SEAL DESIGN CALCULATION SHEET

CONTRACTOR: ASABEA ENGINEERING LIMITED


PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
JOB NO

ITEM DESCRIPTION VALUE RATE (L/sqm) COMMENT


Chipping
SIZE 14MM
TYPE Granite
ALD 8.8
TRAFFIC VOLUME V/L/D 300 - 2000 VEH/LANE/DAY
BASIC VOIDS FACTOR Vf From Fig 5.1 0.19

AJUSTMENT FACTOR CHIPPINGS


Chipping shape Va - Table 5.7 Flaky 0.01
Commercial Vehicles Vt - Table 5.8 15% - 30% -0.01
Climbing lane Vt - Table 5.8 -0.02

BASIC APPLICATION RATE


Design Voids Factor VF VF= Vf+Va+Vt 0.170
Stripping/Bleeding Check From Fig 5.1 OK
Basic Application Rate A A= ALD x VF 1.50

ALLOWANCES (Litres/sqm)
Existing surface size 14mm
Surface texture AT - Table 5.9 1.0mm 0.1
Absorption chippings ABA NA
Embedment AE - Fig 5.2
TOTAL ALLOWANCE 0.1
Other factors ADOPTED APPLICATION
RATE Litres/m2
DESIGN BINDER APPLICATION RATE(litres/sqm)
= A + AT + ABA + AE 1.60

*Check Final Rate does not exceed 2.5litres/sqm OK

DESIGN LOOSE SPREAD RATE m2/m3


Loose Spread Rate F* From Table 5.11 102
* Does not include stockpile waste
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 29TH JUNE, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 0+900 - 1+300 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2 2.1 3 3 10.10
4 Area 2x3 m2 800.00 840.00 1,200.00 1,200.00 4040.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,495.20 2,136.00 2,136.00 7191.20
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,644.72 2,349.60 2,349.60 7910.32
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 8,000 5,721 2,849 -798
13 Dip Sprayer Load at Finish Hot litres 5,721 2,849 -798 -4,900
14 Volume Sprayed Hot 12-13 litres 2,279 2,872 3,647 4,103 12900.28
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14*16 litres 2,054.02 2,588.06 3,286.43 3,697.23 11625.74
18 Spray Application Rate Cold 17 / 4 l/m2 2.568 3.081 2.739 3.081 2.87
19 Over or Under Sprayed Cold 18-6 l/m2 0.970 1.480 1.140 0.160
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.890 -1.400 -1.060 -0.080
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.64 10.91 10.91
26 Ordered Quantity 25+5% m3 7.63 8.02 11.46 11.46
27 Chippings Spread (Actual) m3 6.99 2.04 10.49 4.37 23.89
28 Over or Under Sprayed 27-25 m3 -0.28 -5.60 -0.42 -6.54
29 Actual Rate 4 / 27 m /m3
2
114.42 411.90 114.42 274.60 228.83
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 29TH JUNE, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 1+300 - 1+700 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2.3 2.3 2.2 3 9.80
4 Area 2x3 m2 920.00 920.00 880.00 1,200.00 3920.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.600 1.600 1.600 1.600
9 Volume Required Hot 8x4 litres 1,472.00 1,472.00 1,408.00 1,920.00 6272.00
10 Total Load Required Hot (Approx.) 9+10% litres 1,619.20 1,619.20 1,548.80 2,112.00 0.00
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 8,000 5,903 2,933 927
13 Dip Sprayer Load at Finish Hot litres 5,903 2,933 927 -1,808
14 Volume Sprayed Hot 12-13 litres 2,097 2,971 2,006 2,735 9808.17
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,889.70 2,677.07 1,807.54 2,464.82 8839.12
18 Spray Application Rate Cold 17 / 4 l/m2 2.054 2.910 2.054 2.054 2.27
19 Over or Under Sprayed Cold 18-6 l/m2 0.450 1.310 0.450 0.450
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.370 -1.230 -0.370 -0.370
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 8.36 8.36 8.00 10.91
26 Ordered Quantity 25+5% m3 8.78 8.78 8.40 11.46
27 Chippings Spread (Actual) m3 8.44 8.68 13.13 29.66 59.92
28 Over or Under Sprayed 27-25 m3 0.08 0.32 5.13 18.75
29 Actual Rate 4 / 27 m /m3
2
108.96 105.96 67.04 40.45 80.60
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 30TH JUNE, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 1+700 - 2+100 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2 2.3 3 2.3 9.60
4 Area 2x3 m2 800.00 920.00 1,200.00 920.00 3840.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,637.60 2,136.00 1,637.60 6835.20
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,801.36 2,349.60 1,801.36 7518.72
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 8,000 5,721 4,113 1,560
13 Dip Sprayer Load at Finish Hot litres 5,721 4,113 1,560 -1,235
14 Volume Sprayed Hot 12-13 litres 2,279 1,608 2,553 2,796 9235.33
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 2,054.02 1,448.77 2,300.50 2,519.59 8322.88
18 Spray Application Rate Cold 17 / 4 l/m2 2.568 1.575 1.917 2.739 2.20
19 Over or Under Sprayed Cold 18-6 l/m2 0.970 -0.030 0.320 1.140
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.890 0.050 -0.240 -1.060
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 140 140 140 140
25 Design Quantity 4 / 24 m3 5.71 6.57 8.57 6.57
26 Ordered Quantity 25+5% m3 6.00 6.90 9.00 6.90
27 Chippings Spread (Actual) m3 11.53 17.52 12.88 13.72 55.65
28 Over or Under Sprayed 27-25 m3 5.82 10.95 4.31 7.15
29 Actual Rate 4 / 27 m /m3
2
69.40 52.52 93.19 67.04 70.53
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 30TH JUNE, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 2+100-2+300 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2.2 2.4 3 3 10.60
4 Area 2x3 m2 880.00 960.00 1,200.00 1,200.00 4240.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,566.40 1,708.80 2,136.00 2,136.00 7547.20
10 Total Load Required Hot (Approx.) 9+10% litres 1,723.04 1,879.68 2,349.60 2,349.60 8301.92
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres -1,235 8,000 6,417 4,161
13 Dip Sprayer Load at Finish Hot litres -4,077 6,417 4,161 2,064
14 Volume Sprayed Hot 12-13 litres 2,841 1,583 2,256 2,097 8777.29
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 2,560.67 1,426.25 2,033.48 1,889.70 7910.09
18 Spray Application Rate Cold 17 / 4 l/m2 2.910 1.486 1.695 1.575 1.92
19 Over or Under Sprayed Cold 18-6 l/m2 1.310 -0.110 0.090 -0.030
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -1.230 -0.030 -0.010 0.050
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 8.00 8.73 10.91 10.91
26 Ordered Quantity 25+5% m3 8.40 9.17 11.46 11.46
27 Chippings Spread (Actual) m3 8.14 9.52 11.73 12.18 41.57
28 Over or Under Sprayed 27-25 m3 0.14 0.79 0.82 1.27
29 Actual Rate 4 / 27 m2/m3 108.06 100.81 102.30 98.55 102.43
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 1ST JULY, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 0+900 - 1+300 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2 2 3 2.4 9.40
4 Area 2x3 m2 800.00 800.00 1,200.00 960.00 3760.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 2,136.00 1,708.80 6692.80
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 2,349.60 1,879.68 7362.08
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 2,064 8,000 6,465 4,482
13 Dip Sprayer Load at Finish Hot litres 773 6,465 4,482 2,714
14 Volume Sprayed Hot 12-13 litres 1,292 1,535 1,983 1,769 6577.78
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,163.94 1,383.04 1,786.99 1,593.92 5927.89
18 Spray Application Rate Cold 17 / 4 l/m2 1.455 1.729 1.489 1.660 1.58
19 Over or Under Sprayed Cold 18-6 l/m2 -0.150 0.130 -0.110 0.060
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.070 -0.050 -0.030 0.020
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 10.91 8.73
26 Ordered Quantity 25+5% m3 7.63 7.63 11.46 9.17
27 Chippings Spread (Actual) m3 7.25 7.31 10.92 8.74 34.22
28 Over or Under Sprayed 27-25 m3 -0.02 0.04 0.01 0.01
29 Actual Rate 4 / 27 m /m3
2
110.32 109.51 109.84 109.84 109.88
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 1ST JULY, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 1+300 - 1+700 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2 2 2.5 3 9.50
4 Area 2x3 m2 800.00 800.00 1,000.00 1,200.00 3800.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 1,780.00 2,136.00 6764.00
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 1,958.00 2,349.60 7440.40
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 2,714 1,362 8,000 6,158
13 Dip Sprayer Load at Finish Hot litres 1,362 -21 6,158 3,970
14 Volume Sprayed Hot 12-13 litres 1,352 1,383 1,842 2,188 6765.14
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,218.45 1,246.10 1,660.33 1,971.86 6096.74
18 Spray Application Rate Cold 17 / 4 l/m2 1.523 1.558 1.660 1.643 1.60
19 Over or Under Sprayed Cold 18-6 l/m2 -0.080 -0.040 0.060 0.040
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.000 0.040 0.020 0.040
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 9.09 10.91
26 Ordered Quantity 25+5% m3 7.63 7.63 9.54 11.46
27 Chippings Spread (Actual) m3 7.77 7.50 9.10 11.19 35.57
28 Over or Under Sprayed 27-25 m3 0.50 0.23 0.01 0.28
29 Actual Rate 4 / 27 m /m3
2
102.98 106.61 109.84 107.20 106.66
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 2ND JULY, 2021


Contractor ASABEA ENGINEERING LIMITED
Location KM 1+700-1+985 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2 2 2.65 3 9.65
4 Area 2x3 m2 800.00 800.00 1,060.00 1,200.00 3860.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 1,886.80 2,136.00 6870.80
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 2,075.48 2,349.60 7557.88
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 3,970 2,634 8,000 6,361
13 Dip Sprayer Load at Finish Hot litres 2,634 1,160 6,361 4,237
14 Volume Sprayed Hot 12-13 litres 1,336 1,474 1,639 2,124 6572.58
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,203.69 1,328.26 1,476.91 1,914.34 5923.21
18 Spray Application Rate Cold 17 / 4 l/m2 1.505 1.660 1.393 1.595 1.54
19 Over or Under Sprayed Cold 18-6 l/m2 -0.100 0.060 1.558 1.558
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.020 0.020 -1.478 -1.478
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 9.64 10.91
26 Ordered Quantity 25+5% m3 7.63 7.63 10.12 11.46
27 Chippings Spread (Actual) m3 7.54 7.73 9.13 10.09 34.50
28 Over or Under Sprayed 27-25 m3 0.27 0.46 -0.51 -0.82
29 Actual Rate 4 / 27 m /m3
2
106.10 103.46 116.05 118.91 111.13
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 12TH JULY, 2021


