You are on page 1of 2

Table 7: The represents division of costs and activities according to the number of time units for the

completion of the Karbala metal silo project.


Activity Normal Natural cost Cost per day
No. Activity Name Previous
Code time ( (Million (million)
Activity
Civil Works A day ) Dinars)
Preparing the site and the land of the
project, which includes planning and
1 settlement with scraping the land, 100,000,000 7,142,857
A1 - 14
burying it, fixing dimensions and
removing rubble
Examinations, evaluation and treatment
2 A2 83 120,000,000 1,445,783
of test pillars A1
Excavation and casting of piles under 36
3 A3 A2 1,957,500,000 54,375,000
the benzat
4 Silo schemes and approval A4 - 36 150,000,000 3,260,869
Earthworks with burial under the
foundations of benzan and pouring the A3,4
5 A5 10 143,875,000 14,387,500
blinding layer Benzat group with
moisture blocker coating (A)
35
6 Concrete racking casting for benzate(a) A6 A5 163,500,000 4,671,428

7 Pouring concrete columns(A) A7 A6 30 105,000,000 3,500,000


8 Concrete Hopper Casting (AA) A8 A7 120 216,000,000 1,800,000
Earthworks with burial under the
foundations of the benzan and pouring
9 A9 A3,4 10 143,875,000 14,387,500
the blinding layer Benzat group with
moisture blocker coating (B)
Concrete racking molding for benzat
10 A10 A9 35 163,500,000 4,671,428
(B)
11 Casting concrete columns(B) A11 A10 30 105,000,000 3,500,000
12 Concrete Hopper Casting(B) A12 A11 120 216,000,000 1,800,000
Excavation and burial works under the
operating room, tunnels, hobars, bases
13 of benz and groundwater withdrawal A13 A11 80 50,000,000 625,000
with treatments for the operating
building
Concrete pouring works for the
14 A14 A13 30 140,400,000 4,680,000
operating room and tunnels
Casting works of the upper transverse
15 A15 A13 10 48,600,000 4,860,000
conveyor tunnel depth of 12 m
Concrete works for train and truck
16 receiving holes with tightening of A16 A15 20 26,000,000 1,300,000
grates
Pouring concrete foundations silo
17 A17 A15 10 8,000,000 800,000
loading
Concrete works for pouring yards
18 A18 A16,17 10 86,400,000 8,640,000
surrounding operating rooms
Implementation of the electricity
building with the installation of the
19 A19 A11 30 20,000,000 666,666
transformer with the shed and the bases
of the cable channels
Mechanical Works B
Erection and tightening of metal benzat
20 B1 A8 65 40,000,000 615,384
for line A
Installation and tightening of metal
21 B2 A12 65 40,000,000 615,384
benzat for B line
Manufacture and installation of the
22 B3 A14 180 50,000,000 277,777
steel structure of the operating room
Processing and installation of grain
23 B4 B3 60 62,000,000 1,033,333
cranes
Installation and inspection of screening
24 B5 B1,2 30 10,000,000 333,333
machines
Tightening, erecting and checking the
25 B6 B5 30 20,000,000 666,666
dust system
Tightening and erecting the upper
26 B7 B1,2 90 40,000,000 444,444
conveyor assembly
Tightening and erecting the lower
27 B8 B4 91 29,000,000 318,681
vector group
Processing and tightening the metal
28 B9 A18 20 20,000,000 1,000,000
shed over the receiving holes
Hydraulic tipper installation and
29 B10 A18 25 95,000,000 3,800,000
inspection
Erecting loading silos with telescope
30 B11 A18 30 24,000,000 800,000
hose
Packaging of the operating building
31 B12 B9,10,11 20 30,720,000 1,536,000
with the bond and the Wig Panel
Electrical Works C
Laying of high and low voltage power
32 C1 A19 5 30,000,000 6,000,000
line and control lines
Processing, installation and inspection
33 C2 A19 20 12,000,000 600,000
of lighting poles
Equipping, installing and inspecting
34 C3 C1,C2 15 280,000,000 18,666,666
generators
Installation and inspection of the
35 control room and connection of C4 B12 120 30 ,000,000 250,000
equipment and control cables
Equipping, installing and inspecting
36 C5 A14,15 5 6,000,000 1,200,000
submersibles
Tightening and testing the temperature
37 C6 B1,2 15 10,000,000 666,666
monitoring system for benzos
Air system tightening and installation
38 C7 C6 15 18,000,000 1,200,000
works
Works and installation of electronic
39 C8 C3 20 30,000,000 1,500,000
scale calibration
Works of lightning and ground arrester
40 C9 A13 10 5,250,000 525,000
system
Installation, tightening and inspection
41 C10 B7,8 15 90,000,000 6,000,000
of an electric elevator for people
Installation of switchboard
42 C11 C4,7,8,B6 5 6,000,000 1,200,000
communications and cameras
Internal and external lighting
43 C12 C7,8,B6 10 6,191,028 619,102
installation works
44 Installing a grain sterilizer C13 10,11,12 5 1,000,000 200,000
45 Initial Total Examinations D1 C4,C5,C9,C13 45 64,000,000 1,422,222
Total 5,012,811,028 188,004,689

You might also like