You are on page 1of 10

Guidelines on the Preparation of Economic and Financial Analysis in the

Feasibility Study for IBUILD Greenhouse Subproject

I. Rationale

This guideline aims to provide Local Government Units (LGU) a step-by-step guide in the
preparation of the Economic and Financial Analysis (EFA) in the Feasibility Study (FS) of
Farm-to-Market (FMR) proposals under the Philippine Rural Development Project (PRDP).
Economic and financial analyses (EFA) in PRDP are conducted to determine economic
viability of proposed subprojects requesting funding from the Project. Any LGU who will
prepare Feasibility Studies (FS) must be fully aware about the general policies, guidelines,
data requirements, acceptable data sources and data gathering methodologies
recommended by PRDP in order to accomplish sound economic and financial analyses.

II. General Policies and Guidelines

Below are the general policies and guidelines to be adopted in the preparation of economic
and financial analysis in the feasibility study for IBUILD FMR subprojects.

a) The enhanced template for FMR will be used in the preparation of


Subproject Proposals for 2017 onwards.

b) Every subproject must at least pass the 10% sensitivity scenarios (both
increase in costs and decrease in benefits) in order to qualify for endorsement of
No Objection Letter 1 (NOL1). Qualification requires that under these scenarios the
Net Present Value (NPV) must be positive, Economic Internal Rate of Return
(EIRR) must be greater than 15% and the Benefit-Cost Ratio (BCR) must be equal
or greater than 1.0.

c) Any changes in the data in subsequent FS submissions as compared to


previous submissions should be documented and adequately justified. Frequent
changes in data and assumptions are discouraged. LGUs must be well informed
that all data used in the initial projection are assumed to have been validated in the
field and referenced from credible data sources.

III: Detailed guidelines and instructions in the preparation of Economic and Financial
Analysis (EFA)

General Instructions during preparation of EFA:


1. Always refer to the Program of Works for cost estimates
2. When filling-up the EFA excel file, only fill-in the cells highlighted in yellow
3. For all the data used in the EFA and FS, cite the sources and reference year (Note: use
the latest census). If possible, provide a link to the website of the data source.
Greenhouse Sub Project

Economic and financial analyses (EFA) in PRDP are conducted to determine viability of
proposed subprojects requesting funding from the Project. All proposals are required to
submit feasibility studies utilizing Benefit-Cost Analysis (BCA). The economic model (Figure
1) for Greenhouse considers cost estimates from Estimated Project Costs and Operation &
Maintenance Costs, which are then weighed against benefits such as Vehicles Operating
Cost (VOC) Savings, Savings in Output and Input Hauling, Savings in Travel Time of
Commuters, Benefits from New Agricultural Areas and Savings in Transport Losses. These
streams of benefits are considered in the analysis for they represent the direct impacts of
FMR subprojects to the local community. The period of analysis for FMRs considered the
total useable lifespan of FMRs, which is 20 economic years.

Costs Benefits

Estimated Project Costs Increase in Potential Yield

Operation and Savings from Avoidable


Maintenance Costs Damages

1. Tab1. Conversion of Financial to Economic Cost

The first table in the EFA template is the conversion of financial costs of the project to
economic cost. Items included in evaluating the economic cost are materials,
equipment, skilled labor, unskilled labor, overhead, contingencies and miscellaneous
(OCM), contractor’s profit, taxes, pre-engineering activities and engineering
supervision cost. Shown below is the detailed discussion per item in EFA Table 1.

Financial costs are converted to economic costs using appropriate methodologies and
conversion factors, such as shadow pricing for foreign components of construction
materials and shadow wage rate pricing for unskilled labor hired during construction.
Cost items that have significant foreign exchange component are to be shadow priced
using the Foreign Exchange Premium Factor of 1.2 to reflect its real value to the
economy, while Unskilled Labor expenses are subjected to the Shadow Wage Rate
Factor of 0.6 for the value of unskilled labor to the economy is 60% only of the
minimum wage as set by the NEDA.
Data Requirements Reliable and acceptable data
sources/Acceptable method of
data gathering
Materials Materials are classified into 2 types: Material cost under financial cost
(a) with foreign component and (b) column in EFA template must be the
locally sourced. It is assumed that 60% same with the cost reflected in the
of material costs has a foreign Program of Works (POW). This must
component, which is subjected to be re-checked with the data in the
shadow pricing using a factor of 1.2, POW.
and the remaining 40% is base cost of
locally sourced materials.

Note that shadow price of foreign


exchange is 20% higher than the
official rate and this applies to the
materials with foreign component.

