You are on page 1of 48

Recommended Practice

for
Precast Post-Tensioned
Segmental Construction

Reported by

Joint PCI-PTI Committee on Segmental Construction

WALTER PODOLNY, JR.


(Chairman)

MAHMOUD Z. ARAFAT PETER REINHARDT


THOMAS J. D'ARCY FRED ROBINSON
C. S. GLOYD CHARLES SLAVIS
H. HUBERT JANSSEN MARIO G. SUAREZ
T. ROBERT KEALEY DAVE SWANSON
HEINZ P. KORETZKY MAN-CHUNG TANG
RICHARD M. McCLURE Y. C. YANG
VILAS MUJUMDAR PAUL ZIA
CARL A. PETERSON ZENON A. ZIELINSKI

14
Synopsis
This Joint PCI-PTI committee report presents
basic recommendations for the design and
construction of precast post-tensioned concrete
structures which are composed of individual
segments that are connected by the use of
post-tensioning. The recommendations cover the
fabrication, transportation, and erection of the
precast component segments, details of the
construction of joints, tendons and anchors, and
design considerations applicable to segmental
construction.
It should be emphasized that this report is
published as a guide on segmental construction and
should not be considered a specification. The report
contained herein is an update of the report entitled
"Recommended Practice for Segmental
Construction in Prestressed Concrete," published in
the March-April 1975 PCI JOURNAL.

PCI JOURNALlJanuary- February 1982 15


CONTENTS
Chapter 1 Introduction .................................. 18
1.1 General
1.2 Historical Background
1.3 Limitations of this Recommended Practice
1.4 Scope
1.5 Definitions

Chapter 2 — Examples of Segmental Construction .......... 19


2.1 General
2.2 Airport Control Tower
2.3 Liquid Natural Gas Storage Tanks
2.4 28-Story Office Building
2.5 Cement Clinker Silo
2.6 Floating Vessel for Storage of Liquified Petroleum Gas
2.7 Five Points Station, MARTA Rapid Transit, Atlanta, Georgia
2.8 Precast Segmental Bridge Construction
2.8.1 Balanced Cantilever
2.8.2 Span-by -Span
2.8.3 Progressive Placing
2.8.4 Incremental Launching

Chapter 3 — Fabrication of Precast Segments ............... 36


3.1 General Considerations
3.2 Methods of Casting
3.2.1 The Long-Line Method
3.2.2 The Short-Line Method
3.3 Formwork
3.3.1 General
3.3.2 Provisions for Tendons
3.3.3 Provisions for Supplemental Reinforcement
3.3.4 Tolerances
3.4 Concrete
3.5 Joint Surfaces
3.5.1 Quality
3.5.2 Holes for Tendons and Couplers
3.6 Bearing Areas

Chapter 4 — Transportation, Storage and Erection


ofPrecast Segments ........................... 44
4.1 General
4.2 Plant Handling and Transportation
4.3 Erection Methods

16
4.3.1 Cranes
4.3.2 Winch and Beam
4.3.3 Launching Girder
4.4 Erection Considerations
4.5 Erection Tolerances

48
Chapter5 -- Joints ........................................
5.1 General
5.2 Cast-in-Place Joints
5.3 Dry-Packed Joints
5.4 Grouted Joints
5.5 Match Cast Joints
5.5.1 Epoxy Bonded Joints
5.5.1.1 Selection of Epoxy
5.5.1.2 Application of Epoxy
5.5.2 Dry Joints
5.6 Metal Joints

Chapter 6— Post -Tensioning Tendons ..................... 53


6.1 Sheathing
6.2 Tendon Couplers
6.3 Anchor Plates
6.3.1 Anchor Plates Cast into Precast Segments
6.3.2 Anchor Plates Placed against Precast Surface
6.4 Tendon Layout
6.5 Placement and Stressing of Tendons
6.6 Grouting
6.7 External Tendons

Chapter 7 — Design Considerations ........................ 57


7.1 General
7.2 Force Redistribution
7.3 Handling and Storage of Segments
7.4 Joint Design
7,4.1 Shear
7.4.2 Keys
7.4.3 Compression
7.5 Auxiliary Reinforcement
7.6 Design of Segments for Box Girder Bridges
7.7 Design of Segments for Decked I-Beams

References ............................................... 60

PCI JOURNAUJanuary- February 1982 17


CHAPTER 1 -- INTRODUCTION
1.1 General Thirty-two major bridges outside
Precast post-tensioned segmental of North America were reviewed
construction is defined as a method (in 1971) in a state-of=the-art paper
of construction for bridges, build- about segmental bridges." These
ings, tanks, silos, cooling towers, bridges were built between the
tunnels and other structures in years 1960 and 1969. Many design
which primary load carrying mem- parameters resulted in variations in
bers are composed of precast con- span, number of segment cells,
crete segments post-tensioned to- span-depth ratios, segment lengths,
gether. joints, types, and erection methods.
Six more bridges in various coun-
1.2 Historical Background tries were reviewed in another
The concept of dividing precast state-of-the-art paper published in
concrete structural members into 1975.°
smaller segments and connecting In North America well over 50
them with stressed rods or bars box girder bridges of segmental
dates back as far as 1888 to 1907 construction have either been built
and early ideas about prestressed or are under construction. In 1977 a
concrete by Dohring, Mandl, Lund cable-stayed precast post-tensioned
and others.' segmental bridge was completed."
Five bridges designed in Europe The Portland Cement Association
of a segmental precast girder type Iibrary has two annotated bibliog-
were constructed between 1946 raphies,9' 10 available for review,
and 1950. These girders were pre- which list 195 articles on segmental
stressed longitudinally, vertically and cantilever cast-in-place bridge
and transversely. The 240-ft (73 m) construction between 1962 and
spans were flat two-hinged portal 1975.
frame structures with adjustable Although the term segmental has
hinged bearings to compensate for most often been applied to bridge
shortening due to shrinkage and construction the concept of using
creep of concrete. 42 In 1951, a segmental construction has been
small number of bridge girders in successfully utilized in many proj-
the United States were built of pre- ects other than bridges. For exam-
cast concrete blocks. These blocks ple: the Mutual Life Building in
were strung onto prestressing ca- North Carolina; Gulf Life Tower in
bles, joints of the net section were Jacksonville, Florida; the Five
mortared, harped tendons were Points Station — MARTA Rapid
post-tensioned, and tendons were Transit, Atlanta, Georgia; the Velo-
grouted.s In the United States in drome and Olympic Stadium
1952 a single span girder bridge structures in Montreal, Canada; and
was constructed by dividing each numerous buildings using shells
girder into three precast segments. and roof girders.","
After curing, the segments were re- Chapter 2 presents examples of
assembled at the site with cold the varied use of precast post-
joints and post-tensioned.4 tensioned segmental construction.

18
1.3 Limitations of this steel to the concrete.
Recommended Practice Coating —Material used to pro-
This report is a recommended tect the prestressing steel against
practice on segmental construction, corrosion and/or provide lubrica-
not a building code or specification. tion.
It is presented as a guide to the de- Couplers — Hardware to transmit
sign and construction of structures the prestressing force from one
using segmental elements to insure partial length prestressing tendon
safety and serviceability. En- to another.
gineering judgment must be Grout —A mixture of cement,
and water with or without admix-
applied to these recommendations.
tures. (In some instances sand is
used as a filler).
1.4 Scope Joint — The region of the struc-
These recommendations are in- ture between interfaces of precast
tended to cover those conditions segments with or without adhesive
which affect segmentally con- or grouting materials and with or
structed members differently from without reinforcement.
non-segmentally constructed mem- Prestressing Steel —The part of a
bers. They consider the fabrication, post-tensioning tendon which is
transportation, and erection of the elongated and anchored to provide
precast component segments, the the necessary permanent pre-
construction of joints, tendons and stressing force.
anchors, and design considerations Segment — A precast element
applicable to segmental construc- made out of concrete, with or with-
tion. out reinforcement, prestressed or
non-prestressed.
1.5 Definitions Sheathing or Duct — Enclosure
Adhesive —A bonding material around the prestressing steel.
used in joints. Tendon — The complete assem-
Anchorage — The means by bly for post-tensioning, consisting
which the prestressing force is of anchorages, couplers, and pre-
transmitted from the prestressing stressing steel with sheathing.

CHAPTER 2- EXAMPLES OF SEGMENTAL


CONSTRUCTION

2.1 General 2.2 Airport Control Tower


Many structures have been de- In 1973 a 180-ft (54.86 m) high
signed and built using some varia- airport control tower' 3 consisting of
tion of the concept of segmental four service cores was segmentally
construction. The following exam- constructed using box segments
ples are only a small portion of approximately 10 ft (3 m) square in
those built. These were recently plan and 7' ft (2.3 m) high. The
reported in technical journals. four cores are topped by a 16-ft

PCI JOURNAIJJanuary-February 1982 19


!1I il
Fig. 1(a). Airport control tower. Structural Fig. 1(b). Erection of precast box
steel platforms were set at 15-ft (4.57 m) segments. Note that the modules were
intervals to connect the four service cores. stacked to 180-ft (54.9 m) height.

VERTICAL
POST -
TEN SIONIN

PRECAST
CORE
ELEMENT

DRY PACKED
JOINT

SHIM S

Fig. 2. Isometric view of stacked box


segments. Sketch shows the major
Fig. 1(c). Setting of box segments. components of segment.

ce
Fig. 3. Erection of precast panel for liquid natural gas storage tank.

(4.88 m) high steel cab housing the 2.3 Liquid Natural Gas
control tower observation deck and Storage Tanks
facilities. Vertical post-tensioning In 1974 in the United States, two
was used to stabilize the core seg- 900,000 bb] liquid natural gas stor-
ments during construction and pro- age tanks14 were completed using 8
vide moment and shear capacity to x 60 ft (2.44 x 18.3 m) high precast
resist service loads. Fig. 1 shows wall panels. After completion of
the tower during construction. Fig. erection of the panels the structure
2 is an isometric view of the was post-tensioned circumferen-
stacked and post-tensioned box tially. The tanks are composed of
segments. two concentric walls, the outer wall

PCI JOURNAL/January-February 1982 21


Fig. 4a. Plan of liquid natural gas tank.

having a radius of 134 ft (40.8 m)


and being 13 ft (4 m) beyond the
inner wall. Three feet (0.9 m) of in-
sulating material is placed in the
annular space beside the inner
wall. Mass concrete fills the other
10 ft (3 m) providing resistance to
external impact forces. Fig. 4a is a
plan view showing the segments
placed side by side. Fig. 4b shows a
section of the double wall and the
circumferential post-tensioning.
Figs. 4c and 4d show the tanks in
various stages of construction.

