Professional Documents
Culture Documents
Appendices
1. Meter Survey, Repair and Compensation
2. Meter Selection
3. Drawings and Examples
4. Implementation Metrics
sensors the readings will be in error during upsets if the header pressure and temper-
ature departs significantly from design.
Each system should balance. If a system (e.g. the 150# steam header) does not
balance, a dedicated maintenance effort must be undertaken to achieve closure. See
Appendix 1 - Meter Survey, Repair and Compensation for methodology. Subbal-
ances should be used to track and help achieve closure if maintenance efforts are
unsuccessful.
Data from plot-limit meters is validated by balancing the entire header or by subbal-
ancing the plant plot-limit meters with "submeters" installed in the offplot headers
so as to form smaller balances or “subbalances”. (Experience has demonstrated
that balances or subbalances of greater than eight meters are difficult to maintain).
If subbalance meters are to be added, see Appendix 2 (Meter Selection) to help
decide which type of meter to install. For the purpose of this Best Practice, the term
“balance” is used to describe either a system balance, or a subbalance of a system.
The same method for achieving a balance (Figure J-1) is used whether you are
balancing an entire system or a subbalance to a system.
Figure J-2 shows a subbalance made up of six meters, four plant plot-limit meters
and two submeters. Meters #5 and #6 are the submeters, installed into the offplot
header, and measure flow into or out of the subbalance. The arrows show the direc-
tion of positive flow indicated by the meters (this directional choice is arbitrary).
Flow in the opposite direction from the arrows is negative (arrow direction is arbi-
trary). Using the flow directions shown, the subbalance calculated below should be
equal to zero +/- 5% if all meters are working properly.
Balance = flow5-flow1-flow2-flow3-flow4-flow6 = 0
Groups of meters that make up balances generally never sum to exactly zero. Expe-
rience shows that well maintained balances will trend near zero within about 5%1 of
the total flow of the balance. The Total Flow of the balance equals the flow into or
out of the balance. Since we don’t know if the measurement of the flow into or out
of the balance is accurate we can use our best guess which would be the average of
the flow in and the flow out of the balance. So, our approximation of the Total
Flow of a balance is one-half of the sum of the absolute value of all the metered
flows that make up the balance (or one-half of the sum of the flows into the balance
and the flows out of the balance. For example if we calculate the balance in
Figure J-2 above, it equals 40 mlb/hr. The approximate total flow of the balance
equals 200 mlb/hr which is found by summing the positive flow for each meter in
the balance and then dividing that sum by two. This “balance” is out of balance by
a positive 20 per cent (the meters say more steam is going into the balance than is
going out) which doesn’t meet the standard of balancing within plus or minus five
percent of the total flow of the balance.
1. This is in contrast to a custody transfer meter where agreement between a sales meter and a company owned
check meter is desired to be within 2% with the variation tracked with a control chart to flag significant
changes.
The balance sums are computer monitored and trended around zero to insure data
validity. Figure J-3 is an example of a trended balance that at first does not balance
and after repairing two meters, does balance. Before the meters are working
correctly the sum of the meters does not balance, the meters sum to about 50
mlb/hr. After one meter is repaired the "balance" sums to about -25 mlb/hr (the
minus sign means that the sum of the metered flows out of the balance is greater
than the sum of the metered flows into the balance). After one more meter is
repaired the balance sums near zero. Once a balance balances regularly over a
period of time, each meter in that balance can be relied on to report accurate infor-
mation.
Figure J-5 shows trend number 2 from Figure J-4 but with additional trends of three
of the meters that make up the balance. It is easy to see that meter C made a signifi-
cant change at the same time the balance went off. This focuses attention on meter
C. This method, which has been used at multiple facilities for several years, has
resulted in the elimination of most preventive maintenance for meters. At Rich-
mond this has led to a reduction in meter maintenance support from six mechanics
to one. Using this method inaccurate/bad order meters are quickly identified and
repaired. Meter failures and repairs should be tracked so that recurring problems
can be found and eliminated.
Fig. J-6 Technique to Obtain and Maintain Balance in Steam Measurement Systems
Assign Ownership
Balances
should trend
within 5%
If balances cannot be
maintained within target,
install additional meters to
construct new or
additional sub-balances
J3.0 Appendix 1
• Root valves for orifice meters should come off the upper half of the pipe to
reduce scale and other debris plugging the legs.
• The highest points of the condensate legs for the upstream and downstream
pressure taps should be level with each other.
• Verify meter range matches orifice data sheet.
• For orifice meters, verify that the transmitter or recorder properly accounts for
the square root relationship between the flow and pressure drop.
• For orifice meters insure that the condensate “legs” are of equal length.
• For orifice meters insure that condensate legs have no places where air pockets
can form.
• Check that orifice plate is stamped with the size shown on the orifice meter
data sheet.
• Check that meter reads zero by closing valve on one meter lead and opening
the equalizing valve on the 3-valve manifold. Also, use this zero test to insure
that the meter you are working on in the field is the correct meter in the moni-
toring computer.
• Verify piping is the diameter shown on the orifice data sheet.
• Verify sufficient lengths of straight run of piping both before and after the
sensing element.
• Ensure no leaks in the root valves, legs, or dP cell manifold.
• Insure safe blowdown valves are installed to keep root valves and legs clear.
