ESTIMATE

Name of the work: AM to Marical - Raikode road from Km. 0/0 to 22/400 for the year
2011-12

Sl. Measurements
Description Nos Breadt Quantity Rate per Amount
No Length Depth
h

1 Providing BT patch work for pot holes of depth ranging from


50 to 70mm ,using 40mm HBG metal with required quantity of
10-12 mm size HBG key chips and 80/100 grade bitumen at
45 kgs/1Cum of work for filling the pot holes and sealing the
filled up pot hole with a 15 mm thick layer using 10-12 mm
HBG key chips and 80/100 grade bitumen trimming the edges
to provide vertical faces , cleaning applying tack coat , filling
the pot holes compacting with power Road Roller of 8 to 10
Tonnes finishing and blinding the surface using stone dust/
sand , including cot of all materials T&P , and labour charges
for all operations etc. at site of complete

a) Marical - Raikode road from Km. 0/0 to 22/400 150.00 208.60 1 31290.00
Sqm Sqm
2 Providing BT patch work for pot holes of depth ranging from
25 to 35mm ,using 20-25mm HBG metal with required
quantity of 10-12 mm size HBG key chips and 80/100 grade
bitumen at 45 kgs/1Cum of work for filling the pot holes and
sealing the filled up pot hole with a 15 mm thick layer using
10-12 mm HBG key chips and 80/100 grade bitumen trimming
the edges to provide vertical faces , cleaning applying tack
coat , filling the pot holes compacting with power Road Roller
of 8 to 10 Tonnes finishing and blinding the surface using
stone dust/ sand , including cot of all materials T&P , and
labour charges for all operations etc. at site of complete

a) Marical - Raikode road from Km. 0/0 to 22/400 100.00 148.40 1 14840.00
Sqm Sqm
3 Stripping the excess soil from the shoulder shurface to achieve
the approved level for sectioning the berms, shoulders as per
MORT&H specification No.3003 (As per E-in-C Circular Memo
NO.Maintenance/ E.E(TEC) TA15/AE4/2005, dt.25/04/2005)

a) Marical - Raikode road from Km. 0/0 to 22/400


2 2000.00 1.00 4000.00 5.10 1 20400.00
Sqm Sqm
4 Making up loss of material/ irregularities on the shoulder to
the design level by adding fress approved soil and compacting
with appropriate equipment as per MORT&H specification
No.3003 (As per E-in-C Circular Memo NO.Maintenance/
E.E(TEC) TA15/AE4/2005,
a) Marical - Raikode road from Km. 0/0 to 22/400
2 2200.00 1.00 4400.00 10.50 1 46200.00
Sqm Sqm

444755974.xls Page 1
Sl. Measurements
Description Nos Breadt Quantity Rate per Amount
No Length Depth
h

5 Clearing Juliflora (Prosafis) jungle including up-rooting and


removing of Juliflora stumps including all labour charges etc.,
complete for finished item of work.
a) Marical - Raikode road from Km. 0/0 to 22/400
2 14000.00 2.00 - 56000.00
Deduct 50% Voids -28000.00
28000.00 3.30 1 92400.00
Sqm
6 Clearing of light / heavy / Scrub Jungle including all labour
charges etc., complete for finished item of work.
a) Marical - Raikode road from Km. 0/0 to 22/400
2 1500.00 2.00 - 6000.00
Deduct 50% Voids -3000.00
3000.00 2.00 1 6000.00
Sqm
7 White washing to culverts in two coats with white cement and
approved branch mixing with fevicol and blue including cost
and conveyance of all materials and all labour charges etc.,
complete for finished item of work.
b) Marical - Raikode road from Km. 0/0 to 22/400 350.00 9.80 1 3430.00
Sqm Sqm
8 White washing to guard stones in two coats with white cement
and approved branch mixing with fevicol and blue including
cost and conveyance of all materials and all labour charges
etc., complete for finished item of work.
a) Marical - Raikode road from Km. 0/0 to 22/400 130.00 6.50 1 845.00
No. No.
215405.00
9 Provision for VAT 4.00% 8616.00

10 Provision for Painting of KM, HM, 5th KM and village name boards, 35000.00
Traffic census survey, Culvert repairs
11 Provision for unforeseen items and rounding off 479.00

Total 259500.00

12 Liabilities amount for the yr 10-11 MB No.5218/C 174500.00

Total Rs. 434000.00

444755974.xls Page 2
DATA
Name of the work: AM to Marical - Raikode road from Km. 0/0 to 22/400 for the year 2011-12

Sl.
Description Qty Rate per Amount
No.