Fig. 4c. Precast panel being readied into


position on tank wall. Note connecting
dowels on side of panel.

22
20'- 10 12" TO SUPPORTS

3/B"PL ROOFING

TRUSS POCKET

I8"INSULATION

Cu M FE RENT A Lo
JClR
POST-TENSIONING W LOW-
z U)
w
LIQUID EL.

Ti
>-
I.. W I2-9..
PRECAST WALL., LNG
SEGMENTS
w-
x 00
t- MI Uj PRECAST _~
z WALL m m
° SHOTCRETE \ SEGMENTS _'
- a
SHOTCRETE
10'-O" BERM 3.-0"

Fig. 4b. Section of double wall with post-tensioned precast wall segments.

Fig. 4d. Overall view of LNG tanks during construction.

PCI JOURNAUJanuary-February 1982 23


45'O" -
^VIERENDEEL TRUSS— ^

.,l _ 11 II II II I^ II
I ^^I II l+ II I^
II jl
-'-ii II
II jl ^I Ij ^1 II
^ I__°_ IIii
---_=1f_=«-------^
M -------1 +I I II
I
II
II
II
^I
pi
I^ tl II II
I II II II
I I I! f .
I II I I II I^
^ II
II
'.' I II II
w I ^I

o ^ I- II li
^I N
jq W I
Q> 1---yt------_--_- II 7
II
W
II Q
I II z
II
.. y
I. ii II II
II iI I+
I I! +f li Ii
li 11 II I II
o i 13 II l II I^ II li I I II
II Ij II I I II II II
^
^
I
I II I, II II II II II
II II II I I- I it If
II it II_ __I I__ I 1 _ ^ _I II ij
I _Jj II 11 II II L_ I
II II I ^I jl itII
^-r EI 11
II II II

F
— VIERENDEEL TRUSS- ^

Fig. 5. Plan view of 28-story office building.

2.4 28-Story Office Building and bottom chords of the truss were
In 1974, a 28-story office build- post-tensioned horizontally. The
ing15 used a segmentally con- ends of the truss were then an-
structed Vierendeel truss as the chored into large cast-in-place col-
exterior support for the edges of umns. Fig, 5 is a plan view showing
floors. Truss segments were block-I the location of the trusses and col-
shaped, 17 ft (5.2 m) high, 10 ft (3 umns. Fig. 6 is an elevation of a
m) wide at top and bottom and segmental Vierendeel truss. Fur-
weighed a maximum of 9 tons (8.2 ther design and erection details of
t) each. The block-I's were erected this building can be found in the
side by side at the site and the top Nov.-Dec. 1975 PCI JOURNAL."

24
f COLUMN ECOLUMN
75 7"
h is ' 1 do do _IO'4 29'f

`o IT z-ru4 ^ravr•—
B1 I I TOP CHORD
Z

L^
c–

`P RESTRESSING
c A A TENDON
v
C BOTTOM CHORD
N

VIERENDEEL TRUSS — TYPICAL ELEVATION


E }0'2"
BOTTOM GHDRD
VIERENDEELSS TRU

FLOOR LINE -7 BAR • 10 BARS • 15'-9" ;p •r,q.p 9

I o

j 8" 8 " 18" 10 3$" _^3t


SECT. A-A
^PRtSTRESSING TENDON SECT. BBB SECT. CC
C.I.P. COLUMN

END BLOCK ELEVATION


V7

Fig. 6. Elevation of Vierendeel truss.


^' ^—LOADING /
T
R5 G,11 \ `
CONVEYOR

= FLOW 1

P5

R4

P4

UL :
O 4F
T i R3 -
I P2 k P 3 ®i

CRUSHED ROCK GRADES


^U 1 R2 ^R}

DISCHARGE CHAMBER

CLAY 40
T1
ROCK
r(1NNE PRECAST CONGRETE
L CASF-IN'PLACE CONCRETE

DISCHARGE CONVEYOR-

LEGEND

P I - RADIAL TIE BEAM AND R I - RING BEAM NO. I


ANCHORAGE BLOCK
R 2 - RING BEAM N0. 2
P 2 - SLANTED V- COLUMN
R 3 - RING BEAM N0. 3
P3 - LOWER CONE ELEMENT
R 4 - RING BEAM NO. 4
P4 -WALL PANEL
P5 - CONICAL ROOF ELEMENT R 5 - RING BEAM NO. 5

Fig. 7. Cross section of cement clinker silo showing location of main precast concrete
components.

2.5 Cement Clinker Silo roof, (b) a segmental cylindrical


A cement clinker storage silo'6 wall which contained two levels of
was built in 1975. It has a diameter post-tensioned rings, and (c) an in-
of 214 ft (65.2 m), a height of 130 ft verted cone bottom, two-thirds of
(39.6 m) above ground, and a depth which was below grade. Fig. 7 is a
of 79 ft (24.1 m) below grade. Three cross section of the silo showing its
basic elements were composed of various components. Fig. 8 shows
precast concrete: (a) a conical shell the individual precast components.

26
DETAIL PI
RADIAL TIE BEAM AND
ANCHORAGE BLOCK

33o,,

.
.
–LVL

DETAIL P3
LOWER CONE ELEMENT
DETAIL P2
SLANTED V-COLUMN

IO'8"

Al

.Ii
Ii
It
1:1
3" 1:1

IL:
-6"

DETAIL P5
DETAIL P4
CONICAL ROOF
WALL PANEL
ELEMENT
Io.8u

Fig. 8. Dimensional details of major precast concrete components.

PC[ JOURNALJanuary-February 1982 27


a. Match Castings of Shell Segments

e. Placing Hull Tanks

b. Setting of Shells in Graving Dock

I. In-place Casting of "D" Plates


and Deck
c. tn-place Casting of Longitudinal Bulkheads,
Saddles and Transverse Bulkheads

g. Placing Deck Tanks and Final


d. Launching Stage Outfitting

Fig. 9. Construction sequence used for liquified petroleum gas storage vessel.

2.6 Floating Vessel for and a rise of 11 ft (3.4 m). These


Storage of Liquified shells were match cast and post-
Petroleum Gas tensioned longitudinally. Addi-
In 1977, a prestressed concrete tional cast-in-place bulkheads, sad-
floating vessel" for liquified pe- dles, stiffeners and decks resulted
troleum gas was completed. The in the hull functioning as a multi-
hull dimensions were 461 ft (140.5 cell box girder and providing space
m) long by 136 ft (41.5 m) wide. and support for twelve 400-ton (363
The hull bottom is in the shape of t) steel tanks. Fig, 9 shows the con-
three cylindrical barrel shells. Each struction sequence. Figs. 10, 11,
barrel consisted of precast curved and 12 are photographs of a hull
segmental shells approximately 11 segment being cast, delivered and
ft (3.4 m) long, 45 ft (13.7 m) wide erected.

28
Fig. 10. Match-casting, precast concrete bottom shell segments.

Fig. 11. Graving dock and delivery of 40-ton bottom hull segment.

PCI JOURNAUJanuary-February 1982 29


Fig. 13. Five Points Station, Atlanta Rapid Transit System, Atlanta, Georgia.

2.7 Five Points Station, heaviest precast pieces, weighing


MARTA Rapid Transit, up to 23 tons (20.9 t) apiece, are
Atlanta, Georgia those that make tip the main beams.
The massive roof structure for
this $42 million transit station (see 2.8 Precast Segmental Bridge
Fig. 13) is made up entirely of pre- Construction
cast components (some 450 in all) In precast segmental bridge con-
except for the reinforced concrete struction, short segments are cast in
columns. In plan the roof is 167 ft a plant or near the job site under
(50.9 m) wide and 262 ft (79.86 m) factory simulated conditions, but
long. It rises almost 50 ft (15.2 m) always at some location other than
above the at-grade plaza level. The their final position in the structure,
major elements of the roof structure and then assembled in place. Pre-
are nine longitudinal beams 262 ft cast segmental bridges may be clas-
(79.86 m) long and eleven trans- sified by their method of construc-
verse beams, 167 ft (50.9 m) long. tion.
These beams are composed of up to Generally, the method of con-
20 precast segments, 13 ft (4 m) struction can be divided into four
long, 10 ft 8 in. (3.15 m) high and 2 types:' 8'1$ (1) balanced cantilever,
ft 6 in. (0.76 m) wide. The main (2) span-by-span, (3) progressive
beams are match-cast construction placing, and (4) incremental
glued together with epoxy. The launching or push-out construction.

30
2.8.1 Balanced Cantilever with the environment, traffic flow is
In this method segments are can- not obstructed below, small labor
tilevered from a pier in a balanced force required, and speed of erec-
fashion on each side until midspan tion.
is reached and a closure pour is An interesting concept in bal-
made with a previous half-span anced cantilever segmental con-
cantilever from the preceding pier struction is its incorporation with
as shown in Fig. 14. This procedure cable-stayed bridges. This concept
is then repeated until the structure has been used in the United States
is completed. for the Pasco-Kennewick Bridge s-s
Each segment added is immedi- in the State of Washington as
ately post-tensioned to the already shown in Fig. 15.
completed portion of the structure. 2.8.2 Span-by-Span
Care must be exercised to maintain This type of construction starts at
compression over the entire joint one end of the structure and pro-
area by means of temporary or per- ceeds continuously to the other end
manent post-tensioning until all of the structure, span-by-span, as
of the permanent tendons are opposed to the balanced cantilever
stressed. The magnitude of stresses, where construction starts at the
segment alignment, and elevations piers and symmetrically moves out
must be evaluated at all stages of from the piers. In this type of con-
construction. struction segments are supported
The advantages of cantilever con- during construction by a moveable
struction are minimal interference falsework. The Long Key Bridge in

Fig. 14. Balanced cantilever construction employing a launching girder at the


Sallingsund Bridge. Denmark.

PCI JOURNALJJanuary-February 1982 31


Fig. 15. Precast segments For balanced cantilever construction of the Pasco-Kennewick
Bridge in Washington State.

