Professional Documents
Culture Documents
Guide Document
Phone: 312-786-0300 I Fax: 312-621-1114 I www.pci.org
Balloted by t h e
PC I Com mit tee on Br idg e s
and t he PC I Tec hn i c a l
Ac t ivit ies Coun c i l
This mater ial is disseminated under the
sponsorship of the U.S. D epar tment of
Transpor tation in the interest of infor mation
exchange under DTFH61‐13‐D‐00010 Task
No. 5009. The U.S. G over nment assumes no
liabilit y for the use of the infor mation. The
U.S. G over nment does not endorse produ c ts or
manufac turers. Trademar ks or manufac turers’
names appear in this mater ial only because
they are considered essential to the objec tive
of the mater ial. They are included for
infor mational pur poses only and are not
intended to reflec t a preference, approval, or
endorsement of any one produc t or entit y.
Guide Document
Phone: 312-786-0300 I Fax: 312-621-1114 I www.pci.org
Balloted by t h e
PC I Com mit tee on Br idg e s
and t he PC I Tec hn i c a l
Ac t ivit ies Coun c i l
This mater ial is disseminated under the
sponsorship of the U.S. D epar tment of
Transpor tation in the interest of infor mation
exchange under DTFH61‐13‐D‐00010 Task
No. 5009. The U.S. G over nment assumes no
liabilit y for the use of the infor mation. The
U.S. G over nment does not endorse produ c ts or
manufac turers. Trademar ks or manufac turers’
names appear in this mater ial only because
they are considered essential to the objec tive
of the mater ial. They are included for
infor mational pur poses only and are not
intended to reflec t a preference, approval, or
endorsement of any one produc t or entit y.
This document has been prepared and reviewed through an extensive Precast/Prestressed
Concrete Institute (PCI) Committee process to present a Guide Document on The Design
of Curved, Spliced U-Beam Bridges. Substantial effort has been made to ensure that all
collected data and information included in this report are accurate. PCI, the committee
members, the authors, and the quoted agencies cannot accept responsibility for any errors
or oversights in this report, the use of this material, or in the preparation of any design
and engineering plans. This document is intended for reference by professional personnel
who are competent to evaluate the significance and limitations of its contents and who are
able to accept responsibility for the application of the material it contains. Actual condi-
tions on any project must be given special consideration and more specific evaluation and
engineering judgment may be required that are beyond the intended scope of this work.
The contents do not necessarily reflect the official views or policies of the agencies men-
tioned, and do not constitute a standard or policy for design or construction.
All rights reserved. No part of this book may be reproduced in any form without the written
permission of the Precast/Prestressed Concrete Institute, except by a reviewer who wishes to
quote brief passages in a review written for inclusion in a magazine or newsletter.
Names: PCI Committee on Bridges, issuing body. | PCI Technical Activities Council, issu-
ing body. | Precast/Prestressed Concrete Institute, issuing body, publisher.
Title: Guide document for the design of curved, spliced precast concrete u-beam bridges /
balloted by the PCI Committee on Bridges and the PCI Technical Activities Council.
Description: First Edition. | [Chicago, Illinois] : Precast/Prestressed Concrete Institute,
[2020] | “A PCI report.” | Includes bibliographical references.
Identifiers: ISBN 9781733548885 (print) | ISBN 9781733548892 (ebook)
Subjects: LCSH: Bridges--Design and construction--Handbooks, manuals, etc. | Precast
concrete construction--Handbooks, manuals, etc.
Classification: LCC TG300 .G85 2020 (print) | LCC TG300 (ebook) | DDC 624.2/5--dc23
Printed in U.S.A.
FOREWORD
Precast, prestressed concrete has been used extensively in the nation’s highway bridges beginning in
1949. The rigorous construction of the interstate highway system in the 1950s, and the subsequent
development of higher performance materials and methods, resulted in the recognition that precast,
prestressed concrete is the most durable, cost-effective bridge construction solution for the span
ranges in which it is applicable.
PCI is acknowledged to be the body of knowledge of the precast and precast, prestressed concrete
industry. Since 1954, PCI has researched, refined, and published the technology of this industry. PCI
developed comprehensive guidelines and standards for drafting, design, production, quality control,
and installation of precast concrete. It administers the industry’s first and most comprehensive family
of certification programs for personnel, production, and erection of precast concrete―all of which are
predicated on a continuous process of quality improvement.
This Guide Document for the Design of Curved, Spliced Precast Concrete U-Beam Bridges has been
developed as a resource for bridge engineers. In nine chapters, the guide documents the advancement
of curved, spliced U-beam bridge technology. This technology, which originated and progressed initially
in Colorado over approximately 20 years, has evolved through the collaboration of designers,
contractors, and owners. Much of the current technology is in its second or third generation. Agencies
and builders have shown interest in replication of curved, spliced U-beam bridge technology in several
areas of the United States. However, there are certain areas of practice that have not been quantified.
This has made it difficult for owners and the design community to fully embrace the technical solutions
needed to design, construct, deliver, and maintain curved, spliced U-beam bridge systems.
There was a great need to capture the new advancements in complex and simple concrete bridge
technologies. With assistance provided by the Federal Highway Administration and in collaboration
with the American Association of State Highway and Transportation Officials, PCI enlisted a team of
subject matter experts and educational course developers to meet this need. In addition to this guide,
four training courses have been developed to facilitate the use of the curved, spliced concrete
technology and will be available through the PCI eLearning Center. All participants in developing the
guide and the associated courses have practical experience in the design of concrete bridge solutions,
and many have conducted university research and have NCHRP research program development
experience. Teams of subject matter experts reviewed and critiqued each new manual and course.
iii
THIS PAGE LEFT BLANK INTENTIOANLY.
iv
TRAINING
This Guide Document for the Design of Curved, Spliced Precast Concrete U-Beam Bridges has been
developed as a resource for bridge engineers. Four companion courses based on this document also
have been developed. In nine chapters and appendices, the guide document presents a summary of
current curved, spliced U-beam bridge technology through reference to completed projects and via the
use of a prototype example to step though the basics of the design and engineering of these bridge
structures.
Four instructor-led training (ILT) courses have been developed and delivered to facilitate the use of
this guide. These are now being converted to eLearning modules. The correlation between the chapters
of the guide and the four courses is shown in the figure below.
The Guide Document for the Design of Curved, Spliced Precast Concrete U-Beam Bridges and the related
courses present aspects of current technologies through generous reference to past projects and the
use of a prototype example. In the example, important aspects of curved, spliced precast concrete U-
beam bridge design are discussed and presented in sufficient detail to allow competent designers to
replicate and extend this technology.
The target audience of the Guide Document for the Design of Curved, Spliced Precast Concrete U-Beam
Bridges and its related courses includes bridge engineers of all experience levels, owners, and
contractors with interest in learning about and delivering this developing technology. There is no cost
to enroll in of the courses.
v
1 Develop understanding of curved, spliced, U-Beam technology
• Early development
• Typical applications
2. Understand U-beam cross sections, major components of U-beam systems, and fabrication
techniques
• Precast cross sections
• Precast fabrication
• Handling and transportation
• Components of curved, spliced U-beam systems
3. Understand the role of the designer, specialty engineer, and project specifications in project
delivery
• Designer role and stated assumptions
• The role of the specialty engineer
• Project technical specifications
• Construction engineering report
• Geotechnical topics
4. Understand the role of design criteria in stating important design assumptions, especially those not
clearly defined in current design codes
• Emerging technology, emerging design codes
• Design assumptions
• Limit states – permanent structure
• Limit states – construction phase
5. Understand critical elements and constraints for preliminary layout and sizing of a curved, spliced
U-beam bridge
• Typical Section
• Falsework towers, strongbacks, and ground splices
• Preliminary design guidance
After completing this course, the student will to understand the following:
• History and development of curved, spliced precast concrete U-beam bridge technology
• Major components associated with curved, spliced precast concrete U-beam bridges
• Design and contractual elements related to project delivery
• Applicability of concept and preliminary design engineering
vi
The second course uses a prototype bridge to develop an understanding of the methodologies and
techniques used to model, analyze, and design curved, spliced precast concrete U-beam bridges. Two
submodules are presented as follows:
1. Assumptions and techniques to develop a structural model to analyze the bridge
• Define prototype bridge
• Materials
• Section properties
• Construction sequence
• Model layout
• Temporary works and support conditions
• Pier fixity
• Results
• Time-dependent forces and stresses
• Deflections, camber, and buildup
2. Critical items for design during temporary phases of construction and in the permanent condition
• Handling, transport, and lifting out of forms
• Sectional design for ultimate limit states
• Sectional design for service limit states
• Geometry control
vii
• Diaphragms
• Bearings
After completing this course, the student will be able to understand fundamental concepts related to
the design and engineering of various design details of curved, spliced precast concrete U-beam
bridges.
viii
DEVELOPMENT AND REVIEW
Throughout the development of this document, strict adherence to PCI policies has been followed,
including a series of comprehensive reviews. The outline and each draft were reviewed by the PCI
Committee on Bridges and the AASHTO Committee on Bridges, Technical Subcommittee on Concrete
(T-10). The PCI Committee on Bridges reviewed and balloted the final draft. The document was
submitted to the PCI Technical Activities Council (TAC) for assurance that it meets the institute’s
standards for technical content and quality guidelines for presentation. Primary and secondary
comments resulting from these ballots were resolved by the primary authors and subsequently
approved by the reviewing committees.
ACKNOWLEDGEMENTS
During the development of this document, the primary authors, along with PCI members Gregg Reese,
Maher Tadros, Ozzie Bayrak, Andy Mish, and Reggie Holt spent time to resolve many of the outstanding
issues related to known best practices. Their hard work and determination to bring this manual and
training forward is appreciated.
Many others in addition to the contracted team engaged in discussions at the meetings and read one or
more of the progression of drafts. PCI wishes to thank all these professionals for their time and
expertise. Many of the state highway officials who participated in the writing and review of this
document are acknowledged below.
This PCI document was developed with the oversight of the PCI Committee on Bridges. The following is
a list of the active voting members of this committee at the time this document was balloted.
Finn Hubbard, Chair Reid Castrodale Andy Ko
Fickett Structural Solutions Castrodale Engineering STV Incorporated
Consultants, PC
Glenn Myers, Vice-Chair William R. Cox (retired) Todd Lang
Atkins North America American Segmental Bridge HDR
Institute
Steve Seguirant, TAC Liaison David Deitz Michael Laviolette
Concrete Technology Corp. Palmer Engineering HDR
Sameh S. Badie Kevin R. Eisenbeis Z. John Ma
George Washington University Burns & McDonnell University of Tennessee-Knoxville
Mr. Gregory Aaron Banks, PE Roy L. Eriksson Eric E. Matsumoto
WSP Eriksson Technologies, Inc. California State University
Oguzhan Bayrak Hussam (Sam) Fallaha Michael L. McCool
University of Texas at Austin Florida Dept. of Transportation Beam, Longest & Neff LLC
Shrinivas Bhide R. Jon Grafton Richard Miller
Consultant Formerly Oldcastle Precast, Inc. University of Cincinnati
JP Binard Mark Hoppe (Retired) Andrew Mish
Precast Systems Engineering Kansas DOT Modjeski and Masters Inc.