1 Providing BT patch work for pot holes of depth ranging from 50 to 70mm ,using 40mm HBG metal with
required quantity of 10-12 mm size HBG key chips and 80/100 grade bitumen at 45 kgs/1Cum of work for
filling the pot holes and sealing the filled up pot hole with a 15 mm thick layer using 10-12 mm HBG key
chips and 80/100 grade bitumen trimming the edges to provide vertical faces , cleaning applying tack
coat , filling the pot holes compacting with power Road Roller of 8 to 10 Tonnes finishing and blinding the
surface using stone dust/ sand , including cot of all materials T&P , and labour charges for all operations
etc. at site of complete
Unit - 1Sqm
Materials
Pot hole filling:
40 mm HBG metal 1.00X1.00X0.045X1.10 0.0495 Cum 950.66 1 cum 47.06
10-12 mm size key chiX1.00X0.045X(13/100) 0.0059 Cum 1025.66 1 cum 6.00
80/100 Grade bitumen.00X0.055X45Kgs/Cum 1.890 Kgs 31598.50 1 MT 59.72
( Including tack coat )
Sealing the pot hole:
10-12mm size HBG chi1.00X1.00X0.015X1.33 0.020 Cum 1025.66 1 cum 20.46
Stone dust / Sand 1.00X1.00X0.003 0.003 Cum 234.20 1 cum 0.70
80/100 Grade bitumen0X0.015X80 Kgs/1Cum 1.080 Kgs 31598.50 1 MT 34.13

Labour charges
Pot hole filling with 1.00X1.00X0.045 0.045 Cum 588.00 1 Cum 26.46
40 mm HBG metal
Sealing the filled up 1.00X1.00X0.015 0.015 Cum 588.00 1 Cum 8.82
pot hole using 10-12
mm HBG metal. Add 15% on labour charges 35.28 5.29
208.64
Add TP 0.00% 0.00
TOTAL Rs. 208.64
Or say Rs 208.60
Per Sqm
2 Providing BT patch work for pot holes of depth ranging from 25 to 35mm ,using 20-25mm HBG metal with
required quantity of 10-12 mm size HBG key chips and 80/100 grade bitumen at 45 kgs/1Cum of work for
filling the pot holes and sealing the filled up pot hole with a 15 mm thick layer using 10-12 mm HBG key
chips and 80/100 grade bitumen trimming the edges to provide vertical faces , cleaning applying tack
coat , filling the pot holes compacting with power Road Roller of 8 to 10 Tonnes finishing and blinding the
surface using stone dust/ sand , including cot of all materials T&P , and labour charges for all operations
etc. at site of complete
Unit - 1Sqm
Materials
Pot hole filling:
20-25mm HBG metal 1.00X1.00X0.030X1.15 0.033 Cum 1363.16 1 cum 44.98
10-12 mm size key chi0X1.00X0.03X(13/100) 0.0039 Cum 1025.66 1 cum 4.00
Stone dust / Sand 1.00X1.00X0.003 0.003 Cum 234.20 1 cum 0.70
80/100 Grade bitumen.00X0.055X80Kgs/Cum 2.160 Kgs 31598.50 1 MT 68.25
( Including tack coat )
Labour charges
Pot hole filling with 1.00X1.00X0.030 0.03 Cum 588.00 1 Cum 17.64
20-25mm HBG metal
Sealing the filled up 1.00X1.00X0.015 0.015 Cum 588.00 1 Cum 8.82
pot hole using 10-12
mm HBG metal.
Add 15% on labour charges 26.46 3.97
148.37

TOTAL Rs. 148.37


Or say Rs 148.40
Per Sqm

444755974.xls Page 3
Sl.
Description Qty Rate per Amount
No.

