QUOTE NO: CLQ/MSS/06/2020 DATED June 6, 2020

CLIENT :

MBUGRA SEC SCHOOL

P.O BOX.

PAP ONDITI

RE: LABORATORY FITTING


Dear Sir,

Many thanks for your interest in doing business with us. Please below find your quotation for
the laboratory fittings.

The Scope of the work


i. Gas system to complete
ii. Water system (clean and waste) to
iii. Fume chamber function with fun
iv. Storage shelves for prep room , main lab, office and chemical room
v. Tables *(2 by 8ft)( mobile)
vi. Smootheningthe floor and work tables.
vii. Repairing of external , internal of walls and general painting of the same .
viii. Tiling of worktops with smooth granite tiles
THE BILLS OF QUANTITIES
ITEMS QUANTITY REQUIRED UNIT PRICE( KShs.) TOTALS( KShs.)
Gas taps 14 3500 49000
Water taps 14 3300 46200
T -joints 20 850 17000
L –bow joints 20 200 4000
Straight joints 20 850 17000
Waste 20 629 12580
pipes/sinkwastes
Square tubes 11 2000 22000
Copper pipes ( Heavy 5 rolls 8500 42500
duty)
Credo clips 100 100 10000
Blockboard 16 4800 76800
formica 11 1600 17600
Rego regulator 1 10800 10800
Manifold 2 1800 3600
Control taps 4 2200 8800
Water traps 20 1200 24000
Clean water fitting - 10000 10000
accessories
Waste water fitting - Complete 22000 22000
accessories sockpit
Gas cylinders 13 kg complete with 15000 15000
accessories
Locks , hinges and 6000 6000
fittings
Nails and screws - 5000 5000
Paints and mixings - 27600 27600
( white and blacks)
Plastering cracks and 10000 10000
repairs
Granite tilled tops 4ft by 4ft 25 boxs 1800 45000
Partitioning of prep 12000 12000
/chemical room
Shelves - - 79750
TOTAL MATERIAL 594230
COSTS
Miscellaneous - 58,217
LABOUR for gas ,water, - - 108048
and benches
TOTALS 760495
Testing - - 49870
,commissioning
and handover
NET TOTAL for 810365
whole project

PART B)THE CONTRACT AGREEMENT

The agreement signed between CHEMOLABEQUIP ENTERPRISE P.0 B0X 61815 -00200
NAIROBI and MBUGRA SECSECSCHOOL for the completion of Science Laboratory

Part (1) Terms :

CHEMOLABEQUIP ENTERPRISE means ‘’contractor’’


MBUGRA SECONDARY SCHOOL means client or ‘’employer’’

Contract means Works or fitting and installation of the science laboratory.

WORK PLAN FOR COMPLETION OF THE SCIENCE LABORATORY


Part (2) Completion of the science laboratory will involve:

i. Installation of the gas system in the laboratory and the gas source and storage.
ii. Fitting the gas taps and water taps on the benches and ensuring they are in proper
working condition.
iii. Tiling of the bench tops acid resistant.
iv. Fitting of sinks and waste water system.
v. Painting of the frames of the benches.
vi. Fitting of the shelves under worktops and in the rooms
vii. Repairing and Painting of the external and internal

Part (3): Payments and Warranty

The total value of the works is Kshs 810365(eight hundred and ten thousand three hndred
and sixty five)

i. The work shall start when materials shall be delivered on site.


ii. The work is expected to take 10 days.
iii. The work will be done over the weekends and even late in the night depending on the
weather of the day.
iv. The bills of quanties will be as spelt out in the bills of quantities document without
alterations .
v. The materials onsite and safety of the workers is entirely responsibility of
CHEMOLABEQUIP ENTERPRISE. Their loss and or injury is a responsibility of the
contractor.
vi. When works begin 30% of the total value of the contract shall be paid to the
contractor.( equivalent to Kshs. 243110)
vii. As work progresses there will be another payment of 40% (equivalent to Kshs.324146).
This will be after 5 days of the work .
viii. The remaining 30% (equivalent to Kshs.243110) shall be paid on completion and
handover of the work
ix. The school shall be required to report any fault, leakages and or any works seems to be
improperly done within a period of six months of use. These shall be fixed at the
contractors cost.
x. This contract is legal and binding and will be witnessed by the chairman of the project
and secretary of the employer and the director and the supervisor of the contractor.

Part 4) Witnessing

1) I Mr./Mrs…………………………………………………………………………………………………………the
representative of the client hereby agree with the above .

Position/Director Chemolabequip Enterprise ………………………………………………………………..

Signature ……………………………………………..

Address…………………………………………….
Official Stamp/date……………………………………………

2) I Mr./Mrs…………………………………………………………………………………………………………the
representative of the client hereby agree with the above .

Position/supervisor of the project ………………………………………………………………..

Signature ……………………………………………..

Address…………………………………………….

Official Stamp/date……………………………………………

3) I Mr./Mrs…………………………………………………………………………………………………………the
representative of the contractor hereby agree with the above .

Position/ chairman of the project ………………………………………………………………..

Signature ……………………………………………..

Address…………………………………………….
Official Stamp/date ……………………………………………

4) I Mr./Mrs…………………………………………………………………………………………………………the
representative of the contractor hereby agree with the above .

Position/ Secretary of the project ………………………………………………………………..

Signature ……………………………………………..

Address…………………………………………….

Official Stamp/date ……………………………………………

WORK PLAN FOR COMPLETION OF SCIENCE LABORATORY POWO SEC SCHOOL


The works will start by erection of metallic frames .This may take a period of 5 days .
During this period there will also gas fitting. This is expected to be completed within 3 days.

Fixing and fitting of bench tops formica white acid proof.

Water, waste water, gas system fittings shall also begin with digging of tunnels and laying of
pipes.

Completion of gas and water system installation.

PAYMENTS DETAILS

BANK : KENYA COMMERCIAL BANK KCB

ACCOUNT NAME : CHEMOLABEQUIP ENTERPRISE

ACCOUNT: 1222745895

BRANCH : MOI AVENUE