Richard Brice Troy Jenkins Andrzej S. Nowak
Washington State Dept. of Northeast Prestressed Products Auburn University
Transportation LLC
ix
Active voting members of PCI Committee on Bridges (cont.)
Pinar Okumus Gregg Reese Eric Steinberg
SUNY, University at Buffalo Modjeski and Masters Inc. Ohio University
Michael Oliva Bruce W. Russell Yuhe Yang
University of Wisconsin Oklahoma State University PCI Northeast
Tanarat Potisuk Francesco M. Russo William N. Nickas, Staff Liaison
Oregon Dept. of Transportation Michael Baker International (Non-voting)
Precast/Prestressed Concrete
Institute
Chuck Prussack (Retired) Monica Schultes
Oldcastle Precast Inc. MM Schultes Consulting
Mary Lou Ralls Newman Rita Seraderian
Ralls Newman LLC PCI Northeast
The following are consulting members of the PCI Committee on Bridges. Consulting members are not
held to the same strict attendance standards as voting members as set forth in the PCI Group Operations
Manual. Many of these members attended numerous meetings and participated in committee work
including oral and written reviews of the documents.
Tess Ahlborn William Colquett Zhengzheng Fu
Michigan Technological University Alabama Dept. of Transportation Louisiana Dept. of Transportation
& Development
Musa R. Alawneh John S. Dick David Garber
e.construct Fz LLC J. Dick Precast Concrete Florida International University
Alex Aswad (Retired) Daniel Dowling James S. Guarre
Pennsylvania State University Michael Baker International Berger ABAM/WSP
James M. Barker Bill Dreher (Retired) Antonio M. Garcia
The Collaborative Inc. Wisconsin Dept. of Transportation Garcia Bridge Engineers
Dean Bierwagen D. Scott Eshleman Silvio Garcia
Stanley Consultants Stanley Consultants Inc. Hardesty & Hanover
Scott R. Canfield Mohamed Essili Hossein Ghara
Johnson, Mirmiran & Thompson Consultant Volkert
Inc.
Vijay Chandra Jim Fabinski Michael Haas
VC Consulting LLC EnCon United Collins Engineers Inc.
Dave Chapman Jr. Matt Farrar Ziad Hanna
Knife River Corporation Northwest Idaho Dept. of Transportation Alfred Benesch & Company
Francisco De Jesus Chitty Pedro Fernandez Susan Hida
Florida International University David Evans & Associates Caltrans
Mi Geum Chorzepa Gregg Freeby Fouad Jaber
University of Georgia Formerly Texas Dept. of Nebraska Dept. of Roads
Transportation
x
Consulting Members of the PCI Committee on Bridges (cont.)
Brian Jenner Robert J. Peterman Christopher Michael Vanek
Forterra Building Products Kansas State University WSP
Bruce Johnson (Retired) Scott Phelan Colin Wayne Van Kampen
Oregon Dept. of Transportation David Evans and Assoc. Modjeski and Masters Inc.
Sam Keske Basile G. Rabbat (Retired) Edward Wasserman
Wiss, Janney, Elstner Associates Consultant Modjeski and Masters Inc.
Inc.
Bijan Khaleghi Hugh David Ronald Daniel Werner
Washington State Dept. of Atkins North America Plum Creek Structures
Transportation
Mary Ellen Kimberlin Joe E. Salvadori Kevin Western
Ohio Prestressers Association Michael Baker International Minnesota Dept. of
Transportation
Charles W. Leidholdt Steven L. Schwarz Chris White
Hamilton Form Company Ltd. HR Green Inc. Volkert
Lisette Shana Ludena Gudmund Setberg Hartanto Wibowo
T.Y. Lin International Group Caltrans Iowa State University
Tom Macioce Mohsen A. Shahawy Christopher S. Williams
Pennsylvania Dept. of SDR Engineering Consultants, Inc. Purdue University
Transportation
Marc Maguire C. Shawn Sun Brian Witte
University of Nebraska – Lincoln Louisiana Technical University Parsons
Farshad Mazloom C. Douglas Sutton (Retired) Carin L. Roberts-Wollmann, PE
Kie-Con Inc. Purdue University Virginia Polytechnic Institute and
State University
Bob Mills Maher Tadros Wael Zatar
Hamilton Form Company, Ltd. e.Construct Marshall University
George Morcous David A. Tomley Miloslav Zeman
University of Nebraska – Lincoln Thompson Engineering Dura-Stress Inc.
Azam Nabizadeh Kyle Turner
University of Wisconsin – Michael Baker International
Milwaukee
The following current and past members of the AASHTO Subcommittee on Bridges served on the
Technical Committee for Concrete (T-10). Many of these engineers are also voting and consulting
members of the PCI Committee on Bridges. They also served as an advisory group with the FHWA-
AASHTO-PCI Contract task order no 5010 (DTFH61-11-D-00010-T-5010), “Advanced Precast Element
Design and Construction State of Practice,” under which this product was developed.
xi
Many state highway agency employees and AASHTO staff reviewed draft documents and work plans.
Below are listed those that routinely participated in this multiyear endeavor.
Kevin Western (Chair T-10) Strat Cavros Arielle Ehrlich
Minnesota Dept. of Transportation AASHTO Staff Minnesota Dept. of Transportation
Matt Farrar (Vice Chair T-10) Nancy Daubenberger (past Jamie Farris
Idaho Dept. of Transportation member) Texas Dept. of Transportation
Minnesota Dept. of Transportation
Patrica Bush Bill Dreher (Retired) Gregg Freeby (Retired)
AASHTO Staff Wisconsin Dept. of Transportation Texas Dept. of Transportation
Zhengzheng (Jenny) Fu Bruce Johnson (past member) Tanarat Potisuk
Louisiana Dept. of Transportation Oregon Dept. of Transportation Oregon Dept. of Transportation
& Development
Sue Hida (past member) Bijan Khaleghi Will Potter
Caltrans Washington State Dept. of Florida Dept. of Transportation
Transportation
Mark Hoppe Robert Landry (retired) Gudmund Setberg
Kansas Dept. of Transportation New Hampshire Dept. of Caltrans
Transportation
Reggie Holt (Ex Officio member) Tom Macioce Loren Risch (Retired)
Federal Highway Administration Pennsylvania Dept. of Kansas Dept. of Transportation
Transportation
Fouad Jaber Jim McDonnell
Nebraska Dept. of Roads AASHTO Staff
PCI staff and the institute’s many dedicated members would like to express their gratitude to Jim
McDonnell, Patricia Bush, and Strat Cavros of the AASHTO staff for the opportunity to serve as
subconsultant on this Federal Highway Administration assignment. Their project management,
guidance, and patience throughout this assignment have been invaluable and are deeply appreciated.
The forward-thinking conceptualization of the need for this guide by Reggie Holt of the Federal
Highway Administration should also be acknowledged as key to the project’s success. Kris Brown, John
Dick, and Henry Russell served as technical editors for this document and the courses.
Lastly, a thank you to the primary authors, Bob Anderson and Trevor Kirkpatrick of AECOM Technical
Services, Inc. Their willingness to meet multiple times with interested engineers, the PCI Committee on
Bridges, and AASHTO T-10, the technical committee on concrete design, to harmonize the text of this
guide and its four companion courses is a great contribution to advancing the use of this emerging
concrete bridge technology, today and for generations to come.
xii
INFORMATION FOR USERS
U1.0 About This Document
This document is available as an electronic “eBook” and in a hardcopy version. A simple log-in to the
PCI website is all that is needed to download this and other free resources. The print on demand
hardcopy version must be purchased through the PCI Bookstore for a small fee.
xiii
U1.2.3 Dissemination of Corrections
Corrections to this document if required will be assembled and a notice emailed to those registered.
The replacement pages will readily identify the change and the page will be identified as revised in the
footer.
Two methods are used to disseminate changes. Simple corrections, revisions, and improvements will be
posted as “Errata” on the PCI Publications website, https://www.pci.org/publicationerrata. Or, select
“Errata” on the Publications home page, then look for the title of this document.
Complex revisions that involve more than a few pages may require the user to redownload the entire
document. There will be no cost for this download. Instructions will be emailed as noted above.
In the future, when a new edition is required, an email will notify registered users. Please keep your
contact information current so you can be notified.