Contractor ASABEA ENGINEERING LIMITED
Location KM 2+450 - 2+850 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 3.3 3.3 3.3 3 12.90
4 Area 2x3 m2 1,320.00 1,320.00 1,320.00 1,200.00 5160.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 2,349.60 2,349.60 2,349.60 2,136.00 9184.80
10 Total Load Required Hot (Approx.) 9+10% litres 2,584.56 2,584.56 2,584.56 2,349.60 10103.28
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 4,237 8,000 5,844 3,663
13 Dip Sprayer Load at Finish Hot litres 2,056 5,844 3,663 1,680
14 Volume Sprayed Hot 12-13 litres 2,181 2,156 2,181 1,983 8501.42
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,965.69 1,943.10 1,965.69 1,786.99 7661.48
18 Spray Application Rate Cold 17 / 4 l/m2 1.489 1.472 1.489 1.489 1.48
19 Over or Under Sprayed Cold 18-6 l/m2 -0.110 -0.130 -0.110 -0.110
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.030 -0.050 -0.030 -0.030
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 107 107 107
25 Design Quantity 4 / 24 m3 12.00 12.34 12.34 11.21
26 Ordered Quantity 25+5% m3 12.60 12.96 12.96 11.77
27 Chippings Spread (Actual) m3 13.98 12.54 11.69 11.86 50.07
28 Over or Under Sprayed 27-25 m3 1.98 0.20 -0.65 0.65
29 Actual Rate 4 / 27 m2/m3 94.39 105.26 112.96 101.19 103.45
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 12TH JULY, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 2+850 - 3+250 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2.1 2.5 2.5 2.5 9.60
4 Area 2x3 m2 840.00 1,000.00 1,000.00 1,000.00 3840.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,495.20 1,780.00 1,780.00 1,780.00 6835.20
10 Total Load Required Hot (Approx.) 9+10% litres 1,644.72 1,958.00 1,958.00 1,958.00 7518.72
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 1,680 8,000 6,120 4,391
13 Dip Sprayer Load at Finish Hot litres 196 6,120 4,391 2,644
14 Volume Sprayed Hot 12-13 litres 1,484 1,880 1,728 1,747 6839.89
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,337.17 1,694.56 1,557.63 1,574.75 6164.11
18 Spray Application Rate Cold 17 / 4 l/m2 1.592 1.695 1.558 1.575 1.60
19 Over or Under Sprayed Cold 18-6 l/m2 -0.010 0.090 -0.040 -0.030
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.070 -0.010 0.040 0.050
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.64 9.09 9.09 9.09
26 Ordered Quantity 25+5% m3 8.02 9.54 9.54 9.54
27 Chippings Spread (Actual) m3 7.61 9.57 9.21 9.25 35.65
28 Over or Under Sprayed 27-25 m3 -0.03 0.48 0.12 0.16
29 Actual Rate 4 / 27 m /m3
2
110.32 104.46 108.54 108.12 107.86
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 13TH JULY, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 3+250-3+650 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 2 2 2.2 2.3 8.50
4 Area 2x3 m2 800.00 800.00 880.00 920.00 3400.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 1,566.40 1,637.60 6052.00
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 1,723.04 1,801.36 6657.20
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 2,644 1,246 8,000 6,564
13 Dip Sprayer Load at Finish Hot litres 1,246 -274 6,564 4,904
14 Volume Sprayed Hot 12-13 litres 1,398 1,519 1,436 1,660 6013.19
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,259.80 1,369.34 1,293.94 1,496.01 5419.09
18 Spray Application Rate Cold 17 / 4 l/m2 1.575 1.712 1.470 1.626 1.60
19 Over or Under Sprayed Cold 18-6 l/m2 -0.030 0.110 -0.130 0.030
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.050 -0.030 -0.050 0.050
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 8.00 8.36
26 Ordered Quantity 25+5% m3 7.63 7.63 8.40 8.78
27 Chippings Spread (Actual) m3 8.18 6.99 8.36 8.23 31.76
28 Over or Under Sprayed 27-25 m3 0.91 -0.28 0.36 -0.13
29 Actual Rate 4 / 27 m /m3
2
97.77 114.48 105.26 111.80 107.33
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 14TH JULY, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 3+650-3+985 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 2 2 2 2.9 8.90
4 Area 2x3 m2 800.00 800.00 800.00 1,160.00 3560.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 1,424.00 2,064.80 6336.80
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 1,566.40 2,271.28 6970.48
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 4,904 3,552 2,154 8,000
13 Dip Sprayer Load at Finish Hot litres 3,552 2,154 771 5,841
14 Volume Sprayed Hot 12-13 litres 1,352 1,398 1,383 2,159 6292.12
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,218.72 1,259.80 1,246.10 1,945.84 5670.46
18 Spray Application Rate Cold 17 / 4 l/m2 1.523 1.575 1.558 1.677 1.58
19 Over or Under Sprayed Cold 18-6 l/m2 -0.080 -0.030 -0.040 0.080
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.000 0.050 0.040 0.000
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 7.27 10.55
26 Ordered Quantity 25+5% m3 7.63 7.63 7.63 11.08
27 Chippings Spread (Actual) m3 7.37 7.66 7.54 10.56 33.14
28 Over or Under Sprayed 27-25 m3 0.10 0.39 0.27 0.01
29 Actual Rate 4 / 27 m /m3
2
108.54 104.38 106.10 109.84 107.21
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 14TH JULY, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 2+450 - 2+850 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2 2 2 2.7 8.70
4 Area 2x3 m2 800.00 800.00 800.00 1,080.00 3480.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 1,424.00 1,922.40 6194.40
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 1,566.40 2,114.64 6813.84
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 5,841 4,473 3,121 1,632
13 Dip Sprayer Load at Finish Hot litres 4,473 3,121 1,632 -275
14 Volume Sprayed Hot 12-13 litres 1,368 1,352 1,489 1,908 6116.32
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,232.41 1,218.45 1,341.96 1,719.21 5512.03
18 Spray Application Rate Cold 17 / 4 l/m2 1.541 1.523 1.677 1.592 1.58
19 Over or Under Sprayed Cold 18-6 l/m2 -0.060 -0.080 0.080 -0.010
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.020 0.000 0.000 0.070
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 7.27 9.82
26 Ordered Quantity 25+5% m3 7.63 7.63 7.63 10.31
27 Chippings Spread (Actual) m3 7.23 7.46 7.54 9.94 32.17
28 Over or Under Sprayed 27-25 m3 -0.04 0.19 0.27 0.12
29 Actual Rate 4 / 27 m /m3
2
110.63 107.20 106.10 108.70 108.16
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 15TH JULY, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 2+850-3+250 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2.2 2.3 2.3 2.6 9.40
4 Area 2x3 m2 880.00 920.00 920.00 1,040.00 0.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 0.00 0.00 0.00 0.00 0.00
10 Total Load Required Hot (Approx.) 9+10% litres 0.00 0.00 0.00 0.00 0.00
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 8,000 6,462 4,926 3,249
13 Dip Sprayer Load at Finish Hot litres 6,462 4,926 3,249 1,333
14 Volume Sprayed Hot 12-13 litres 1,538 1,536 1,677 1,916 6667.25
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,385.78 1,384.25 1,511.76 1,726.74 6008.53
18 Spray Application Rate Cold 17 / 4 l/m2 1.575 1.505 1.643 1.660 1.60
19 Over or Under Sprayed Cold 18-6 l/m2 -0.030 -0.100 0.040 0.060
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.050 -0.020 0.040 0.020
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 8.00 8.36 8.36 9.45
26 Ordered Quantity 25+5% m3 8.40 8.78 8.78 9.92
27 Chippings Spread (Actual) m3 8.21 8.58 8.38 10.05 35.22
28 Over or Under Sprayed 27-25 m3 0.21 0.22 0.02 0.60
29 Actual Rate 4 / 27 m2/m3 107.20 107.20 109.84 103.46 106.92
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 15TH JULY, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 3+250 - 3+650 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 2 2 3 2.4 9.40
4 Area 2x3 m2 800.00 800.00 1,200.00 960.00 3760.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 2,136.00 1,708.80 6692.80
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 2,349.60 1,879.68 7362.08
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 1,333 8,000 6,587 4,467
13 Dip Sprayer Load at Finish Hot litres -20 6,587 4,467 2,808
14 Volume Sprayed Hot 12-13 litres 1,352 1,413 2,120 1,659 6544.35
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,218.72 1,273.49 1,910.24 1,495.32 5897.77
18 Spray Application Rate Cold 17 / 4 l/m2 1.523 1.592 1.592 1.558 1.57
19 Over or Under Sprayed Cold 18-6 l/m2 -0.080 -0.010 -0.010 -0.040
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.000 0.070 0.070 0.040
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 10.91 8.73
26 Ordered Quantity 25+5% m3 7.63 7.63 11.46 9.17
27 Chippings Spread (Actual) m3 8.16 7.31 11.48 9.28 36.22
28 Over or Under Sprayed 27-25 m3 0.89 0.04 0.57 0.55
29 Actual Rate 4 / 27 m /m3
2
98.07 109.51 104.56 103.46 103.90
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 23RD AUGUST, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 3+650 - 3+985 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 2 3 3 3 11.00
4 Area 2x3 m2 800.00 1,200.00 1,200.00 1,200.00 4400.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 2,136.00 2,136.00 2,136.00 7832.00
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 2,349.60 2,349.60 2,349.60 8615.20
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 2,808 8,000 5,880 3,875
13 Dip Sprayer Load at Finish Hot litres 1,486 5,880 3,875 1,937
14 Volume Sprayed Hot 12-13 litres 1,322 2,120 2,006 1,937 7384.62
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,191.33 1,910.24 1,807.54 1,745.91 6655.02
18 Spray Application Rate Cold 17 / 4 l/m2 1.489 1.592 1.506 1.455 1.51
19 Over or Under Sprayed Cold 18-6 l/m2 -0.110 -0.010 -0.090 -0.150
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.030 0.070 -0.010 -0.070
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 10.91 10.91 10.91
26 Ordered Quantity 25+5% m3 7.63 11.46 11.46 11.46
27 Chippings Spread (Actual) m3 7.46 11.96 11.11 11.14 41.67
28 Over or Under Sprayed 27-25 m3 0.19 1.05 0.20 0.23
29 Actual Rate 4 / 27 m2/m3 107.20 100.33 108.06 107.72 105.83
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 19TH AUGUST, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 12+252 - 12+652 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 3 3.2 3.5 3.3 13.00
4 Area 2x3 m2 1,200.00 1,280.00 1,400.00 1,320.00 5200.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 2,136.00 2,278.40 2,492.00 2,349.60 9256.00
10 Total Load Required Hot (Approx.) 9+10% litres 2,349.60 2,506.24 2,741.20 2,584.56 10181.60
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 1,937 8,000 5,763 3,157
13 Dip Sprayer Load at Finish Hot litres 23 5,763 3,157 1,079
14 Volume Sprayed Hot 12-13 litres 1,915 2,237 2,606 2,078 8835.55
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,725.37 2,015.68 2,348.43 1,873.12 7962.60
18 Spray Application Rate Cold 17 / 4 l/m2 1.438 1.575 1.677 1.419 1.53
19 Over or Under Sprayed Cold 18-6 l/m2 -0.160 -0.030 0.080 -0.180
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.080 0.050 0.000 -0.100
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 10.91 11.64 12.73 12.00
26 Ordered Quantity 25+5% m3 11.46 12.22 13.37 12.60
27 Chippings Spread (Actual) m3 11.73 12.80 12.95 12.54 50.01
28 Over or Under Sprayed 27-25 m3 0.82 1.16 0.22 0.54
29 Actual Rate 4 / 27 m /m3
2
102.30 100.03 108.12 105.26 103.93
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 23RD AUGUST, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 12+652 - 13+052 LEFT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 2.2 2.3 3 2.3 9.80
4 Area 2x3 m2 880.00 920.00 1,200.00 920.00 3920.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,566.40 1,637.60 2,136.00 1,637.60 6977.60
10 Total Load Required Hot (Approx.) 9+10% litres 1,723.04 1,801.36 2,349.60 1,801.36 7675.36
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 8,000 6,546 4,781 2,935
13 Dip Sprayer Load at Finish Hot litres 6,546 4,781 2,935 1,345
14 Volume Sprayed Hot 12-13 litres 1,454 1,765 1,846 1,590 6655.27
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,310.46 1,590.49 1,663.75 1,433.02 5997.73
18 Spray Application Rate Cold 17 / 4 l/m2 1.489 1.729 1.386 1.558 1.54
19 Over or Under Sprayed Cold 18-6 l/m2 -0.110 0.130 -0.210 -0.040
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.030 -0.050 -0.130 0.040
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 8.00 8.36 10.91 8.36
26 Ordered Quantity 25+5% m3 8.40 8.78 11.46 8.78
27 Chippings Spread (Actual) m3 7.95 8.51 12.18 8.79 37.43
28 Over or Under Sprayed 27-25 m3 -0.05 0.15 1.27 0.43
29 Actual Rate 4 / 27 m /m3
2
110.74 108.12 98.49 104.61 105.49
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 23RD AUGUST, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 13+052 - 13+412 LHS
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 2 2 2 1.5 7.50
4 Area 2x3 m2 800.00 800.00 800.00 600.00 3000.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 1,424.00 1,068.00 5340.00
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 1,566.40 1,174.80 5874.00
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 8,000 6,663 5,173 3,879
13 Dip Sprayer Load at Finish Hot litres 6,663 5,173 3,879 2,853
14 Volume Sprayed Hot 12-13 litres 1,337 1,490 1,294 1,026 5146.96
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,205.02 1,342.51 1,166.60 924.31 4638.44
18 Spray Application Rate Cold 17 / 4 l/m2 1.506 1.678 1.458 1.541 1.55
19 Over or Under Sprayed Cold 18-6 l/m2 -0.090 0.080 -0.140 -0.060
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 -0.010 0.000 -0.060 0.020
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 7.27 5.45
26 Ordered Quantity 25+5% m3 7.63 7.63 7.63 5.72
27 Chippings Spread (Actual) m3 6.97 7.60 6.73 5.61 26.90
28 Over or Under Sprayed 27-25 m3 -0.30 0.33 -0.54 0.16
29 Actual Rate 4 / 27 m /m3
2
114.86 105.26 118.91 107.03 111.51
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 25TH AUGUST, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 12+252 - 12+652 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 4 4 4 4 16.00
4 Area 2x3 m2 1,600.00 1,600.00 1,600.00 1,600.00 6400.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 2,848.00 2,848.00 2,848.00 2,848.00 11392.00
10 Total Load Required Hot (Approx.) 9+10% litres 3,132.80 3,132.80 3,132.80 3,132.80 12531.20
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 2,853 8,000 5,235 2,378
13 Dip Sprayer Load at Finish Hot litres 118 5,235 2,378 -406
14 Volume Sprayed Hot 12-13 litres 2,735 2,765 2,857 2,784 11140.74
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 2,464.82 2,492.21 2,574.37 2,508.64 10040.04
18 Spray Application Rate Cold 17 / 4 l/m2 1.541 1.558 1.609 1.568 1.57
19 Over or Under Sprayed Cold 18-6 l/m2 -0.060 -0.040 0.010 -0.030
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.020 0.040 0.070 0.050
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 14.55 14.55 14.55 14.55
26 Ordered Quantity 25+5% m3 15.28 15.28 15.28 15.28
27 Chippings Spread (Actual) m3 16.77 15.54 17.65 15.09 65.04
28 Over or Under Sprayed 27-25 m3 2.22 0.99 3.10 0.54
29 Actual Rate 4 / 27 m /m3
2
95.43 102.98 90.65 106.06 98.78
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 25TH AUGUST, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 12+652 - 13+052 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 2.1 2.2 2.3 2.3 8.90
4 Area 2x3 m2 840.00 880.00 920.00 920.00 3560.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,495.20 1,566.40 1,637.60 1,637.60 6336.80
10 Total Load Required Hot (Approx.) 9+10% litres 1,644.72 1,723.04 1,801.36 1,801.36 6970.48
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 8,000 6,548 5,010 3,333
13 Dip Sprayer Load at Finish Hot litres 6,548 5,010 3,333 1,743
14 Volume Sprayed Hot 12-13 litres 1,452 1,538 1,677 1,590 6257.17
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,308.41 1,385.78 1,511.76 1,433.02 5638.96
18 Spray Application Rate Cold 17 / 4 l/m2 1.558 1.575 1.643 1.558 1.58
19 Over or Under Sprayed Cold 18-6 l/m2 -0.040 -0.030 0.040 -0.040
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.040 0.050 0.040 0.040
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.64 8.00 8.36 8.36
26 Ordered Quantity 25+5% m3 8.02 8.40 8.78 8.78
27 Chippings Spread (Actual) m3 7.82 8.19 9.99 8.61 34.61
28 Over or Under Sprayed 27-25 m3 0.18 0.19 1.63 0.25
29 Actual Rate 4 / 27 m2/m3 107.44 107.47 92.11 106.84 103.46
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 26TH AUGUST, 2021.


