofing work – 2,000/-
Total – 5,200/-
6. Additional putty application work 1200sqft X 10.50= 12,600/- 72,600/-
at 4Nos. ventilation ducts inside Scaffolding Charge – 60,000/-
wall. Total – 72,600/-
7. Total building area cleaning and 25 Labours X 800= 20,000/- 45,600/-
debris removal charges. Tipper & Hitachi charges for
debris removal – 25,600/-
Total – 45,600/-
8. Common area floor slabs were not 9 Labours X 800= 7,200/- 10,600/-
level. Chipping done before floor Jack Hammer Rent = 1,000/-
tiling at 7, 8 & 9th floors. Debris removal – 2,400/-
Total – 10,600/-
9. Atrium area octagonal portions 8 Labours X 800= 6,400/- 9,800/-
were not equal. Some portions Jack Hammer Rent = 1,000/-
broken and chipping done for some Debris removal – 2,400/-
portions. Total – 9,800/-
10. External area plastering patch 52 Labours X 1,000= 52,000/- 68,000/-
works done before painting because Repairing materials from
the plaster coming out while water FOSROC – 16,000/-
washing. Total – 68,000/-
11. Waste removed from lift pits at 9 Labours X 800=7,200/- 7,200/-
basement 2.
12. Swimming pool inside portions 8 Labours X 800= 6,400/- 10,000/-
concrete chipped, waste removed Debris removal – 1,600/-
and patch works done before water Materials charge – 2,000/-
proofing because of the wall levels Total – 10,000/-
were not in level.
13. Swimming pool inside leak Total Amount – 40,000/- 40,000/-
rectified and water proofing done.
14. STP tank inside cleaned and waste 8 Labours X 800= 6,400/- 6,400/-
removed.
15. STP tank inside water proofing Total Amount – 55,000/- 55,000/-
work done.
16. All plumbing ducts bottom portions 16 Masons X 1,000= 16,000/- 58,400/-
was not plastered and finished. 8 Helpers X 800= 6,400/-
Now the works completed. Materials charges – 24,000/-
Scaffolding charges – 12,000/-
Total – 58,400/-
17. Fire stair case side sunshade inside 8 Masons X 1,000= 8,000/- 23,400/-
slope and curves are made proper. 8 Helpers X 800= 6,400/-
Materials Charges – 9,000/-
Total – 23,400/-
18. External area re plastering done 4 Labours for chipping X 800= 21,900/-
before painting because the plaster 3,200/-
coming out while water washing at Debris removal – 1,600/-
10B rear side balcony area wall. 3 Masons X1,000= 3,000/-
2 Helpers X 800= 1,600/-
Material charges
Including conveyance –
12,500/-
TOTAL AMOUNT 5,90,025/-

You might also like