Only cells highlighted in yellow must


be filled in as the values for “with
foreign component” and “locally-
sourced” will automatically be
computed.
Equipment Equipment cost is the equipment Equipment cost under financial cost
rental cost based from the 2009 column in EFA template must be the
Association of Carriers and Equipment same with the cost reflected in the
Lessors, Inc. (ACEL) Rates. Program of Works (POW). This must
be re-checked with the data in the
Only cells highlighted in yellow must POW.
be filled in. Equipment cost is base
cost, which does not include taxes. Tax
for this item is already calculated
under “Taxes” item.
Skilled Labor Skilled labor includes heavy Skilled labor cost under financial cost
equipment operator, mason, foreman, column in EFA template must be the
carpenter, welder and steel same with the cost reflected in the
fabricators. Program of Works (POW). This must
be re-checked with the data in the
Only cells highlighted in yellow must POW.
be filled in. Skilled labor is base cost
which does not include taxes. Tax for
this item is already calculated under
“Taxes” item.
Unskilled Labor Unskilled labor includes laborers, Unskilled labor cost under financial
helpers, warehouse men, and cost column in EFA template must be
timekeepers. the same with the cost reflected in
the Program of Works (POW). This
Only cells highlighted in yellow must must be re-checked with the data in
be filled in. The assumption is that the POW.
conversion factor for unskilled labor is
0.6 since its value is 60% only of the
minimum wage rate (source: NEDA).
Overhead, Overhead, Contingencies and OCM cost under financial cost column
Contingencies and Miscellaneous (OCM) is 12% of total in EFA template must be the same
Data Requirements Reliable and acceptable data
sources/Acceptable method of
data gathering
Miscellaneous direct cost if subproject cost is PhP5 with the cost reflected in the
(OCM) million below; 9% if PhP5 million to Program of Works (POW). This must
PhP50 million; 7% if PhP50 million to be re-checked with the data in the
PhP150 million; 6% if above PhP150 POW.
million.

Only cells highlighted in yellow must


be filled in. Tax for this item is already
calculated under “Taxes” item.
Contractor’s Profit Contractor's Profit is 10% of total Contractor’s Profit under financial
direct cost if project cost is PhP5 cost column in EFA template must be
million below; 8% otherwise. the same with the cost reflected in
the Program of Works (POW). This
Only cells highlighted in yellow must must be re-checked with the data in
be filled in. Tax for this item is already the POW.
calculated under “Taxes” item.
Taxes Tax is 12% of total mark-up value of Taxes under financial cost column in
the base cost and all items sourced EFA template must be the same with
locally. Taxes should not be included in the cost reflected in the Program of
the economic value of project cost. Works (POW). This must be re-
checked with the data in the POW.
Pre-engineering Pre-engineering activities include FS Pre-engineering activities cost has
Activities and DED Preparation, and Right of already been derived under financial
Way Acquisition Costs. Pre- cost column in EFA template which is
engineering activities are 5% of base 5% of base direct cost + 12% tax.
direct cost + 12% tax; economic cost, This cost cannot be found in the
however, should exclude tax. Program of Works (POW) since it is
not included in the total project cost
to be funded by PRDP. This cost must
be shouldered by PLGU/MLGU. In
deriving for the economic cost, tax
should be excluded.
Engineering Engineering Supervision is 5% of base Engineering Supervision cost has
Supervision direct cost + 12% tax; economic cost, already been derived under financial
however, should exclude tax. cost column in EFA template which is
5% of base direct cost + 12% tax.
This cost cannot be found in the
Program of Works (POW) since it is
not included in the total project cost
to be funded by PRDP. This cost must
be shouldered by PLGU/MLGU. In
deriving for the economic cost, tax
should be excluded.
1. Tab2. Investment Cost

Tab 2 of the EFA presents a summary, in economic terms, of investment cost and
operating & maintenance cost over the 20-year project life of each FMR. The detailed
computations for investment cost and operating & maintenance cost are presented in
Tab1 and Tabs 3 (3a and 3b), respectively.

Data Requirements Reliable and acceptable data


sources/Acceptable method of data
gathering
Total Economic Total economic value under Total economic value is the capital cost
Value investment cost reflects the of the project in terms of economic cost.
economic value of the subproject
converted from the total financial
cost. Economic value is reflected on
year 0 since this cost represents the
capital cost but in economic terms.
The PLGU/MLGU is not required to
provide inputs as the cell already
has a formula.
Total Investment Total investment cost is the sum of Total investment cost is the sum of the
Cost the total economic value. The economic value. Basically, the total
PLGU/MLGU is not required to investment cost is the capital cost.
provide inputs as the cell already
has a formula.
Operation and Operation means to operate the The Operation and Maintenance of the
Maintenance Cost system in a right manner ensuring completed Other Infrastructure
that all the component structures Subprojects is both the responsibility of
are running in good condition. the Local Government Unit and the
Maintenance refers to ensuring that beneficiary community/ies. Costs for
all component structures of the this section are derived in table 3a
system are periodically repaired, (Road Maintenance Unit Cost).
monitored and maintained in a
correct manner.