Contractor ASABEA ENGINEERING LIMITED
Location KM 13+052 - 13+412 RIGHT DUAL CARRIAGE
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400.00 400.00 400.00 400.00
3 Width m 2 2.4 2.4 3 9.80
4 Area 2x3 m2 800.00 960.00 960.00 1,200.00 3920.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,708.80 1,708.80 2,136.00 6977.60
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,879.68 1,879.68 2,349.60 7675.36
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 1,743 8,000 6,250 4,572
13 Dip Sprayer Load at Finish Hot litres 269 6,250 4,572 2,544
14 Volume Sprayed Hot 12-13 litres 1,474 1,750 1,677 2,028 6930.29
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14x16 litres 1,328.26 1,577.49 1,511.76 1,828.08 6245.58
18 Spray Application Rate Cold 17 / 4 l/m2 1.660 1.643 1.575 1.523 1.60
19 Over or Under Sprayed Cold 18-6 l/m2 0.060 0.040 -0.030 -0.080
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.020 0.040 0.050 0.000
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 8.73 8.73 10.91
26 Ordered Quantity 25+5% m3 7.63 9.17 9.17 11.46
27 Chippings Spread (Actual) m3 8.13 9.33 9.05 #VALUE! #VALUE!
28 Over or Under Sprayed 27-25 m3 0.86 0.60 0.32 #VALUE!
29 Actual Rate 4 / 27 m2/m3 98.40 102.86 106.10 #VALUE! #VALUE!
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)
LOCATION: OYOKO-BANKO
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 0+900 - 1+300 LEFT DUAL CARRIAGE
DATE 29TH JUNE 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.550 1.600
2 WEIGHT OF TRAY kg 1.300 1.300 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.200 0.250 0.300
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.205 0.256 0.308
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 2.279 2.849 3.419
8 RATE OF APPLICATION (HOT TO COLD) l/m3 2.054 2.568 3.081
9 AVERAGE RATE l/m2 2.568

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.6 1.6 1.6
Weight of Tray + Chippings (F) kg 2.5 2.8 2.8

Weight of Chippings ( C = F-E ) kg 0.9 1.2 1.2

Application rate (kg/m²) D=C/B 10.00 13.33 13.33


Application rate (m²/mᶟ) = A/D 137.30 102.98 102.98
AVERAGE RATE 114.42

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 0+900 - 1+300 LEFT DUAL CARRIAGE
DATE 29TH JUNE 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.500 1.500
2 WEIGHT OF TRAY kg 1.200 1.200 1.200
3 WEIGHT OF BITUMEN (1-2) kg 0.300 0.300 0.300
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.308 0.308 0.308
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 3.419 3.419 3.419
8 RATE OF APPLICATION (HOT TO COLD) l/m3 3.081 3.081 3.081
9 AVERAGE RATE l/m2 3.081

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA KIA K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 1.5 1.5 1.5

Weight of Chippings ( C = F-E ) kg 0.3 0.3 0.3

Application rate (kg/m²) D=C/B 3.33 3.33 3.33


Application rate (m²/mᶟ) = A/D 411.90 411.90 411.90
AVERAGE RATE 411.90

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

LOCATION: OYOKO-BANKO
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 0+900 - 1+300 LEFT DUAL CARRIAGE
DATE 29TH JUNE 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.600 1.650
2 WEIGHT OF TRAY kg 1.250 1.300 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.250 0.300 0.250
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.256 0.308 0.256
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 2.849 3.419 2.849
8 RATE OF APPLICATION (HOT TO COLD) l/m3 2.568 3.081 2.568
8 AVERAGE RATE l/m2 2.739

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.6 1.6 1.6
Weight of Tray + Chippings (F) kg 2.5 2.8 2.8

Weight of Chippings ( C = F-E ) kg 0.9 1.2 1.2

Application rate (kg/m²) D=C/B 10.00 13.33 13.33


Application rate (m²/mᶟ) = A/D 137.30 102.98 102.98
AVERAGE RATE 114.42

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

LOCATION: OYOKO-BANKO

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 0+900 - 1+300 LEFT DUAL CARRIAGE
DATE 29TH JUNE 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.550 1.600 1.600
2 WEIGHT OF TRAY kg 1.250 1.300 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.300 0.300 0.300
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.308 0.308 0.308
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 3.419 3.419 3.419
8 RATE OF APPLICATION (HOT TO COLD) l/m3 3.081 3.081 3.081
9 AVERAGE RATE l/m2 3.081

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 1.5 1.6 2.4
98
Weight of Chippings ( C = F-E ) kg 0.3 0.4 1.2

Application rate (kg/m²) D=C/B 3.33 4.44 13.33


Application rate (m²/mᶟ) = A/D 411.90 308.93 102.98
AVERAGE RATE 274.60

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+300 - 1+700 LEFT DUAL CARRIAGE
DATE 29TH JUNE 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.450 1.500 1.300
2 WEIGHT OF TRAY kg 1.250 1.200 1.200
3 WEIGHT OF BITUMEN (1-2) kg 0.200 0.300 0.100
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.205 0.308 0.103
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 2.279 3.419 1.140
8 RATE OF APPLICATION (HOT TO COLD) l/m3 2.054 3.081 1.027
9 AVERAGE RATE l/m2 2.054

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.8 2.3 2.1

Weight of Chippings ( C = F-E ) kg 1.6 1.1 0.9

Application rate (kg/m²) D=C/B 17.78 12.22 10.00


Application rate (m²/mᶟ) = A/D 77.23 112.34 137.30
AVERAGE RATE 108.96

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)
LOCATION: OYOKO-BANKO
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+300 - 1+700 LEFT DUAL CARRIAGE
DATE 29TH JUNE,2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.600 1.900 2.050
2 WEIGHT OF TRAY kg 1.300 1.600 1.800
3 WEIGHT OF BITUMEN (1-2) kg 0.300 0.300 0.250
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.308 0.308 0.256
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 3.419 3.419 2.849
8 RATE OF APPLICATION (HOT TO COLD) l/m3 3.081 3.081 2.568
9 AVERAGE RATE l/m2 2.910

