You are on page 1of 7

Reader's Comment

STATE OF THE ART FOR LONG SPAN PRESTRESSED CONCRETE


BRIDGES OF SEGMENTAL CONSTRUCTION

GEOFFREY C. LACEY, JOHN E. BREEN AND NED H. BURNS

PCI JOURNAL, SEPTEMBER-OCTOBER 1971

Comments by Shu-t'ien Li, Professor Emeritus and Consulting En-


gineer, Rapid City, South Dakota, and B. Barwick, N. D. Lea &
Associates Ltd. Vancouver B.C., Canada; closure by the authors.

Shu-t'ien Li: The authors have at- countries, has omitted some very im-
tempted a long-awaited, very wel- portant long span prestressed con-
come subject with their "State of the crete bridges that should certainly
Art for Long Span Prestressed Con- be listed, even if restricted by the
crete Bridges of Segmental Con- category of "segmental construc-
struction." It is a highly stimulating tion."
subject, especially in the U.S.A., Segmental construction has been
which, despite its many spectacular used for both cast-in-place concrete
engineering feats, has stayed in the by segments and precast segments.
short span range of prestressed con- Either type can be cantilevered out
crete bridges, despite PCI's timely section by section or erected on
effort to extend standard spans from falsework, with each segment being
100 to 170 ft. prestressed back to the balancing ex-
The authors' impressive and inclu- tension on the other side of the pier
sive title, and a quite compatible or to the abutments.
synoptic note under the subject, are Some of these long span pre-
both without the restriction of being stressed concrete bridges have been
"precast." The report, however, quite spectacular achievements.
quickly shifted its particular atten- Without referring to the Bendorf
tion to segmental, precast, post-ten- Bridge, already mentioned by the
sioned box girder bridges, as evi- authors, and a recent Urato Bay
denced by Table 1. A perusal of this Bridge with a longer span length of
table reveals that it covers pre- 754.5 ft., suffice it to cite the well
stressed concrete bridges in the cen- known Gladesville Bridge with an
ter span range from 102 to 487 ft. In arch span of 1000 ft. over an arm of
the present state of the art, these Sydney Harbour in Australia. This
bridges fall in the medium span arch bridge consists of precast box
range rather than the truly long span segments, post-tensioned longitudi-
range. nally as well as transversely. An-
The authors' table, though partial- other notable prestressed concrete
ly covering some notable prestressed bridge is the viaduct at Lake Chil-
concrete spans in twelve different Ion, Switzerland, for which each seg-
104 PCI Journal
ment was cast against its matching this type of construction which mer-
neighbor, with adjustments so as to its mention, namely the Chillon Via-
give a curved soffit profile and to ac- duct, Switzerland( 64 >. This structure
commodate horizontal curves and comprises two independent bridges
superelevation. each 7211 ft. long consisting of a sin-
With the availability of high qual- gle cell box with cellular cantilever
ity, high strength, lightweight aggre- wings. Each bridge is divided into
gate concrete and super high five independent sections by expan-
strength polymer concrete, segmen- sion joints, longitudinal forces being
tal construction, precasting, and taken by the two abutments and
post-tensioning, the technical and braced columns in the middle of
economical limit could easily extend each of the three intermediate sec-
far beyond the existing example of a tions.
1000-ft. span for long span pre- Erection was by cantilever with
stressed concrete bridges. Further, epoxy joints using a travelling erec-
by properly incorporating the con- tion truss capable of horizontal
cepts of continuity, cantilevers with movement to provide for the hori-
suspended span, double-cantilevers, zontal curvature of the viaduct and
framed cantilevers, inclined struts, with jacks at each bogie to maintain
stress-ribbons, deck suspensions, verticality of the truss irrespective
arch rib action, stayed girder ar- of the varying superelevation on the
rangement, the bowstring truss, the structure.
Vierendeel truss with polygonal The weight of precast elements
chords, and self-anchored suspen- varied from 45 to 80 tons; the depth
sion systems, and by the application varied from 18.5 ft, at the columns to
of longitudinal, transverse, and verti- 7.2 ft. at midspan. Spans are general-
cal prestressing one can extend com- ly either 302, 321 or 341 ft., with end
petitive concrete bridge spans to as spans of 139 and 149 ft. Two basic
much as 1500 ft. arrangements of cantilevers that
were used are shown in Fig. A and
combinations of these made up any
B. Barwick: May I congratulate the of the spans in the viaduct.
authors on a most interesting and
timely paper. Supporting twin columns were at
26.2 ft. on centers, hinged at the top,
I first investigated precast segmen- with those columns less than 72 ft.
tal construction when preparing pre-
high being hinged at the bottom and
liminary designs for the approach all others being fixed to the founda-
structures to a proposed vehicular tion.
crossing of Burrard Inlet in Vancou-
Stressing was by 12/0.5 in. strand
ver, visiting Holland in 1969 to in-
cables, a system used almost exclu-
vestigate the potential of this form sively in precast segmental cantile-
of construction. My overriding im-
ver bridges in Europe. One set of ca-
pression was the great speed of erec-
tion attained and the excellent ap- bles is anchored in the girder webs
pearance of the finished product. and primarily provides for the nega-
Table 1 in the paper is a neces- tive moments during construction;
sarily incomplete list of segmental, the other set is located in the bottom
precast, post-tensioned box girder slab and anchored at the top surface
bridges. However, there is in my of this slab. Total deck area of this
opinion one outstanding example of project is 600,000 sq. ft. with a total
January-February 1972 105