xiv
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES___TABLE OF CONTENTS
TABLE OF CONTENTS
TABLE OF FIGURES ........................................................................................................................................... TOF-1
CHAPTER 1 CURVED, SPLICED PRECAST CONCRETE U-BEAM CONCEPT ....................................... 1-1
1.1 GENERAL ................................................................................................................................................... 1-1
1.2 OBJECTIVE................................................................................................................................................. 1-1
1.3 LIMITS OF APLICABILITY.................................................................................................................... 1-2
1.4 DEFINITIONS AND GLOSSARY OF TERMS .................................................................................... 1-2
1.5 NOTATION................................................................................................................................................. 1-4
1.5.1 Loads................................................................................................................................................... 1-4
1.5.2 General ............................................................................................................................................... 1-5
1.6 UNITS .......................................................................................................................................................... 1-6
1.7 REFERENCE CODE ................................................................................................................................. 1-6
CHAPTER 2 - IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM .................................... 2-1
2.1 GENERAL ................................................................................................................................................... 2-1
2.1.1 Review of Projects ......................................................................................................................... 2-1
2.1.2 U-Beam Cross Section .................................................................................................................. 2-3
2.1.3 Span-to-Depth Ratios ................................................................................................................... 2-3
2.2 FABRICATION AND CONSTRUCTION ............................................................................................. 2-4
2.2.1 U-Beam Fabrication ...................................................................................................................... 2-4
2.2.2 Transportation in Yard ................................................................................................................ 2-7
2.2.3 Transportation to and at Site .................................................................................................... 2-9
2.2.4 Temporary Falsework and U-Beam Placement .............................................................. 2-11
2.2.5 Lid Slabs.......................................................................................................................................... 2-14
2.2.6 Closure Joints................................................................................................................................ 2-15
2.2.7 Post-Tensioning........................................................................................................................... 2-15
2.2.8 Deck Screeding............................................................................................................................. 2-18
CHAPTER 3 - PROJECT DELIVERY..................................................................................................................... 3-1
3.1 DESIGNER ROLE AND STATED ASSUMPTIONS .......................................................................... 3-1
3.2 SPECIALTY ENGINEER ROLE AND SUBMITTALS ...................................................................... 3-2
3.3 TECHNICAL SPECIFICATIONS ........................................................................................................... 3-3
3.3.1 Erection Plan ................................................................................................................................... 3-3
3.3.2 Geometry Control Procedures .................................................................................................. 3-4
CHAPTER 4 - DESIGN CRITERIA ........................................................................................................................ 4-1
TABLE OF FIGURES
Figure 2.1. Comparison of cross sections of U-beams used for recent projects in Colorado and
Florida. ......................................................................................................................................................................... 2-3
Figure 2.2 Specialized casting forms. ............................................................................................................... 2-5
Figure 2.3 U-beam reinforcing details. ............................................................................................................ 2-6
Figure 2.4 Precast concrete section with thickened bottom slab. ........................................................ 2-6
Figure 2.5 U-beam section and straddle carriers. ....................................................................................... 2-7
Figure 2.6 Steel lifting spreader. ........................................................................................................................ 2-8
Figure 2.7 Spreader bar attachments. .............................................................................................................. 2-8
Figure 2.8 Transportation of U-beam to site. ............................................................................................. 2-10
Figure 2.9 Transportation of U-beam at site. ............................................................................................. 2-10
Figure 2.10 Temporary falsework towers .................................................................................................. 2-12
Figure 2.11 U-beam framing. ............................................................................................................................ 2-13
Figure 2.12 U-beam lid slab examples. ......................................................................................................... 2-15
Figure 2.13 U-beam with tongue section. .................................................................................................... 2-17
Figure 2.14 Post-tensioned details. ................................................................................................................ 2-18
Figure 2.15 Deck screeding preparations for U-beam bridge. ............................................................ 2-19
Figure 5.1 Typical layout of deck slab reinforcing. ..................................................................................... 5-1
Figure 5.2 Ground splice. Photo: AECOM........................................................................................................ 5-4
Figure 5.3 Span versus span-to-depth ratio of composite U-beam. ..................................................... 5-6
Figure 5.4 Span versus gross area of U-beam section. .............................................................................. 5-6
Figure 5.5 Span versus average weight of post-tensioning. .................................................................... 5-7
Figure 5.6 Span versus maximum web shear reinforcing (per web)................................................... 5-7
Figure 5.7 Extreme top and bottom compression fiber for precast and composite cross
sections. ....................................................................................................................................................................... 5-9
Figure 6.1 Prototype bridge elevation and typical section. ..................................................................... 6-3
Figure 6.2 Assumed construction sequence .................................................................................................. 6-4
Figure 6.2 (continued) Assumed construction sequence. ........................................................................ 6-5
Figure 6.2 (continued) Assumed construction sequence. ........................................................................ 6-6
Figure 6.3 Analysis model for prototype bridge. ......................................................................................... 6-9
Figure 6.4 Section properties. .......................................................................................................................... 6-10
Figure 6.5 Flexure in right U-beam from permanent loads. ................................................................. 6-13
Figure 6.6 Flexure in right girder. .................................................................................................................. 6-14
Figure 6.7 Shear in right girder. ...................................................................................................................... 6-14
1.2 OBJECTIVE
The objective of this document is to provide up-to-date guidelines for preliminary and final
design of curved, spliced U-beam systems. Primarily through examples and references to
constructed projects, information is presented for the design and detailing of the primary
components of curved, spliced U-beam bridge systems. This document is not intended to be all-
encompassing, nor should it limit the ingenuity of design professionals in developing
innovative solutions. Rather, it serves to communicate the current state of the art as
represented by recent successfully completed projects. This document draws on PCI’s State-of-
the-Art Report CB-01-12, Curved Precast Concrete Bridges,1 for examples of bridges that have
been successfully constructed during the past 20 years. The U-beam system presented in this
document relies heavily on the concept of lid slabs, which was developed for those projects in
Colorado around the year 2000. The intent of this document is to describe the design and
construction of over 20 bridges during the past 15 years. The contemporary prototype
example presented is representative of the majority of projects that have been constructed.
It is assumed that individuals employing this document possess a fundamental understanding
of pretensioned and post-tensioned concrete. Also, an understanding of modeling and analysis,
including behaviors produced by time-dependent effects of concrete, is recommended.
1.5 NOTATION
This section defines notation used in this document. Notation used in the appendices is defined
in those sections.
1.5.1 Loads
Permanent loads:
CR = force effects due to creep
DC = dead load of structural components and nonstructural attachments
DW = dead load of wearing surfaces and utilities
EH = horizontal earth pressure load
EL = miscellaneous locked-in force effects resulting from the construction process
PS = secondary forces from post-tensioning for strength limit states; total prestressing
forces for service limit states
SH = force effects due to shrinkage
Transient loads:
BR = vehicular braking force
CE = vehicular centrifugal force
CEQ = construction equipment
CLL = construction live load
CT = vehicular collision force
CV = vessel collision force
DIFF = differential (unbalanced) dead load from one cantilever
EQ = earthquake load
EL = locked in forces/stresses from primary and secondary effects of post-tensioning
FR = friction load
IM = vehicular dynamic load allowance
LL = vehicular live load
LS = live load surcharge
PL = pedestrian live load
1.5.2 General
A = member cross-sectional area
Acp = total area enclosed by outside perimeter of concrete cross section
Af = area of reinforcement required for transverse flexure
Aps = area of prestressed reinforcement steel on the tension face of the beam
As = area of nonprestressed steel in flexural tension zone; or, area of nonprestressed steel
in the tie of a strut-and-tie model
Astrand = area of a single prestressing strand (0.217 in.2 for 0.6 in. diameter strands)
Av = area of reinforcement required for longitudinal shear and torsion
b = width of compression face of member
c = distance from extreme compression fiber to the neutral axis
d = distance from extreme compression fiber to centroid of longitudinal tension
reinforcement
D = depth of composite section
f’c = compressive strength of concrete for use in design
f’ci = design concrete compressive strength at time of transfer of prestress for pretensioned
members and at time of initial loading for nonprestressed members; design concrete
strength at time of application of tendon force for post-tensioned members
fpc = compressive stress in concrete after all prestress losses have occurred either at the
centroid of the cross section resisting transient loads or at the junction of the web and
flange where the centroid lies in the flange.
fpe = effective stress in prestressing steel after allowance for all losses
fpu = nominal ultimate stress of prestressing steel (270 ksi for low-lax strands)
fr = modulus of rupture of concrete
I = moment of inertia
L or l = span length
M = moment
N = number of post-tensioning strands
1.6 UNITS
This document uses primarily U.S. customary units.
2- 1 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
Table 2.1. Partial summary of recent U-beam designs
Bridge name Location Span Back span/ Cross Cross Deck Span/depth Beam
configuration, ft main span section section
thickness (deck + U- spacing
@ midspan @ pier beam)*
187-200-200-187 0.94
I-25 over US- CO 153-240-154 0.64 7 ft 2 in. 7 ft 2 in. 9.0 in. 30.3 18 ft 8 in.
85 (tBF = 6 in.) (tBF = 1 ft 8
in.)
119-177-187-131 0.7
‡ Depth of composite section at pier (haunched section) is used to calculate span-to-depth ratio.
2- 2 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
For the projects presented in Table 2.1, the average span-to-depth ratio (L/D) equals 28 for the
composite U-beam, beam plus deck slab, with a range from 22 to 33 depending on the project.
Appendix F provides additional information pertaining to parameters from numerous
constructed projects.
Figure 2.1.
Comparison of cross sections of U-beams used for recent projects in Colorado and Florida.
Figures 2.1 shows that the PCI Type U84-4 uses a 10 in. thick web, compared with the 9 in. web
thickness shown and commonly used for the Colorado section. The Colorado cross section was
designed to allow variable web thicknesses from 7.5 to 10 in., which was achieved by varying
the internal forms. The thicker web allows installation of larger tendon ducts and hence larger
post-tensioning forces. By contrast, the area and weight of the PCI-U84-4 is slightly larger than
the Colorado section. The PCI sections, presented in appendix F, were developed with industry
inputs from governing agencies, contractors, designers, and precasters, and represent the most
recent evolution of the current state of the art.
2- 3 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
• use of continuous span units
• moderate curvatures from 750 to 1000 ft in the alignments
Simple spans, inefficient end-span layouts of continuous units, and highly curved alignments
less than 750 ft may lead to span-to-depth ratios of less than 30:1.
2- 4 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
As will be discussed in section 7.1, it is structurally advantageous to add prestress after lifting
the member from the form and transporting the precast concrete section in the yard and
before leaving the plant, to give greater torsional capacity and to control cracking. Reiterating,
the initial post-tensioning (stage 1) is normally done all at the same time, generally after the U-
beams are lifted from the forms while in yard storage, and always before the tubs are placed
on the delivery vehicle. To date, and as discussed in the previous paragraph, projects have
used pretensioned strands and bonded and grouted initial post-tensioning tendons to provide
the initial prestressing required for stage 1. For the bonded, grouted systems, round and flat
ducts have both been used with flat ducts, potentially providing more compact duct
arrangements and smaller anchorage zone dimensions. Nevertheless, the use of flat ducts is
cautioned in situations where the fluid head of concrete is significant and may result in
unacceptable deformations to the ducts during casting.
The precast concrete U-beam sections contain post-tensioning ducts in the bottom flange and
webs, and for pier segments, in the top flanges and webs. The sections may be removed from
the forms as mildly reinforced members or may be partially post-tensioned if needed to
control handling stresses. In some cases, the bottom flange may contain special monostrand
tendons that are tensioned before lifting the U-beam from the bed. However it is done, all
sections are generally prestressed by post-tensioning before leaving the plant. There are
exceptions, where the beam length is short and the radius is large, that will meet criteria with
only mild reinforcing steel.
a) Steel casting form. Precast concrete lid b) Section of interior mold for casting
slabs are visible in the background. trapezoidal U-beam.
Figure 2.2
Specialized casting forms.
2- 5 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
Reinforcing bar cages with post-tensioning ducts installed are prefabricated, or “pre-tied”, and
lifted into the formwork systems (Fig. 2.3). Cages may also be tied in the formwork based on
preference. Figure 2.3(a) shows welded-wire web reinforcement bent in a custom bending
machine. Figure 2.3(b) shows the finished fabricated reinforcement cage ready to be inserted
in the tub form. The headed reinforcing bar terminations may be used to reduce congestion of
this reinforcement as it protrudes into the deck slab.
2- 6 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
Figure 2.4(a) shows a two-stage approach to thicken the bottom flange of the precast concrete
U-beam. The precast concrete section in Fig. 2.4(a) has threaded reinforcing bar inserted into
form savers on the interior faces at the bottom of the webs. The concrete surface has been
intentionally roughened to ¼ in. amplitude to improve bond with the secondary concrete
casting. This approach saves weight for U-beam segment transportation and eliminates the
required modification of the interior form to accommodate the thickening if cast with the U-
beam. However, this approach adds labor and materials for the tying of reinforcing bar and the
casting of the secondary concrete placement in the field, and necessitates design checks for
shear stress and shear reinforcement across the cold joint. For recent bridges in Florida, the
contractor was given the option to construct the bottom slab thickening as either precast in the
form or as a secondary placement, for which the monolithic option was chosen.4 Figure 2.4(b)
shows a monolithically cast thickened bottom flange.
Figure 2.5
U-beam section and straddle carriers.
Photo: Dura-Stress
2- 7 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
Figure 2.6
Steel lifting spreader.
Figure 2.7
Spreader bar attachments.