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 1.9 3 2.9

Weight of Chippings ( C = F-E ) kg 0.7 1.8 1.7

Application rate (kg/m²) D=C/B 7.78 20.00 18.89


Application rate (m²/mᶟ) = A/D 176.53 68.65 72.69
AVERAGE RATE 105.96

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+300 - 1+700 LEFT DUAL CARRIAGE
DATE 29TH JUNE,2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.450 1.500 1.300
2 WEIGHT OF TRAY kg 1.250 1.200 1.200
3 WEIGHT OF BITUMEN (1-2) kg 0.200 0.300 0.100
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.205 0.308 0.103
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 2.279 3.419 1.140
8 RATE OF APPLICATION (HOT TO COLD) l/m3 2.054 3.081 1.027
9 AVERAGE RATE l/m2 2.054

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 3.4 2.9 3.2

Weight of Chippings ( C = F-E ) kg 2.1 1.6 1.9

Application rate (kg/m²) D=C/B 23.33 17.78 21.11


Application rate (m²/mᶟ) = A/D 58.84 77.23 65.04
AVERAGE RATE 67.04

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

LOCATION: OYOKO-BANKO
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+300 - 1+700 LEFT DUAL CARRIAGE
DATE 29TH JUNE, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.450 1.500 1.300
2 WEIGHT OF TRAY kg 1.250 1.200 1.200
3 WEIGHT OF BITUMEN (1-2) kg 0.200 0.300 0.100
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.205 0.308 0.103
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 2.279 3.419 1.140
8 RATE OF APPLICATION (HOT TO COLD) l/m3 2.054 3.081 1.027
9 AVERAGE RATE l/m2 2.054

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 4.5 4.5 4.1

Weight of Chippings ( C = F-E ) kg 3.2 3.2 2.8

Application rate (kg/m²) D=C/B 35.56 35.56 31.11


Application rate (m²/mᶟ) = A/D 38.62 38.62 44.13
AVERAGE RATE 40.45

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

LOCATION: OYOKO-BANKO
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+700 - 2+100 LEFT DUAL CARRIAGE
DATE 30TH JUNE, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 2
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.450 1.600 1.350
2 WEIGHT OF TRAY kg 1.250 1.200 1.200
3 WEIGHT OF BITUMEN (1-2) kg 0.200 0.400 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.205 0.410 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 2.279 4.558 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 2.054 4.108 1.541
9 AVERAGE RATE l/m2 2.568

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 2.5 3.7 3.6

Weight of Chippings ( C = F-E ) kg 1.2 2.4 2.3

Application rate (kg/m²) D=C/B 13.33 26.67 25.56


Application rate (m²/mᶟ) = A/D 102.98 51.49 53.73
AVERAGE RATE 69.40

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

LOCATION: OYOKO-BANKO

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+700 - 2+100 LEFT DUAL CARRIAGE
DATE 30TH JUNE, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 2
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.470 1.500 1.600
2 WEIGHT OF TRAY kg 1.300 1.355 1.455
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.145 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.149 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.652 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.489 1.489
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 3.8 2.9 5.3

Weight of Chippings ( C = F-E ) kg 2.5 1.6 4

Application rate (kg/m²) D=C/B 27.78 17.78 44.44


Application rate (m²/mᶟ) = A/D 49.43 77.23 30.89
AVERAGE RATE 52.52

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+700 - 2+100 LEFT DUAL CARRIAGE
DATE 30TH JUNE, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.600 1.520 1.410
2 WEIGHT OF TRAY kg 1.355 1.345 1.270
3 WEIGHT OF BITUMEN (1-2) kg 0.245 0.175 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.251 0.179 0.144
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 2.792 1.994 1.595
8 RATE OF APPLICATION (HOT TO COLD) l/m3 2.516 1.797 1.438
9 AVERAGE RATE l/m2 1.917

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 2.2 2.9 3.2

Weight of Chippings ( C = F-E ) kg 0.9 1.6 1.9

Application rate (kg/m²) D=C/B 10.00 17.78 21.11


Application rate (m²/mᶟ) = A/D 137.30 77.23 65.04
AVERAGE RATE 93.19

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+700 - 2+100 LEFT DUAL CARRIAGE
DATE 30TH JUNE, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.600 1.650
2 WEIGHT OF TRAY kg 1.250 1.300 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.250 0.300 0.250
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.256 0.308 0.256
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 2.849 3.419 2.849
8 RATE OF APPLICATION (HOT TO COLD) l/m3 2.568 3.081 2.568
9 AVERAGE RATE l/m2 2.739

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 3.4 2.9 3.2

Weight of Chippings ( C = F-E ) kg 2.1 1.6 1.9

Application rate (kg/m²) D=C/B 23.33 17.78 21.11


Application rate (m²/mᶟ) = A/D 58.84 77.23 65.04
AVERAGE RATE 67.04

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF OYOKO-BANKO ROAD (8.2KM)

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+100 - 2+300 LEFT DUAL CARRIAGE
DATE 30TH JUNE, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.600 1.900 2.050
2 WEIGHT OF TRAY kg 1.300 1.600 1.800
3 WEIGHT OF BITUMEN (1-2) kg 0.300 0.300 0.250
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.308 0.308 0.256
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 3.419 3.419 2.849
8 RATE OF APPLICATION (HOT TO COLD) l/m3 3.081 3.081 2.568
9 AVERAGE RATE l/m2 2.910

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.6 2.3 2.2

Weight of Chippings ( C = F-E ) kg 1.4 1.1 1

Application rate (kg/m²) D=C/B 15.56 12.22 11.11


Application rate (m²/mᶟ) = A/D 88.26 112.34 123.57
AVERAGE RATE 108.06

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+100 - 2+300 LEFT DUAL CARRIAGE
DATE 30TH JUNE, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.450 1.600
2 WEIGHT OF TRAY kg 1.250 1.300 1.450
3 WEIGHT OF BITUMEN (1-2) kg 0.150 0.150 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 1.030 1.030
5 VOLUME OF BITUMEN (3/SG) litres 0.154 0.146 0.146
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.709 1.618 1.618
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.541 1.458 1.458
9 AVERAGE RATE l/m2 1.486

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.5 2.3 2.5

Weight of Chippings ( C = F-E ) kg 1.3 1.1 1.3

Application rate (kg/m²) D=C/B 14.44 12.22 14.44


Application rate (m²/mᶟ) = A/D 95.05 112.34 95.05
AVERAGE RATE 100.81

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+100 - 2+300 LEFT DUAL CARRIAGE
DATE 30TH JUNE, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.455 1.410 1.430
2 WEIGHT OF TRAY kg 1.290 1.250 1.260
3 WEIGHT OF BITUMEN (1-2) kg 0.165 0.160 0.170
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.169 0.164 0.174
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.880 1.823 1.937
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.695 1.643 1.746
9 AVERAGE RATE l/m2 1.695

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.6 2.5

Weight of Chippings ( C = F-E ) kg 1 1.4 1.3

Application rate (kg/m²) D=C/B 11.11 15.56 14.44


Application rate (m²/mᶟ) = A/D 123.57 88.26 95.05
AVERAGE RATE 102.30

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+100 - 2+300 LEFT DUAL CARRIAGE

DATE 30TH JUNE,2021


Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.415 1.385 1.400
2 WEIGHT OF TRAY kg 1.240 1.250 1.250
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.135 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.138 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.538 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.386 1.541
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.3 2.6 2.5

Weight of Chippings ( C = F-E ) kg 1.1 1.4 1.3

Application rate (kg/m²) D=C/B 12.22 15.56 14.44


Application rate (m²/mᶟ) = A/D 112.34 88.26 95.05
AVERAGE RATE 98.55

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 0+900 - 1+300 RIGHT DUAL CARRIAGE
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.350 1.480 1.500
2 WEIGHT OF TRAY kg 1.200 1.350 1.355
3 WEIGHT OF BITUMEN (1-2) kg 0.150 0.130 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.154 0.133 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.709 1.481 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.541 1.335 1.489
9 AVERAGE RATE l/m2 1.455

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.3 2.5 2.2

Weight of Chippings ( C = F-E ) kg 1.1 1.3 1

Application rate (kg/m²) D=C/B 12.22 14.44 11.11


Application rate (m²/mᶟ) = A/D 112.34 95.05 123.57
AVERAGE RATE 110.32

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 0+900 - 1+300 RIGHT DUAL CARRIAGE
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.415 1.520 1.560
2 WEIGHT OF TRAY kg 1.250 1.350 1.390
3 WEIGHT OF BITUMEN (1-2) kg 0.165 0.170 0.170
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.169 0.174 0.174
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.880 1.937 1.937
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.695 1.746 1.746
9 AVERAGE RATE l/m2 1.729

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.6 2.1

Weight of Chippings ( C = F-E ) kg 1.2 1.4 0.9

Application rate (kg/m²) D=C/B 13.33 15.56 10.00


Application rate (m²/mᶟ) = A/D 102.98 88.26 137.30
AVERAGE RATE 109.51

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 0+900 - 1+300 RIGHT DUAL CARRIAGE
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.425 1.580 1.435
2 WEIGHT OF TRAY kg 1.265 1.450 1.290
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.130 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.133 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.481 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.335 1.489
9 AVERAGE RATE l/m2 1.489

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.1 2.2 3

Weight of Chippings ( C = F-E ) kg 0.9 1 1.8

Application rate (kg/m²) D=C/B 10.00 11.11 20.00


Application rate (m²/mᶟ) = A/D 137.30 123.57 68.65
AVERAGE RATE 109.84

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)
LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 0+900 - 1+300 RIGHT DUAL CARRIAGE
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.455 1.470
2 WEIGHT OF TRAY kg 1.240 1.300 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.155 0.170
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.159 0.174
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.766 1.937
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.592 1.746
9 AVERAGE RATE l/m2 1.660

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.2 2.2

Weight of Chippings ( C = F-E ) kg 1 1.5 1

Application rate (kg/m²) D=C/B 11.11 16.67 11.11


Application rate (m²/mᶟ) = A/D 123.57 82.38 123.57
AVERAGE RATE 109.84

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)
LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+300 - 1+700 RIGHT DUAL CARRIAGE
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.390 1.550 1.540
2 WEIGHT OF TRAY kg 1.260 1.350 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.130 0.200 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 1.030 1.030 1.030
5 VOLUME OF BITUMEN (3/SG) litres 0.126 0.194 0.136
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.402 2.157 1.510
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.264 1.944 1.361
9 AVERAGE RATE l/m2 1.523

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.7 2.21

Weight of Chippings ( C = F-E ) kg 1 1.5 1.2

Application rate (kg/m²) D=C/B 11.11 16.67 13.33


Application rate (m²/mᶟ) = A/D 123.57 82.38 102.98
AVERAGE RATE 102.98

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+300 - 1+700 RIGHT DUAL CARRIAGE
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.485 1.600
2 WEIGHT OF TRAY kg 1.325 1.350 1.455
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.135 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.138 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.538 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.386 1.489
9 AVERAGE RATE l/m2 1.558

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA KIA K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 2.3 2.3 3

Weight of Chippings ( C = F-E ) kg 1 1 1.7

Application rate (kg/m²) D=C/B 11.11 11.11 18.89


Application rate (m²/mᶟ) = A/D 123.57 123.57 72.69
AVERAGE RATE 106.61

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+300 - 1+700 RIGHT DUAL CARRIAGE
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.420 1.515 1.530
2 WEIGHT OF TRAY kg 1.285 1.340 1.355
3 WEIGHT OF BITUMEN (1-2) kg 0.135 0.175 0.175
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.138 0.179 0.179
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.538 1.994 1.994
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.386 1.797 1.797
9 AVERAGE RATE l/m2 1.660

