You are on page 1of 2

Ko Hein Htet Aung Site

Sanitary & Water Supply Cost of Labour


No. Particular Quantity Unit Rate Per Amount(Ks)
1 Fixing of 4"Ø P.V.C pipe 300 Rft 1800 Rft 540000
2 Fixing of 3"Ø P.V.C pipe 560 Rft 1500 Rft 840000
3 Fixing of 2"Ø P.V.C pipe 640 Rft 1200 Rft 768000
4 Fixing of 1"Ø P.V.C pipe 560 Rft 1000 Rft 560000
5 Fixing of 3/4"Ø P.V.C pipe 640 Rft 900 Rft 576000
6 Fixing of 1/2"Ø P.V.C pipe 80 Rft 900 Rft 72000
7 Fixing of 1/2" Ø P.P.R pipe 320 Rft 1100 Rft 352000
8 Fixing of 3/4" Ø P.P.R pipe 380 Rft 1100 Rft 418000
9 Fixing of main valves
2"Ø ANA Gate valve, Check valve 8 Nos 8000 Nos 64000
1"Ø P.V.C Gate valve 20 Nos 6000 Nos 120000
1"Ø P.V.C Ball valve 11 Nos 5000 Nos 55000
3/4"Ø P.P.R Gate valve 10 Nos 4000 Nos 40000
Basin tap (H & C) 7 Nos 10000 Nos 70000
1/2" T-valve, L-valve 25 Nos 3000 Nos 75000
Stand shower 6 Nos 25000 Nos 150000
Spray shower 7 Nos 4500 Nos 31500
Wall tap 6 Nos 5500 Nos 33000
Vent cap 20 Nos 3000 Nos 60000
Steel sink tap 4 Nos 3000 Nos 12000
Steel sink 4 Nos 25000 Nos 100000
10 Fixing of Basin 7 Nos 25000 Nos 175000
11 Fixing of E.W.C pan 7 Set 35000 Set 245000
12 Holding on Brickwall 180 Nos 5000 Nos 900000
13 Holding on Concrete floor 20 Nos 10000 Nos 200000
14 Hacking on Brickwall 420 Rft 700 Rft 294000
15 Fixing of saddle 396 Nos 650 Nos 257400
16 Fixing of solar heater 1 Set 50000 Set 50000
17 Fixing of Submersible pump 1 Set 50000 Set 50000
18 Fixing of Pressure pump 1 Set 50000 Set 50000
19 Fixing of hanger bracket 186 Nos 1500 Nos 279000
20 Fixing of cleanout plug 10 Nos 3000 Nos 30000
21 Fixing of towel rail, paper holder, Shelf plate& 28 Nos 5000 Nos 140000
soap dish
22 Fixing of floor drain 7 Nos 4500 Nos 31500
23 Fixing of mirror 7 Nos 10000 Nos 70000
Page(1) 7,708,400
Ko Hein Htet Aung Site
Sanitary & Water Supply Cost of Labour
No. Particular Quantity Unit Rate Per Amount(Ks)
24 Fixing of water level float switch 2 Set 30000 Set 60000
25 Excavation of earthwork 1 Item 250000 Item 250000
26 Fixing of pipe sleeve, ground tank, over 1 Item 350000 Item 350000
head tank, septic tank & concrete floor
27 Checking on pipeline pressure test 5 room 50000 room 250000

Page(2) 910,000
⸫ Total Amount Page(1)+Page(2) 8,618,400