2- 8 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
2.2.3 Transportation to and at Site
Figure 2.8 shows a steerable trucking configuration for transporting precast concrete sections
of spliced U-beams. The beams are supported approximately 15% of the overall length from
the ends of the unit, that is, near the 0.15 points, to increase the cantilever overhangs and
reduce longitudinal and torsional moments at midspan. With this arrangement, negative
moments in the cantilevers are increased and both top and bottom compression and tension
limits need to be checked. Moreover, the support location should be determined for each stage
of construction such as during storage, transport, and handling. Variations of curvature, length,
thickened slabs, end diaphragms, and tongue details are factors that affect: 1) the location of
the U-beam centroid; 2) the design of stage 1 prestressing; and 3), the selection and
optimization of support locations. Similar to spreader bars, and depending on the equipment
available to the hauler, the tub can be placed so the centroidal axis of the U-beam align with the
center of truck support resistance without inducing overturning into the system. The stresses
induced in the U-beam due to these various support locations that exist during construction
must be countered with the stage 1 prestressing in order to keep them within allowable limits.
Some longitudinal prestressing must be installed before transport to assist the section in
resisting applied forces including torsional cracking limits. As explained in section 7.1 and
appendix A, it is recommended by Washington DOT that the section is designed to resist its
own self-weight plus dynamic allowances of 20% of self-weight upwards and 20% of self-
weight downwards for transport.5 The designer may elect to increase these percentages
considering the feasibility of the selected shipping route, hauling equipment, and consideration
of local practice. Further discussion in section 7.1.3 indicates that when the beam is erected on
temporary supports and before stressing continuity post-tensioning is likely the controlling
temporary load case. For more information regarding transportation analysis methodologies,
see the PCI Bridge Design Manual.11
a) U-beam at plant, ready for transport. b) Arrival of U-beam at site. Photo: Modjeski
and Masters.
2- 9 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
Figure 2.9
Transportation of U-beam at site.
Photo: Modjeski and Masters.
Figure 2.9 shows a photo of a U-beam handled at the job site with eccentric spreader bars,
which help to balance U-beam twist associated with a two-crane pick.
2- 10 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
2.2.4 Temporary Falsework and U-Beam Placement
An advantage of curved precast concrete construction is that it employs minimal shoring
compared with cast-in-place construction. Correspondingly, the layout of temporary
falsework, if used, is an important aspect of design. The length of U-beam segments may be
influenced by precaster plant lifting capacity, shipping limits, and contractor crane capacity.
Site constraints such as clearances to traffic lanes and shoulders, utility interferences and
obstructions, and available falsework locations may also dictate the length of U-beam
segments. Figure 2.10 shows several examples of feasible tower layouts. In general, the towers
are roughly placed at the span’s points of contraflexure to minimize forces at the closure joints.
The layout of falsework towers need not be perpendicular to the centerline alignment. For
example, the temporary towers can be skewed for a pair of U-beams and the concrete framing
of the diaphragms and closure joints can be offset. Also, U-beam lines can be designed
completely independently with different splice locations if necessary due to site constraints.
Where insufficient space exists for support from towers below, U-beams can be suspended
from above by strongbacks [Fig. 2.11(a)]. Strongbacks are attached to an adjacent U-beam and
cantilevered to hang an adjacent U-beam; the other end is typically supported by a shoring
tower or permanent pier. In the case of strongbacks, and depending on the length of the
cantilevering U-beam, significant additional top post-tensioning, temporary and/or
permanent, is generally required to control stress conditions over the piers. Straddle bents and
cantilevered shoring bents are other options when there is insufficient space for a
conventional tower.
2- 11 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
b) Single tower used at splice location are c) Temporary cast-in-place concrete columns
cross-braced to withstand hurricane-force with sand jacks and steel positioning beams
winds. to support the U-beams at splices. The
columns are later removed and discarded.
Figure 2.10
Temporary falsework towers
2- 12 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
2- 13 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
diaphragm construction is accomplished in the field. The tongue section allows reduction of U-
beam segment weight for transport and handling, aids for fit-up tolerances at the abutments, a
precast concrete bearing seat, and field installation of the post-tensioning anchorage zone.
During a short window of time in the field operations, that is, before the load is transferred to
permanent U-beam bearings at piers, the system is on falsework, closure joints are cast, and
before post-tensioning, the U-beam system is sensitive to the effects of settlement at the
falsework towers, which will induce tensile stresses over the piers. Design and field inspection
protocols should be established to monitor settlement of temporary shoring. Concerns related
to settlement at the falsework towers can be mitigated and remedied by: using low bearing
pressures for spread footing design, use of deep foundations, monitoring settlements over a
period of time before grouting bearings and casting closures, and developing contingency
plans including shimming or jacking to correct settlements and/or misalignments. Second-
stage post-tensioning should occur shortly after the closures gain strength to limit the time
window for potential settlement and also cyclical events related to thermal and shrinkage
stresses imposed on early-age (and low-early-strength) closure joint concrete.
2- 14 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
a) U-beam at abutment with forms ready for c) Precast concrete lid slabs stored in the
the cast-in-place concrete lid slabs. Photo: J precast concrete plant.
Dick Precast Concrete Consultant.
b) Precast concrete lid slabs with deck d) Removable grout bedding form under
overhang cantilevers and precast concrete precast concrete deck panels.
stay-in-place deck panels between U-beams.
Figure 2.12
U-beam lid slab examples.
2.2.7 Post-Tensioning
The normal application of first-stage (in the yard) and second-stage (in the field) post-
tensioning offers some challenges. For the first-stage post-tensioning (the first-stage may also
be pretensioned), there is the need to define this work scope for either the precaster or the
2- 15 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
contractor. The contractor may prefer a sole source for the U-beams, while the precaster may
or may not want to self-perform this work item. Hence, the division of work is a contractual
issue to be addressed between the contractor and precaster, and is generally within the scope
of the post-tensioning supplier/subcontractor. For the installation of second-stage post-
tensioning, attention should be given to the physical space for jacks, the trimming of strands
during the post-tensioning process, the amount of loss along the tendon length, and
installation of strands over long runs of duct. During stressing, and because U-beams can move
relative to each other, the post-tensioned structure should be treated as a system and the
sequence of stressing examined. This includes the consideration of intermediate diaphragms
and possibly deck forms.
In recent projects, a gap of 3 ft at closures and 4 ft at expansion joints has been adequate to
successfully tension four 15-strand tendons using end U-beam segments incorporating a
tongue section (Fig. 2.13).4 Nonetheless, these distances are considered minimums; second-
stage post-tensioning can be difficult and professional installation is recommended. Some
suppliers may need more than these minimums, and jacking clearance aspects should be
resolved in the design phase or subsequently in review of the shop drawings. Large elongations
of several feet can be expected for the initial stressing of a continuity tendon, so a full-size jack
stressing from an open end is recommended if possible. Stressing from the opposite end is also
common to account for losses along the length of the tendon and can normally be accomplished
with a short-stroke jack. Tendon lengths of 890 ft with (19) 0.6 in. strand in 4 in. nominal
diameter ducts, and about 1345 ft with (27) 0.6 in. strand in 4.75 in. diameter ducts, have been
successfully installed.
Figures 2.14(a) and 2.14(b) show typical post-tensioning details. In Fig. 2.14(b) the closure is
the width of the web. Also, because of space limitations and potential post-tensioning and
reinforcement congestion, well-consolidated concrete should be achieved. High-flow concrete,
self-consolidating concrete, or simply smaller aggregate sizes may be considered to attain good
results.
The decision to use unbonded or bonded post-tensioning and the amount of each is left to the
designer and the governing agencies. Unbonded (greased and sheathed tendons) are
commonly protected at their ends by proprietary caps. For bonded tendons, grouting proceeds
subsequent to the tendon stressing. Governing specifications generally prescribe grouting
within two weeks after the tendons are seated to their final stress, to prevent corrosion of the
strands in the humid environment of the ducts. Procedures and materials for grouting will
follow normal protocols established by the engineer and governing agency. This discussion is
outside the scope of this document. The designer is alerted to show details and locations for
inlets at low points and grout vents to allow for burping of accumulated air, negate voids, and
uniform protection of the strands by the grout. Refer to PTI M50.3-12, Guide Specification for
Grouted Post-Tensioning,8 for the latest industry guidance related to the grouting of post-
tensioning tendons.
2- 16 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
Figure 2.13
U-beam with tongue section.
2- 17 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
2- 18 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
To summarize, an engineer should evaluate the need for temporary shoring and the effects of
removal of the deck slab to determine whether the lid slab should remain and only a partial
deck removal specified.
Figure 2.15
Deck screeding preparations for U-beam bridge.
Photo: AECOM.
2- 19 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 2
IMPLEMENTATION OF CURVED, SPLICED U-BEAM SYSTEM
2- 20 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 3
PROJECT DELIVERY
PROJECT DELIVERY
Depending on the project delivery method, the contract documents developed by the
governing agency, engineer of record (EOR), and contracting team may vary.
For a design-build project, the governing agency may prescribe various performance
requirements in terms of the roadway geometrics, horizontal and vertical clearance, load
carrying capacity, and durability expectations. Many of the engineering tasks are performed by
the design-build contracting team, including the EOR, during the pre-bid to communicate the
bidder’s intention, and post-bid to prepare construction documents necessary to build the
structures and for governing agency review to confirm compliance with the project’s
performance specifications.
For a design-bid-build project, the EOR is employed by the governing agency and generally the
contract documents are developed to greater detail during the pre-bid phase. Indeed, the
development of precise design-bid-build contract documents is encouraged; nonetheless, they
are not intended to preclude innovation and need to provide flexibility for the contractor and
his specialty engineer and precast concrete fabricator. The contract documents need to
communicate a feasible way to construct the bridge structure and may be modified by the
contracting team to suit the chosen means and methods.
This section describes many of the typical design considerations and construction practices
that are now being used to build curved, spliced U-beam bridges.
DESIGN CRITERIA
4.1 GENERAL
Articles 5.12.3 and 5.12.3.4 of the AASHTO LRFD specifications2 give the primary code
guidance regarding design aspects of curved, spliced precast concrete U-beam bridge systems.
Topics including shear and torsional checks and guidance related to erection stage analysis
may be considered by the design professional and the governing agency. This document
echoes that guidance. AASHTO LFRD specifications Article C3.12.3 gives guidance related to
the exclusion of thermal gradient effects based on local performance experience. As the state of
the art moves forward, there will be further consensus developed for the interpretation of
AASHTO LRFD specifications and it is likely design specifications will be broadened to fully
encompass the general case of curved, spliced precast concrete U-beam design. AASHTO LRFD
specifications provides supplementary guidance in Article 5.12.5 for special concrete design
cases.
Note that the discussion of this section is brief and will be expanded on by use of example in
later sections and by information found in the appendices.
Figure 5.1
Typical layout of deck slab reinforcing.
