GENERAL PROGRESS
Work started at 8:30 am. In general the purpose is to make the boat ready for survey work, to make
note all repairs works needed.
Classification
Repairs
GENERAL PROGRESS
Work started at 8:30 am. First part of the IRS survey has finished.
Classification
Repairs
General
IRS inspected the cargo Hull and engine.IRS ask recommended to fully overhaul engine.
Dock repairs
Painting in progress:
Rudder shaft was inspected by IRS and found to satisfactory.rudder bush to be renewed.