4 Stripping the excess soil from the shoulder shurface to achieve the approved level for sectioning the
berms, shoulders as per MORT&H specification No.3003 (As per E-in-C Circular Memo NO.Maintenance/
E.E(TEC) TA15/AE4/2005, dt.25/04/2005)

Unit = 1 Sqm
Taking out put of 100 Sqm and assuming average depth of stripping as 75mm, quantity of
earth cutting involved = 7.50 Cum

LABOUR
0.10 Nos of Mate 237.00 Each 23.70
2.50 Nos of Mazdoor 196.00 Each 490.00
Sundries for caution boards, tools for ramming etc., LS 0.40
TOTAL 514.10
4% Statutory taxes
TOTAL 514.10
Note :- The earth stripped from earthen Rate for 1 Sqm 5.14
shoulders to be dumped on the side slopes Or say 5.10
locally for disposal
1 Sqm
5 Making up loss of material/ irregularities on the shoulder to the design level by adding fress approved soil
and compacting with appropriate equipment as per MORT&H specification No.3003 (As per E-in-C Circular
Memo NO.Maintenance/ E.E(TEC) TA15/AE4/2005,
Unit = 1 Sqm
Taking out put of 100 Sqm and assuming average thickness of filling to be 100mm, quantity
of tresh material / earth involved = 15 Cum

Labour
0.18 Nos of Mate 237.00 Each 42.66
4.50 Nos of Mazdoor 196.00 Each 882.00
Machinery
0.25 Hours Excavator 1.0 Cum Bucket capacity @ 1950.00 Hour
60 Cum / 1 Hour

Tipper (L.S. towards having other amenities 24.00 t.Km 4.5/t.KM 108.00
complete & rounding off is average lead in
Km. For borrow earth) = 24 x L = (1 Km lead
is considred, Hence L=1)

Add 10% of cost of transportation to cover 108.00 10.80


cost of loading and un-loading

Sundries for caution boards, tools for LS 3.56


ramming etc.,
TOTAL 1047.02
4% Statutory taxes Add 4% TP
TOTAL 1047.02
Rate for 1 Sqm 10.47
Or say 10.50
1 Sqm
7 Earth work excavation and levelling of berms / Blindage /Filling scour portionswith all available soils like
red earth and hard gravelly soils with an extra 1 Km lead on initial lead and lift including breaking clods,
sectioning and tamping including all operational charges etc complete asper Morth specification for finished
item of work.

1.00 Cum rate as per SSR item 243 43.00 Cum 43.00
1.00 ADD seignorage charges 22.00 Cum 22.00
1.00 ADD 1 Km lead charges 21.50 Cum 21.50
TOTAL 86.50
Say Rs. 86.50
Cum
444755974.xls Page 4
Sl.
Description Qty Rate per Amount
No.

8 Clearing Juliflora (Prosafis) jungle including up-rooting and removing of Juliflora stumps including all labour
charges etc., complete for finished item of work.
1.00 Sqm rate as per SSR item 198 3.30 Sqm 3.30
TOTAL 3.30
Say Rs. 3.30
Sqm
9 Clearing of light / heavy / Scrub Jungle including all labour charges etc., complete for finished item of work.

1.00 Sqm rate as per SSR 196 2.00 Sqm 2.00


TOTAL 2.00
Say Rs. 2.00
Sqm

10 Collection and supply of good gravel and spreading irrespective of thickness including watering ,etc
including cost, seigniorage charges and conveyance of all materials to site including all leads and lifts and
labour charges and as directed by the Engineer-in-charge.

1.16 cum Cost of Gravel 92.10 cum 106.84


1.00 cum Spreading charges 23.00 cum 23.00
Total 129.84
Total Rate 129.84
Say Rs. 129.80 per cum

14 White washing to culverts in two coats with white cement and approved branch mixing with fevicol and
blue including cost and conveyance of all materials and all labour charges etc., complete for finished item
of work.

1.00 Sqm As per approved 9.75 Sqm 9.75


9.75
Total 9.75
Say Rs. 9.80
Sqm
15 White washing to guard stones in two coats with white cement and approved branch mixing with fevicol
and blue including cost and conveyance of all materials and all labour charges etc., complete for finished
item of work.
1.00 RM rate as per SSR 294 a1 6.50 RM 6.50
6.50
Total 6.50
Say Rs. 6.50
Each

444755974.xls Page 5
ROAD METAL RATES

NAME OF WORK ::- Name of the work: AM to Marical - Raikode road from Km. 0/0 to 22/400 for the year 2011-12

Deduct
Initial cost Machine
Lead in Blasting Seigniorage stacking Toal Cost
Sl.No Description of Metal Source of Supply
Kms
Conveyance less
charges
crushing
charges charges for per Cum
stacking charges
conveyance

A) FOR ROAD WORKS


60 to 63 mm IRC and MoRTH
1 4 48.80 349.45 70.00 0.00 50.00 -10.55 507.70
HBG metal