5- 1 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
The typical section shown in Fig. 5.1, including U-beam and deck, is well suited for a 44 ft wide
bridge using stay-in-place deck forms, but the optimum solution may vary significantly based
on approved materials and local preference. Overhangs of 6 ft are considered unusual and
difficult to form in many locations, and may drive the design. Thinner lid slabs have been used:
3½ to 4 in. for cast-in-place and 3 in. for precast concrete panels. These designs lessen
reinforcing bar cover for the lid slab and allow more tolerance in deck steel placement.
Additionally, smaller aggregate sizes can be used to provide more flexibility in deck steel
placement.
5- 2 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
build-out condition of a single girder on a tower that will eventually support two girders
should be investigated for stability.
Tolerance to build falsework towers should be anticipated. Commonly, shims and sand jacks
provide for suitable vertical tolerance of the tower legs and have been successfully employed.
Shims may be wooden, neoprene, or steel plate, and these may be used in combination and will
allow precise placement of field sections for the benefit of geometry control of the U-beam
system. Field surveys of the temporary pads at the falsework towers occur as a step in the
contractor’s geometry control plan.
5- 3 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
5.4 STRONGBACKS
Most commonly, strongbacks are used to support midspan field segments in situations where
falsework towers cannot be placed due to restrictions below and should be considered during
the design phase. In practice, the use of strongbacks is complicated by the weight of the field
sections and by stress limits of the U-beam segment over pier cantilever. For both points,
additional temporary or permanent post-tensioning may need to be applied to meet stress
conditions during erection and when construction is finalized. The anchorage of the post-
tensioning and its interface with the strongback hardware must be checked to assure fit-up of
all pieces. Furthermore, the length of the free cantilever will affect the magnitude of bending
moment and stress over the pier. The cantilevers are usually kept as short as possible to limit
the amount of stress; however, the configuration of the strongbacks must consider stresses at
all the points of the U-beam system and should be incorporated into the time-dependent
analysis of the structure during design.
Figure 5.2
Ground splice.
Photo: AECOM.
5- 4 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
5.6 SECTIONAL DESIGN FOR SERIVE LIMIT STATE
The following sections discuss guidelines for preliminary design of precast concrete U-beam
bridges.
5- 5 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
Figure 5.3
Span versus span-to-depth ratio of composite U-beam.
Figure 5.4
Span versus gross area of U-beam section.
5- 6 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
Figure 5.5
Span versus average weight of post-tensioning.
Figure 5.6
Span versus maximum web shear reinforcing (per web).
The values for span presented here are for initial design and planning purposes. The collected
data may not capture the effect of nonuniform spans, skewed piers, optimized end-span length,
or other design considerations one is likely to encounter during a typical project. For these
reasons, the design values presented here are to be verified by the engineer during the design
process.
5- 7 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
The maximum span versus average weight of post-tensioning graph includes both 15 and 19
strands for the continuity tendons. In some instances, it is desirable to use a particular U-beam
size for portions of the bridge with spans that are less than the maximum possible span. In this
case, economy may be achieved by reducing the number of strands in the continuity or spot
tendons. Other projects, including some listed in appendix F, showed prestressing quantities
varies roughly between 4.0 and 6.0 lb/ft2 (pretensioning and post-tensioning).
Neglecting secondary effects and assuming an approximate tendon eccentricity, the required
number of strands at either the positive or negative moment region may be approximated by
the following equations:
𝜎𝑠𝑒𝑟𝑣𝑖𝑐𝑒 −𝑃𝑇 − 𝜎𝑎𝑙𝑙𝑜𝑤
𝑁=
1 𝑒𝑦
𝑓𝑝𝑒 𝐴𝑠𝑡𝑟𝑎𝑛𝑑 +
𝐴 𝐼 (ksi or psi)
Where
N = number of post-tensioning strands
allow = allowable tensile stress
service− PT = service tensile stress without post-tensioning (assumed to be the same sign as
sigma allow)
A = member cross-sectional area of the precast or composite section
f pe = effective stress in post-tensioning after allowance for all losses (approximated as
0.6 f pu )
f pu = nominal ultimate stress of prestressing steel (270 ksi for low-relaxation strands)
Astrand = area of post-tensioning strand (0.217 in.2 for 0.6 in. diameter strands)
e = strand eccentricity at the section being considered (calculated assuming the
strand eccentricity is approximately 0.85 of the depth of the U-beam)
y = distance from extreme top or bottom compression fiber to the neutral axis of the
precast or composite section
I = moment of inertia of the precast or composite section
Figure 5.7 shows the distance from the extreme top and bottom compression fiber for the
precast concrete U-beam, precast concrete U-beam with lid slab, and precast concrete U-beam
with lid slab and concrete deck (see Figure 6.4 for values). The precast U-beam carries the
weight of the wet lid slab, the precast concrete U-beam with lid slab carries the weight of the
wet concrete deck, and the precast concrete U-beam with lid slab and concrete deck carries
live load and superimposed dead load. Generally using the composite values of A, I and y will
result in the most conservative approximation of the number of strands required. The actual
strand quantity will be refined as the design proceeds.
5- 8 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
a) Precast U-beam
5- 9 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
longitudinal and torsional moments increase by 5% (the length squared). The outside girder
line will always be subjected to more dead load and live load, yet the inside and outside girders
are nearly always designed similarly. Furthermore, if a single spine model is used, proper
determination of the distribution factor for live load for the outside girder line is significant.
Experience has shown that determination of the live-load distribution factor can be
conservatively determined by using the lever rule or other methods which are also not
significantly affected by curvature. Special situations may also apply. For example, if piers are
not radial but parallel, girder lengths can be roughly equal or even shorter on the outside
girder line. Furthermore, if the girder lines are shifted, the deck can produce counterbalancing
torsions for composite loads and shift deck dead loads away from the exterior girder to the
interior.
Article 4.6 of the AASHTO LRFD specifications discusses the analysis type recommended for
varying degrees of curvature. Indeed, section 4.6.1.2.3 states that a three-dimensional single
curved girder line model is sufficient if the degree of curvature within a single span is between
12 and 34 degrees. The designer should decide, in developing the model, the significance of the
degree of curvature, force effects (including torsion) to the outside girder, and application of
distribution factor. It is noted that a dual spine model accounts for the girder length effect and
live-load distribution factor within the model.
Table 5.2. Girder lengths for 200 ft curved span (22 ft 8 in. girder spacing)
Bridge Column A Column B
centerline B/A
Length of interior girder, ft Length of outside girder, ft
radius, ft
Straight (R =
200 200 1.00
infinite)
5- 10 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
longitudinal flexibility. The foundation conditions will typically determine if frame action
between the substructure and superstructure is feasible and that the frame has sufficient
strength and flexibility to accommodate volume changes. Very stiff foundations, such as
footings founded on multiple piles can generate large forces under design movements when
combined with inflexible piers. Locally stiff piers may still be used in a rigid frame if they are
combined with taller, more flexible piers. Locating the center of rigidity of the frame to limit
movement at stiffer pier locations is a design methodology to accommodate stiff substructure
and foundation elements. Girder lines can also have independent supports. The designer may
also take advantage of flexibility from creep effects in the structural system and a reduction in
stiffness due to permissible column cracking.
The prototype bridge discussed in section 6, and shown in Fig. 6.1, was analyzed for
combinations of fixed bearings and integral piers. The piers analyzed were 20 ft tall from the
top of foundation cap to top of beam seat. Table 5.3 shows the resulting bottom of column
longitudinal moment for the controlling pier in each case. The effects of longitudinal wind and
temperature gradient are neglected for this study because they do not contribute to the
Strength I load case. Braking loads are distributed equally according to the number of fixed
bearing or integral piers. Live load is for HL-93 loading placed for maximum longitudinal
moment at the base of the column. Time-dependent effects are for long term losses. Axial loads
and transverse moment caused by the bridge curvature or eccentric loading is not shown here
but contribute to the loading demands on the piers and must be considered for design. The
base of column was assumed fixed for all cases.
Table 5.3. Longitudinal moment resultants for pier fixity study
Longitudinal moment for controlling pier, kip-ft
Table 5.3 shows that there is significant increase in the longitudinal moment at the base of the
columns for cases with more fixed bearings or integral piers. The predominant component of
longitudinal moment is secondary effects of post-tensioning and uniform temperature.
5- 11 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 5
PRELIMINARY DESIGN AND SPAN LAYOUT
Cases 2 and 3 have similar base moments as cases 5 and 6 (multiple fixed bearing and multiple
integral piers, respectively). Although the piers in cases 5 and 6 are subject to double
curvature, in this study the long spans of the superstructure are relatively flexible compared
with the substructure, providing relatively little restraint to the top of the column for load
cases involving superstructure axial shortening. In this study, the moment at the top of the
column for case 6 uniform temperature loading is approximately 8000 kip-ft, or approximately
40% of the base moment.
In contrast, the results of cases 1 and 4 (one fixed bearings or integral pier) differ. The
predominant difference is due to compatibility between the superstructure and substructure
for live loading for the case with integral piers. In the fixed bearing case, superstructure
rotations are accommodated through bearing rotation, and the rotations do not result in
significant column moment.
For the integral pier case, the total axial force in the superstructure is higher, necessitating
additional post-tensioning to control stresses in the superstructure. The effect in this study
likely results in 2 to 3 additional strands at the pier location. The effect of axial loads and
differential stiffness between the substructure and superstructure is lessened for taller, more
flexible piers. It is clear from the study that design related to fixed and integral scenarios
points to the need for an articulation study early in the design process.
5- 12 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
6.2 MATERIALS
The U-beams of the prototype bridge were assumed to have a 28-day concrete compressive
strength of 8.5 ksi. The cast-in-place concrete portions of the U-beams (closure placements,
diaphragms, blisters, haunched bottom slab) were assumed to have a 28-day compressive
strength of 6.5 ksi. The bridge deck and lid slab were assumed to have a compressive strength
of 4.5 ksi. Creep and shrinkage properties were according to CEB/FIP.12 High-slump concrete
was assumed for better placement in the precast concrete U-beam forms.
Reinforcing steel was assumed to be ASTM A615, Grade 60. Prestressing strand was assumed
to be 0.6 in. diameter ASTM A416 Grade 270 for low-relaxation strands, and prestressing bars
were assumed to be ASTM A722 Grade 150. Tendons and bars for the prototype bridge were
assumed to be grouted and bonded.
Appendix A provides a more complete description of the material properties.
6-4
Stage 2: Erect U-beams (bottom tendons not shown).
Stage 3: Cast bottom flange thickening, closures, intermediate diaphragms, and end diaphragms.
(April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
Figure 6.2
Assumed construction sequence
Stage 4: Stress transverse post-tensioning in diaphragms (if used).
6-5
Stage 5: Cast lid slab.
(April 2020)
Assumed construction sequence.
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
6-6
Stage 7: Remove temporary supports and cast deck.
(April 2020)
Assumed construction sequence.
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
To capture the effects of creep and shrinkage and locked-in forces, the prototype bridge was
modeled using a time-dependent analysis that incorporated the construction sequence,
including the age of the bridge components at the time of erection. The substructure elements
were assumed to be three months old when the beams were set. Table 6.1 provides a detailed
description of the construction stages shown in Fig. 6.2.
