CADANGAN MEROBOH DAN MEMBINA SEMULA TANGKI SEPTIK / LOJI KUMBAHAN, PEMBAIKAN JALAN MENDAP DAN KERJA-

KERJA YANG LAIN YANG BERKAITAN DI KOMPLEKS MAHKAMAH BARU MUAR, JOHOR.

BILL NO. B6 - SEWERAGE (ALL PROVISONAL)


CONTRACT JALINAN SANJUNG
ITEM RATE RATE
DESCRIPTION OF WORKS UNIT QTY AMOUNT (RM) AMOUNT (RM)
NO (RM) (RM)

Pipework

Vitrified clay pipe (VCP) and fittings as specified; laid and


jointed in trench on and including standard bedding as
specified and connection to manholes; trench
excavation, backfilling with selected material and well
compacted as specified ; disposal of surpus excavated
material, all as per drawing JKRJ-B(19)-PT

A 225mm diameter pipes sizes; not exceeding 2.00m


depth; average depth 1.50m m 40 250.00 10,000.00 180.00 7,200.00

B 225mm diameter pipes sizes; not exceeding 2.00m


depth; average depth 2.00m m 40 250.00 10,000.00 190.00 7,600.00

C 225mm diameter pipes sizes;exceeding 2.00m depth but


not exceeding 4.00m depth; average depth 2.25m m 200 280.00 56,000.00 200.00 40,000.00

D 225mm diameter pipes sizes;exceeding 2.00m depth but


not exceeding 4.00m depth; average depth 2.50m m 20 280.00 5,600.00 210.00 4,200.00

INSPECTION CHAMBER

Inspection Chamber constructed with 230mm thick


brickwall in cement mortar (1:3) and rendered on
exposed surfaced with 20mm thick cement and sand
(1:2) trowelled finish; 150mm thick reinforced concrete
Grade 20 as specified bed; complete with frame and
proof cover(heavy duty cast iron) as specified; including
all necessary excavation, formwork and concrete works;
disposal of surplus excavated material, all as per drawing
JKRJ-B(19)-PT

E Maximum depth not exceeding 2.00m; average depth


1.25m depth no. 4 800.00 3,200.00 1,500.00 6,000.00

MANHOLES

Precast Concrete Manhole as specified

Manholes to sizes and details as specified constructed of


standard reinforced cocrete chamber ring with concrete
encasement; complete with 400mm thick concrete;
including Vertified Clay Pipe sewer pipe and double
socket for connection, branches and channels; with
standard manholes cover (heavy duty) and frame with
hinges & locking device; pit excavation commencing from
formation level; disposal of surplus excavated materials
including all necessary as per drawing No.
JKRJ-B(19)-PT

F To invert, not exceeding 2.00m depth; average no. 4 2,500.00 10,000.00 3,800.00 15,200.00
2.00m depth

G To invert, exceeding 2.00m depth but not exceeding


4.00m depth; average 2.25m depth no. 5 2,700.00 13,500.00 3,900.00 19,500.00

H To invert, exceeding 2.00m depth but not exceeding


4.00m depth; average 2.50m depth no 6 2,900.00 17,400.00 4,000.00 24,000.00

TOTAL 125,700.00 123,700.00

Additional item

A Temporary diversion / pumping existing MH/IC LS 1,000.00 3,500.00

B Inspection for PDC6, PDC7, CCTV and PDC8 by IWK LS 15,000.00 10,000.00

TOTAL 141,700.00 137,200.00

diskaun 17,200.00
GRAND TOTAL 141,700.00 120,000.00

Different 21,700.00
% 15.3%