ADDITIONAL WORK ERECTION RUNWAY BASE COST ARISMA

25%
1 Rental Workshop 100,000,000.00 125,000,000.00
2 Engineering Support Dokument to CIB 40,000,000.00 50,000,000.00

3 Supply Material & Fabrikasi Modifikasi Bracket Cremona WT. Crane Semi Gantry Crane 1800 64,800,000.00 81,000,000.00
- Cutting & Drilling hole Cremona H400 x 200 x 200 LG, qty 38 item
- Cutting & Drilling Top Runway H400 x 200 x 100 LG, qty 16 item
- Supply Bracket Plate 12mm untuk cremona Joint, Qty 38 item
- Supply Bracket Plate 12mm untuk runway Joint, Qty 16 item

4 Modifikasi Siffener Kolomn @60PCS 1612.8 18,600,000.00 23,250,000.00


- Mon demob material dari CIB ke workshop

5 Modifikasi Support Electrical Cable & Utility Air Line, Kolomn B32, B33 4,500,000.00 5,625,000.00

6 Modifikasi Dinding, Electrical Cable. Konsol Kolomn B 31' 14,000,000.00 17,500,000.00

7 Modifikasi Top Konsol WT. Crane 890 16,600,000.00 20,750,000.00


- Mon demob material dari CIB ke workshop

8 Modifikasi Runway Semi Gantry B31'-B32' 5500 36,850,000.00 46,062,500.00


9 Drilling hole for bolt clamp & Supply Bolt clamp 800 pcs 11,200,000.00 14,000,000.00

10 Load Unload & Delivery Semi Gantry Crane 20,000,000.00 25,000,000.00


11 Adaptor Kaki Gantry Crane 40,000,000.00 50,000,000.00
12
13
14
15
458,187,500.00