50 to 55 mm IRC and MoRTH


2 4 48.80 379.45 70.00 0.00 50.00 -10.55 537.70
HBG metal

40 to 45 mm IRC and MoRTH


3 do 4 48.80 489.45 70.00 0.00 50.00 -10.55 647.70
HBG metal

4 SS Revetment work 300mm do 4 48.80 84.45 67.00 0.00 50.00 -10.55 239.70

5 SS Revetment work 225mm do 4 48.80 87.45 67.00 0.00 50.00 -10.55 242.70

Quarry spall(Field picked


6 metal) do 4 48.80 -10.55 70.00 0.00 50.00 -10.55 147.70
Av. Of rate 25mm & 40mm

7 RR Masonry do 4 48.80 144.45 67.00 0.00 50.00 -10.55 299.70

8 CRS stone do 4 48.80 207.45 69.00 0.00 50.00 -10.55 364.70


150 mm soling stone
9 do 4 48.80 71.45 70.00 0.00 50.00 -10.55 229.70
HBG metal
40 to 45 mm IRC and MoRTH
10 25 229.40 489.45 70.00 122.36 50.00 -10.55 950.66
HBG M/C metal

25 to 27 mm IRC and MoRTH


11 do 25 229.40 819.45 70.00 204.86 50.00 -10.55 1363.16
HBG M/C metal

19 to 22 mm IRC and MoRTH


12 do 25 229.40 939.45 70.00 234.86 50.00 -10.55 1513.16
HBG M/C metal

12 to 14 mm IRC and MoRTH


13 do 25 229.40 679.45 70.00 169.86 50.00 -10.55 1188.16
HBG M/C metal
9.5 to 11.20 mm IRC and
14 MoRTH do 25 229.40 549.45 70.00 137.36 50.00 -10.55 1025.66
HBG M/C metal
5 to 7 mm IRC and MoRTH
15 do 25 229.40 419.45 70.00 104.86 50.00 -10.55 863.16
HBG M/C metal

2.36 to 5 mm IRC and MoRTH


16 do 25 229.40 249.45 70.00 62.36 50.00 -10.55 650.66
HBG M/C metal

HBG Stone chips 2.36mm


17 do 25 229.40 225.45 0.00 0.00 50.00 -10.55 494.30
and below

18 Gravel 2 30.20 45.20 0.00 0.00 22.00 -5.30 92.10

B) FOR C.D. WORKS


0

1 40 mm SS-5 HBG M/C metal 25 229.40 489.45 70.00 122.36 50.00 -10.55 950.66

2 25 mm SS-5 HBG M/C metal do 25 229.40 817.45 70.00 204.36 50.00 -10.55 1360.66

3 20 mm SS-5 HBG M/C metal do 25 229.40 833.45 70.00 208.36 50.00 -10.55 1380.66

4 12 mm SS-5 HBG M/C metal do 25 229.40 677.45 70.00 169.36 50.00 -10.55 1185.66

5 10 mm SS-5 HBG M/C metal do 25 229.40 549.45 70.00 137.36 50.00 -10.55 1025.66

6 6 mm SS-5 HBG M/C metal do 25 229.40 417.45 70.00 104.36 50.00 -10.55 860.66
Quarry @ 5/4 on AAA road
7 Sand for Mortar 14 134.80 214.70 0.00 0.00 40.00 -5.30 384.20

8 Sand for Filling do 14 134.80 64.70 0.00 0.00 40.00 -5.30 234.20
9 HYSD Steel 0.00 0.00 0.00 0.00

10 6mm Mild Steel 0.00 0.00 0.00 0.00

11 Mild Steel 0.00

12 Cement 0.00 0.00 0.00 0.00


RATE OF BITUMEN

Name of the work: AM to Marical - Raikode road from Km. 0/0 to 22/400 for the year
2011-12

Dt. 16.4.11
COST OF BITUMEN / MT Packed Packed Emulsion
(60/70) (80/100)
Initial cost (Ex. Chennai) 30859.07