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.4 2.4

Weight of Chippings ( C = F-E ) kg 1 1.2 1.2

Application rate (kg/m²) D=C/B 11.11 13.33 13.33


Application rate (m²/mᶟ) = A/D 123.57 102.98 102.98
AVERAGE RATE 109.84

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

LOCATION: KWADASO-TRABUOM

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+300 - 1+700 RIGHT DUAL CARRIAGE
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.415 1.450 1.485
2 WEIGHT OF TRAY kg 1.240 1.290 1.340
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.160 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.164 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.823 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.643 1.489
9 AVERAGE RATE l/m2 1.643

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.5 2.4 2.2

Weight of Chippings ( C = F-E ) kg 1.3 1.2 1

Application rate (kg/m²) D=C/B 14.44 13.33 11.11


Application rate (m²/mᶟ) = A/D 95.05 102.98 123.57
AVERAGE RATE 107.20

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (8.2KM)

LOCATION: KWADASO-TRABUOM

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+700 - 1+985 RIGHT DUAL CARRIAGE
DATE 2ND JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.365 1.400 1.500
2 WEIGHT OF TRAY kg 1.200 1.250 1.360
3 WEIGHT OF BITUMEN (1-2) kg 0.165 0.150 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 1.030 1.030
5 VOLUME OF BITUMEN (3/SG) litres 0.169 0.146 0.136
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.880 1.618 1.510
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.695 1.458 1.361
9 AVERAGE RATE l/m2 1.505

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.3 2.4 2.4

Weight of Chippings ( C = F-E ) kg 1.1 1.2 1.2

Application rate (kg/m²) D=C/B 12.22 13.33 13.33


Application rate (m²/mᶟ) = A/D 112.34 102.98 102.98
AVERAGE RATE 106.10

Prepared by: Checked by: Approved by:


EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH
Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+700 - 1+985 RIGHT DUAL CARRIAGE
DATE 2ND JULY, 2021.
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.560 1.450
2 WEIGHT OF TRAY kg 1.225 1.400 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.160 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.164 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.823 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.643 1.541
9 AVERAGE RATE l/m2 1.660

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.2 2.3

Weight of Chippings ( C = F-E ) kg 1.2 1.3 1.1

Application rate (kg/m²) D=C/B 13.33 14.44 12.22


Application rate (m²/mᶟ) = A/D 102.98 95.05 112.34
AVERAGE RATE 103.46

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+700 - 1+985 RIGHT DUAL CARRIAGE
DATE 2ND JULY, 2021.
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.302 1.365 1.410
2 WEIGHT OF TRAY kg 1.150 1.240 1.280
3 WEIGHT OF BITUMEN (1-2) kg 0.152 0.125 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.156 0.128 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.732 1.425 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.561 1.284 1.335
9 AVERAGE RATE l/m2 1.393

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA KIA K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 1.9 3 2.4

Weight of Chippings ( C = F-E ) kg 0.7 1.8 1.2

Application rate (kg/m²) D=C/B 7.78 20.00 13.33


Application rate (m²/mᶟ) = A/D 176.53 68.65 102.98
AVERAGE RATE 116.05

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 1+700 - 1+985 RIGHT DUAL CARRIAGE
DATE 2ND JULY, 2021.
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.401 1.510 1.455
2 WEIGHT OF TRAY kg 1.250 1.350 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.151 0.160 0.155
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.155 0.164 0.159
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.721 1.823 1.766
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.551 1.643 1.592
8 AVERAGE RATE l/m2 1.595

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.8 1.9

Weight of Chippings ( C = F-E ) kg 1.2 1.6 0.7

Application rate (kg/m²) D=C/B 13.33 17.78 7.78


Application rate (m²/mᶟ) = A/D 102.98 77.23 176.53
AVERAGE RATE 118.91

Prepared by: Checked by: Approved by:

CONTRACTOR NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+450 - 2+850 LEFT DUAL CARRIAGE
DATE 12TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.380 1.445 1.430
2 WEIGHT OF TRAY kg 1.240 1.280 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.140 0.165 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.144 0.169 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.595 1.880 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.438 1.695 1.335
9 AVERAGE RATE l/m2 1.489

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 3 2.1 2.8

Weight of Chippings ( C = F-E ) kg 1.8 0.9 1.6

Application rate (kg/m²) D=C/B 20.00 10.00 17.78


Application rate (m²/mᶟ) = A/D 68.65 137.30 77.23
AVERAGE RATE 94.39

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+450 - 2+850 LEFT DUAL CARRIAGE
DATE 12TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.520 1.520 1.610
2 WEIGHT OF TRAY kg 1.380 1.390 1.450
3 WEIGHT OF BITUMEN (1-2) kg 0.140 0.130 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.144 0.133 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.595 1.481 1.823
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.438 1.335 1.643
9 AVERAGE RATE l/m2 1.472

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 3 2.2

Weight of Chippings ( C = F-E ) kg 1 1.8 1

Application rate (kg/m²) D=C/B 11.11 20.00 11.11


Application rate (m²/mᶟ) = A/D 123.57 68.65 123.57
AVERAGE RATE 105.26

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+450 - 2+850 LEFT DUAL CARRIAGE
DATE 12TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.415 1.420 1.500
2 WEIGHT OF TRAY kg 1.250 1.300 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.165 0.120 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.169 0.123 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.880 1.368 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.695 1.232 1.541
9 AVERAGE RATE l/m2 1.489

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.3 2.2

Weight of Chippings ( C = F-E ) kg 1.2 1.1 1

Application rate (kg/m²) D=C/B 13.33 12.22 11.11


Application rate (m²/mᶟ) = A/D 102.98 112.34 123.57
AVERAGE RATE 112.96

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+450 - 2+850 LEFT DUAL CARRIAGE
DATE 12TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.455 1.510 1.530
2 WEIGHT OF TRAY kg 1.310 1.350 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.145 0.160 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.149 0.164 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.652 1.823 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.489 1.643 1.335
9 AVERAGE RATE l/m2 1.489

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.3 2.4 2.6

Weight of Chippings ( C = F-E ) kg 1.1 1.2 1.4

Application rate (kg/m²) D=C/B 12.22 13.33 15.56


Application rate (m²/mᶟ) = A/D 112.34 102.98 88.26
AVERAGE RATE 101.19

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+850 - 3+250 LEFT DUAL CARRIAGE
DATE 12TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.355 1.400 1.600
2 WEIGHT OF TRAY kg 1.200 1.250 1.440
3 WEIGHT OF BITUMEN (1-2) kg 0.155 0.150 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.159 0.154 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.766 1.709 1.823
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.592 1.541 1.643
9 AVERAGE RATE l/m2 1.592

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.5 2.3

Weight of Chippings ( C = F-E ) kg 1 1.3 1.1

Application rate (kg/m²) D=C/B 11.11 14.44 12.22


Application rate (m²/mᶟ) = A/D 123.57 95.05 112.34
AVERAGE RATE 110.32

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+850 - 3+250 LEFT DUAL CARRIAGE
DATE 12TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 2
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.530 1.400 1.520
2 WEIGHT OF TRAY kg 1.360 1.250 1.345
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.150 0.175
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.154 0.179
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.709 1.994
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.541 1.797
9 AVERAGE RATE l/m2 1.695

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2 1.575
Weight of Tray + Chippings (F) kg 2.2 2.22 3

Weight of Chippings ( C = F-E ) kg 1 1.02 1.8

Application rate (kg/m²) D=C/B 11.11 11.33 20.00


Application rate (m²/mᶟ) = A/D 123.57 121.15 68.65
AVERAGE RATE 104.46

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+850 - 3+250 LEFT DUAL CARRIAGE
DATE 12TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 2
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.485 1.420 1.355
2 WEIGHT OF TRAY kg 1.350 1.255 1.2
3 WEIGHT OF BITUMEN (1-2) kg 0.135 0.165 0.155
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.138 0.169 0.159
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.538 1.880 1.766
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.386 1.695 1.592
9 AVERAGE RATE l/m2 1.558

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.8 2.2 2.19

Weight of Chippings ( C = F-E ) kg 1.6 1 0.99

Application rate (kg/m²) D=C/B 17.78 11.11 11.00


Application rate (m²/mᶟ) = A/D 77.23 123.57 124.82
AVERAGE RATE 108.54

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+850 - 3+250 LEFT DUAL CARRIAGE
DATE 12TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.340 1.400 1.540
2 WEIGHT OF TRAY kg 1.200 1.250 1.370
3 WEIGHT OF BITUMEN (1-2) kg 0.140 0.150 0.170
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.144 0.154 0.174
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.595 1.709 1.937
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.438 1.541 1.746
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.8 2.2

Weight of Chippings ( C = F-E ) kg 1 1.6 1

Application rate (kg/m²) D=C/B 11.11 17.78 11.11


Application rate (m²/mᶟ) = A/D 123.57 77.23 123.57
AVERAGE RATE 108.12

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+250 - 3+650 LEFT DUAL CARRIAGE
DATE 13TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.490 1.550
2 WEIGHT OF TRAY kg 1.340 1.350 1.390
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.140 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.144 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.595 1.823
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.438 1.643
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 3 2.3 2.3

Weight of Chippings ( C = F-E ) kg 1.8 1.1 1.1

Application rate (kg/m²) D=C/B 20.00 12.22 12.22


Application rate (m²/mᶟ) = A/D 68.65 112.34 112.34
AVERAGE RATE 97.77

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+250 - 3+650 LEFT DUAL CARRIAGE
DATE 13TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.510 1.445 1.555
2 WEIGHT OF TRAY kg 1.350 1.260 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.185 0.155
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.190 0.159
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 2.108 1.766
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.900 1.592
9 AVERAGE RATE l/m2 1.712

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.5 2.19 2.2

Weight of Chippings ( C = F-E ) kg 1.3 0.99 1

Application rate (kg/m²) D=C/B 14.44 11.00 11.11


Application rate (m²/mᶟ) = A/D 95.05 124.82 123.57
AVERAGE RATE 114.48

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+250 - 3+650 LEFT DUAL CARRIAGE
DATE 13TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.355 1.500 1.550
2 WEIGHT OF TRAY kg 1.200 1.360 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.155 0.140 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 1.030 1.030
5 VOLUME OF BITUMEN (3/SG) litres 0.159 0.136 0.146
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.766 1.510 1.618
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.592 1.361 1.458
9 AVERAGE RATE l/m2 1.470

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 3 2.2

Weight of Chippings ( C = F-E ) kg 1 1.8 1

Application rate (kg/m²) D=C/B 11.11 20.00 11.11


Application rate (m²/mᶟ) = A/D 123.57 68.65 123.57
AVERAGE RATE 105.26

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+250 - 3+650 LEFT DUAL CARRIAGE
DATE 13TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.440 1.460 1.430
2 WEIGHT OF TRAY kg 1.300 1.300 1.255
3 WEIGHT OF BITUMEN (1-2) kg 0.140 0.160 0.175
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.144 0.164 0.179
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.595 1.823 1.994
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.438 1.643 1.797
9 AVERAGE RATE l/m2 1.626

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.2 2.6

Weight of Chippings ( C = F-E ) kg 1 1 1.4

Application rate (kg/m²) D=C/B 11.11 11.11 15.56


Application rate (m²/mᶟ) = A/D 123.57 123.57 88.26
AVERAGE RATE 111.80

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+650 - 3+985 LEFT DUAL CARRIAGE

DATE 14THJULY, 2021


Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.435 1.540
2 WEIGHT OF TRAY kg 1.240 1.280 1.410
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.155 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.159 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.766 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.592 1.335
9 AVERAGE RATE l/m2 1.523