Florida [see Fig. 16(a)] uses a the span-by-span method described


structural steel trusswork soffit above in that construction starts at
mounted on adjacent piers, which one end of the structure and pro-
is moved by a barge-mounted crane ceeds continuously to the other end
from span to span.20,2' of the structure. The progressive
The segments could be assem- placing method is based on the bal-
bled in final position on falsework anced cantilever concept. In this
(or fill), they could be assembled on method, the precast segments are
the ground and lifted into place, or placed continuously from one end
they could be assembled on false- of the structure to the other in suc-
work parallel to the final location cessive cantilevers on the same
and pushed laterally into place. side of the various piers, rather than
The segments could also be par- by balanced cantilevers on each
tially assembled on the ground, side of the pier.
lifted onto falsework, and the as- Because of the length of can-
sembly completed on the false- tilever (one span) in relation to con-
work. An experimental bridge con- struction depth, the erection
structed at the Pennsylvania Trans- stresses become prohibitive and
portation Research Facility 1 ' was temporary supports such as cable
erected on non-movable falsework stays or pier bents are usually re-
as shown in Fig. 16(b). quired. The erection procedure
2.8.3 Progressive Placing utilizing temporary stays is illus-
Progressive placing is similar to trated in Fig. 17. The first few seg-

32
Fig. 16(a). Span-by-span technique using movable steel truss (Long Key Bridge).

Fig. 16(b). Span-by-span technique using falsework at Pennsylvania Transportation


Research Facility.

ments placed near the pier may be quired to control the cantilever
placed in a cantilever fashion until stress.
the stresses become excessive. At This method can be used to ad-
this point temporary stays (or some vantage where site conditions pro-
other temporary support) are re- hibit the use of the span-by-span

PCI JOURNAl.JJanuary-February 1982 33


Fig. 17. Schematic of progressive placing technique (from Reference 4).

method. Where access to pier loca- ally launched segmental bridge


tions is precluded, this method can constructed in the United States,
be used to transport equipment and carries two lanes of U.S. 136 over
materials for pier construction from the Wabash River near Covington,
above, over that portion of the Indiana. It is a six-span structure
completed structure. This method with end spans of 93 ft 6 in. (28.5
is of interest for applications in the m) and four interior spans of 187 ft
100 to 160-ft (30.5 to 48.8 m) span (57 n).22,23
ranges. In this type of construction seg-
2.8.4 Incremental Launching ments of the bridge superstructure
Another variant of the segmental are positioned to the rear of the
concept has evolved in Europe. In abutment and post-tensioned to-
the United States, it is referred to as gether. The assembly of units is
incremental launching or push-out launched stepwise forward one unit
construction. The first increment- at a time to allow for succeeding

34
Fig. 18. Schematic of incremental launching
sequence (Courtesy of F. Leonhardt).

units to be positioned to the rear of longitudinal direction as shown in


the abutment. Fig. 18. To allow the superstructure
Bridge alignment in this type of to move forward, special sliding
construction may be either straight bearings are provided. To reduce
or on a curve; however, the curve the large negative bending mo-
must be a constant radius curve, ments that the structure would be
vertically and/or horizontally. subjected to during launching, a
Longitudinal prestressing con- fabricated structural steel launching
sists of two families of tendons: nose is attached to the lead seg-
tendons concentrically placed and ment. Long spans are subdivided
tensioned before launching, and by means of temporary piers to
tendons placed and tensioned after keep negative moments at an ac-
launching, that is, negative moment ceptable level.
tendons over the supports and pos- Complete coordination of all op-
itive moment tendons in the bottom erations is essential to prevent the
of the section in the central portion occurrence of a "runaway struc-
of the span. ture," unexpected twist, or exces-
Hydraulic jacks are used to pro- sive displacement of the structure
gressively launch successive con- while on or between temporary or
centrically prestressed units in a final supports.

PCI JOURNAL/January-February 1982 35


CHAPTER 3- FABRICATION OF PRECAST
SEGMENTS

3.1 General Considerations Because of economic consid-


It is generally preferable to use erations the variation of the cross
as few units as possible, consistent section of girder segments is gener-
with economic shipping and erec- ally limited to changing the depth
tion. During design of a segmental and the thickness of the bottom
structure, consideration should be flange. Curves in the vertical and
given to the selection of cross sec- horizontal direction and superele-
tions which simplify formwork, vation of the structure can be easily
lead to production efficiency, and accommodated.
overall project economy. If a segment is damaged beyond
In the case of girder segments, repair in transportation or erection,
economy and speed of production a new segment should be cast. It is
may be increased by: preferable to match-cast it against
(a) Keeping the length of the one or both of the mates but, if not
segments equal and keeping them possible, a tolerance provision
straight, even for curved structures. should be made for erecting the
(b) Proportioning the segments new segment which will not ad-
or parts of them, such as keys, in versely affect the geometry or
such a way that easy stripping of aesthetics of the completed struc-
the forms is possible. ture. If damage occurs to the joint
(c) Maintaining a constant web area during transporting or erec-
thickness in the longitudinal direc- tion, the segment may be erected at
tion. the discretion of the Engineer.
(d) Maintaining a constant thick- Generally, this will be allowed
ness of the top flange in the lon- when the damage is to a small area
gitudinal direction. and the damage is patched after
(e) Keeping the dimensions of erection. This precludes destroying
the fillet between webs and the top the fit of the match-cast surfaces.
flange constant. The location of the damage and its
(f} In case of variable depth, effect on the segment's strength and
keeping webs vertical to avoid a serviceability should be considered
variable bottom flange width. in the Engineer's decision.
(g) Avoiding interruptions of the Evaluation of segments having
surfaces of webs and flanges caused manufacturing defects should rec-
by protruding parts for anchorages, ognize that many of the segments in
inserts, etc. a segmental bridge may have ex-
(h) Using a repetitive pattern, if cess capacity since concrete dimen-
practical, for tendon and anchorage sions are kept constant for stan-
locations. dardization purposes and control-
(i) Minimizing the number of ling sections may be located else-
diaphragms and stiffeners. where in the structure. Bottom slab
(j) Avoiding dowels which pass and web dimensions, for example,
through the forms, when possible. are usually critical only in the sup-

36
port area. Honeycombing of ele- 3.2.2 The Short-Line Method
ments outside this area, provided it Principle —The segments are
is suitably repaired, need not be cast at the same place in stationary
cause for rejection. forms and against a neighboring
element. After casting, the neigh-
3.2 Methods of Casting boring element is taken away and
Segments to he erected with the last element shifted to the place
wide joints may be cast separately. of the neighboring element, clear-
Match-cast joint members are cast ing the space to cast the next ele-
by the "long-line" or "short-line" ment. A horizontal casting opera-
method. tion is illustrated in Figs. 20a
3.2.1 The Long-Line Method through 20c. Segments intended to
Principle — All of the segments be used horizontally may also be
are cast, in correct relative position, cast vertically.
on a long line. One or more form- Advantages — The space needed
work units move along this line. for the short-line method is small in
The formwork units are guided by a comparison to the long-line
pre-adjusted soffit. An example of method, approximately three times
this method is shown in Figs. 19a to the Iength of a segment. The entire
19c. For further practical details of process is centralized. Horizontal
the long-line fabrication method and vertical curves and twisting of
see Reference 24. the structure are economically ob-
Advantages — A long line is easy tained by adjusting the position of
to set up and to maintain control the neighboring segment.
over the production of the seg- Disadvantages — To obtain the
ments. After stripping the forms it desired structural configuration
is not necessary to take away the very precise workmanship, quality
segments immediately. control procedures, and geometry
Disadvantages — Substantial control are required. The neigh-
space may he required for the long boring segments must be accurately
line. The minimum length is nor- positioned for each match-casting.
mally slightly more than half the
length of the longest span of the 3.3 Formwork
structure. It should be constructed 3.3.1 General
on a firm foundation which will not All forms should be carefully de-
settle or deflect under the weight of signed and it is highly recom-
the segments. Because the forms mended that forms be designed by
are mobile, equipment for casting, Engineers with experience in the
curing, etc., has to move from place segmental method and the proce-
to place. In case the structure is dure, as well as form design.
curved, the long line must be de- Formwork should be designed to
signed to accommodate the curva- safely support all loads that might
ture. This, however, increases the be applied without undesired de-
complexity of the form and the formations or settlements. Soil sta-
more appropriate method to pro- bilization of the foundations may be
duce curved bridges is by the required, or the formwork may be
short-line method. designed so that adjustments can be

PCI JOURNAL1January-February 1982 37


Formwork

Fig. 19(a). Cross section of formwork using long-line method.

outside Formwork
Inside Formwork

ELEVATION

PLAN
Fig. 19(b). Formwork at start of casting (long-line method).

QQ

ELEVATION

Hil _
PLAN
Fig. 19(c). Formwork after casting several segments (long-line method).

38
AFTER STRIPPING DURING CASTING

r INSIDE
FORMWORK

CARRIAGE

TURN BU

Fig. 20(a). Formwork for short-line method. !t should be designed to facilitate


inspection.

age

Fig. 20(b). Formwork just before separation of segments (short-line method).

Fig. 20(c), Formwork just before casting next segment (short-line method).