Add C.S.T@ 2.00 % 0.00 617.18 0.00

Deduct loading -- --

Deduct Stacking -10.00 --

Deduct cost of Empty Emulsion Drums -- -1000.00 -1000.00

Total 0.00 30466.25 -1000.00

Lead from Madras

For bulk 647.00 Kms

For Emulsion 647.00 Kms

Lead charges @ 1.75 per KM 1132.25 1132.25

Total 31598.50 132.25

OR SAY 31599.00 133.00


FOR BITUMEN

to site
TOTAL
Or say
SSR 2010-11 SSR 2010-11
LEAD CHARGES Cost of Materials, Labour
Earth/Gravel/ Metal
Sand
loading 10.60 21.10 Material Rates
unloading 5.30 10.55 Roughstone 300mm (HBG)for revetment
stacking 5.30 10.55 Roughstone 225mm (HBG)for revetment
SS Revetment work 225mm
SS Revetment work 300mm
1 21.50 19.10 SS Revetment work 450mm
2 30.20 26.70 Laterite for Revetment 225mm
3 40.20 40.20 Laterite for Revetment 300mm
4 48.80 48.80 Jeddy stone above 450mm to 600mm
Quarry spall(Field picked metal)
5 57.40 57.40 Av. Of rate 25mm & 40mm
6 66.00 66.00 8.60 HBG Stone chips 2.36mm and below
7 74.60 74.60 2.36 to 5 mm IRC & MoRTH HBG M/C metal
8 83.20 83.20 5 to 7 mm IRC & MORTH HBG M/C metal
9 91.80 91.80 9.5 to 11.20 mm IRC & MoRTH HBG M/C metal
10 100.40 100.40 12 to 14 mm IRC & MoRTH HBG M/C metal
11 109.00 109.00 19 to 22 mm IRC & MoRTH HBG M/C metal
12 117.60 117.60 25 to 27 mm IRC & MoRTH HBG M/C metal
13 126.20 126.20 40 to 45 mm IRC & MoRTH HBG metal
14 134.80 134.80 50 to 55 mm IRC & MoRTH HBG metal
15 143.40 143.40 60 to 63 mm IRC & MoRTH HBG metal
16 152.00 152.00 65 mm IRC & MoRTH HBG metal
17 160.60 160.60 75 mm IRC & MoRTH HBG metal
18 169.20 169.20 RR masonry
19 177.80 177.80 CRS masonry
20 186.40 186.40 150 mm soling stone HBG metal
21 195.00 195.00 Gravel
22 203.60 203.60 6 mm SS-5 m/c HBG metal
23 212.20 212.20 10 mm SS-5 m/c HBG metal
24 220.80 220.80 12 mm SS-5 m/c HBG metal
25 229.40 229.40 20 mm SS-5 m/c HBG metal
26 238.00 238.00 25 mm SS-5 m/c HBG metal
27 246.60 246.60 40 mm SS-5 m/c HBG metal
28 255.20 255.20 50 mm SS-5 m/c HBG metal
29 263.80 263.80 60 mm SS-5 m/c HBG metal
30 272.40 272.40 7.20 65 mm SS-5 m/c HBG metal
31 279.60 279.60 75 mm SS-5 m/c HBG metal
32 286.80 286.80 75-100 mm SS-5 m/c HBG metal
33 294.00 294.00
34 301.20 301.20 Sand for Mortar
35 308.40 308.40 Sand for Filling
36 315.60 315.60 HYSD Steel
37 322.80 322.80 Mild Steel
38 330.00 330.00 Cement
39 337.20 337.20 Mild Steel 6mm
40 344.40 344.40 Blasting charges
41 351.60 351.60 Blasting charges
42 358.80 358.80 Blasting charges for rough stone
43 366.00 366.00 Seigniorage charges
44 373.20 373.20 Metal
45 380.40 380.40 Gravel/earth
46 387.60 387.60 Sand
47 394.80 394.80 Labour Rates
48 402.00 402.00 Mate
49 409.20 409.20 Mazdoor skilled, Mason
50 416.40 416.40 Mazdoor unskilled
51 423.60 423.60 Machinery Rates
52 430.80 430.80 1 Dozer( D 80 )
53 438.00 438.00
54 445.20 445.20
55 452.40 452.40 2 Mortor Grader
56 459.60 459.60
57 466.80 466.80
58 474.00 474.00
3 Hydraulic Excavator
59 481.20 481.20
60 488.40 488.40
61 495.60 495.60
4 Front end loader
62 502.80 502.80
63 510.00 510.00
5 Tipper- 5.5 Cum

64 517.20 517.20

65 524.40 524.40
66 531.60 531.60
6 Vibratory roller 8 tonne
67 538.80 538.80
68 546.00 546.00
7 Smooth wheeled roller 8 tonne