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.19 2.8

Weight of Chippings ( C = F-E ) kg 1 0.99 1.6

Application rate (kg/m²) D=C/B 11.11 11.00 17.78


Application rate (m²/mᶟ) = A/D 123.57 124.82 77.23
AVERAGE RATE 108.54

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+650 - 3+985 LEFT DUAL CARRIAGE
DATE 14THJULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.380 1.400 1.395
2 WEIGHT OF TRAY kg 1.220 1.240 1.255
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.160 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.164 0.144
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.823 1.595
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.643 1.438
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.8 2.3

Weight of Chippings ( C = F-E ) kg 1 1.6 1.1

Application rate (kg/m²) D=C/B 11.11 17.78 12.22


Application rate (m²/mᶟ) = A/D 123.57 77.23 112.34
AVERAGE RATE 104.38

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+650 - 3+985 LEFT DUAL CARRIAGE
DATE 14THJULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.510 1.410
2 WEIGHT OF TRAY kg 1.255 1.350 1.260
3 WEIGHT OF BITUMEN (1-2) kg 0.145 0.160 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.149 0.164 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.652 1.823 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.489 1.643 1.541
9 AVERAGE RATE l/m2 1.558

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.3 2.1 3

Weight of Chippings ( C = F-E ) kg 1.1 0.9 1.8

Application rate (kg/m²) D=C/B 12.22 10.00 20.00


Application rate (m²/mᶟ) = A/D 112.34 137.30 68.65
AVERAGE RATE 106.10

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+650 - 3+985 LEFT DUAL CARRIAGE
DATE 14THJULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.420 1.520 1.450
2 WEIGHT OF TRAY kg 1.250 1.380 1.270
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.140 0.180
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.144 0.185
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.595 2.051
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.438 1.849
9 AVERAGE RATE l/m2 1.677

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.4 2.2

Weight of Chippings ( C = F-E ) kg 1.2 1.2 1

Application rate (kg/m²) D=C/B 13.33 13.33 11.11


Application rate (m²/mᶟ) = A/D 102.98 102.98 123.57
AVERAGE RATE 109.84

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+450 - 2+850 RIGHT DUAL CARRIAGE
DATE 14THJULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.485 1.515 1.550
2 WEIGHT OF TRAY kg 1.350 1.350 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.135 0.165 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.138 0.169 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.538 1.880 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.386 1.695 1.541
9 AVERAGE RATE l/m2 1.541

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.7 2 2.5

Weight of Chippings ( C = F-E ) kg 1.5 0.8 1.3

Application rate (kg/m²) D=C/B 16.67 8.89 14.44


Application rate (m²/mᶟ) = A/D 82.38 154.46 95.05
AVERAGE RATE 110.63

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION
CONTRACTOR: : KWADASO-TRABUOM
ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+450 - 2+850 RIGHT DUAL CARRIAGE
DATE 14TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.370 1.380 1.400
2 WEIGHT OF TRAY kg 1.200 1.230 1.250
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.150 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 1.030 1.030 1.030
5 VOLUME OF BITUMEN (3/SG) litres 0.165 0.146 0.146
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.834 1.618 1.618
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.653 1.458 1.458
9 AVERAGE RATE l/m2 1.523

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.4 2.5

Weight of Chippings ( C = F-E ) kg 1 1.2 1.3

Application rate (kg/m²) D=C/B 11.11 13.33 14.44


Application rate (m²/mᶟ) = A/D 123.57 102.98 95.05
AVERAGE RATE 107.20

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+450 - 2+850RIGHT DUAL CARRIAGE
DATE 14TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.425 1.455 1.580
2 WEIGHT OF TRAY kg 1.250 1.300 1.420
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.155 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.159 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.766 1.823
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.592 1.643
9 AVERAGE RATE l/m2 1.677

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA KIA K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 2.4 2.8 2.3

Weight of Chippings ( C = F-E ) kg 1.1 1.5 1

Application rate (kg/m²) D=C/B 12.22 16.67 11.11


Application rate (m²/mᶟ) = A/D 112.34 82.38 123.57
AVERAGE RATE 106.10

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+450 - 2+850RIGHT DUAL CARRIAGE
DATE 14TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.465 1.510 1.490
2 WEIGHT OF TRAY kg 1.300 1.350 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.165 0.160 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.169 0.164 0.144
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.880 1.823 1.595
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.695 1.643 1.438
9 AVERAGE RATE l/m2 1.592

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 3 2 2.4

Weight of Chippings ( C = F-E ) kg 1.8 0.8 1.2

Application rate (kg/m²) D=C/B 20.00 8.89 13.33


Application rate (m²/mᶟ) = A/D 68.65 154.46 102.98
AVERAGE RATE 108.70

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+850 - 3+250RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.450 1.465 1.500
2 WEIGHT OF TRAY kg 1.280 1.320 1.355
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.145 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.149 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.652 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.489 1.489
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.5 2.4

Weight of Chippings ( C = F-E ) kg 1 1.3 1.2

Application rate (kg/m²) D=C/B 11.11 14.44 13.33


Application rate (m²/mᶟ) = A/D 123.57 95.05 102.98
AVERAGE RATE 107.20

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+850 - 3+250RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.385 1.400 1.390
2 WEIGHT OF TRAY kg 1.220 1.250 1.250
3 WEIGHT OF BITUMEN (1-2) kg 0.165 0.150 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 1.030 1.030
5 VOLUME OF BITUMEN (3/SG) litres 0.169 0.146 0.136
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.880 1.618 1.510
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.695 1.458 1.361
9 AVERAGE RATE l/m2 1.505

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.5 2.2

Weight of Chippings ( C = F-E ) kg 1.2 1.3 1

Application rate (kg/m²) D=C/B 13.33 14.44 11.11


Application rate (m²/mᶟ) = A/D 102.98 95.05 123.57
AVERAGE RATE 107.20

Prepared by: Checked by: Approved by:


EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH
Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+850 - 3+250 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.410 1.415 1.455
2 WEIGHT OF TRAY kg 1.250 1.250 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.165 0.155
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.169 0.159
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.880 1.766
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.695 1.592
9 AVERAGE RATE l/m2 1.643

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.4 2.4

Weight of Chippings ( C = F-E ) kg 1 1.2 1.2

Application rate (kg/m²) D=C/B 11.11 13.33 13.33


Application rate (m²/mᶟ) = A/D 123.57 102.98 102.98
AVERAGE RATE 109.84

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 2+850 - 3+250 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.350 1.360 1.375
2 WEIGHT OF TRAY kg 1.200 1.200 1.200
3 WEIGHT OF BITUMEN (1-2) kg 0.150 0.160 0.175
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.154 0.164 0.179
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.709 1.823 1.994
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.541 1.643 1.797
9 AVERAGE RATE l/m2 1.660

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA KIA K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.5 2.3

Weight of Chippings ( C = F-E ) kg 1.2 1.3 1.1

Application rate (kg/m²) D=C/B 13.33 14.44 12.22


Application rate (m²/mᶟ) = A/D 102.98 95.05 112.34
AVERAGE RATE 103.46

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+250 - 3+650 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.425 1.450 1.475
2 WEIGHT OF TRAY kg 1.255 1.300 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.150 0.125
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.154 0.128
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.709 1.425
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.541 1.284
8 AVERAGE RATE l/m2 1.523

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.6 2.2 2.7

Weight of Chippings ( C = F-E ) kg 1.4 1 1.5

Application rate (kg/m²) D=C/B 15.56 11.11 16.67


Application rate (m²/mᶟ) = A/D 88.26 123.57 82.38
AVERAGE RATE 98.07

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+250 - 3+650 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.375 1.450 1.470
2 WEIGHT OF TRAY kg 1.250 1.280 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.125 0.170 0.170
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.128 0.174 0.174
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.425 1.937 1.937
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.284 1.746 1.746
9 AVERAGE RATE l/m2 1.592

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.1 2.6

Weight of Chippings ( C = F-E ) kg 1.2 0.9 1.4

Application rate (kg/m²) D=C/B 13.33 10.00 15.56


Application rate (m²/mᶟ) = A/D 102.98 137.30 88.26
AVERAGE RATE 109.51

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+250 - 3+650 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.490 1.415 1.500
2 WEIGHT OF TRAY kg 1.320 1.270 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.145 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.149 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.652 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.489 1.541
9 AVERAGE RATE l/m2 1.592

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.5 2.5

Weight of Chippings ( C = F-E ) kg 1 1.3 1.3

Application rate (kg/m²) D=C/B 11.11 14.44 14.44


Application rate (m²/mᶟ) = A/D 123.57 95.05 95.05
AVERAGE RATE 104.56

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+250 - 3+650 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.420 1.405 1.355
2 WEIGHT OF TRAY kg 1.245 1.245 1.235
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.160 0.120
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.164 0.123
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.823 1.368
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.643 1.232
9 AVERAGE RATE l/m2 1.558

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.3 2.5

Weight of Chippings ( C = F-E ) kg 1.2 1.1 1.3

Application rate (kg/m²) D=C/B 13.33 12.22 14.44


Application rate (m²/mᶟ) = A/D 102.98 112.34 95.05
AVERAGE RATE 103.46

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+650 - 3+985 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.495 1.585
2 WEIGHT OF TRAY kg 1.340 1.350 1.455
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.145 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.149 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.652 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.489 1.335
9 AVERAGE RATE l/m2 1.489

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.5 2.2

Weight of Chippings ( C = F-E ) kg 1.2 1.3 1

Application rate (kg/m²) D=C/B 13.33 14.44 11.11


Application rate (m²/mᶟ) = A/D 102.98 95.05 123.57
AVERAGE RATE 107.20

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+650 - 3+985 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.370 1.400 1.500
2 WEIGHT OF TRAY kg 1.200 1.255 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.145 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.149 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.652 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.489 1.541
9 AVERAGE RATE l/m2 1.592

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.5 2.4 2.4

Weight of Chippings ( C = F-E ) kg 1.3 1.2 1.2

Application rate (kg/m²) D=C/B 14.44 13.33 13.33


Application rate (m²/mᶟ) = A/D 95.05 102.98 102.98
AVERAGE RATE 100.33

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+650 - 3+985 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 2
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.480 1.465 1.510
2 WEIGHT OF TRAY kg 1.345 1.320 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.135 0.145 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.138 0.149 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.538 1.652 1.823
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.386 1.489 1.643
9 AVERAGE RATE l/m2 1.506

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.3 2.2 2.6

Weight of Chippings ( C = F-E ) kg 1.1 1 1.4

Application rate (kg/m²) D=C/B 12.22 11.11 15.56


Application rate (m²/mᶟ) = A/D 112.34 123.57 88.26
AVERAGE RATE 108.06

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 3+650 - 3+985 RIGHT DUAL CARRIAGE
DATE 15TH JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 2
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.410 1.420
2 WEIGHT OF TRAY kg 1.255 1.250 1.3
3 WEIGHT OF BITUMEN (1-2) kg 0.145 0.160 0.120
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.149 0.164 0.123
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.652 1.823 1.368
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.489 1.643 1.232
9 AVERAGE RATE l/m2 1.455

