Keerthana S 19026
Activity on Arrow diagram:
5
A(10) G(12)
C(5) D1 8
1
B(8) 6
4
2
6 D(6) 4
6 F(5)
E(8)
3
E1 = 0 L6 = E6 = 26
E2 = E1 + 8 L5 = L6 - 12
0+8 26-12
=8 = 14
E3 = E2 + 8 L4 = L5 - 0
8+8 14-0
= 16 = 14
E4 = E2 + 6 L3 = L6 - 5
8+6 26-5
= 14 = 21
E5 = Max (E1+10, E2+5, E4+0) L2 = Min (L3 -8, L4 -6, L5 -5)
Max (0+10, 8+5, 14+0) Min (21-8, 14-6, 14-5)
= 14 =8
E6 = Max (E5 +12, E3 +5) L1 = Min (L5 -10, L2 -8)
Max (14+12, 16+5) Min (14-10, 8-8)
= 26 =0
Critical path : 1 – 2 – 4 – 5 – 6
Normal Crash
Normal Crash
Activit Predecesso cost cost cost
time(weeks time(weeks
y r (Rs000 (Rs000 slope
) )
) )
A - 10 20 7 30 3.333333
B - 8 15 6 20 2.5
C B 5 8 4 14 6
D B 6 11 4 15 2
E B 8 9 5 15 2
F E 5 5 4 8 3
G A, D, C 12 3 8 4 0.25
Longest path : 1 – 2 – 4 – 5 – 6 (B – D – G )
= 8 + 6 +0 + 12
= 26 weeks
Total cost = Direct cost + Indirect cost
(000’s) = 71 + (2.8*26)
= 71 + 72.8
= 143.8 (or 1,43,800)
A = 30-20 = 3.333
10-7
B = 20-15 = 2.5
8-6
C = 14-8 = 6
5-4
D = 15-11 = 2
6-4
E = 15-9 = 2
8-5
F = 8-5 = 3
5-4
G 4-3 = 0.25
12-8
Step 3:- To compare critical activities, the cost slope for G is least then we try to reduce
the duration of G
We are reducing the duration of G by four weeks which means instead of 12 it
becomes 8.
and 1 – 2 – 3 – 6
= 8+8+5
= 21 weeks
and 1 – 2 – 3 – 6
= 6+8+5
= 19 weeks
Inference: If we look at cost Rs. 1,33,600 is lower than the Rs. 134,800 and
1,34,200. After crashing G, the cost is Rs. 1,33,600 which is increasing further. So, it is
better to reduce the total completion time from 26 weeks to 22 weeks.