PCI J0URNALl January-February 1982 39


Fig. 21. Form used to construct I-shaped girder segments. (Note: Plane
of deck may be varied with respect to web of I-beam).

made to compensate for settlement. given to those parts of the forms


Since production of segments is that have to change in dimensions.
based on multiple reuse of forms, To facilitate alignment or adjust-
the formwork should be sturdy and ment, special equipment, such as
special attention should be given to screw or hydraulic jacks, should be
construction details. Forms should provided.
also be easy to strip and handle. An Attachments to the form such as
example of a form used to construct anchorages, sheathing, blockouts
1-shaped girder segments is shown and inserts should be designed in
in Fig. 21. such a way that their position is
Cement paste Ieakage through rigid during casting. Fittings should
formwork joints should be pre- not interfere with stripping of the
vented. This can normally be forms.
achieved by using a flexible sealing Accelerated curing may cause
material. Special attention should temperature gradients in the con-
be given to the junction of tendon crete which may be harmful to the
sheathing with the forms. segments especially in the cooling
The forms may need to be flex- phase. Cantilever flanges and other
ible in order to accommodate slight thin elements cool faster than
differences of dimensions with the heavier parts of the section and
previously cast segment. They cracking of elements has occurred
should be designed in such a man- due to this phenomenon. This
ner that the necessary adjustments should be guarded against by close
for the desired camber, curvature control of the heating and cooling
and twisting can be achieved accu- process.
rately and easily. When using accelerated curing it
Special consideration should be is furthermore advisable to cure the

40
segment being cast together with Chapter 7 lists the requirements
the segment it was cast against. This for supplemental reinforcement.
prevents temperature deformations 3.3.4 Tolerances
of the hardened segment during Tolerances as specified by appli-
curing of the new segment which cable codes of practice can gener-
may lead to open joints upon erec- ally be used for segmental con-
tion. struction, It should be borne in
Internal vibration is commonly mind, however, that tolerances on
used. If the form is designed for dimensions which directly influ-
external vibrators they should be ence alignment or shape of the
attached at locations that will erected segmental structure require
achieve optimum consolidation and particular attention. Formwork for
permit easy replacement during the segmental box girder bridge con-
casting operations. To break the struction that meet the tolerances
suction during stripping, air jets
shown in Table 1 (see next page)
may be employed if required. are normally considered accept-
3.3.2 Provisions for Tendons able.
Holes for prestressing tendons Depending upon the detail at
may be formed by: bridge piers, the tolerances for the
(a) Sheathing which remains after soffit of the pier segment may need
hardening of the concrete. Flexible special attention. The actual di-
sheathing made of spirally wound
mensions of a segment should be
metal may be stiffened from the in- determined immediately after re-
side by means of inflatable rubber moving the forms. If specified tol-
duct tubes during the casting oper-
erances are exceeded, acceptance
ation. or rejection should be based on the
(b) Rigid sheathing with smooth
effect on final alignment and on
or corrugated walls may be used whether the effect can be corrected
that will not deform excessively
in later segments.
under the pressure of vibrating the
plastic concrete. Sheathing should 3.4 Concrete
be carefully aligned and tied at Uniform quality of concrete is es-
close intervals to avoid displace- sential for segmental construction.
ment. Procedures for obtaining high
Holes should be accurately po- quality concrete are covered in
sitioned, particularly when a large ACI,25 PCI,E8 and PCA27 publica-
number of holes are required. tions.
Often, sheathing with tendons in Both normal weight and struc-
place require no stiffening. Further tural lightweight concrete can be
information on forming holes for made consistent and uniform with
tendons and tendon anchorages is proper mix proportioning and pro-
presented in Chapter 6. duction controls, Normally concrete
3.3.3 Provisions for Supplemental for segmental construction will
Reinforcement have a slump of'3 to 5 in. (76 to 127
Supplemental mild steel rein- mm) and 28-day strength greater
forcement is used to resist forces than the strength specified by
not provided for by prestressing. structural design. It is recom-

PCI JOURNALJJanuary-February 1982 41


Table 1. Formwork tolerances for segmental box girder bridge
construction. (To correlate tolerances, see sketches on next page.)
Webthickness ...................................... ±Y4 in. (6.4 mm)
Depth of bottom slab ........................ ±'1a to 0 in. (6.4 to 0 mm)
Depth of top slab .....................................± % in. (3.2 mm)
Overall depth of segment .............. ±rlax in.lft (2.6 mm/m), of depth,
±' in. max, (12.5 mm)
Overall top slab width .......+'/s2 in./ft (2.6 mm/m), ± 1 in. max. (25 mm)
Length of match-cast segment (not cumulative) ................ ±¼ injft
(10.4 mm/m), + 1 in. max. (25 mm)
Diaphragmthickness .................................+ N in. (6.4 mm)
Grade of form edge and soffit ...............± Yls in. in 10 ft (0.5 mm/n)
Tendon hole location in bulkhead ................... ± '4 in. (1.6 mm)
Positionof shear keys ................................ ±'/a in. (3.2 mm)
Vertical plumbness ..................................±Vss in. (0.8 mm)
E nd squareness ......................................'/ss in. (0.8 mm)

Finished segment tolerances should not exceed the following:


Web thickness ...................................... ±% in. (9.5 mm)
Depthof hottom slab ........................+ r to 0 in. (12.7 to 0 mm)
Depthof top slab ............................... .....±'/4 in. (6,3 mm)
Overall top slab width .......± %a in./ft (5.2 mm/m), ± I in. max. (25 mm)
Diaphragm thickness ................................+ % in. (12.5 mm)
Grade of form edge and soffit ................± ys in. in 10 ft (1.0 mm/m)
Tendon hole location ............................... . ±% in. (3.2 mm)
Positionof shear keys ................................ ±' in. (6.3 mm)
Vertical plumbness ................................. ±ha in. (1.6 mm)
Endsquareness .................................... ± Ii s in. (1.6 nun)

mended that statistical methods be aggregates and poor sands should


used to evaluate concrete mixes. be avoided. Creep and shrinkage
The methods and procedures data for concrete mixes should be
used to obtain the characteristics of available or should be determined
concrete required by the design by tests.
may vary somewhat depending on It is dangerous to use corrosive
whether the segments are cast in admixtures such as calcium chlor-
the field or in a plant. The results ide or those containing substantial
will be affected by curing temper- chlorides, nitrates, sulphates and
ature and type of curing. Liquid or fluorides. Water-reducing admix-
steam curing or electric heat curing tures and also air-entraining ad-
may be used. mixtures which improve concrete
A sufficient number of trial mixes resistance to environmental effects,
should be made to assure uniform- such as deicing salts and freeze and
ity of strength and modulus ofelas- thaw actions, are highly desirable,
ticity. Careful selection of aggre- However, their use should be rig-
gates, cement, admixtures and idly controlled in order not to in-
water will improve strength and crease undesirable variations in
modulus of elasticity and will also strength and modulus of elasticity
reduce shrinkage and creep. Soft of the concrete.

42
/DVERALL TOP SLAB WIDTH
I
ENDON HOLE

0 000oQ 0000000

°o 0o DEPTH OF
DUCTS WEB
7 KEY TOP SLAB

OVERALL DEPTH
WEB OF SEGMENT
SS 90, THIC N SS
0 0 __ o 0
SQUARENESS —"— DEPTH OF
(MEAS. ON GRADE OF BOTTOM SLAB
DIAGONALS) FORM EDGE

WIDTH OF WEB

SEGMENTAL BOX GIRDER

POSITION OF POSITION OF
SHEAR KEYS - - --- i - SHEAR
-SHEAR KEYS

^+-DIAPHRAGM t I
WEB KEY I I THICKNESS I
--------4-4-------

GRADE OF SOFFIT —4— VERTICAL


PLUM RNESS

LONGITUDINAL SECTION

Isometric view and longitudinal section of box girder showing


tolerances designated in Table 1.

Mixes should be designed to to a level that subsequent drying


minimize creep and shrinkage. Re- will not produce unexpected de-
liable data on the potential of the formations.
mix in terms of strength gain and
creep and shrinkage performance 3.5 Joint Surfaces
should be used as a basis for im- Requirements concerning surface
proved design parameters. condition should be stricter for
Proper vibration should be used match-cast joints than for wide
to afford use of lowest slump con- joints filled with mortar or concrete.
crete and to allow for the optimum 3.5.1 Quality
consolidation of the concrete. Best results in match-casting are
Consideration should be given to achieved if the joint surfaces are
delaying erection of segments until even and smooth. Surface crushing
their internal moisture is reduced or chipping off of edges during

PCI JOURNALJanuary-February 1982 43


post-tensioning caused by point when producing segments joined
contact are thus avoided. by post-tensioning. Care is required
Chamfers at match-cast joints are to prevent leakage or penetration
not recommended since they are of joint-filling materials into the
difficult to manufacture and de- duct so as to prevent blocking the
crease the joint contact area consid- passage of the tendons,
erably. In case chamfers are con-
sidered desirable, as may be ex- 3.6 Bearing Areas
pected in buildings or special Bearing areas at reactions should
structures with exposed "architec- be smooth and in frill contact to as-
tural" surfaces, the effect of the sure uniform distribution of bearing
area reduction should be duly in- forces. If possible, in view of man-
vestigated. For wide joints, rough ufacturing and erection tolerances,
surfaces are preferable as they pro- it may be desirable to place bearing
duce better bond between segment elements like pads or steel plates in
and filling material. the forms before casting. Other-
3.5.2 Holes for Tendons and wise, cement mortar or an epoxy
Couplers mortar may be required between
holes or sheathing for tendons the segment and bearing area to en-
should be located very precisely sure full contact.

CHAPTER 4— TRANSPORTATION, STORAGE AND


ERECTION OF PRECAST ELEMENTS

4.1 General determined carefully to prevent


Due to the interdependence
damage of segments during han-
which exists between design, fabri-
dling. Lifting hooks or inserts
cation, and erection, close coordi-
should have an adequate safety
nation is required and is of major factor, a minimum of 4.0 on han-
importance. The design concept, by
dling loads plus 50 percent impact
specifying member size, generally
is suggested. Transportation over
dictates the choice of transportation
uneven surfaces may produce static
methods. Erection methods may
and dynamic stresses which need to
also be dictated by the design con-
be considered, especially at an
cept.
early age of a segment. Special care
should be exercised during han-
4.2 Plant Handling and dling and transportation to protect
Transportation cantilevers or projections against
Segments should he handled damage or cracking.
carefully, without impact, in a Plant handling and transportation
manner that limits stresses to val- greatly influence the construction
ues compatible with the strength cost. The way the segment is trans-
and age of the concrete. Location of ported from the casting yard into its
lifting hooks and inserts should be final position, the site conditions,

44
Fig. 22, Winch and beam erection method.

segment weight and number of re- Stacking may induce deformations


handlings are major parameters in- in the segment which may
fluencing costs. "lock-in" because of creep and ad-
Since it is essential to prevent ditional strength gain of segment
deformation of the segments caused concrete while in storage.
by uneven settlement, especially Inserts, anchorages, and other
twisting, storage should be on embedded items may need to be
sound supports. Segments should protected from corrosion, and from
not be unnecessarily exposed to penetration of water or snow during
uneven shrinkage caused by mois- cold weather. Contact surfaces to
ture loss due to excessive wind or be bonded with epoxy should be
partial sunlight exposure. Storage of kept free of contaminants.
segments should be arranged to Scheduling of segments is very
minimize damage, deflection, twist, important; fabrication, transporta-
and discoloration of the segments. tion, and erection schedules should
Stacking should be limited to avoid be coordinated so that at least the
excessive direct or eccentric forces. next matching segment is delivered