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.21 2.2 2.8

Weight of Chippings ( C = F-E ) kg 1.01 1 1.6

Application rate (kg/m²) D=C/B 11.22 11.11 17.78


Application rate (m²/mᶟ) = A/D 122.35 123.57 77.23
AVERAGE RATE 107.72

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+252 - 12+652 LEFT DUAL CARRIAGE
DATE 19TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.510 1.500 1.520
2 WEIGHT OF TRAY kg 1.380 1.350 1.380
3 WEIGHT OF BITUMEN (1-2) kg 0.130 0.150 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.133 0.154 0.144
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.481 1.709 1.595
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.335 1.541 1.438
9 AVERAGE RATE l/m2 1.438

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - S

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.5 2.6

Weight of Chippings ( C = F-E ) kg 1 1.3 1.4

Application rate (kg/m²) D=C/B 11.11 14.44 15.56


Application rate (m²/mᶟ) = A/D 123.57 95.05 88.26
AVERAGE RATE 102.30

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+252 - 12+652 LEFT DUAL CARRIAGE
DATE 19TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.485 1.550
2 WEIGHT OF TRAY kg 1.325 1.350 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.135 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.138 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.538 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.386 1.541
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.6 2.6

Weight of Chippings ( C = F-E ) kg 1 1.4 1.4

Application rate (kg/m²) D=C/B 11.11 15.56 15.56


Application rate (m²/mᶟ) = A/D 123.57 88.26 88.26
AVERAGE RATE 100.03

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+252 - 12+652 LEFT DUAL CARRIAGE
DATE 19TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.420 1.425 1.550
2 WEIGHT OF TRAY kg 1.250 1.280 1.375
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.145 0.175
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.149 0.179
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.652 1.994
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.489 1.797
9 AVERAGE RATE l/m2 1.677

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.8 2.2

Weight of Chippings ( C = F-E ) kg 1 1.6 1

Application rate (kg/m²) D=C/B 11.11 17.78 11.11


Application rate (m²/mᶟ) = A/D 123.57 77.23 123.57
AVERAGE RATE 108.12

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+252 - 12+652 LEFT DUAL CARRIAGE
DATE 19TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.390 1.550 1.400
2 WEIGHT OF TRAY kg 1.250 1.385 1.275
3 WEIGHT OF BITUMEN (1-2) kg 0.140 0.165 0.125
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 1.030 1.030
5 VOLUME OF BITUMEN (3/SG) litres 0.144 0.160 0.121
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.595 1.780 1.348
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.438 1.604 1.215
9 AVERAGE RATE l/m2 1.419

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 3 2.2

Weight of Chippings ( C = F-E ) kg 1 1.8 1

Application rate (kg/m²) D=C/B 11.11 20.00 11.11


Application rate (m²/mᶟ) = A/D 123.57 68.65 123.57
AVERAGE RATE 105.26

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+652 - 13+052 LEFT DUAL CARRIAGE
DATE 23RD AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.455 1.440 1.430
2 WEIGHT OF TRAY kg 1.290 1.300 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.165 0.140 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.169 0.144 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.880 1.595 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.695 1.438 1.335
9 AVERAGE RATE l/m2 1.489

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.3 2.5 2.19

Weight of Chippings ( C = F-E ) kg 1.1 1.3 0.99

Application rate (kg/m²) D=C/B 12.22 14.44 11.00


Application rate (m²/mᶟ) = A/D 112.34 95.05 124.82
AVERAGE RATE 110.74

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+652 - 13+052 LEFT DUAL CARRIAGE
DATE 23RD AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.430 1.545
2 WEIGHT OF TRAY kg 1.240 1.255 1.375
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.175 0.170
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.179 0.174
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.994 1.937
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.797 1.746
9 AVERAGE RATE l/m2 1.729

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.8 2.2

Weight of Chippings ( C = F-E ) kg 1 1.6 1

Application rate (kg/m²) D=C/B 11.11 17.78 11.11


Application rate (m²/mᶟ) = A/D 123.57 77.23 123.57
AVERAGE RATE 108.12

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+652 - 13+052 LEFT DUAL CARRIAGE
DATE 23RD AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.425 1.435 1.520
2 WEIGHT OF TRAY kg 1.300 1.300 1.375
3 WEIGHT OF BITUMEN (1-2) kg 0.125 0.135 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.128 0.138 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.425 1.538 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.284 1.386 1.489
9 AVERAGE RATE l/m2 1.386

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.6 2.7 2.19

Weight of Chippings ( C = F-E ) kg 1.4 1.5 0.99

Application rate (kg/m²) D=C/B 15.56 16.67 11.00


Application rate (m²/mᶟ) = A/D 88.26 82.38 124.82
AVERAGE RATE 98.49

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+652 - 13+052 LEFT DUAL CARRIAGE
DATE 23RD AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.455 1.550 1.400
2 WEIGHT OF TRAY kg 1.300 1.380 1.270
3 WEIGHT OF BITUMEN (1-2) kg 0.155 0.170 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.159 0.174 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.766 1.937 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.592 1.746 1.335
9 AVERAGE RATE l/m2 1.558

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.6 2.1 2.6

Weight of Chippings ( C = F-E ) kg 1.4 0.9 1.4

Application rate (kg/m²) D=C/B 15.56 10.00 15.56


Application rate (m²/mᶟ) = A/D 88.26 137.30 88.26
AVERAGE RATE 104.61

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 13+052 - 13+412 LEFT DUAL CARRIAGE
DATE 24TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.505 1.470 1.495
2 WEIGHT OF TRAY kg 1.350 1.345 1.335
3 WEIGHT OF BITUMEN (1-2) kg 0.155 0.125 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.159 0.128 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.766 1.425 1.823
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.592 1.284 1.643
9 AVERAGE RATE l/m2 1.506

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.5 2 2.5

Weight of Chippings ( C = F-E ) kg 1.3 0.8 1.3

Application rate (kg/m²) D=C/B 14.44 8.89 14.44


Application rate (m²/mᶟ) = A/D 95.05 154.46 95.05
AVERAGE RATE 114.86

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 13+052 - 13+412 LEFT DUAL CARRIAGE
DATE 24TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.500 1.415
2 WEIGHT OF TRAY kg 1.250 1.320 1.255
3 WEIGHT OF BITUMEN (1-2) kg 0.150 0.180 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.154 0.185 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.709 2.051 1.826
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.541 1.849 1.645
9 AVERAGE RATE l/m2 1.678

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.2 3

Weight of Chippings ( C = F-E ) kg 1 1 1.8

Application rate (kg/m²) D=C/B 11.11 11.11 20.00


Application rate (m²/mᶟ) = A/D 123.57 123.57 68.65
AVERAGE RATE 105.26

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION : KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 13+052 - 13+412 LEFT DUAL CARRIAGE
DATE 24TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.450 1.500
2 WEIGHT OF TRAY kg 1.250 1.300 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.150 0.150 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 1.030 1.030 1.030
5 VOLUME OF BITUMEN (3/SG) litres 0.146 0.146 0.146
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.618 1.618 1.618
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.458 1.458 1.458
9 AVERAGE RATE l/m2 1.458

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 1.9 2.4 2.8

Weight of Chippings ( C = F-E ) kg 0.7 1.2 1.6

Application rate (kg/m²) D=C/B 7.78 13.33 17.78


Application rate (m²/mᶟ) = A/D 176.53 102.98 77.23
AVERAGE RATE 118.91

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 13+052 - 13+412 LEFT DUAL CARRIAGE
DATE 24TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.495 1.500 1.555
2 WEIGHT OF TRAY kg 1.340 1.360 1.400
3 WEIGHT OF BITUMEN (1-2) kg 0.155 0.140 0.155
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.159 0.144 0.159
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.766 1.595 1.766
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.592 1.438 1.592
9 AVERAGE RATE l/m2 1.541

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA KIA K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.3 1.3 1.3
Weight of Tray + Chippings (F) kg 2.29 2.3 3

Weight of Chippings ( C = F-E ) kg 0.99 1 1.7

Application rate (kg/m²) D=C/B 11.00 11.11 18.89


Application rate (m²/mᶟ) = A/D 124.82 123.57 72.69
AVERAGE RATE 107.03

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180 °C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE Access Single lane
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.390 1.380 1.395
2 WEIGHT OF TRAY kg 1.220 1.240 1.260
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.140 0.135
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.144 0.138
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.595 1.538
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.438 1.386
9 AVERAGE RATE l/m2 1.523

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 2.3 2.5

Weight of Chippings ( C = F-E ) kg 1.2 1.1 1.3

Application rate (kg/m²) D=C/B 13.33 12.22 14.44


Application rate (m²/mᶟ) = A/D 102.98 112.34 95.05
AVERAGE RATE 103.46

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180 °C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE Access Single lane
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.510 1.450
2 WEIGHT OF TRAY kg 1.340 1.335 1.300
3 WEIGHT OF BITUMEN (1-2) kg 0.160 0.175 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.164 0.179 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.823 1.994 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.643 1.797 1.541
9 AVERAGE RATE l/m2 1.660

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA KIA K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.5 2.4

Weight of Chippings ( C = F-E ) kg 1 1.3 1.2

Application rate (kg/m²) D=C/B 11.11 14.44 13.33


Application rate (m²/mᶟ) = A/D 123.57 95.05 102.98
AVERAGE RATE 107.20

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180 °C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE Access Single lane
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.450 1.465 1.455
2 WEIGHT OF TRAY kg 1.280 1.290 1.340
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.175 0.115
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.179 0.118
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.994 1.311
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.797 1.181
8 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.6 2.2 2.19

Weight of Chippings ( C = F-E ) kg 1.4 1 0.99

Application rate (kg/m²) D=C/B 15.56 11.11 11.00


Application rate (m²/mᶟ) = A/D 88.26 123.57 124.82
AVERAGE RATE 112.22

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180 °C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE Access Single lane
DATE 1ST JULY, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.350 1.450 1.455
2 WEIGHT OF TRAY kg 1.200 1.260 1.310
3 WEIGHT OF BITUMEN (1-2) kg 0.150 0.190 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.154 0.195 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.709 2.165 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.541 1.951 1.489
9 AVERAGE RATE l/m2 1.660