Figure 6.3
Analysis model for prototype bridge.
The gross-section properties of the permanent piers were determined according to the
proportions of the piers, which were assumed to be rectangular for the prototype bridge
analysis. Cracking of the piers was not considered for the prototype analysis.
Figure 6.4 shows the section properties used for the prototype bridge. Thickened bottom
flange properties are not shown but were also developed and used for the prototype bridge.
Torsional moment of inertia is shown as it is required for the stiffness analysis. The warping
constant, required to calculate torsional stresses due to loads applied away from the shear
center, is not shown. See chapter 7 for a discussion on torsion of U-beam segments.
Figure 6.4
Section properties.
6 - 10 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
6.6 TEMPORARY WORKS
Section 5.3 discusses the use and design of temporary towers. In the prototype example,
temporary towers were used to support the precast concrete U-beam segments before making
closure and stressing post-tensioning continuity tendons. Because the statical system of the U-
beams changed from simple supports in the initial stages to continuous supports at the later
stages, the stiffness of the temporary towers affected the distribution of forces in the
superstructure, and the stiffness of the temporary towers was included in the time-dependent
analysis. Settlement of the temporary towers should be addressed when the closure
placements are made and bearings over the piers are engaged, and before significant
longitudinal post-tensioning is applied. Because this window of time is generally not long, and
because the change in load is small, settlement is generally not a significant concern, provided
attention is given the bearing pressures of the founding materials.
Parametric studies will help to determine if shoring stiffness is a significant design condition
for stresses or deflections and build-ups. If so, the proper measures to accommodate the
chosen shoring stiffness should be included in the contract plans, and the specialty engineer
will also need to consider these in the design of temporary works.
The stiffness of the temporary towers was approximated using spring supports with stiffness
equal to the axial stiffness of typical temporary falsework.
Additionally, post-tensioning operations and casting the lid slab introduced uplift at some
bearings on the temporary towers. For this reason, compression-only supports were used for
the bearings on the temporary towers. The compression-only springs tracked the total force in
the bearing elements through the construction stages and became inactive when the sum of
forces in the bearings at a particular construction stage became negative. In the prototype
example, the support towers did not lift off simultaneously; thus, compression-only springs
become a convenient way to address step-wise liftoffs without adding more stages.
6 - 11 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
Concrete Box-Girder Bridges,13 rigorous parametric studies were performed that led to the
following span L over radius R ratio recommendations when:
• L/R < 0.2, designed as straight and ignore torsions;
• 0.2 < L/R < 0.8, analyzed as a curved single-spine girder; and,
• L/R > 0.8, analyzed using the finite element method or more sophisticated analysis.
Using these parameters for the prototype example with R = 750 and L = 200, L/R = 0.267,
which is just above the threshold where curvature is ignored which is consistent with the
AASHTO LRFD specifications. To provide an example that can be used for a moderate
curvature, the prototype analysis uses dual longitudinal spine elements and transverse slab
elements. The design professional may choose a more simplified analysis, using a single spine,
and neglecting curvature if indicated by layout parameters.
The ratio of midspan moment determined using dual curved longitudinal spine elements and
transverse slab elements and the lever rule applied to a straight, single-spine model was 7006
kip-ft (analysis)/8720 kip-ft (lever rule) = 0.80.
6 - 12 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
Figure 6.5
Flexure in right U-beam from permanent loads.
Based on the results of Fig. 6.5, the post-tensioning moment counteracts the dead load
moments. While the effects of creep and shrinkage are relatively small compared with dead
loads, they add to the dead load moment and must be considered in the design.
Figures 6.6 through 6.8 show flexure, shear, and torsion in the right U-beam due to the
permanent loads in Fig. 6.5 and live loads. Note that results due to temperature loadings not
plotted because they are relatively small for the prototype bridge, but are dependent on the
fixity of the structure and may be larger for differing bridge layouts. For example, temperature
loads can be a concern with longer spans and shorter (more fixed) piers.
6 - 13 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
Figure 6.6
Flexure in right girder.
Figure 6.7
Shear in right girder.
6 - 14 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
Figure 6.8
Torsion in right girder.
6 - 15 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
6.11 TRANSVERSE DECK SLAB
The transverse deck slab functions as the roadway surface. It transfers live loading
transversely to the longitudinal U-beams and is part of the longitudinal and transverse
structural systems. For the longitudinal system, beam elements were used to model the lateral
transfer of live loading between the U-beams (Fig. 6.10). The beam element thickness was the
same as the deck thickness, and the width of the beam elements was based on the tributary
spacing between adjacent nodes. Beam elements were defined between the spine elements
with member eccentricities representing the edge of the U-beam top flanges.
Figure 6.9
Principal web stress.
6 - 16 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
Figure 6.10
Global longitudinal modeling of transverse section.
The design of the conventionally reinforced deck slab and contribution of web bending due to
loading of the transverse deck cross section may be captured through traditional influence
surfaces or by modern modeling techniques, such as finite element analysis. Section 7.2
discusses this in more detail. The prototype example focuses on the longitudinal U-beam
design.
6 - 17 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
Because the amount of prestressing or post-tensioning in the casting bed is small for precast
concrete U-beams relative to precast concrete I-beams, the requirement for initial camber is
less applicable. Instead, adequate mild, or preferably prestressing, reinforcing is provided to
limit stresses in the precast concrete U-beam during handling, transport, and lifting. Section
7.1 discusses handling, transport, and lifting in more detail.
Compared with precast concrete I-beams, camber growth in precast concrete U-beams is
relatively small, typically ½ in. or less, due to the relatively small amount of initial prestressing
and short time duration between casting and erecting the beams and ultimately the closure of
the system. Deflections can be made more predictable by balancing prestress deflection
against deadload deflection. This can be especially useful for unbalanced span ratios.
Pretensioning of members can occur in straight parts of bridges with both straight and curved
alignments. Pretensioning is usually much less expensive than post-tensioning, especially if
fewer tendons can be used.
6 - 18 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
6.12.3 Build-Up Calculation and Deck Screeding
The build-up, sometimes referred to as the haunch, makes up the difference between the
bottom of the concrete deck (based on the roadway finish grade elevations) and the top of the
precast concrete U-beams. The build-up is calculated for construction phases based on
predicted deflections of the U-beams during the build-out, varies along the length of the U-
beams, and is a function of the following:
• prescribed minimum build-up
• prescribed minimum difference in build-up between adjacent segments
• finish grade elevations
• concrete deck thickness
• U-beam segment camber due to prestressing and self-weight
• deflection of the U-beam during the build-out (may be the same or different for each
web)
• rotation of the U-beams to accommodate bridge superelevation
• stiffness of temporary tower supports
Figure 6.11 shows an exaggerated view of the build-up of a representative U-beam. A case with
upward beam camber is shown (build-up is less at midspan than at the ends), but, as discussed
in section 6.12.1, the beam camber could be such that the build-up is greater at midspan than
at the ends. For the reasons discussed in section 6.12.2, build-up is specified for both the left
and right webs of the U-beam. The deck screed and formwork for the concrete deck are set
based on the calculated build-up. A minimum build-up of 1 in. is recommended, and
corresponds to the build-up at the left web at the beam centerline in Fig. 6.11.
Table 6.2 is a sample table that may be used for drawing production. The table shown is for the
right web of the right U-beam. Similar tables are required for each web. Appendix D provides a
sample calculation for build-up of a select location on the prototype bridge.
6 - 19 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
Figure 6.11
U-beam build-up (exaggerated view).
The information presented in Table 6.2 will allow the contractor to calculate the following key
elevations during construction:
• elevation of lid slabs
• final deck elevations for deck casting
6 - 20 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
6 - 21 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 6
MODELING AND ANALYSIS
The “analysis points” column in Table 6.2 is the length along the top flange at the midpoint of
the top flange. The total deflection at each construction stage is the deflection at the end of
each stage after all loads were applied and time-dependent effects occurred.
The theoretical deflections, elevations, and build-ups from the design phase were based on an
assumed construction sequence. In the construction phase, theoretical deflections, elevations,
and build-ups should be verified by the contractor and the erection engineer based on the
actual construction sequence, including variations from the timeline assumed in design. Field
survey and dry-run measurements are required by the contractor to confirm screed elevations
before casting the concrete deck.
Deflections of spliced girders during construction are significantly less than conventional
simple span prestressed girders. The inherent stiffness from continuity and the lower amounts
of required prestressing force, combined with the load-balancing effect of the continuity post-
tensioning, greatly reduce movements of the structure during construction and over time.
Appropriate setting of deck grades is much less critical than with long-span, conventional
precast concrete girder bridges.
Because actual construction schedules usually vary from what is assumed in design, the
specifications typically require the specialty engineer to recalculate these values. Therefore,
presentation of build-ups in the design plans for design-bid-build contract delivery may be
redundant and their inclusion is a decision made by the governing agency.
6 - 22 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
DESIGN CONSIDERATIONS
This section discusses critical items for the design of U beams during temporary phases of
construction and in the permanent condition. This section builds on the analysis discussion of
the previous chapter and is supplemented by the sample design criteria and calculations in
appendices A and D.
7- 1 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
7.1.1 Internal Bracing
The curvature of a U-beam segment results in torsional moments along the length of the
segment. Before casting the lid slab, torsion moments on the open section are resisted by a
combination of St. Venant and warping torsion. The torsional stiffness is reduced by cracking
of the concrete. If torsional stresses in the open section exceed the code limits, control of
torsional stresses may accomplished by the early addition of the lid slab, temporary internal
bracing, and/or the introduction of prestressing force. Further, the introduction of thin web
cross sections may require bracing or casting of a lid slab before transport, depending on the
cross section used.
The addition of the lid slab increases the torsional stiffness of the segment by as much as 50
times or more, depending on the precast concrete section used (Fig. 6.4). The actual build-up
of torsional stresses is incremental. The open section is subjected to torsional stresses due to
the self-weight of the U-beam. The open section also supports the weight of the lid slab. The
closed section created by the lid slab and U-beam resists additional incremental loads. The
connection between the lid slab and U-beam must be designed and detailed to be sufficiently
strong to resist the incremental torsional stresses that occur after the connection is
established. Alternatively, the engineer may choose to design and detail a more robust
connection that does not account for the incremental build-up of torsional stresses. In all
projects constructed to date, the lid slab to U-beam connections have performed well.
Internal bracing or concrete diaphragms may be required during some stages of construction
to control deformations and stresses of an open web box system. Internal bracing spanning
between the top flanges has been previously used, including:
• horizontal struts at lifting points only, discussed in more detail in section 7.1.3
• horizontal ties at regular intervals along the segment to limit web deflections when
setting overhang brackets and casting the deck
• horizontal struts at regular intervals along the segment with diagonal bracing between
horizontals to create a torsional “truss”
U-beam cross sections are generally sufficiently robust that internal bracing outside lifting
points does not contribute greatly to load capacity. Conversely, this bracing will increase costs
and create interferences and difficulties during construction. The early placement of the lid
slab generally eliminates the need for internal bracing for the girders that are described.