PCI JOURNAUJanuary-February 1982 45


to the job site before the previous where access is easily available.
segment is erected. Portal cranes straddling or attached
Transportation may be by truck, to the decks have also been used.
rail, or barge or a combination of Cranes can be used with balanced
such modes. Modification of trans- cantilever, span-by-span, and pro-
portation vehicles or equipment gressive placing types of con-
may be dictated by size and weight structiou.
of the segment. Local hauling reg- 4.3.2 Winch and Beam
ulations may limit width, length, The winch and beam (see Fig.
height, and weight of segments for 22) is a lifting device that extends
transportation over highways with- over the completed portion of the
out special permits. bridge deck on a short cantilevered
mechanism anchored to the bridge
deck. From this position, a segment
4.3 Erection Methods is lifted and held in place until
Erection is commonly accom- post-tensioning can occur. After
plished by truck, crawler, or barge post-tensioning, the winch and
mounted cranes; winch and hoist; beam is moved onto the newly
launching girder; or at times, by added segment and the process is
specially designed equipment cus- repeated.
tom made for the project. Precast column segments may be
Several parameters will influence placed on the column with the
the method of erection. The size same basic equipment cantilevered
and weight of the unit will deter- temporarily out from a tower at-
mine, or be determined by, the tached to the completed portion of
erection equipment available. The the column. The winch and beam is
height of the structure above exist- commonly used with balanced can-
ing terrain, or navigation clearance, tilever and progressive placing
will determine if the units can be types of construction.
erected by truck, crawler, or barge 4.3.3 Launching Girder
mounted cranes. In some cases, The launching girder (see Fig.
precast units may be Iifted up from 14) is a special mechanism that
a barge or truck by a winch and travels along the completed deck
hoist located on the pier or com- spans and maintains the work flow
pleted portion of the structure. If at that level. The essential parts of
the height of the structure is such the launching girder are a main
that truck or barge cranes are not truss with a length somewhat
practical or if the structure is a long greater than the maximum bridge
viaduct, a movable launching girder span, three leg frames which are
or a movable falsework may he attached to the main truss, and a
necessary and economically justifi- trolley which travels along the
able. bottom chord of the girder and is
capable of moving the segment in
the longitudinal, transverse, and
4.3.1 Cranes vertical directions, During con-
Mobile cranes moving on land or struction, by assuming various po-
floating on barges may be used sitions, the girder can place seg-

46
0

c = Real slope change


e = Theoretical slope change
I4-el 3%

Fig. 23. Longitudinal slope change tolerance.

ments in cantilever, place segments ous post-tensioning, temperature


over piers, and can move to the effects, settlement or other loading
next span so that the construction conditions should be investigated
process can be repeated. This is the before final post-tensioning of the
fastest method of cantilever con- structure.
struction, but it is limited to large
projects because of the high initial 4.5 Erection Tolerances
cost of the launching girder, The erection tolerances dis-
cussed below apply principally to
segmental box girder bridges.
4.4 Erection Considerations Maximum deviation between
Segments should be stabilized outside faces of adjacent segments
and braced to resist construction in the erected position should not
loads, impact, wind loads, acciden- exceed 1/a in. (6 mm). Longitudi-
tal forces, etc. Segments must be nally, the angular deviation from
free from restraint during post-ten- the theoretical slope change be-
sioning. tween two successive segments is
Depending on the type of recommended not to exceed 0.3
construction/erection methods percent as shown in Fig. 23. Trans-
utilized, changes in post-tensioning versely, the angular deviation from
forces may affect various conditions the theoretical slope difference
which should be considered in de- between two successive segment
sign. These may be the redistribu- joints is recommended not to ex-
tion of forces at supports, stability ceed 0.1 percent as shown in Fig.
due to prestressing, effect of reac- 24.
tions (shear) at temporary supports The most important item of toler-
or the additional loads imposed by ance or acceptance is the final
heavy handling, lifting equipment overall geometry of the erected
or devices. superstructure. The elevation of the
The shortening of the segments deck surface in the completed
and jointing material due to previ- structure should not vary substan-

PCI JOURNAWanuary-February 1982 47


design incorporates a wearing sur-
W
face andlor separately cast traffic
barriers or edge beams which per-
mit a smoothing out of smalI align-
ment and elevation errors. For this
reason, it is recommended that
traffic barriers and edge beams be
cast separately (they may be cast in
place or precast) and not precast
with the segments.s
w = Real slope difference
In case correction in the align-
= Theoretical difference ment is required, adjustments
should be acceptable to the En-
gineer. Stainless steel wire mesh
llia in. (1.6 mm) thick with mesh di-
Fig. 24. Transverse slope difference
tolerance.
mensions of in. (3.2 mm) embed-
ded in the epoxy joint have been
used for this purpose. Insertion of 8
tially from the theoretical profile x 12-in. (200 x 300 mm) shims of
grade elevation. In cantilever built this kind brings about a small an-
structures the final elevation is ob- gular change. However, undesira-
tained only after completion of the ble stress concentrations should be
closure sections between succes- guarded against. Solid steel plates
sive cantilevers, subsequent post- are, for this reason, less suitable. If
tensioning, and after all creep and a larger joint is required, the seg-
shrinkage have taken place. ments should be held in place until
For bridge decks more liberal an adequate cast-in-place joint is
tolerances may he accepted if the constructed.

CHAPTER 5- JOINTS
5.1 General further discussion of design consid-
Joints separate the structure into erations for joints is presented in
a number of segments. It is gener- Chapter 7.
ally preferable to use as few seg- joints are either wide or match-
ments as possible consistent with cast. Wide joints may be cast in
transportation and erection eco- place with concrete, dry packed
nomics. The joint surface is usually with mortar, or grouted. Match-cast
oriented approximately perpen- joints are normally bonded with
dicular to the centroidal axis of the epoxy but dry joints have been
structure. used in special instances. For all
The capacity of a joint is a func- types of joints the surfaces must be
tion of the prestressing force nor- clean, free from grease, oil or other
mal to the joint and development of contaminates. Where epoxy bond-
friction on the joint face. This ing is to be used the joint surfaces
Chapter discusses the joint types. A should be lightly sandhlasted while

48
maintaining the match-cast fit. to ensure maximum compaction.
Post-tensioning tendons crossing Serration of the joint is recom-
joints should be approximately per- mended.
pendicular to the joint surface in The height of each concrete
the direction of the smaller dimen- placement or lift must be limited so
sion of the segment element con- that the concrete can be properly
cerned, i.e., flange or web thick- consolidated. Ports are normally
ness; but may be inclined in the di- provided in the joint form for in-
rection of the larger dimension, i.e., spection. Formwork should be
flange width or web depth. This is sealed to prevent leakage of paste.
to minimize any unbalanced Cast-in-place joints should be ade-
shearing force which could lead to quately cured.
dislocation of edge zones at joints. The sharpness of line of assem-
Holes for the passage of tendons bled segments with wide joints de-
must be located very precisely. pends mainly on the accuracy of the
Particular care is required to com- manufacturing of the joints during
pletely seal tendon ducts at joints erection and less on the accuracy of
in order to prevent penetration of the segments. Curvature and
joint filling material into the duct, twisting of the structure may occur
thereby blocking passage of ten- within the joints from the post-
dons, and also to prevent unsightly tensioning unless proper care is
leakage at joints during grouting. taken to prevent it.

5.2 Cast-In-Place Joints 5.3 Dry-Packed Joints


In the case of cast in place or The width of dry-packed joints
other types of wide joints, prior to should not exceed approximately
construction of the joint, the adja- 2' in. (65 mm). Mortar should be
cent concrete surfaces should be introduced into the joint in batches
roughened and kept thoroughly not exceeding 10 lbs (4.5 kg) by
wet, or a bonding agent approved weight. Each batch should be
by the Engineer may be applied. thoroughly tamped and packed be-
The design width of a joint must fore the next batch is placed. Mor-
allow access for coupling of con- tar should be rammed into place
duits, welding or lapping of rein- using a heavy hammer and ram, or a
forcement, and thorough compac- pneumatic tamper. Containment
tion of concrete. Typical joint formwork may be necessary, par-
widths are equal to the deck slab ticularly at the bottom of the joint.
thickness or one-half of the web The strength of the mortar in the
width, but not less than 4 in. (100 joint may be lower than that of the
mm). concrete in the adjacent segments
The compressive strength of the and this factor may be a critical de-
joint concrete at a specified age sign consideration for the structure.
should be equal to the strength of The use of special high strength
the concrete in the adjacent precast mortars may have to be considered.
segments. High early strength The mortar should have a compres-
portland cement may be used. sive strength of at least 4000 psi
Aggregate size should he selected (281 kglcm2 ) measured on cubes in

PCI JOURNAL)January-February 1982 49


accordance with ASTM C-109. 2 If sedimentation has occurred.
an expansive additive is used the In both grouting methods venting
U.S. Army Corp. of Engineers is of extreme importance. Horizon-
Specification CRD-588 30 may be tal joints should be vented at the
used. Mortar should be thoroughly highest points and at several points
mixed and have zero slump. on each side. The vents should
Maximum aggregate size normally have provisions for closure which
does not exceed is in. (5 mm). can withstand grout pressure. The
strength of the grout in the joint
5.4 Grouted Joints may be lower than that of the con-
The width of grouted joints crete in adjacent segments and this
should not exceed approximately I factor may be a critical design con-
in. (25 mm). Grouted joints may be sideration for the structure. The
made with either gravity or pres- compressive strength of the grout at
sure methods. In either case provi- a specified age should be at least
sions should be made to contain the 4000 psi (281 kglcm l ) measured on
grout. cubes in accordance with ASTM
When gravity grouting is used, C-109.2& If an expansive additive is
rodding or tamping should be used used the U.S. Army Corp. of En-
to consolidate the grout. Problems gineers Specification CRD-5883°
may be encountered with gravity may be used. Non-metallic grout
methods, particularly on horizontal mixes should he used when the
joints. For this reason the grout grout will be exposed to weather.
should consist of approximately
three parts of cement, one part of 5.5 Match-Cast Joints
clean sand passing a #16 mesh 5.5.1 Epoxy Bonded Joints
screen, and a water-reducing agent Epoxy resins used for bonding of
which minimizes sedimentation. match-cast joints are high quality
The total water content should be products having compressive, ten-
kept as low as practical. Shrinkage sile, bond, and shear strengths
compensating additives should be equal or superior to concrete.
considered. These products are subject to strict
Pressure grouting of joints re- specifications and laboratory cer-
quires adequate preparations and tification of their chemical, physi-
equipment that is in good and clean cal and mechanical properties.
condition. The joint should be Manufacturers' recommendations
tightly sealed in order to sustain the for successful application in the
pressure. Pressure grouting is par- field should be strictly adhered to.
ticularly effective when joint forms The three major purposes of
can be easily used. Joint forms epoxies used in match-cast joints
should be vented. At the conclusion are:
of the grouting operation, the vent 1. Epoxy serves as an erection aid.
should be closed, and the pressure A. The epoxy, while in its gel
increased a minimum of 15 psi (1 form, serves as a lubricant between
kg/cros ) at the vent. Twenty-four segments during the fitting process.
hours after grouting, the vent B. The epoxy serves as a medium
should he opened and filled if for filling up unwanted voids and

