You are on page 1of 1

BILL OF QUANTITIES AND BUDGET ESTIMATES FOR THE CONSTRUCTION OF AN

100M3 (100,000L) CAPACITY RESERVE WATER TANK IN NTANCHE COMMUNITY


AMOUNT
S.N DESIGNATION U Qty U.P
(CFA)
I-0 PRELIMINARY WORKS
I-1 Site preparation LS 1.00 200,000 200,000
I-2 Setting out LS 1.00 100,000 100,000
Sub total I 300,000
II-0 FOUNDATION
II-1 Excavation of trenches M3 150.00 6,000 900,000
Stone work for foundation including the
II-2 M3 37.50 15,000 562,500
formation hardcore base
Reinforced concrete slab (Dosage
II-3 M3 19.00 200,000 3,800,000
400kg/m3)
Sub total II 5,262,500
III-0 ELEVATION WORKS
30cm THK Stone work construction of the
III-1 M2 81.00 15,000 1,215,000
walls
R.C. for the internal peripheral walls (20cm
III-2 thickness) - Waterproofing admixture or M3 13.50 200,000 2,700,000
additives
III-3 R.C. for the chain beams and cover slab M3 14.50 200,000 2,899,200
III-4 Water proofing cement surface finish M2 131.60 3,000 394,800
Sub total III 7,209,000
IV-0 PLUMBING WORKS
IV-1 Piping installation LS 1.00 300,000 300,000
IV-2 Plumbing accessories LS 1.00 300,000 300,000
Sub total IV 600,000
V-0 EXTERNAL WORKS
Fabrication and installation of a CAT
V-1 No. 1.00 200,000 200,000
Ladder
V-2 Construction of concrete drain gutter ml 6.00 12,000 72,000
V-3 Construction of Waste chamber No. 1.00 15,000 15,000
V-4 Construction of water outlet chamber No. 1.00 10,000 10,000
Sub total IV 297,000
GRAND TOTAL (HT) 13,668,500