.cf.n_r^ k .ter... L.,<

CAUTI LEV Et2 of 157.4


' 2 ^1 I 16.4i ExPanolon.

I)< i0.5^ ^4xlli

57.8 26 2i
3018'
CANTILEVE2 of 137.81

i _ f

Y1

1,,,^g•I
^,^„ i iG•4 i ^3.1^ `Anahbr gts {or fiandons
—' in boi4om 51a6
SECTION-ATCOLUMN SECTION NEA2 MID-5PA 4

Fig. A

construction cost, including founda- larly useful alternative for the two
tions, of approximately $8,000,000. span bridges over existing highways
The Hartelkanaal Bridge in Hol- mentioned in the paper.
land is in fact two separate struc- Nowhere in their paper do the au-
tures joined only by a cast-in-place thors mention the importance of an
median strip, and is not connected accurate assessment of redistribution
by a deck slab as stated in the paper. of moments due to creep in indeter-
The authors state that shear keys in minate structures or of deflections
the webs transmit vertical shear during construction, particularly
forces while the resin sets and also with the free cantilever method. The
serve a very useful function in con- calculation of prestressing losses as
trolling alignment. The provision of accurately as possible is of maximum
a key in the top slab is also consid- importance; empirical rules, such as
ered essential to provide control those of AASHO, are of little help in
over the lateral alignment. the design of more complex struc-
An interesting variation of the tures.
cantilever construction technique is Small differences in alignment of
to use an auxiliary pylon(65 ) and sus- two cantilever arms are taken out by
pend segments from this by means of means of jacking at the midspan sec-
inclined prestressing bars. By using tion, but such differences in align-
such a system it should be possible ment must be small to keep the jack-
to cantilever the full span length in ing forces (and resulting stresses)
each direction from a pier, a particu- within reasonable limits.
106 PCI Journal
I am surprised at the proposal to which applies to spans in excess of
use I-girders for spans of up to 200 300 ft., is the weight of the elements
ft., since this form of construction is involved in large spans. This leads to
only practical for straight, square difficulties in handling, transporta-
spans, which are becoming increas- tion and erection with correspond-
ingly rare. Furthermore, the relative- ingly high costs. I should be pleased
ly poor load distribution capability to hear the authors' comments on
of I-beams leads to larger amounts these problems.
of prestress than necessary with
REFERENCES
other forms of construction, and the
low span/depth ratio imposes eco- 64. Routes nationales Suisses, Department
des Travaux publics du Canton de
nomic penalties when cut or fill is Vaud, Construction des Viaducs de
necessary on the approaches to such Chillon.
a structure. 65. Ulrich Finsterwalder, "Free Cantilever
Construction of Prestressed Concrete
Precast segmental construction Bridges and Mushroom Shaped
Bridges," First International Sympos-
undoubtedly has a great future in ium, Concrete Bridge Design, ACI
North America and the authors are publication SP-23, pp. 481-491.
to be congratulated in seizing the 66. "Bridge across the River Yssel at De-
venter, Holland," unpublished report
opportunity to investigate this meth- by B. V. N. Consultants, The Hague,
od of construction. However, cast-in- Holland.
place box girder construction still 67. Barwick, B., "A Report on the Design
and Construction of Precast, Pre-
has a large part to play in the field of stressed Concrete Segmental Highway
bridge construction. Bridges in Holland-1969," unpub-
lished.
Precast segmental construction
has two major problems, of which Authors' closure: The authors appre-
the initial cost of equipment to pro- ciate the interest shown by the dis-
duce and erect the elements is one cussers and feel that their construc-
area in which considerable econo- tive remarks add to the subject of
mies might be made. For a typical long span prestressed concrete
structure in Holland (e6) for two sets bridges of segmental construction.