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.21 3 2.18

Weight of Chippings ( C = F-E ) kg 1.01 1.8 0.98

Application rate (kg/m²) D=C/B 11.22 20.00 10.89


Application rate (m²/mᶟ) = A/D 122.35 68.65 126.09
AVERAGE RATE 105.70

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION

CONTRACTOR: ASABEA ENGINEERING LIMITED

PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8


LOCATION: KWADASO-TRABUOM

DAILY SPRAY RECORD SHEET

Date 1ST JULY 2021


Contractor ASABEA ENGINEERING LIMITE
Location ACCESS
Type. Treatment PRIMER SEAL
Grade of Bitumen AC-10 BITUMEN
Refinery/ AC-10 BITUMEN supplier TOTAL PETROLEUM,TAKORADI
Quarry supplier A. KANNI
Prin. Technician Engineer CONTRACTOR / GHA
ITEM REFER UNIT Run 1 Run 2 Run 3 Run 4 TOTAL
1 AREA
2 Length m 400 400 400 400
3 Width m 2 2 2 2.4 8.40
4 Area 2x3 m2 800.00 800.00 800.00 960.00 3360.00
5 SIZE OF LOAD
6 Design Application Rate Cold l/m2 1.600 1.600 1.600 1.600
7 Volume Correction For Temp. Hot Table 2.4 1.1127 1.1127 1.1127 1.1127
8 Design Application Rate Hot 6x7 l/m2 1.780 1.780 1.780 1.780
9 Volume Required Hot 8x4 litres 1,424.00 1,424.00 1,424.00 1,708.80 5980.80
10 Total Load Required Hot (Approx.) 9+10% litres 1,566.40 1,566.40 1,566.40 1,879.68 6578.88
11 SPRAYING
12 Dip Sprayer Load at Start Hot litres 8,000 6,648 5,174 3,776
13 Dip Sprayer Load at Finish Hot litres 6,648 5,174 3,776 2,007
14 Volume Sprayed Hot 12-13 litres 1,352 1,474 1,398 1,769 5992.78
15 Temperature Sprayed o
C 180 180 180 180
16 Volume Correction for 15oC Table 2.4 0.9012 0.9012 0.9012 0.9012
17 Volume Sprayed Cold 14*16 litres 1,218.72 1,328.26 1,259.80 1,593.92 5400.70
18 Spray Application Rate Cold 17 / 4 l/m2 1.523 1.660 1.575 1.660
19 Over or Under Sprayed Cold 18-6 l/m2 -0.080 0.060 -0.030 0.060
20 Tolerance ( 5% ) 6x0.05 l/m2 0.08 0.08 0.08 0.08
21 Spray Outside Tolerance Cold 20-19 l/m2 0.000 0.020 0.050 0.020
22 CHIPPINGS
23 Chipping Size mm 14 14 14 14
24 Chipping Design Rate m2/m3 110 110 110 110
25 Design Quantity 4 / 24 m3 7.27 7.27 7.27 8.73
26 Ordered Quantity 25+5% m3 7.63 7.63 7.63 9.17
27 Chippings Spread (Actual) m3 7.73 7.46 7.13 9.08 31.41
28 Over or Under Sprayed 27-25 m3 0.46 0.19 -0.14 0.35
29 Actual Rate 4 / 27 m /m3
2
103.46 107.20 112.22 105.70 107.14
REMARKS:

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+252 - 12+652 RIGHT DUAL CARRIAGE
DATE 25TH AUGUST 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.400 1.380
2 WEIGHT OF TRAY kg 1.230 1.250 1.250
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.150 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.154 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.709 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.541 1.335
9 AVERAGE RATE l/m2 1.541

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.6 2.5 2.4

Weight of Chippings ( C = F-E ) kg 1.4 1.3 1.2

Application rate (kg/m²) D=C/B 15.56 14.44 13.33


Application rate (m²/mᶟ) = A/D 88.26 95.05 102.98
AVERAGE RATE 95.43

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+252 - 12+652 RIGHT DUAL CARRIAGE
DATE 25TH AUGUST 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.365 1.500
2 WEIGHT OF TRAY kg 1.250 1.200 1.360
3 WEIGHT OF BITUMEN (1-2) kg 0.150 0.165 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.154 0.169 0.144
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.709 1.880 1.595
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.541 1.695 1.438
9 AVERAGE RATE l/m2 1.558

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA KIA K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.4 3 2.1

Weight of Chippings ( C = F-E ) kg 1.2 1.8 0.9

Application rate (kg/m²) D=C/B 13.33 20.00 10.00


Application rate (m²/mᶟ) = A/D 102.98 68.65 137.30
AVERAGE RATE 102.98

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+252 - 12+652 RIGHT DUAL CARRIAGE
DATE 25TH AUGUST 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.500 1.510
2 WEIGHT OF TRAY kg 1.250 1.340 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.150 0.160 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.154 0.164 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.709 1.823 1.823
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.541 1.643 1.643
8 AVERAGE RATE l/m2 1.609

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.7 2.3 2.8

Weight of Chippings ( C = F-E ) kg 1.5 1.1 1.6

Application rate (kg/m²) D=C/B 16.67 12.22 17.78


Application rate (m²/mᶟ) = A/D 82.38 112.34 77.23
AVERAGE RATE 90.65

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION: KWADASO-TRABUOM

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+252 - 12+652 RIGHT DUAL CARRIAGE
DATE 25TH AUGUST 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.480 1.429 1.510
2 WEIGHT OF TRAY kg 1.310 1.300 1.351
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.129 0.159
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.132 0.163
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.470 1.812
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.325 1.633
9 AVERAGE RATE l/m2 1.568

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.5 2 3

Weight of Chippings ( C = F-E ) kg 1.3 0.8 1.8

Application rate (kg/m²) D=C/B 14.44 8.89 20.00


Application rate (m²/mᶟ) = A/D 95.05 154.46 68.65
AVERAGE RATE 106.06

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+652 - 13+052 RIGHT CARRIAGE
DATE 25TH AUGUST 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.400 1.450 1.650
2 WEIGHT OF TRAY kg 1.255 1.300 1.490
3 WEIGHT OF BITUMEN (1-2) kg 0.145 0.150 0.160
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.149 0.154 0.164
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.652 1.709 1.823
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.489 1.541 1.643
9 AVERAGE RATE l/m2 1.558

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 3 2.3 2.1

Weight of Chippings ( C = F-E ) kg 1.7 1.1 0.9

Application rate (kg/m²) D=C/B 18.89 12.22 10.00


Application rate (m²/mᶟ) = A/D 72.69 112.34 137.30
AVERAGE RATE 107.44

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8
LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+652 - 13+052 RIGHT CARRIAGE
DATE 25TH AUGUST,2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.610 1.700
2 WEIGHT OF TRAY kg 1.325 1.470 1.555
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.140 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.144 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.595 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.438 1.489
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 1.9 3 2.8

Weight of Chippings ( C = F-E ) kg 0.7 1.8 1.6

Application rate (kg/m²) D=C/B 7.78 20.00 17.78


Application rate (m²/mᶟ) = A/D 176.53 68.65 77.23
AVERAGE RATE 107.47

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+652 - 13+052 RIGHT CARRIAGE
DATE 25TH AUGUST,2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.540 1.600 1.700
2 WEIGHT OF TRAY kg 1.370 1.440 1.550
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.160 0.150
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.164 0.154
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.823 1.709
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.643 1.541
9 AVERAGE RATE l/m2 1.643

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 3.2 2.8 2.1

Weight of Chippings ( C = F-E ) kg 2 1.6 0.9

Application rate (kg/m²) D=C/B 22.22 17.78 10.00


Application rate (m²/mᶟ) = A/D 61.79 77.23 137.30
AVERAGE RATE 92.11

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 12+652 - 13+052 RIGHT CARRIAGE
DATE 25TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.570 1.600 1.700
2 WEIGHT OF TRAY kg 1.395 1.450 1.570
3 WEIGHT OF BITUMEN (1-2) kg 0.175 0.150 0.130
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.179 0.154 0.133
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.994 1.709 1.481
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.797 1.541 1.335
9 AVERAGE RATE l/m2 1.558

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2 2.3 3.5

Weight of Chippings ( C = F-E ) kg 0.8 1.1 2.3

Application rate (kg/m²) D=C/B 8.89 12.22 25.56


Application rate (m²/mᶟ) = A/D 154.46 112.34 53.73
AVERAGE RATE 106.84

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION: KWADASO-TRABUOM
CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 13+052 - 13+412 RIGHT CARRIAGE
DATE 26TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 2
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.420 1.520 1.525
2 WEIGHT OF TRAY kg 1.280 1.350 1.350
3 WEIGHT OF BITUMEN (1-2) kg 0.140 0.170 0.175
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.144 0.174 0.179
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.595 1.937 1.994
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.438 1.746 1.797
9 AVERAGE RATE l/m2 1.660

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.2 2.4 3

Weight of Chippings ( C = F-E ) kg 1 1.2 1.8

Application rate (kg/m²) D=C/B 11.11 13.33 20.00


Application rate (m²/mᶟ) = A/D 123.57 102.98 68.65
AVERAGE RATE 98.40

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

LOCATION: KWADASO-TRABUOM

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 13+052 - 13+412 RIGHT CARRIAGE
DATE 26TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 2
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.470 1.515 1.600
2 WEIGHT OF TRAY kg 1.300 1.350 1.455
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.165 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.169 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.880 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.695 1.489
9 AVERAGE RATE l/m2 1.643

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.9 2.3 2.2

Weight of Chippings ( C = F-E ) kg 1.7 1.1 1

Application rate (kg/m²) D=C/B 18.89 12.22 11.11


Application rate (m²/mᶟ) = A/D 72.69 112.34 123.57
AVERAGE RATE 102.86

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 13+052 - 13+412 RIGHT CARRIAGE
DATE 26TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.500 1.520 1.425
2 WEIGHT OF TRAY kg 1.355 1.350 1.280
3 WEIGHT OF BITUMEN (1-2) kg 0.145 0.170 0.145
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.149 0.174 0.149
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.652 1.937 1.652
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.489 1.746 1.489
9 AVERAGE RATE l/m2 1.575

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.2 1.2 1.2
Weight of Tray + Chippings (F) kg 2.1 3 2.3

Weight of Chippings ( C = F-E ) kg 0.9 1.8 1.1

Application rate (kg/m²) D=C/B 10.00 20.00 12.22


Application rate (m²/mᶟ) = A/D 137.30 68.65 112.34
AVERAGE RATE 106.10

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A
GHANA HIGHWAY AUTHORITY
REGIONAL MATERIALS LABORATORY - ASHANTI REGION
PROJECT: UPGRADING OF KWADASO-TRABUOM ROAD (15.2KM)-LOT 8

CONTRACTOR: ASABEA ENGINEERING LIMITED

CHECK SHEET FOR TRAY TESTING OF BITUMEN SPRAY RATE - SEAL

TYPE OF BITUMEN AC-10 BITUMEN


SPRAY TEMPERATURE 180°C
TEMPERATURE CONVERSION FACTOR 0.9012
AREA REPRESENTED CARRIAGEWAY
CHAINAGE KM 13+052 - 13+412 RIGHT CARRIAGE
DATE 26TH AUGUST, 2021
Prin. Technician Engineer CONTRACTOR / GHA

TRAY NO. 1 B 3
CHAINAGE
1 WEIGHT OF TRAY + BITUMEN kg 1.520 1.475 1.560
2 WEIGHT OF TRAY kg 1.350 1.340 1.420
3 WEIGHT OF BITUMEN (1-2) kg 0.170 0.135 0.140
4 SPECIFIC GRAVITY OF BITUMEN g/ml 0.975 0.975 0.975
5 VOLUME OF BITUMEN (3/SG) litres 0.174 0.138 0.144
6 AREA OF TRAY m2 0.090 0.090 0.090
7 RATE OF APPLICATION (5/6) l/m2 1.937 1.538 1.595
8 RATE OF APPLICATION (HOT TO COLD) l/m3 1.746 1.386 1.438
9 AVERAGE RATE l/m2 1.523

CHECK SHEET FOR TRAY TESTING OF CHIPPING APPLICATION SPREAD RATE - SEAL

BULK DENSITY A KG/M3 1373


Tray No: KIA K K1

Area of Tray (B) m² 0.09 0.09 0.09


Weight of Tray E kg 1.6 S 1.2
Weight of Tray + Chippings (F) kg 2.6 2.3 2.3

Weight of Chippings ( C = F-E ) kg 1 #VALUE! 1.1

Application rate (kg/m²) D=C/B 11.11 #VALUE! 12.22


Application rate (m²/mᶟ) = A/D 123.57 #VALUE! 112.34
AVERAGE RATE #VALUE!

Prepared by: Checked by: Approved by:

EMMANUEL AFRIYIE NANCY CRENTSIL JOHN ESSAH AMISSAH


Site Supervisor Prin. Technician Engineer Materials Engineer
CONTRACTOR G.H.A G.H.A