• Verify positive flow direction of the meter. For DP meters, insure that the high
leg (+) on the DP cell is connected to the upstream side of the orifice in the
positive flow direction, or if this is difficult, block in one root valve and
partially blow down the leg to drive the meter to 100% positive or negative.
J4.0 Appendix 2
Application Install if line can be shut- Install if line cannot be Install if flow is steadily Install if flow is normally
down and if the normal shutdown or if flow over 175 ft/sec or has over 175 ft/sec or has
flow rate doesn't vary by varies by more than 3:1 regular excursions regular excursions
more than a factor of 3:1. higher than 250 ft/sec. higher than 250 ft/sec.
Design Recommenda- Insure that the normal Don't use a turbine Insure that the normal Insure that the normal
tions flow rate will be in the meter on vents, flow rate will be in the flow rate will be in the
upper two-thirds of the letdowns and deaera- upper two-thirds of the upper two-thirds of the
meter range. tors or where large, fast meter range. meter range.
changes in steam flow
occur.
Insure that the normal Specify 3 inch flanges Specify 3 inch flanges
flow rate results in a on the meter and use a on the meter and use a
"significant" pressure Specify 3 inch flanges three inch full port valve. three inch full port valve.
drop across the orifice. on the meter and use a
three inch full port valve.
Insure that the normal
Use a smart DP cell to flow rate results in a
measure orifice pres- Initially install a 5 or 10 "significant" pressure
sure drop for improved degree rotor and drop across the flow
accuracy monitor the rotor element.
frequency to insure that
the rotor does not over-
If low DP's are expected Use a smart DP cell to
speed
use a smart DP cell that measure orifice pres-
maintains accuracy at sure drop for improved
low ranges. If the frequency is accuracy
normally greater than
600 hertz with a low
See Chevron Instrument If low DP's are expected
pitch rotor then consider
Manual for further use a smart DP cell that
installing an annubar or
design information. maintains accuracy at
a vortex shedding meter.
low ranges.
Effect of water in steam Water can build up Slugs of water will Water will plug the Water shouldn't hurt the
line. behind orifice plate and destroy a 1.5 inch diam- lower holes of the vortex meter but will
cause inaccuracies eter turbine wheel annubar cause inaccuracies
Recommendation: Eliminate water from Eliminate water from Eliminate water from Eliminate water from
steam lines with steam lines with steam lines with steam lines with
adequate drip legs and adequate drip legs and adequate drip legs and adequate drip legs and
trapping trapping trapping trapping
Installation while system Shut down required for Can be hot tapped Can be hot tapped Can be hot tapped
is on-line installation
Yes, 16:1 turndown with 30:1 Turndown when 4:1 Turndown 20:1 to 30:1 Turndown
two dp cells. used with nonlinear depending on density
interpolation software
Service ability Requires a shutdown to Can be removed and Can be removed and Can be removed and
check orifice. serviced during opera- serviced during opera- serviced during opera-
tion. tion. tion.
turbine meter rotors should last about two years. Condensate in the line is death to
turbine meter rotors. Condensate in steam lines is also not good for the lines them-
selves and the equipment the lines serve. With proper drip legs and traps conden-
sate problems can be controlled. If the flow in the line is very high, such that it
would overspeed a five degree rotor then an insertion averaging pitot tube or vortex-
shedding meter should be used.
J5.0 Appendix 3
Required or
Drawing Type Description Desirable
1. Onplot Utility Onplot UF&CD's schematically represent the Required
Flow & Control steam distribution system inside the plant plot-
Diagrams (or litdmit. UF&CD's are intended to show all major
G2/Mesa)(1) steam lines and all branches off these lines.
Because UF&CD's are not as detailed as
P&ID's, they are not adequate by themselves
for equipment blinding and isolation planning.
2. Offplot P&ID Offplot P&ID's schematically represent the Required
complete steam distribution system up to the
plot-limit of each plant in the refinery.
3. Offplot Maps Offplot Maps geographically represent the Desirable
offplot steam distribution system up to the plot-
limit of each plant in the refinery. They show
the physical routing of lines, and the location of
main valves and meters. They are intended to
be used to locate lines, valves, meters, etc. in
the field, but not for purposes requiring a
detailed representation of the system (e.g. line
isolation plans). For these purposes, the offplot
p&id's should be consulted.
4. Offplot Utility Offplot UFD's are simplified versions of the Desirable
Flow Diagrams p&id's that also indicate typical flow informa-
or equivalent or tion not covered on the p&id's.
G2/Mesa(1)
(1) G2/Mesa is a steam management/optimization computer program that schematically represents the
entire refinery steam system.
The offplot UF&CD and the onplot UF&CD’s (or G2/Mesa) also detail the location
of flow, temperature, and pressure meters that form the basis of the measurement
and validation system. Examples of the above drawings with design criteria are
attached.
J6.0 Appendix 4
Status Codes
00 Refinery decided against implementation
0 Not applicable to this facility
1 No plans underway
2 Evaluating applicability, feasibility and incentives for implementing in
facility
3 Developing/updating plans to implement
4 Implementing plan, <50% completed
5 Implementing plan, >50% completed
6 Fully implemented and completed; not confirmed by formal audit or other
means
7 Fully implemented and completed; confirmed by formal audit or other
means