Horizontal struts along the length of the girder do not affect torsional stresses unless they are
connected by diagonals to create a truss, similar to steel tubs to control torsions. Lid slabs are
more desirable as they can be incorporated into the permanent structure.
Stresses due to torsional moments may also be controlled by introducing prestressing force
before casting the lid slab. Based on the recommendations of the AASHTO LRFD specifications
Eq. 5.8.2.1-3, consider torsional effects when the applied torsion is greater than 0.25 times the
torsion cracking moment Tcr, including the strength reduction factor. From AASHTO LRFD
specifications Eq. 5.8.2.1-4, the torsional cracking moment is defined as
7- 2 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
2
Acp f pc
Tcr = 0.125 f 'c 1+ (kip-in.)
pc 0.125 f ' c
Where
f 'c = compressive strength of concrete for use in design (ksi)
Acp = total area enclosed by outside perimeter of concrete cross section (in.2)
7.1.2 Overturning
During plant handling and transport, the segments must be supported in such a way that the
segments are prevented from rotating due to the torsional moment about the longitudinal axis
of the segment. Restraint of the segment may be accomplished by a restraint system or by
offsetting lifting and support points. Rotation of the girder must also be prevented once the
segments are lifted onto the temporary falsework or permanent piers.
Overturning is not typically an issue and is generally controlled with proper handing and
bunking rather than external bracing, which would only be necessary in unusual situations.
7.1.3 Lifting
U-beam segments are generally lifted using strand lift loops or high-strength bars with
sufficient embedment to develop the required strength. Lifting points can be located near the
ends of the segment or away from the ends to reduce the positive moment during lifting. . For
example, a significant reduction in torsional demand is realized by positioning the temporary
supports inboard by 10% of the segment length (Fig. 7.1). Shifting the lifting points inboard
will require stress checks for negative moment at the cantilever supports. Twenty percent of
the segment length produces approximately equal positive and negative moments; however,
the section moduli at the top and bottom of the U- beams are not equal, so a support point that
equalizes stresses and not moments may be advisable. The optimum location of lifting points
varies and is best determined based on experience and calculation.
Inboard lifting points should be evaluated for erection considerations as they require larger
crane radii to swing girders into position. Lifting points at the ends of the girder are sometimes
necessary to facilitate erection.
7- 3 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
Figure 7.1
Torsional analysis and demand.
For a given U-beam cross section, the introduction of prestressing force in the casting yard
(see section 7.1.1) in combination with careful placement of supports during lifting and
transport may eliminate the need for regular horizontal struts or diagonal bracing to control
torsional distortion during lifting and transport.
As noted in section 7.1.2, care must be taken to prevent the U-beam segment from rotating
when lifting in the plant or during girder placement. This is accomplished by offsetting the
center of action of the spreader bar and U-beam segment. Figure 7.2 shows a typical spreader
bar and lifting hook arrangement.
Care must be used to consider the dynamic effect discussed in section 2.2.3 when lifting,
handling, and transporting segments.
Figure 7.2
Spreader bar and lifting hooks.
Figure 7.3 shows analyses that were performed to determine the behavior of the U-beam
segments during lifting, transporting, and placing on temporary falsework with the lid slab
7- 4 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
casting operation. For lifting and transporting, the midspan moment is significantly less than
for the case when the beam is placed on falsework. Table 7.1 shows a comparison of midspan
stresses made for four 100 ft long beams, that is, straight and with radii of 500, 750, and 1000
ft. This comparison shows that for longitudinal stresses, the behavior of the four beams is
similar. In general, the curvature of the beams can be ignored for this stress check.
Figure 7.3
Lifting, transport, and falsework evaluations.
7- 5 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
Table 7.1. Midspan stresses for beams for lifting and transport
Top stress, psi Bottom stress, psi
Beam radius
Left Right Left Right
Straight (R = infinity) -166 -166 139 136
1000 ft -172 -161 126 144
750 ft -174 -158 126 151
500 ft -177 -154 120 151
Classical Beam -173 140
Theory
Additional evaluations were made for beams supported at their ends and with lid slab loads
applied. Figure 7.4 shows transverse stress conditions that exist in the bottom slab and webs
for an 84 in. deep × 100 ft long × 500 ft radius U-beam. Applying the beam dead weight and lid
slab load of 0.66 kip/ft, the longitudinal moment demand at mid-span is estimated to be 3700
kipft, and the torque demand is estimated to be 240 kipft at the beam ends. Finite element
results summarized in Table 7.2 show longitudinal stresses at midspan at the corners of the
top and bottom flanges differing by approximately 200 psi from straight-beam (Mc/I) theory
and 200 to 350 psi from an equivalent finite element analysis on a straight beam. Transverse
stresses in the top of the bottom slab are estimated by the finite element analysis to be 145 psi
maximum. These relative comparisons between finite element results and classical beam
theory (using Mc/I) are performed for self-weight and do not include the effect of prestressing
or impact for transport. Note that tension is positive in Tables 7.1 and 7.2.
7- 6 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
Figure 7.4
Deformations and stress on U-beam segment.
Understanding that systems constructed with smaller radii and longer spans could increase
the effects of out-of-plane behaviors, it is recommend the cut-off for more rigorous analysis be
established at L/R = 0.2 as recommended by NCHRP Report 620 [7-1].13 This is implemented
in the AASHTO LRFD specifications, Article 4.6.1.2.4c. Hence, the first step of analysis
refinement after the cut-off is a grillage model, which is presented for the prototype beam in
chapter 6. This ratio is applicable for the bridges on falsework or in their permanent
configuration.
7- 7 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
The design checks discussed in general in the following sections and presented in more detail
in appendix D are based on the results of the three-dimensional modeling discussed in section
6.9.
7- 8 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
• As = 1.0(Av) + 0.5(Af)
• As = 0.5(Av) + 1.0(Af)
• As = 0.7(Av + Af)
Where
Av = area of reinforcement required for longitudinal shear and torsion
Af = area of reinforcement required for transverse flexure
The width of the web effective for shear was according to the AASHTO LRFD specifications,
Article 5.8.2.9, and reduced for post-tensioning ducts based on the requirements of the
AASHTO LRFD specifications, Article 5.8.6.1.
where
Aps = area of prestressed steel on the tension face of the beam
b = width of the compression face of the beam
d = distance from the extreme fiber in compression to the centroid of the steel on the
tension side of the member
The reinforcement ratio varies along the length of the bridge due to the profile of the
continuity tendons, the addition of local bottom or top tendons, and changes in the bridge
cross section. The reinforcement ratio differs for positive and negative moment regions.
Reinforcement ratios for key locations of the prototype bridge were calculated to provide a
reference to the designer (Table 7.3). An example calculation for reinforcement ratio is
included with the ultimate flexure check in appendix D.
7- 9 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
Table 7.3. Reinforcement ratios for prototype bridge
Location Reinforcement ratio
7- 10 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
limits on principal stress to limit cracking in the web under service conditions, including
construction stages.
Principal web stresses are generally checked for each construction stage and for the structure
in the final stage for both short- and long-term creep and shrinkage results at the centroid of
the cross section. An example principal web stress calculation is included in appendix D.
7- 11 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 7
DESIGN CONSIDERATIONS
7- 12 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
DESIGN DETAILS
This chapter includes design details for U-beam bridges, including the following:
• typical section and post-tensioning
• lid slab and deck details
• precast concrete tongue section
• interior haunch section
• blisters
• diaphragms
• bearings
Qualitative design discussion related to various elements is provided throughout this chapter.
In-depth discussion is provided for unique elements, such as the diaphragm, over more
common elements, such as the deck slab.
The prototype project that is the focus of this document is not intended to represent the most
efficient and cost-effective design alternative, nor is the discussion in this chapter intended to
provide a comprehensive view of all possible details and design decisions that must be
included in a given project. Instead, it serves an example of one prototype project with focus
on some of the more important structural design requirements. Other items that should be
considered by the design professional may include, but are not limited to:
• reinforcing to resist curvature effects in webs (see bar 3B21 in Fig. 8.11)
• stressing jack access at expansion joints and intermediate tendon anchorages
• superstructure to substructure connections without bearings
- pinned connections
- integral connections
• bottom slab anchorages and blisters
• expansion joint details
• splice details
- splice length
- splice reinforcement
- shear interface between precast concrete U-beam and cast-in-place splice
- post-tensioning duct connections
• staged deck slab placement to minimize dead load stress in cast-in-place deck over the
piers
Figure 8.1
Typical section of prototype bridge.
Figure 8.2 shows the post-tensioning layout for the prototype bridge. The post-tensioning is
composed of three types of tendons. Each segment has two nine-strand tendons in the bottom
flange designed to support its self-weight. The U-beam section has four draped continuity 15-
strand tendons in each web that pass through internal ducts from the beginning to the end of
each unit, linking all the U-beam segments in the unit when the final stressing is complete. The
geometry of tendons is arranged in a parabolic pattern, although harped arrangements are
equally feasible. In general, Colorado designs have used a parabolic pattern instead of the
harped pattern. Also, a top flange 12-strand tendon in each web is provided over the middle
pier. These tendons were sized to limit the Service III tension and Service I compression
stresses within allowable limits during all stages of construction and final service life of the
bridge. Figure 8.3 shows post-tensioning coupling at a field splice using couplers (red) and
heat shrink sleeves (black).
Post-tensioning ducts are spliced within cast-in-place closure placements between U-beam
segments. Because the lengths of cast-in-place splices are relatively short (less than 2 ft), duct
protrusions from the ends of the beam segments are very rigid and not easily moved.
Therefore, mitigation of duct extension translation during beam concrete placement is
paramount for field splicing success; otherwise, the integrity of this splice will be
Figure 8.2
Post-tensioning of prototype bridge.
Figure 8.3
Post-tensioning coupling details at field splice.
Figure 8.4
Typical slab reinforcement.
Figure 8.5
Typical lid slab reinforcement before main deck placement.
Figure 8.6
Typical slab reinforcement detail over top flange.
If used, the lid slabs are cast in place or installed as precast concrete elements after the beams
are erected to limit the transport weight (Fig. 8.5). The design of the lid slab is recommended
to account for horizontal shear forces at the interface between the lid slab and U-beam,
horizontal shear forces at the interface between the lid slab and deck slab, torsional force flows
via diaphragm and strut-and-tie action, longitudinal distribution reinforcing, and transverse
moment capacity due to the weight of the deck placement and subsequent superimposed dead
and live loads after the deck is cast.
Figure 8.7
Tongue extension elevation reinforcement.
Figure 8.8
Tongue extension section reinforcement.
Figure 8.9
Tongue extension isometric view of reinforcement.
Figure 8.10
Haunch detail at piers.
Figure 8.11
Haunch reinforcement detail (assuming construction joint).
Figure 8.12
Plan view of top blister.
(Connecting block reinforcing not shown.)
8 - 10 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
Figure 8.13
Partial elevation of top blister.
(Connecting block reinforcing not shown.)
Figure 8.14
Section of top blister.
8 - 11 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
Figure 8.15
Isometric view of top blister.
