Professional Documents
Culture Documents
ource Names July October January April July October January April July October January April July October January April July
Mode E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
1 Enterprise Models LTD
741 days Mon 18/10/01 Mon 21/08/02
16 Market studies 60 days Mon 18/10/01 Fri 18/12/21 3 Marketing Dept Marketing Dept
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Enterprise Models LTD
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Sat 20/05/30
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names July October January April July October January April July October January April July October January April July
Mode E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
27 System module 36 days Thu 19/08/15 Thu 19/10/03
development
28 Integration of 24 days Fri 19/10/04 Wed 19/11/06 27
system module
29 K Testing 82 days Thu 19/11/07 Fri 20/02/28 26 Johan[0%];Testing team
40 N Re-Test 95 days Fri 20/04/24 Fri 20/09/04 37;38 Johan[0%];Testing team Johan[0%];Testing team
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Enterprise Models LTD
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Sat 20/05/30
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Page 2