50
surface flaws on the jointing sur- joints see Section 7.4.
faces. Bridge model tests and other
2. Epoxy improves the durability cif structural tests having epoxied
match-cast joints. joints with large keys have been
A. Complete filling of the joint tested up to failure and were found
provides weather tightness. to perform excellently. Breen stated
3. Epoxy improves the structural that "Epoxied joints did not induce
performance of match-cast joints. any discernable weakness of this
Since the tensile strength of type of construction. "31
epoxy itself and the bond strength If this high-performance epoxy is
between epoxy and concrete can be not provided, the joint or key will
equal or superior to the tensile be a plane of weakness in the
strength of concrete, the use of a structure. The durability, capacity
suitable epoxy restores "the tensile to sustain overloads, and moment
strength of concrete" at the match- capacity of the individual slabs at
cast joints. The significance of this the joints are affected, and must he
is: attended to by using alternative
A. The use of epoxy increases the methods.
overload at which the joint opens 5.5.1.1 Selection of Epoxy
and makes the magnitude of this The compressive strength of the
equal to the load required for epoxy should equal that of the con-
cracking the sections surrounding crete in adjacent segments under
the joints. Crack development any environmental condition that
under overloading tends to be may be encountered during the life
similar to that in a monolithic of the structure.
structure. This also improves the Only highly cross-linked epoxy
tightness of the closure of such adhesives that have been
cracks upon removal of the load. thoroughly tested in accordance
B. The joints are subjected to with current ASTM32 and applica-
secondary effects which make com- ble industry standards should be
plete restoration of tensile strength used. Information which should he
desirable. For example, tempera- obtained from the manufacturer, or
ture gradients in top slabs of box be determined by test, must in-
girder bridges can cause consider- clude as a minimum:
able tensile stresses. Also, the dis- (a) Workability, pot life and
tribution of bending moments in "open time" at various tempera-
the top slab caused by wheel loads ture s.
is more effective across moment- (b) Compressive strength and
resisting joints. It is evident that modulus of elasticity at various
joints without epoxy do not have temperatures after curing for at
moment capacity unless there is least 7 days at 68 F (20 C).
substantial compression normal to (c) Direct shear strength of
the joint face. Such compression is bonded concrete prisms at various
usually not provided in negative temperatures, with notation of
moment areas of box girders de- whether failure occurs in the joint
signed for zero tension under full or in the concrete.
loading. For a further discussion of (d) Ability to bond in such a way

PCI JOURNAUJanuary-February 1982 51


that the tensile strength of the con- the duct, and to seal any pockets
crete is fully restored. that form at the joint.
(e) Creep behavior of the epoxy In the case of unforseen inter-
compound. ruptions, the "open time" may have
5.5.1.2 Application of Epoxy expired before the segments are
The adhesive should be supplied fully joined. In such an event the
in preweighed packs or cans of epoxy should be completely re-
resin and hardener component. moved according to the instructions
Resin and hardener should have of the manufacturer. Sandblasting
different colors. may be necessary. Particular atten-
Components of the epoxy mix tion to the manufacturer's recom-
should be proportioned and mixed mendations and AASHT0 93 is re-
thoroughly until a uniform color is quired in cold weather.
obtained, following the instructions 5.5.2 Dry Joints
of the manufacturer. Each batch The requirements for the use of
should be assigned a number. The dry joints are similar to those for
adhesive should be applied im- epoxy bonded joints but with an
mediately after mixing, and the even greater emphasis on the qual-
joint surfaces brought together be- ity of the matching faces. Surfaces
fore the pot life expires. A record of should be carefully checked to en-
the location of the joint where the sure that any high points or other
batch of epoxy is used, weather, projections are eliminated.
temperature, and observed pot life Care should be taken during
should be maintained. Tests should erection of segments to ensure that
be conducted to verify uniformity joints are completely closed before
of mixing in the field. applying the final prestress.
The concrete surfaces which are In bridge construction special
to be bonded should not be wet; a treatment is required at the deck
damp but not dark, shiny surface is level to seal the joints against pen-
permissible. A wet concrete surface etration of moisture. In cold cli-
may be dried with hot air prior to mates where de-icing salts are used
applying the adhesive. special care should be taken to pre-
The adhesive should be applied vent salt penetration through the
in a uniform thickness to both sur- joints into the tendon ducts. For
faces. Some post-tensioning should this reason the use of dry joints is
be applied within the "open time" not recommended where corrosive
of the adhesive. If the correct environments exist or where bridge
amount of adhesive has been used, decks are salted.
a little will extrude from the joint
when pressure is applied. It is rec- 5.6 Metal Joints
ommended that a minimum of 30 Mating pairs of steel plates which
psi (2 kglcm 2 ) be applied to the are joined by welding, or similar
joint. After the stressing has been suitable steel connections have
completed, a wiper should be been used. However, they should
pushed into each open tendon duct be considered more as connections
or sheathing to remove or even out than as typical joints between pre-
any epoxy that may have entered cast elements in segmental struc-

52
tures. Special attention is required be applied to prevent staining of
for welded joints to prevent crack- adjacent surfaces and to protect the
ing or spalling of the concrete. integrity of welds and contact sur-
Protection against corrosion should faces.

CHAPTER 6- POST TENSIONING TENDONS

6.1 Sheathing ducts exceeding 400 ft (122 m) in


Sheathing is used to form the length should be vented over each
holes or enclose the space in which intermediate support, and at such
the prestressing steel is located. It locations as shown on the plans.
is usually located inside the con- Intermediate vents may not be re-
crete section; however, in some quired for ducts less than 400 ft
cases it has been located outside (122 m) in length.35
the section. Sheathing placed inside the con-
The prestressing steel can be crete should be resistant to damage
placed with the sheathing, or in- caused during installation and
stalled after the concrete is placed. placing of the concrete and the in-
The cross section of the sheathing stallation of pull-through tendons.
should be adequate to allow proper If the sheathing wall has inade-
installation of the prestressing steel quate strength to resist such dam-
and to provide enough passage area ages, it may be protected by in-
for filling the sheathing with grout serting inflatable duct tubes, steel
subsequent to stressing, The ratio pipe, etc. during the placement of
of the net area of the prestressing concrete. The sheathing should be
steel to sheathing cross-sectional adequate to prevent leakage of con-
area should comply with the Guide crete into the void, and should be
Specification for Post-Tensioning secured against buoyancy.
Materials in Reference 34. For long When semi-rigid sheaths are
ten do , [more than 100 ft (30 m)l used, they should bend sufficiently
inserttci into the sheathing after the to follow the required tendon pro-
concrete is placed, it is recom- file. All sheaths should be tied
mended that slightly oversized either to the reinforcing bar cage or
sheathing be used to facilitate in- to special supports. Semi-rigid
stallation of tendons. (Note that the sheathing of 2 3/4 in. (70 mm) diam-
sheathing size given in Reference eter or larger should be tied at a
34 is considered a minimum.) maximum of 5-ft (1.5 m) intervals.
Sheathing should have sufficient Smaller diameter or flexible
grouting inlets, vent pipes for es- sheathing should be tied more fre-
cape of air, shut-off valves, and quently to minimize wobble.
drains to allow proper grouting and In certain applications, the
to avoid accumulation of water sheathing is arranged outside the
during construction in freezing cli- concrete section either in voids of
mates. For continuous structures, the section or along the outside of

PCI JQURNALJanuary-February 1982 53


the concrete cross section. In addi- sions should be made to assure that
tion to the requirements listed couplers can move during prestress-
above, all sheathing should be ing. Large coupler void areas
protected against corrosion or made should be deducted from gross sec-
of non-corrosive material such as tion areas when computing stresses
polyethylene. at the time of prestressing. Enclo-
Sharp curvature and/or changes sures around the couplers must be
of angle should be avoided and provided with a vent pipe.
sheathing splices should he tightly
applied and fastened to facilitate 6.3 Anchor Plates
the threading of tendons through The anchor plate is the compo-
the sheathing. nent of a post-tensioning system
Sheathing may be connected at which transmits the prestressing
the joints by: force from the tendon anchoring
(a) In the case of match-cast seg- device directly to the concrete. Its
ments, joining the two matching function is to distribute the con-
surfaces with the epoxy filler will centrated forces from the anchoring
establish the connection and con- device over a larger bearing area to
tinuity of the sheathing void. the concrete. The bearing surface
(b) Telescopic sleeves pushed should be perpendicular to the pre-
over the protruding ducts. stressing steel to prevent undesira-
(c) Screw-on type sleeves. ble secondary stresses of the pre-
(d) Rubber or plastic sleeves. stressing steel and to optimize the
(e) Gaskets. effectiveness of the anchors. The
In all cases, leak tightness should anchor plate should be of such
be assured to avoid the entrance of shape and dimensions as to limit
jointing materials into the sheath- the bearing stresses to those
ing, causing possible blockage. specified in the Post-Tensioning
Sheathing protruding from the sur- Manual, 34 the AASHTO Bridge
face is easily damaged, and must be Specifications, 33 or other applicable
repaired prior to making the con- codes. Mild steel reinforcement
nection. Post-tensioning ducts behind the anchor plates should be
should be swabbed or wiped to en- detailed to resist bursting stresses.
sure the removal or smoothing out 6.3.1 Anchor Plates Cast into
any epoxy that might have leaked Precast Segments
into the duct. This is the most commonly used
procedure. The concrete should be
6.2 Tendon Couplers thoroughly vibrated behind the
Couplers should be designed to bearing plate to avoid honeycomb-
develop the ultimate strength of the ing and to achieve proper strength.
tendons they connect. Adjacent to However, over-vibration may cause
the coupler, the tendon should be segregation of concrete.
straight for a minimum length of 12 6.3.2 Anchor Plates Placed Against
times the diameter of the coupler Precast Surface
unless the curvature is very minor When the bearing plate is placed
or the strength of the system is de- against the hardened surface of the
termined by tests. Adequate provi- precast element, dry-packed mortar

