NUSEL-BALE
PROJECT TITLE
PROJECT TITLE:GNL_2018_RFQ0021_NUSEL-
BALE ENGINEERING LTD_SPURLINE
CONSTRUCTION TO MARYLAND MALL
QUANT
S/N ACTIVITY ITY UNIT UNIT(Naira) AMOUNT NAIRA
250500 250,500.00
Pre-construction/pre-
C1.0 mobilization activities 1 LUMP SUM
1,000 16,000.00
C2.0 Pipeline stringing activity 16 m
3550 21,300.00
Pipeline route excavation
C3.0 work/activity 6 m
6500 52,000.00
Thrust boring
C4.0 8 Meter
28650 687,600.00
C5.0 Pipeline welding work 24 joints
1050 16,800.00
Lowering of pipes
C6.0 16 meter
Backfilling 1500 9,000.00
C7.0 6 meter
7550 120,800.00
Hydro testing of the pipeline
C8.0 16 meter
4550 72,800.00
Flushing, cleaning and drying
of the pipeline
C9.0 16 meter
10560 253,440.00
Radiographic test
C10.0 24 joints
490730 490,730.00
Nitrogen purging of the
pipeline (for inertness of the
line prior to cold cutting and
also introduction of nitrogen
prior to commissioning)
C11.0 1 LUMP SUM
number 39780 159,120.00
Cold-cutting of pipeline
C12.0 while purging with nitrogen 4
LUMP SUM 200560 200,560.00
C13.0 EHS 1
185900 185,900.00
We hope our above offer meets your expectation as we look forward to serve you to your
utmost satisfaction.