Operation and Maintenance cost is


already linked to table 3b (Annual
Maintenance Cost). The
PLGU/MLGU is not required to
provide inputs as the cell already
has a formula.
Total Operation Total Operation and Maintenance Total operation and maintenance cost is
and Maintenance Cost is the sum of the total the sum of the operation and
Cost operation and maintenance costs. maintenance cost per year.
The PLGU/MLGU is not required to
provide inputs as the cell already
has a formula.
Total Investment Total Investment and O&M Cost is Total investment cost is the sum of the
and O&M Cost the sum of the economic cost and economic cost and O&M cost.
O&M cost. The PLGU/MLGU is not
required to provide inputs as the
cell already has a formula.
Tab3a. Annual Road Maintenance Unit Cost

This table details the required maintenance activities and corresponding costs. Such
costs are also converted to economic costs, adopting similar principles in Tab1.

Data Requirements Reliable and acceptable data


sources/Acceptable method of
data gathering
Common road This aspect reflects the Activities and costs to be filled in
maintenance activities activities done during the the highlighted cells must be
include, but are not operation and maintenance of consistent with the activities and
limited to, the following the Portland Cement Concrete costs reflected in the Operation
items: Pavement (PCCP). Only cells and Maintenance Plan and Budget
 Repainting, highlighted in yellow must be (Appendix E).
replacement faucet, filled in.
repair of lightning
fixtures and door knob For economic conversion, it is
(Warehouse) assumed that all laborers
 Cleaning/replacement involved in the O&M activities
of industrial exhaust are unskilled laborers. The
fan (warehouse) assumption is that conversion
 Repair of wooden factor for unskilled labor is
palette (Warehouse) 0.6 since its value is 60% only
 Change of Net lining of the minimum wage rate
(cacao SD) (source: NEDA).
 Replacement of UV
Sheets (Cacao SD)
 Replacement of drying
trays (Cacao SD)
 Inspection & Repair of
fermentary boxes
 Inspection & Repair of
platform (fermentary)

Tab3b.Annual Maintenance Cost

This provides an overview of maintenance activities and annual costs. Such costs are
also converted to economic costs, adopting similar principles in Tab1.

Data Requirements Reliable and acceptable


data sources/Acceptable
method of data gathering
Road length: Total proposed road length must Total road length must be the
Portland Cement be entered in the highlighted cells. same with the road length
Concrete found in FS and POW.
Pavement (PCCP)
Data Requirements Reliable and acceptable
data sources/Acceptable
method of data gathering
Unit Maintenance Cost: Unit maintenance cost for PCCP Cost for the O&M per
Portland Cement must be the economic cost of O&M kilometer is not the financial
Concrete per kilometer as reflected in table cost but the economic cost
Pavement (PCCP) 3a (Road Maintenance Unit Cost). derived from table 3a. This
PLGU/MLGU is not required to cost must be re-checked in
provide inputs as the cell already table 3a.
has a formula.
Annual Maintenance Annual maintenance cost for PCCP Annual maintenance cost is
Cost: is the product of the total proposed the annual economic cost for
Portland Cement road length and the O&M cost per the O&M activities of the
Concrete kilometer. Formula is already proposed road.
Pavement (PCCP) derived, thus PLGU/MLGU is not
required to provide inputs in the
cells for annual maintenance cost.
Capital Maintenance Annual Capital Maintenance is Every six years, there is an
every 6th year undertaken every six years. additional 60% of the annual
PLGU/MLGU is not required to cost for the periodic
provide inputs as the cell already maintenance of the road.
has a formula.
Total Annual Total annual maintenance cost is Total annual maintenance
Maintenance Cost being derived by adding the annual cost must be the same with
maintenance cost for PCCP and the total investment and O&M
capital maintenance every 6th year. cost found in table 2
These cells already contained (Investment Cost). These
formula for derivation of the costs must be consistent with
results. the cost in FS particularly
under Investment and O&M
Cost in the Economic Cost
portion of the FS.