54
or another suitable material should tendon profile. The effects of con-
be used between the plate and the crete creep and changes of the
concrete to achieve a good degree statical system during construction
of stress distribution under the should be considered.
bearing plate. The strength of the Anchorages, couplers and splices
mortar or other material should not of post-tensioning tendons should
be less than the concrete strength preferably not be located in areas
on which it bears, and the thickness where yielding may occur under
of the joint should he limited to a ultimate load conditions.
maximum oft in. (50 mm).
The reinforcement of the con- 6.5 Placement and Stressing
crete underneath the dry-packed of Tendons
mortar or other material should be When tendons are installed in the
the same as if the plate was cast segments before casting, they are
into the precast segment. usually coupled together at each
The preparation of the surface joint. This construction method
under the bearing plate will de- permits stressing of part of a ten-
pend on the type of plate and don, after installing one or more
placing procedure used. segments, before the full length is
When the bearing plate is not completely installed.
cast into the concrete, the surface Tendons may also be installed
should be clean and free from after casting and erection in parital
foreign matter. The surface should lengths and coupled together at
be wire brushed to remove all la- special openings. Usually, how-
tents and loose concrete chips. If ever, these tendons are installed
the hearing plate is to be grouted, full length. It may be noted, that
proper bond should be assured. this coupling procedure permits
intermediate stressing of portions of
6.4 Tendon Layout the structure, by using tendons of
Attention should be given to the variable lengths, stressing the short
tendon layout to make it compatible ones first and long ones later. The
with: prestressing steel should be free of
(a) Sequence of the segmental detrimental rust when installed into
construction. the structure. Special attention
(b) Progressive and subsequent should be given to the temporary
load conditions which the segmen- corrosion protection of the pre-
tal structure will undergo while stressing steel until grouted.
being erected,
(c) Concrete placement. 6.6 Grouting
(d) Effective section used in de- The purpose of grouting is to
sign. provide corrosion protection to the
It is important to anticipate the prestressing steel, and to develop
secondary effects (stresses due to bond between the prestressing
restrained deformations) which steel and the surrounding concrete.
post-tensioning may have on the To accomplish this, the grout
structure, and how these effects can should fill all the voids in and
be influenced by changes in the around the post-tensioning tendon

PCI JOURNAL/January-February 1982 55


for its entire length. Grouting mate- the grout pumped into the sheath-
rials, preparation of grout, and ing.
grouting procedures should follow Grouting should not be done if
the Recommended Practice for the temperature in the duct is less
Grouting of Post-Tensioned Pre- than 35 F (2 C) or if the surround-
stressed Concrete 36 wherever ap- ing concrete temperature is less
plicable. than 32 F (0 C).
Grouting of tendons should be When grouting vertical tendons
completed as soon as practical after the potential of segregation of the
tensioning of the tendons. It is rec- grout is greater than with horizontal
ommended that all tendons which tendons. To minimize sedimenta-
are in the same group be grouted tion and to avoid dehydration and
within a short period of time. Grout consequent blockage of grout and
crossing over from one duct into possible joint leaks, the grout
another, which sometimes occurs at should have the property of in-
a joint, will be easier to detect and hibiting water separation when
remedy if all tendons in the group under pressure. Additives for this
are grouted in a short interval of purpose may be used with approval
time. of the Engineer.
As a consequence of this prac- Precautions should be taken to
tice, some time may elapse be- reduce the danger of blockage of
tween stressing and grouting of grout due to the couplers. Couplers
the first tendon in such a group. If are generally housed in a special,
the period of time that a tendon is enlarged encasement, which
left ungrouted exceeds 20 days, 37 a should:
temporary corrosion protection (a) Have the same open cross
system for the tendon should be sectional area for passage of grout
employed. as the rest of the tendon.
Grouting is preferably done from (b) Be provided with a grout inlet
the lowest points of the tendon, to- and/or vent pipe.
ward the higher points, where vent
pipes should be installed. The 6.7 External Tendons
grouting should be done slowly and External tendons have been used
at low pressure to insure full dis- in segmental construction. Atten-
placement of the air. Highly tion should be paid to the strength
pressurized and rapid grouting may of the anchorage in relation to the
create entrapped air. The tendon tendon, corrosion protection, and
may be flushed with water before the ultimate moment and shear
grouting to avoid blockage when capacity of the structure.
injecting the grout. Sufficient If external tendons are used, con-
purging of grout should be allowed struction details should prevent ac-
to demonstrate that the exiting cess of water into the ducts or an-
grout has the same consistency as chorages.

56
CHAPTER 7- DESIGN CONSIDERATIONS
7.1 General Handling and storage of precast
The analysis and design of seg- segments requires special attention
mental structures are essentially so that no warping or bending of
the same as for monolithic pre- individual segments will take
stressed concrete structures except place. It is suggested that the En-
that due consideration should be gineer specify the method of sup-
given to the following items: port during storage and handling.
(a) Redistribution of forces due to
creep of concrete, which changes
the stresses of the as built condi- 7.4 Joint Design
tions, and erection conditions. The joints between segments
(b) Weather-proof tightness and should he capable of transferring the
strength of connections and joints. compressive, shearing, and tor-
(c) Storage and handling of seg- sional forces determined by the de-
ments before and during construc- sign. There should be no tensile
tion. stresses in extreme fibers when all
(d) Camber, during erection and possible design loads such as live
in the casting bed. load, temperature, wind, construc-
tion loads, etc. are properly consid-
7.2 Force Redistribution ered. Longitudinal bending mo-
In most cases, the statical system ments in the top slab due to wheel
of the structure during construction loads should be included in the
stages is not the same as in the final analysis. Temperature variation
stage under service load. Redis- through the cross section may cause
tribution of forces due to creep and significant stresses in bridge
shrinkage of concrete should be superstructures and should not be
considered. neglected.
As the structural system changes The joints are subjected to shear
during construction, creep of con- stresses. In box girder bridges, the
crete tends to redistribute the mo- joints are generally perpendicular
ments and forces in the structure to to the neutral axis. Shear forces act
approach the conditions as if the in the plane of the joint, and per-
structure were built totally on pendicular to that plane are pre-
falsework. However, depending on stressing forces. In many precast
environmental factors, concrete segmental bridges, the ratio of the
properties and construction prestressing forces and shear forces
schedules, the degree of this redis- is seldom less than 5. For a dry
tribution varies. match-cast concrete-to-concrete
Calculation of the force redis- joint, if the friction coefficient is as-
tribution may follow the recom- sumed to be 1.0, the resulting
mendations of ACT Committee safety against sliding would equal
209311 or other recognized methods. 5. Therefore, under those condi-
tions, dry joints of this type would
7.3 Handling and Storage of safely transfer the shear even with-
Segments out keys or serrations. If the

PCI JOURNAL/January-February 1982 57


match-cast joint is filled with shear forces higher than possible
epoxy, the "friction concept" with a single, large key.
applies as well. The large key is easily designed
Shear in match-cast joints can be as a corbel, and leaves ample op-.
safely transferred without keys, portunity for penetration of the
using either dry or epoxied joints. matching surfaces by anchors, ten-
The epoxy joint, however, is mostly dons, etc. The large keys are lo-
used because of its other desirable cated in or near the neutral axis of
properties. Note that all require- the section. This ensures placement
ments are satisfied only by using in a compression zone even in case
epoxies with good bond capabilities of moment reversals.
and tensile strength. Tests per- The shear capacity of' multiple
formed on epoxy joints have dem- keys depends largely on the two-
onstrated their adequacy. dimensional stress condition in the
7.4.1 Shear keys caused by compression and
Shear-friction provisions are shear very similar to the dry
given in AASHTO Specifications "9 concrete-to-concrete joint. As in any
and in the AC! Building Code other joint, the multiple key de-
(318-77). 44 Diagonal or vertical web pends, for its strength, on compres-
tendons may he used to reduce sion normal to the joint. As a con-
shear forces or to increase shear sequence of this, multiple keys lo-
capacity; however, attention should cated in a precompressed tension
be given to the location of these zone may have little to contribute
tendon anchorages. If tendons are to shear transfer under full load,
considered effective for increasing because of a low ratio of normal
the shear capacity they should meet force to shear force.
the applicable provisions of' the 7.4.3 Compression
Specifications" or Codes 44 for de- As indicated in Chapter 5, the
veloping shear reinforcement. If compressive strength of materials
wide joints are used, they should used in a joint may be lower than
contain non-prestressed shear that of the concrete in adjacent
reinforcement equivalent to that in segments and this factor may be a
the adjacent segments. critical design consideration for the
7.4.2 Keys structure. If a dry joint is used, con-
Keys in the webs and slabs of sideration should be given to the
segments are useful to facilitate prevention of spalling around the
alignment and to transfer shear edges of the contact area. It is rec-
during erection. Two systems are ommended that dry joints be used
used: only when previous performance
1. A large, single, reinforced key indicates acceptable transfer of
usually designed for transfer of forces and long-term weather-
shear caused by a number of seg- proofing.
ments.
2. A large number of unrein- 7.5 Auxiliary Reinforcement
forced small multiple keys which, In addition to the primary rein-
when properly arranged and de- forcement for transverse bending,
signed, are capable of transferring shear and torsion, auxiliary rein-