69 553.20 553.20
8 Water tanker 6 Kilolitre
70 560.40 560.40
71 567.60 567.60 9 Tractor
72 574.80 574.80 10 Tractor with rotavator
11 Tractor with ripper attachment

73 582.00 582.00
74 589.20 589.20
12 Air Compressor
75 596.40 596.40
76 603.60 603.60 13 Wet mix plant 60 TPH
14 Mechanical broom Hydraulic
77 610.80 610.80
15 Bitumen Pressure Distributor

78 618.00 618.00
79 625.20 625.20
16 Emulsion Pressure Distributor

80 632.40 632.40
17 Hot mix Plant – 120 TPH capacity

81 639.60 639.60
82 646.80 646.80
18 Hot mix Plant – 100 TPH capacity

83 654.00 654.00
84 661.20 661.20
19 Hot mix Plant – 60 TPH capacity

85 668.40 668.40
86 675.60 675.60
20 Hot mix Plant – 40 to 60 TPH capacity

87 682.80 682.80
88 690.00 690.00
21 Paver Finisher Hydrostatic with sensor
control 100 TPH

89 697.20 697.20
90 704.40 704.40
22 Paver finisher Mechanical 100

91 711.60 711.60
23 Hydraulic Chip Spreader
92 718.80 718.80
24 Tandem Road roller

93 726.00 726.00
25 Pneumatic Road roller

94 733.20 733.20
26 Pot-Hole repair machine
95 740.40 740.40
27 Bitumen boiler oil fired
96 747.60 747.60
97 754.80 754.80 28 GSB Plant 50 Cum
29 Mastic Cooker
98 762.00 762.00
30 Batching and Mixing Plant (a) 30 Cum
99 769.20 769.20 capacity
(b) 15 - 20 Cum capacity
100 776.40 776.40
31 Transit mixer

101 783.60 783.60


32 Concrete pump of 45 and 30 cum
102 790.80 790.80
103 798.00 798.00 33 Cranes
104 805.20 805.20 (a) 80 tonnes
105 812.40 812.40 (b) 35 tonnes
106 819.60 819.60 (c) 3 tonnes
(d)Crane with grab bucket 0.75 cum
107 826.80 826.80
(e)Crane with grab bucket 1 cum
108 834.00 834.00
34 Concrete bucket
109 841.20 841.20
110 848.40 848.40 35 Kerb casting machine
111 855.60 855.60 36
112 862.80 862.80 Concrete mixer
113 870.00 870.00
114 877.20 877.20 (a)0.28 cum
(b) 1.0 cum
115 884.40 884.40
37 Piling rig with bantonite pump

116 891.60 891.60


38 Concrete paver finisher with 40 HP motor

117 898.80 898.80


39 Integrated stone crusher
118 906.00 906.00

119 913.20 913.20


120 920.40 920.40 40
121 927.60 927.60 Pre stressing jack with pump and access
122 934.80 934.80
123 942.00 942.00 41 Generator
124 949.20 949.20 250 KVA
125 956.40 956.40 125 KVA
126 963.60 963.60 100 KVA
127 970.80 970.80 35 KVA
42 Pneumatic sinking of Plants
128 978.00 978.00
43 Truck 5.5 cum per 10 tonnes