of forms, including all hydraulic With the state-of-the-art developing
equipment and steam curing, one rapidly, and with many unique ap-
crane for handling elements in the proaches to the subject being devel-
casting yard and one movable erec- oped by engineers around the world,
tion truss, costs were $120,000, $70,- it is not surprising that the paper did
000 and $200,000 respectively for a not fully cover the subject.
total of $390,000, a not inconsidera- Dr. Li is correct in pointing out
ble investment. Such costs, with the that the paper was deliberately lim-
exception of the erection truss, do ited to precast elements. Our list is
not vary much with the size of the certainly incomplete even for pre-
project and my own conclusion(67) cast segmental construction, as has
from my visit to Holland was that a been pointed out in the discussion
minimum length of 1600 ft. of pre- by Mr. Barwick.
cast elements, i.e. a single box 1600 In the future we may see more
ft. long or a pair of boxes 800 ft. long span bridges in the 1000 ft.
long, was necessary in any single span range, but present needs for
project to justify precast segmental many design situations will not in-.
construction economically. volve large numbers of bridges in
The other major disadvantage, this span range. The paper reviewed
January-February 1972 107
structures which contain spans long- were approximately 950 per square
er than can be accomplished with foot (or about 5 per cent). No erec-
usual standard girders and, in this tion truss is utilized in the Corpus
sense, are long spans. True, they Christi bridge or in many other seg-
may be moderate spans when com- mental bridges. Use of regular lifting
pared to the few cases exceeding equipment has kept costs down.
1000 ft., but to most bridge engi- Contractors have designed special
neers 500 ft. is a long span. appurtenances at modest cost for
Deflection control in these struc- erection of precast segments.
tures is very important, as Mr. Bar- Design of the segments can pur-
wick points out. Experience has posely minimize weight to keep
shown that the fully continuous within construction equipment capa-
structures have experienced less bilities. Physical size of segments
time-dependent deflection problems can be limited to a module which
than with structures which were can be shipped by truck or other
built as cantilevers out to a hinge at means of transportation readily
midspan. Consideration of prestress available. The segment weight prob-
losses is important, but the long time lem need not be an inherent problem
deflection history of most of the with precast segmental construction.
structures reviewed in the paper has Overall, the situation in the United
been very satisfactory. Erection States would not seem to be as bad
techniques are extremely important as the European experience cited in
to control the built-in deflection (or the discussion would indicate. The
camber) which can be introduced by authors do not feel that economics
the joints between segments. Even can be pontificated on. Experience
techniques for alignment at closure with the Corpus Christi bridge indi-
may not successfully correct for de- cates that a designer has control over
flections introduced by serious angle the factors which keep lifting weight
changes due to errors in jointing. and erection costs under control.
Cost requirements may not be as The interest expressed by many
limiting as the discussion by Mr. engineers in segmental construction
Barwick would point out. Actual bid in prestressed concrete seems to in-
prices for a 400 ft. long, 50 ft. wide, dicate that wide use of the technique
segmentally constructed three-span will be seen in the future. Experi-
bridge at Corpus Christi, Texas, ence with its use should result in
were $18 to $20 per square foot. more favorable costs, especially if
Form costs with high quality metal some standardization of cross sec-
forms and a reasonable length soffit tions can be achieved.