58
forcement is normally required in frame. Transverse prestressing in
segments for: the deck slab has often been used.
(a) Concentrated forces at reac- Deck slab design should also in-
tions and at tendon anchorages. clude longitudinal local bending
(h) Volume change forces. moment in the deck slab due to
(c) Temporary forces imposed wheel loads which can cause sig-
during fabrication, transportation, nificant flexural stresses. If curved
or erection. tendons are used, radial forces due
(d) Temperature gradient stresses to curvature of tendons should be
between the top and bottom of the considered. In some cases tendons
segment and between inside and are given curvature in addition to
outside surfaces of exterior webs. the principal tendon curvature at
Horizontal and vertical rein- certain locations in order to ac-
forcement should be placed be- commodate better distribution of
tween segments in wide joints voids in the concrete or arrange-
filled with mortar or concrete when ment of anchors; forces due to these
the transverse thickness of the joint secondary trajectories should be
is more than 2 in. (50 mm). carefully evaluated. Fillets or rein-
forcement may be added for this
purpose.
7.6 Design of Segments for Diaphragms are normally re-
Box Girder Bridges quired at abutments, piers and
lr or constant depth segmental hinges. Intermediate diaphragms
bridges, span-to-depth ratios from contribute very little to load dis-
18 to 25 are currently considered tribution and are not recom-
practical and economical. Midspan mended.
depth of variable depth girders may Special consideration should he
have span-to-depth ratios of 40 to given to the effects of severe en-
50; span-to-depth ratios of equal to vironmental exposure.
that of constant depth girders are For more information on seg-
used at the piers. mental box girder bridges refer to
Simple single cell box girders the Precast Segmental Box Girder
may be used if the width of the Bridge Manual.37
deck is less than 20 percent of the
span. This is based on the use of
simple beam theory for which the 7.7 Design of Segments for
distribution of longitudinal stresses Decked I-Beams
is limited to a deck width per web The spanning capability of typi-
of 10 percent of the span length. cal I-shaped sections is extended
For wider decks, multiple cells are when the beam and deck are pre-
desirable and the webs should be cast integrally.
located to reduce moments in the Moment redistribution due to
top slab and to minimize transverse creep of the concrete should be
bending of the webs. Generally, considered in order to estimate the
these moments are computed with interaction between the beams and
sufficient accuracy by considering the deck slabs if the structural sys-
the box section as a closed rigid tem changes during construction.

PCI JOURNAL'January-February 1982 59


REFERENCES
1. Leonhardt, Fritz, Prestressed Concrete Dallas-Ft. Worth Airport," PCI JOUR-
Design and Construction, Wilhelm NAL, V. 18, No, 6, Nov.-Dec. 1973, pp.
Ernst & Sohn, Berlin, Germany, 2nd 72-91.
Edition, 1964. 14. Arafat, Mahmoud Z., "Giant Precast Pre-
2. Billington, David P., "Historical Per- stressed LNG Storage Tanks at Staten
spective on Prestressed Concrete," PCI Island," PCI JOURNAL, V. 20, No, 3,
JOURNAL, V. 21, No, 5, Sept,-Oct. 1976, May-June 1975, pp. 22-33.
pp. 48-71. 15. Martynowicz, A., McMillan, C. B.,
3. Bennett, W. Burr, Jr., "Manufacture and "Large Precast Prestressed Vierendeel
Production of Prestressed Concrete," Trusses Highlight Multistory Building,"
PCI JOURNAL, V. 21, No, 5, Sept,-Oct. PCI JOURNAL, V. 20, No. 6, Nov.-Dec.
1976, pp. 191-203. 1975, pp. 50-65.
4. Muller, jean, "Ten Years of Experience 16. Perry, William E., "Precast Prestressed
in Precast Segmental Construction," Clinker Storage Silo Saves Time and
PCI JOURNAL, V. 20, No. 1, Jan.-Feb. Money," PCI JOURNAL, V. 21, No, 1.
1975, pp. 28-61. Jan. -Feb. 1976, pp. 50-67.
5. Lacey, Geoffrey C., Breen, John E., and 17. Anderson, Arthur R., "World's Largest
Burns, Ned H., "State of the Art for Prestressed LPG Floating Vessel," PCI
Long Span Prestressed Concrete JOURNAL, V. 22, No. 1, Jan.-Feb. 1977,
Bridges of Segmental Construction," pp. 12-31.
PCI JOURNAL, V. 16, No, 5, Sept.-Oct. 18. Ballinger, C. A., Podolny, W. Jr., and
1971, pp. 53-77. Abrahams, M. J., "A Report on the De-
6. Grant, Arvid, "Pasco-Kennewick sign and Construction of Segmental Pre-
Bridge—The Longest Cable Stayed stressed Concrete Bridges in Western
Bridge in North America," Civil Europe — 1977," International Road
Enginee ri ng-ASCE, V. 47, No. 8, August Federation, Washington, D.C., June
1977. 1978. (Also available from Federal
7. Grant, Arvid, "The Pasco-Kennewick Highway Administration, Office of Re-
Intercity Bridge," PCI JOURNAL, V. search and Development, Washington,
24, No. 3, May-June 1979, pp. 90-111. D.C., Report No. FHWA- RD- 78-44.)
8. Bridges, Conrad, and Coulter, Clifford 19. Podolny, W. Jr., "An Overview of Pre-
S., "Geometry Control for the Intercity cast Prestressed Segmental Bridges,"
Bridge," PCI JOURNAL, V. 24, No. 3, PCI JOURNAL, V. 24, No. 1, Jan.-Feb.
May-June 1979, pp. 112-125. 1979, pp. 56-87.
9. Carlson, C., Ady, Nancy, "Special Bib- 20. Gallaway, Thomas M., "Design Features
liography No. 185 — Segmented Post- and Prestressing Aspects of Long Key
Tensioned Construction," Portland Ce- Bridge," PCI JOURNAL, V. 25, No. 6,
ment Association, Skokie, Illinois, Nov.-Dec. 1980, pp. 84-96.
March 1968. 21. Muller, Jean, "Construction of Long Key
10. Carlson, C., Ady, Nancy, "Supplement Bridge," PCI JOURNAL, V. 25, No. 6,
to Special Bibliography No. 185 - Nov.-Dec. 1980, pp. 97-111.
Segmented Post-Tensioned Construc- 22. "First Incrementally Launched Post-
tion," Portland Cement Association, Tensioned Box Girder Bridge to be Built
Skokie, Illinois, October 1975. in the United States," Bridge Report,
11. Zielinski, Z. A., "Prestressed Slabs and Post-Tensioning Institute, Phoenix,
Shells Made of Prefabricated Compo- Arizona, December 1976.
nents," PCI JOURNAL, V. 9, No. 4, Au- 23. "Wabash River Bridge, Covington, In-
gust 1964, pp. 69-80. diana," Bridge Report, SR 201.01 E.,
12. Zielinski, Z. A., "Prefabricated Building Portland Cement Association, Skokie,
Made of Triangular Prestressed Compo- Illinois, 1978.
nents," ACI Journal, Proceedings V. 61, 24. Walker, Homer M., Janssen, H. Hubert,
No. 4, April 1964. and Kelly, John B., "The Kentucky River
13. Lamberson, Eugene A., "Post- Bridge — Variable Depth Precast Pre-
Tensioned Structural Systems — stressed Segmental Concrete Structure,"

60
PCI JOURNAL, V. 26, No, 4, July- 33, "Interim Specifications Bridges 1979,"
August 1981, pp. 60-85. Section 1.6.25, American Association of
25. ACI Manual of Concrete Practice, Part State Highway and Transportation Offi-
I, American Concrete Institute, Detroit, cials, Washington, D.C., 1979.
Michigan, 1979. 34. PCI Post-Tensioning Manual, Pre-
26. Manual for Quality Control . for Plants stressed Concrete Institute, Chicago,
and Pr»duction of Precast Prestressed Illinois, 1972. PTI Post-Tensioning
Concrete Products, Prestressed Con- Manual, Post-Tensioning Institute,
crete Institute, Chicago, Illinois, 1977. Phoenix, Arizona, 1976.
27. Design and Control of Concrete Mix- 35. Bezouska, T. J., "Field Inspection of
tures, Portland Cement Association, Grouted Prestressed Tendons," Project
Skokie, Illinois, 1979. No. 0906 71204, California Department
28. "Proposed Recommendations for Seg- of Transportation, Sacramento, Califor-
mental Construction in Prestressed nia, 1977.
Concrete," FIP Commission — Prefabri- 36. PCI Committee on Post-Tensioning,
cation, Third draft, September 1977. "Recommended Practice for Grouting of
29. 1980 Annual Book of ASTM Standards, Post-Tensioned Prestressed Concrete,"
Part 13, Cement; Lime; Gypsum, PCI JOURNAL, V. 17, No. 6, Nov.-Dec.
"ASTM C109-80 Standard Test Method 1972, pp. 18-25.
for Compressive Strength of Hydraulic 37. Precast Segmental Box Girder Bridge
Cement Mortars (Using 2-in. Or 50-mm Manual, Published Jointly by the Pre-
Cube Specimens)," American Society stressed Concrete Institute (Chicago, Il-
for Testing and Materials, Philadelphia, linois) and the Post-Tensioning Institute
Pennsylvania, 1980. (Phoenix, Arizona), 1978, 116 pp.
30. CRD-C588-60 Corps. of Engineers 38. Subcommittee 2, ACI Committee 209,
Specification for Expansive Grout. "Prediction of Creep, Shrinkage, and
31. Kashima, S. and Breen, J. E., "Con- Temperature Effects in Concrete
struction and Load Tests of' a Segmental Structures," Designing for Effects of
Precast Box Girder Bridge Model," Re- Creep, Shrinkage and Temperature in
search Report 121-5, Center Iar High- Concrete, SP-27, American Concrete In-
way Research, The University of Texas stitute, Detroit, Michigan, 1971.
at Austin, February 1975. 39. Standard Specification for Highway
32. 1980 Annual Book of ASTM Standards, Bridges, 12th Edition, American Associ-
Part 14, Concrete and Mineral Aggre- ation of State Highway and Transporta-
gates, "ASTM C881-78 Standard Speci- tion Officials, Washington, D.C., 1977.
fication for Epoxy-Resin-Base Bonding 40. "Building Code Requirements for
Systems for Concrete," American Soci- Reinforced Concrete (ACI 318-77),"
ety for Testing and Materials, Philadel- American Concrete Institute, Detroit,
phia, Pennsylvania, 1980. Michigan, 1977.

NOTE: Discussion of this report is invited. Please submit


your discussion to PCl Headquarters by September 1, 1982.

PCI JOURNAUJanuary-February 1982 61

You might also like