129 985.20 985.20

130 992.40 992.40


131 999.60 999.60 44 Road marking machine
45 Mobile slurry seal equipment

132 1006.80 1006.80


46 Plate compacter

133 1014.00 1014.00


134 1021.20 1021.20 47 Drilling equipment
135 1028.40 1028.40
136 1035.60 1035.60
137 1042.80 1042.80
138 1050.00 1050.00
139 1057.20 1057.20
140 1064.40 1064.40
141 1071.60 1071.60
142 1078.80 1078.80
143 1086.00 1086.00
144 1093.20 1093.20
145 1100.40 1100.40
146 1107.60 1107.60
147 1114.80 1114.80
148 1122.00 1122.00
149 1129.20 1129.20
150 1136.40 1136.40
151 1143.60 1143.60
152 1150.80 1150.80
153 1158.00 1158.00
154 1165.20 1165.20
155 1172.40 1172.40
156 1179.60 1179.60
157 1186.80 1186.80
158 1194.00 1194.00
159 1201.20 1201.20
160 1208.40 1208.40
161 1215.60 1215.60
162 1222.80 1222.80
163 1230.00 1230.00
164 1237.20 1237.20
165 1244.40 1244.40
166 1251.60 1251.60
167 1258.80 1258.80
168 1266.00 1266.00
169 1273.20 1273.20
170 1280.40 1280.40
171 1287.60 1287.60
172 1294.80 1294.80
173 1302.00 1302.00
174 1309.20 1309.20
175 1316.40 1316.40
176 1323.60 1323.60
177 1330.80 1330.80
178 1338.00 1338.00
179 1345.20 1345.20
180 1352.40 1352.40
181 1359.60 1359.60
182 1366.80 1366.80
183 1374.00 1374.00
184 1381.20 1381.20
185 1388.40 1388.40
186 1395.60 1395.60
187 1402.80 1402.80
188 1410.00 1410.00
189 1417.20 1417.20
190 1424.40 1424.40
191 1431.60 1431.60
192 1438.80 1438.80
193 1446.00 1446.00
194 1453.20 1453.20
195 1460.40 1460.40
196 1467.60 1467.60
197 1474.80 1474.80
198 1482.00 1482.00
199 1489.20 1489.20
200 1496.40 1496.40
s, Labour

136.00
117.00
71.00
95.00
114.00
98.00
114.00
156.00

236.00
260.00
430.00
560.00
690.00
950.00
830.00
500.00
390.00
360.00
325.00
260.00
155.00
218.00
82.00
50.50
428.00
560.00
688.00
844.00
828.00
500.00
390.00
360.00
325.00
260.00
210.00

220.00
70.00
70.00
67.00

50.00
22.00
40.00

237.00
243.30 258
196.00

Spreading Per Hour


Cutting
Cleaning 1729.9
Clearing Per Hour
Spreading
GSB
WMM 2600
Soil Ordinary Per Hour

Soil Marshy
Soil unsuitable 1808.5
Soil loading Per Hour

Aggregate Per Hour 1320


loading
Transportation Per Hour
of soil,
GSB,WMM, Hot
mix etc 629.8
Per
tonne
Km 4.5
Per Km 45
Earth/Soil, GSB, Per Hour

WMM 1704.6
Soil compaction Per Hour
,BM compaction

746.5
Water transport Per Hour
345
Pulling Per Hour 345
Scarifying Per Hour 345
Scarifying Per Hour

345
General Per Hour
purpose 370
Wet mix Per Hour 1320
Surface Per Hour
cleaning 290
Applying Per Hour
bitumen tack
coat
940
Applying Per Hour
emulsion tack
coat 690
DBM/BM/SDC Per Hour

/Premix 23000
DBM/BM/SDC Per Hour

/Premix 19550
DBM/BM/SDC Per Hour

/Premix 17250
DBM/BM/SDC Per Hour

/Premix 15525
DBM/BM/SDC Per Hour

/Premix 2530
Paving of WMM, Per Hour
paving of DLC
1090
Surface Per Hour
dressing 2070
Rolling of Per Hour
Asphaltic
surface 1320
Rolling of Per Hour
Asphaltic
surface 1035
Repair of pot- Per Hour
holes 750
Bitumen Per Hour
Spraying 170
Producing GSB Per Hour 920
Mastic wearing Per Hour
coat 52
Concrete mixing Per Hour
2130
Concrete mixing Per Hour
1670
Transportation Per Hour
of concrete mix
1336.8
Pumping of Per Hour
Concrete 630

Lifting purpose Per Hour 950


630
280
Well foundation Per Hour
1725
Well foundation Per Hour
2875
For pouring Per Hour
concrete 12
Kerb making Per Hour 250
Concrete mixing Per Hour

345
Concrete mixing Per Hour
520
0.75 m dia to Per Hour
1.20 m dia
boring
attachment 4485
Paving of Per Hour
concrete
surface 2360
Crushing of Per Hour
spalls 100 TPH 7070
Stressing of
Crushing of Per Hour
steel wires/
spalls 200 TPH 14880
stands Per Hour

110

Generation of per hour 1550


electric energy per hour 1090
per hour 920
per hour 620
Pneumatic Per K.m.
sinking of wells 3740
Material Per Km.
transport
45
Material Per
transport tonne
per km 4.5
Road marking Per Hour 90
Mixing and Per Hour
laying slurry
seal 920
For compacting Per Hour
in medians
40
For drilling Per Hour 1035