108 PCI Journal


LOSS OF PRESTRESS, CAMBER AND DEFLECTION OF NON-COMPOSITE
AND COMPOSITE PRESTRESSED CONCRETE STRUCTURES

D. E. BRANSON AND K. M. KRIPANARAYANAN

PCI JOURNAL, SEPTEMBER-OCTOBER 1971

Comment by James R. Libby, James R. Libby & Associates, San


Diego, California.

James R. Libby: The methods and shrinking until the slab curing pe-
principles discussed by the authors riod ends.
can be used with the Wang 700/701 The data under "Prestressing
computer to compute the loss of pre- Steel" require no explanation except
stress as well as the rotation at any for the relaxation coefficient. A value
section of a prestressed concrete of 10 is used for stress-relieved
member. If the rotations are com- strand while 40 is more appropriate
puted at several points along the for low-relaxation strand.
member, the deflection of the mem- Under "Concrete", the data are
ber can easily be determined be- presented for the precast concrete
cause the rotation is equal to the and the slab concrete. The E coeffi-
moment divided by the product of cient is equivalent to the 33 constant
the elastic modulus and the moment in the formula for E (Eq. 6) and per-
of inertia of the section. mits adjusting this value when the
A sample output from the Wang properties of the concrete being
700/701 is enclosed, Fig. B. The da- used are well known. The strength,
ta shown are all input data except shrinkage and creep parameters are
for the lower table which lists time, those required for Eqs. 1, 7 and 8.
steel stress, fiber stresses and rota- The value of E used at any point in
tion. This particular sample output is time in the computations is a func-
for a post-tensioned member. A dif- tion of Eqs. 1 and 6. The remaining
ferent program is used for preten- input data are self explanatory.
sioned members. The output data are given at sev-
The data listed under "Time" are eral points in time automatically.
used in the numerical intergration These are generally before and after
procedure to control different the application of loads. The output
events. For example, shrinkage of data should also be self explanatory.
precast concrete begins when curing The computations with this program
ends, creep and relaxation begin at are done using the numerical inte-
the time of stressing, internal stresses gration method with one-day time
change when the slab and other intervals.
loads are applied, and strain compat- Approximately 5 min. is required
ibility between the slab and precast to run the program. The Constant
members starts when the slab is Data do not have to be re-entered
placed but the slab does not start for each run.
January-February 1972 109
Times(Days) Prestressing Steel
End Precast Cure 7 Yield Strength(ksi) 247
Prestressing 12 Es(ksi) 27800
Application of Slab 197 Relaxation Coef. 10.0
End Slab Cure 204 Area(in2) 5.520
Application of SDL 1 206
Application of SDI. 2 None
End Anal y sis 600

Concrete
Precast Slab
Compressive Strength, 28 days(ksi) 5.500 5.000
Weight(pcf) 115 114
E Coef. 26 26
Ultimate Shrinkage .000350 .000300
Creep Ratio 1.50
Time Dep endency Parameters
c -Strength 2.24 2.24
d -Strength .92 .92
a -Shrinkage 1.00 1.00
b -Shrinkage. 35.00 35.00
a'-Creep .60
b'-Creep 10.00

SECTION: midsnan
Section Properties
Distance(in) from Centroid
Area(in2) I(in4) to Extreme Precast Fibers
Top Bottom
Net Precast 949 625158 30.870 44.120
Transformed Precast 1013 710047 33.230 41.760
Transformed Composite 1637 1226561 19.320 55.670

Thickness of Slab(in) 6.500

Loads(ft-k) Tendon
Precast DL 1535.000 Initial Prestress(ksi) 189
Slab DL 1278.000 Location, from Bottom(in) 6.375
SDL 1 300.000

Time Steel Fiber Stresses(ksi) Rotation


(Days) Stress(ksi) Beam Slab x lOexp6
Bottom Top CGS Bottom Top

12 189.500 2.588 .062 2.373 14.67


197 144.449 1.825 .228 1.689 21.26
197' 152.942 .923 .946 .925 12.62
206 152.723 .919 .949 .922 -.020 .010 12.58
206' 154.330 .756 1.006 .777 .035 .086 11.41

600 150.360 .681 1.052 .712 -.264 .236 10.45

Fig. B

The program gives a structural eral variables on loss of prestress


engineer the means of practically and on long term deflections in his
investigating the effects of the sev- own office and at nominal cost.

110 PCI Journal

You might also like