You are on page 1of 2

s. no. Workers charges Construction Price per sq. ft.

Total price
with material area in sq.
ft.
1 Dismantling, cleaning, - - 35000/-
throughing off
2 Construction work 190 200 38000/-
3 Tiles work 390 250 97500/-
4 Electrical work 190 220 41800/-
5 Plumbing work 190 200 38000/-
6 Paint work According to _ 20000/- approx.
area left for
paint
=270300/- total

K.K. ENGINEER & PROMOTERS Pvt. Ltd.

Quotation of Washroom

Worker charge with material (Cement, brick, tiles, sand etc.)

Washroom fitting product name and price detail chart:

Company ‘s Commode Urinals Washbasin Sensor Tab Total


Name price
Hindware 19000*2 =38000/- 18490*2= 36980/- 13170*3=39510/- 7501*1=7501/- 121991/-

Cera 17000*2=34000/- 11880*2=23760/- 13490*3=40470/- 13155*1=13155/- 111385/-

Kohler 33600*2=67200/- 20000*2=40000/- 29250*3=87750/- 16000*1=16000/- 210950/-

Other fitting prices:


 All internal and outer fitting pipes and other material: 80000/-
 Sensor lights: 8000/-
 Doors: 17000*3= 51000/-
 Door handles: 2500*3= 7500/-
 Full length wall hung urinal division: 10200*2= 20400/-
 Counter top basin division: 5500*2= 11000/-
 Dolphy automatic hand dryer: 4199*2= 8398/-
 Led vanity light for washbasin: 2400*3= 7200/-
 Mirror for washbasin: 5000*3= 15000/-
 Toilet paper roll holder: 800*2=1600/-

Total price of the work-

Hindware: 602390/-

Cera: 591783/-

Kohler: 691348/-

Note:
 20% payment to be given at the starting of work.
 The payment of material will have to be given at the time of delivery.

Alok Chauhan
General Manager
KK Engineers & Promoters Pvt. Ltd.