1 Project Description............................................................................................................. 3
2 Scope of Work ................................................................................................................... 3
3 Flow rate requirement: ..................................................... Error! Bookmark not defined.
4 Quality Specification ......................................................................................................... 4
5 Consumption of Utilities .................................................................................................... 4
6 By-products of water treatment. ........................................................................................ 4
7 Codes & Standards ............................................................................................................. 5
8 Concept .............................................................................................................................. 5
9 Equipment list .................................................................................................................... 5
10 Power Supply ..................................................................................................................... 5
11 Finishing ............................................................................................................................ 8
12 Documentation ................................................................................................................... 8
13 Warranty. ......................................................................... Error! Bookmark not defined.
14 Contracting authority ......................................................................................................... 8
14.1 Tender submission ................................................. Error! Bookmark not defined.
14.2 Time table .............................................................. Error! Bookmark not defined.
14.2.1 Issue of Notice ................................................... Error! Bookmark not defined.
14.2.2 Query Handling .................................................. Error! Bookmark not defined.
14.3 Confidentiality ......................................................................................................... 9
14.4 Costs incurred by Vendors ...................................................................................... 9
14.5 Quality review ......................................................................................................... 9
14.6 Content of Tender .................................................................................................... 9
1 Project Description
Waste Water Treatment plant for the chemical, physical and biological treatment
(as optional) of industrial waste water emanating from edible oil and fats
processing plant.
2 Scope of Work
The tender shall include the following works, supply, and services:
• Concept development and detailed engineering for the complete treatment plant to
fulfill treated water specification as detail hereunder.
The treatment plant must comply with the following quality parameters measured at
the inlet and outlet of the plant.
Savola ICDOC
target Standard
Parameter Min Max Outlet
COD mg/L 2000 20900 1000 3000 mg/L
BOD mg/L 180 1070 400 1500 mg/L
TDS mg/L 400 3632 2000 10000 mg/L
Suspended 5000 mg/L
solids mg/L 610 4220 2000
Oils and grease` 600 mg/L
mg/L 32 3620 600
PH 3 4 6-7 4-12
4 Consumption of Utilities
By-products such as sludge resulting from the water treatment shall be de-
watered and dried for easy disposal.
6 Codes & Standards
All design, fabrication, inspection, and testing of the plant will be done with
respect
to the latest American or European Standards. In case of non-availability of
standards, good engineering practice will be adopted.
7 Concept
The sewage generated from the processing of oils and fats are collected in a fat
trap and pumped to a collection pond in the water treatment plant unit where it
will undergo a series of chemical, physical, and biological treatment to arrive at
the desired quality parameters, after which it will released to the municipal
drainage network or diverted for reuse in irrigating plants.
8 Equipment list
Supplier must list in detail all equipment in the supply indicating the cost of
each.
Battery limits shall be clearly mentioned and all works required to be done by
Buyer shall be clearly indicated.
9 Power Supply
NOTE: All machines should be designed for the local electrical supply i.e.
3 PHASE 380/400 V 60Hz
1 PHASE 220 V 60Hz
CONTROL VOLTS: 24VDC
d) Panel should be equipped with a power monitoring module to display the voltage,load in
ampere, consumption in KWH, Peak load readings etc..
e) Terminals and terminal strips have a permanent and consecutive marking acc. to the
wiring diagram.
f) The components have a permanent marking acc. to the wiring diagram. They are
consecutively marked on the mounting plate and also individually.
h) The wiring colours should be different for different voltage type and level.e.g blue for
24VDC positive, white for 24VDC negative, red for 220VAC , Black for three phase 380VAC
supply.
i) All cable entries to the devices, terminal boxes and to the panels should be through cable
glands and should be water, oil and dust proof.
j) Cables connecting to motors and instruments in the field from the main panel should be
chemical resistant cables.
k) Panels should be equipped with circulation fan and exhaust holes with filters at the
bottom.
l) Main panel switch should be equipped for Pad Lock cut off.
m) HMI should be user friendly and should display all machine status. All parameter
adjustment should have user access protection.
Motors Siemens
3. Machine safety:
4. All devices on the unit i.e. sensors, switches, motors, valves, etc.. Are to be properly
tagged by engraved metal strips as per the electrical drawings.
6. It should be equipped with audible and visual alarms, the different color lights
indicating the status of the compressor like Fault, run stop, standby etc…
7. All plant data to be collected and send to a centralized line monitoring system where
data can be viewed analysed and archived.
Plant status
Plant faults in clear written text
Plant delivery consumption
Plant chemical and utility consumption
User authorization
External Interface
10. Documentation:
a) All documentation for panel components and devices installed on the machine to be
provided.
10 Finishing
11 Documentation
12 Contracting authority
The relevant contracting authority is the Office of the strategic sourcing and
supply, Savola Foods Company -
12.1 Confidentiality
Savola undertakes to use its best endeavors to hold confidential any information
provided by Vendors, subject to its obligations under prevailing laws.
Vendors wishing that any of the information supplied in their tender would not
be disclosed should identify this sensitive information clearly and specify the
reason for its sensitivity. Savola will consult such Vendors before making a
decision on disclosure of the information concerned on foot of any relevant
Freedom of Information request which may be received.
Savola requires that all information made available to the Vendor in the course
of this project be treated in strict confidence, unless indicated otherwise by
Savola in particular instances.