ID Task Name Duration Start

1
Secondary & Lateral 204 days Mon 10/28/19
Sewer line Construction
2
Yohannis to Tsion Square 180 days Mon 10/28/19
3
Preparation of Ground 17 days Mon 10/28/19
4
Earth Work 59 days Wed 11/13/19
5
Trench Excavation to 15 days Wed 11/20/19
different depths
6
Extra Soft rock 17 days Wed 12/11/19
excavation
7
Extra Hard rock 22 days Fri 1/3/20
excavation
8
Gravity Sewers 47 days Wed 1/8/20
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start

9
Pipe Bedding and 20 days Tue 2/4/20
Surrounding with Red
Ash
10
Installation of 150mm 20 days Tue 2/4/20
service connection
saddle and anchor
blocks
11
Backfill with imported 8 days Tue 3/3/20
& excavated materials
& Cart away any
excavated susrplus
materials

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Name Duration Start

12
Construction of 20 days Tue 3/3/20
Manholes
13
Finshing Works 39 days Tue 3/31/20
(Permanent restoration
of excavated trench
surface)
14
Afincho Ber Shola 150 days Mon 10/28/19
Ethiopia Tikidem
15
Preparation of Ground 17 days Mon 10/28/19
16
Earth Work 59 days Wed 11/20/19
17
Trench Excavation to 15 days Wed 11/20/19
different depths

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Name Duration Start

18
Extra Soft rock 17 days Wed 12/11/19
excavation
19
Extra Hard rock 22 days Fri 1/3/20
excavation
20
Gravity Sewers 47 days Tue 2/4/20
21
Pipe Bedding and 20 days Tue 2/4/20
Surrounding with
Red Ash
22
Installation of 150mm 20 days Tue 2/4/20
service connection
saddle and anchor
blocks

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Name Duration Start

23
Backfill with 15 days Tue 3/3/20
imported &
excavated materials
& Cart away any
excavated susrplus
24
materials of
Construction 25 days Tue 3/3/20
Manholes
25
Finshing Works 31 days Tue 4/7/20
(Permanent
restoration of
excavated trench
26
surface)
Rufael Anbesa Matemia 161 days Mon 10/28/19
27
Preparation of Ground 17 days Mon 10/28/19
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task Name Duration Start

28
Earth Work 59 days Wed 11/20/19
29
Trench Excavation to 15 days Wed 11/20/19
different depths
30
Extra Soft rock 17 days Wed 12/11/19
excavation
31
Extra Hard rock 22 days Fri 1/3/20
excavation
32
Gravity Sewers 47 days Tue 2/4/20
33
Pipe Bedding and 20 days Tue 2/4/20
Surrounding with Red
Ash

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID Task Name Duration Start

34
Installation of 150mm 20 days Tue 2/4/20
service connection
saddle and anchor
blocks
35
Backfill with imported 15 days Tue 3/3/20
& excavated materials
& Cart away any
excavated susrplus
materials
36
Construction of 25 days Tue 3/3/20
Manholes

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID Task Name Duration Start

37
Finshing Works 40 days Tue 4/7/20
(Permanent restoration
of excavated trench
surface)
38
Site Handover 5 days Tue 6/2/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
Finish Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
M T S W S T F M T S W S T F

Thu 8/6/20

Fri 7/3/20

Tue 11/19/19
Mon 2/3/20
Tue 12/10/19

Thu 1/2/20

Mon 2/3/20

Thu 3/12/20
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
Finish Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
M T S W S T F M T S W S T F

Mon 3/2/20

Mon 3/2/20

Thu 3/12/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
Finish Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
M T S W S T F M T S W S T F

Mon 3/30/20

Fri 5/22/20

Fri 5/22/20

Tue 11/19/19
Mon 2/10/20
Tue 12/10/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
Finish Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
M T S W S T F M T S W S T F

Thu 1/2/20

Mon 2/3/20

Wed 4/8/20
Mon 3/2/20

Mon 3/2/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
Finish Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
M T S W S T F M T S W S T F

Mon 3/23/20

Mon 4/6/20

Tue 5/19/20

Mon 6/8/20
Tue 11/19/19
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
Finish Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
M T S W S T F M T S W S T F

Mon 2/10/20
Tue 12/10/19

Thu 1/2/20

Mon 2/3/20

Wed 4/8/20
Mon 3/2/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
Finish Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
M T S W S T F M T S W S T F

Mon 3/2/20

Mon 3/23/20

Mon 4/6/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
Finish Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
M T S W S T F M T S W S T F

Mon 6/1/20

Mon 6/8/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Construction of Second
Summary Manual Summary Rollup Progress
Date: Thu 3/26/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16

You might also like