Tab 4 Increase in Potential Yield

Data Requirements Reliable and acceptable


data sources/Acceptable
method of data gathering
Utilization Rate % Utilization rate or area of the Ex. CAGRI, OPAG, PAGRI
greenhouse being used
Proportion out of the % utilization rate for specific IBUILD data based on POW
total utilization rate commodity
Number of Seedlings Number of seedlings to be stored Ex. CAO
in the greenhouse (per
commodity) or the number of the
capacity of crop or total population
of crop in the greenhouse facility
Seedlings planted per Number of seedlings planted per Ex. CAO
hectare hectare or the total number of
seedlings/plant per hectare
outside the greenhouse facility
Data Requirements Reliable and acceptable
data sources/Acceptable
method of data gathering
Estimated Area to be the quotient of the total number of
planted seedlings and seedlings planted
per hectare
Yield per hectare (w/o Actual average of historical/time Ex., BAS
project) series data say 10 years or 5 years
Yield of commodity per hectare
without the project

Since this is without the project the


data must be constant over
economic life of the project
Total production (w/o Estimated area to be planted times
project) yield per hectare (without the
project)
Yield per hectare (with average Yield of commodity per Ex. BAS
project) hectare with the project

It is allowable to project an
increase per year to achieve the
maximum average yield of the
commodity
Total production (with Estimated area to be planted times
project) yield per hectare (with the project)
Additional Volume Difference between total
production (with project) and total
production (w/o project)
Selling Price Selling price or prevailing market Ex. BAS
price of the commodity
Net Benefit Additional volume times selling
price or prevailing market price

Tab 5 Savings from Avoidance of Damages

Data Requirements Reliable and acceptable


data sources/Acceptable
method of data gathering
Total number of This is the total capacity of Ex. CAGRI, OPAG, PAGRI
seedlings seedlings inside the greenhouse
facility
% mortality without The percent of mortality outside Ex. CAO
greenhouse greenhouse facility
Total number of Total number of seedlings times %
available seedlings mortality without greenhouse
Number of seedlings Number of seedlings/plant per Ex. CAO
per hectare hectare
Area planted (with Total number of seedlings divided
project) by the number of seedlings per
hectare
Area planted (w/o Total number of available
Data Requirements Reliable and acceptable
data sources/Acceptable
method of data gathering
project) seedlings divided by the number of
seedlings per hectare
Yield per hectare Actual average of historical/time Ex. CAO
series data say 10 years or 5 years
Yield of commodity per hectare
without the project
Number of cropping The actual crop season/rotation Ex. BAS and CAO
seasons per year practice per commodity
total production (with The sum of Area planted (with
project) project), yield per hectare and
number of cropping season
Total production The sum of Area planted (without
(without project) project), yield per hectare and
number of cropping season
additional production The difference between total
production (with project) and total
production (without project)
Selling price Selling price or prevailing market Ex. PSA, CAO, BAS etc
price of per commodity
Net Benefit The product of additional
production and selling price

Tab 6. Economic Analysis

This summarizes all the benefits and costs derived from the previous tables and yields
the computed EIRR, NPV, and BCR to reflect economic viability of the subproject.

Data Requirements Reliable and acceptable data


sources/Acceptable method of
data gathering
Economic Net Present PLGU/MLGU is not It must be noted that ENPV result
Value (ENPV) required to provide inputs should be positive to make sure
in this portion as this will that the investment yields a
automatically be computed. positive impact to the society. A
project that has a negative ENPV
result will be rejected.
Economic Internal Rate PLGU/MLGU is not EIRR must be above 15%. Projects
of Return (EIRR) required to provide inputs with an EIRR below 15% will be
in this portion as this will rejected.
automatically be computed.
Benefit-Cost Ratio (BCR) PLGU/MLGU is not BCR must be equal or greater than
required to provide inputs 1.0. A project with a BCR below
in this portion as this will 1.0 will not be accepted.
automatically be computed.

Tab 7. Sensitivity Analysis


This indicates the feasibility of the subproject given several scenarios of reduced
benefits and increased costs. The following scenarios are given: increase in cost of 5%,
10%, 15%, 20%, 30% and decrease in benefits of 5%, 10%, 15%, 20%, 30%) and the
feasibility of the subproject is tested for each scenario.

Data Requirements Directions in filling-up Reliable and acceptable data


data requirements sources/Acceptable method of
data gathering
Sensitivity Analysis PLGU/MLGU is not The proposed subproject will be
required to provide inputs accepted if its economic indicators
in this portion as this will (ENPV, EIRR and BCR) are
automatically be computed. satisfactory at both sensitivity
scenarios of increase of cost by
Sensitivity analysis 10% and a decrease of benefits by
assesses risks by 10%.
identifying the variables
that most influence a
project’s net benefits and
quantifying the extent of
their influence.

You might also like