Figure 8.16
Block-out for top flange post-tensioning blister.
8 - 12 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
8.6 DIAPHRAGM
Diaphragms are cast at all the permanent piers to tie the two U-beams together and transmit
loads to the bearings. The diaphragm carries vertical shear and torsion from the webs of the U-
beam around the access opening to the bearings on the pier cap located at the centerline of
each U-beam. Figure 8.17 shows the elevation view of the diaphragm at pier 3. The diaphragms
at the end of the unit are similar. This section demonstrates strut-and-tie layouts that may be
used to design a diaphragm for the prototype curved U-beam bridge with each U-beam
supported on single bearings (See Figure 8.21).
Integral construction, or use of two bearings supporting each U-beam under the webs
eliminates indirect supports. Hence, the diaphragm analysis can be simplified and reinforcing
requirements reduced. Furthermore, the later details may potentially eliminate the need for a
diaphragm between U-beams and facilitate skewed construction.
The interior diaphragm is 8 ft tall and approximately 32 ft wide and is 4 ft thick (Fig. 8.17). The
horizontal span between bearings is approximately 23 ft, which depends on the superstructure
cross slope. The assumed bearing plate at each bearing is 3 ft wide. The diaphragm includes
two 3 ft diameter inspection access opening at the center of the U-beams to conform to
Occupational Safety and Health Administration requirements.
Figure 8.17
Elevation view of interior diaphragm at pier 2.
Internal diaphragms are generally complex elements that must resist the introduction and
transfer of various loads and reactions. Figure 8.18, adapted from Beaupre et al. (2011),16
shows an example of diaphragm cracking for a U-beam bridge that may occur if the bearing are
set substantially inboard from the webs and force transfer is not accounted for by
reinforcing—for example, to maintain traffic clearance by pier placement.
8 - 13 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
Figure 8.18
Concrete box with centered bearing, similar to diaphragm for prototype.
Figures 8.19 and 8.20 show the application of diaphragm shear and torsion loadings used for
the prototype bridge. In Fig. 8.20, beam action of the diaphragm is illustrated by the moment
diagram (shaded orange) due to applied torques and the deflected shape shown with a dashed
line. Anticipated tension and compression zones of the diaphragm are labeled. The web shear
and torsion forces are assumed to be placed at the center of the transverse horizontal ties at
the upper and portions of the web. Additionally, there is substantial continuity post-tensioning
at the top of the section at the pier; hence, the need to provide some hanger reinforcing in the
webs at this location is clear. Nonetheless, there are conflicting opinions and research
regarding the placement of the resultant web shear and torsion forces, especially in the
selection of the vertical level for the applied load. This is a complicated issue that partially
depends on the longitudinal moment and shear-load-carrying behavior of the spans adjacent
to the diaphragm. By providing some tie-up reinforcement in the web, the web cracking shown
in Fig. 8.18 can be controlled. Nevertheless, the amount of tie-up reinforcing is substantial, and
it is proposed to count all vertical reinforcing within d/2 of the diaphragm faces, plus the width
of the diaphragm, when evaluating the demand versus the capacity of the tie-up bars. Struts
from the upper portion of the tie-up reinforcing will be able to travel through the webs to
nodes located at the middepth of the webs.
Figure 8.19
Diaphragm loads for shear.
8 - 14 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
Figure 8.20
Diaphragm beam action due to applied torsional loads.
Strut-and-tie models may be used for the shear and torsion components to analyze their
effects.16,17 Figure 8.21(a) shows the fan-shaped strut distribution of global longitudinal
moment and shear forces. Figure 8.21(b) qualitatively shows the shear loads applied at the
upper and lower portion of each web and the applied force couple resulting from pure torsion
applied to one web. Ties at the upper and lower levels of the webs redirect the applied forces
to the bearings. External to and between the U- beams, the diaphragm carries resultant
torsional moment and shear between the two boxes via beam action.
8 - 15 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
Figure 8.21
Qualitative strut-and-tie models for diaphragm.
For the diaphragms at the ends of each unit where the continuity post-tensioning tendons are
anchored, it is necessary to analyze and design reinforcement to resist the tensile stresses
developed by the distribution of the anchorage forces into the diaphragm and U-beams. Figure
8.22 shows a simplified two-dimensional strut-and-tie model for the transfer of anchor loads
from the diaphragm into the web and flanges of the U-beam. The top and bottom flange force is
the equivalent force based on the section stress. The strut-and-tie model shows the controlling
tie force is 0.25 to 0.30 of the factored applied post-tensioning force P. Based on this tie force,
the area of steel required can be determined.
8 - 16 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
Figure 8.22
Strut-and-tie model for tendon anchorage force distribution into the diaphragm at ends of
unit.
8 - 17 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
8.7 Bearings
The connection of the superstructure to substructure is an important design consideration.
Bearings are engaged when the beams are placed or when falsework loads are released. The
superstructure can be supported on bearings or made integral with the substructure assuming
the piers are flexible enough to allow the necessary movements. The elimination of the
bearings could result in lower initial cost and future maintenance savings. If bearings are used,
pot or disk-type bearings may be an option. Figures 8.23 and 8.24 show the bearing
configuration assumed for the prototype bridge. These figures show the bearing details for a
fixed bearing. Bearings can be grouted at the permanent piers, which allows some translational
and rotational tolerances to be built out during construction due to the room around pintles.
Figure 8.23
Transverse view of bearing.
With consideration of tolerances in the bearing design, it may be possible to erect directly on
the bearings to eliminate shoring. Welded connections with steel taper plates have been used
in some applications. The advantage of a welded connection is that tongue sections can be
placed directly on the bearings without the use of falsework. If this detail is used, field welding
must be properly detailed and executed for long-term performance and tolerances accounted
for. If nonuniform bearing pressures are created, the elastomers can be overstressed and fail.
Elastomeric bearings are feasible provided they are designed with sufficient load and
rotational capacities. Rotational checks must be made with code-recommended rotational
setting tolerances. Furthermore, attention shall be given to all erection stages and any blocking
or restraint required to prevent bearings from moving or disengaging during construction.
8 - 18 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
Figure 8.24
Longitudinal view of grouted fixed bearing.
8 - 19 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 8
DESIGN DETAILS
8 - 20 (April 2020)
DESIGN OF CURVED, SPLICED PRECAST CONCRETE U-BEAM BRIDGES_______________CHAPTER 9
REFERENCES
REFERENCES
1. PCI Bridge Committee. 2012. Curved Precast Concrete Bridges State-of-the-Art Report. CB-
01-12. Chicago, IL: PCI.
2. AASHTO (American Association of State Highway and Transportation Officials). 2017.
AASHTO LRFD Bridge Design Specifications. 8th ed., customary U.S. units. Washington, DC:
AASHTO.
3. Nickas, W. N., and J. S. Dick. 2015. “Sharing New Technology Through PCI Bridge
Technoquests.” Aspire 9 (3): S-1–S-15 (supplement).
www.aspirebridge.com/magazine/2015Summer/ASPIRESupplementSummer2015.pdf
4. Stelmakc, T. 2016. “Design Considerations for Horizontally Curved Precast Concrete U-
Girders.” Aspire 10 (1): 30–32. www.aspirebridge.com/magazine/2016Winter/CBT-
DesignConsiderationforHorizontallyCurvedPrecastConcreteUGirders.pdf
5. WSDOT (Washington State Department of Transportation) Bridge and Structures Office.
2011. Bridge Design Manual (LRFD). M 23-50.05. Olympia, WA: WSDOT.
8. PTI (Post-Tensioning Institute). 2012. Guide Specification for Grouted Post-Tensioning.
M50.3-12. Farmington Hills, MI: PTI.
9. Brice, R. 2018. “Designing Precast, Prestressed Concrete Bridge Girders for Lateral
Stability: An Owner’s Perspective.” Aspire 12 (1): 10–12.
10. AASHTO. 2017. Guide Specification for Wind Loads During Construction. AASHTO GSWLB 1.
Washington, DC: AASHTO.
11. PCI Bridge Design Manual Steering Committee. 2014. Bridge Design Manual. MNL-133. 3rd
ed. Chicago, IL: PCI.
12. CEB/FIP (Euro-International Concrete Committee/International Federation for
Prestressing). 1990 International System of Unified Standard Codes of Practice for
Structures. Volume 2: CEB-FIP Model Code for Concrete Structures. Paris, France: CEB.
13. NCHRP (National Cooperative Highway Research Program). 2008. Development of Design
Specifications and Commentary for Horizontally Curved Concrete Box-Girder Bridges. NCHRP
Report 620. Washington, DC: Transportation Research Board.
www.trb.org/Main/Public/Blurbs/160353.aspx
14. Bressan, M., and P. D. Kinderman. 2014. “Satus Creek Bridge.” Aspire 8 (2): 24–26.
15. Rogowsky, D. M., and P. Marti. 1991. Detailing for Post-Tensioning. VSL Report Series 3.
Bern, Switzerland: VSL International.
https://www.ethz.ch/content/dam/ethz/special-interest/baug/ibk/concrete-and-bridge-design-
dam/lehre/masterstudium/Stahlbeton/Unterlagen/Detailing_for_post-tensioning.pdf
16. Beaupre, R. J., R. B. Anderson, and V. Bridges. 2010. Diaphragm for a Segmental Concrete
Bridge. ACI Special Publication SP-273. Farmington Hills, MI: ACI.
17. Schlaich, J., K. Schafer, and M. Jennewein. 1987. “Toward a Consistent Design of Structural
Concrete.” PCI Journal 32 (3): 74-150.
TBD-BD (to be determined by designer): These features, related to the layout and
configuration of the bridge structure, shall be determined by the engineering design
team in accordance with the requirements specified and/or directed by the governing
agency.
A2.1.1 Selected concrete mixture proportions, reinforcing type, and covers to satisfy
local practice and the anticipated exposure to environmental conditions
a. Tolerable ranges of the assumed beam age at time of erection or closure shall be
shown in the plans.
Material Density/effect
Reinforced concrete* 150 lb/ft3
Plain concrete without reinforcement 145 lb/ft3
Post-tensioned concrete 155 lb/ft3
Structural steel 490 lb/ft3
Sacrificial deck thickness† TBD-BD
Stay-in-place (SIP) or temporary
TBD-BD
forms‡
Note: TBD-BD = to be determined by designer.
* Compute the concrete density accounting for concrete strength according to
AASHTO LRFD Table 3.4.1-1.
† Many governing agencies require a nominal thickness of the deck to be
included as a sacrificial overlay. If a sacrificial overlay is used, it shall be
included in the dead load of the slab but shall be omitted from its section
properties.
‡ If metal SIP forms are used, their weight shall be distributed over the
projected area of the metal forms for the unit weight of metal forms and
concrete required to fill the form flutes. The governing agency shall be
consulted regarding the use of metal SIP forms, SIP pretensioned concrete
deck panels, or temporary forms.
Apply AASHTO LRFD specifications live-load HL93 design truck or tandem plus 0.64 kip/ft
uniform lane load.
AASHTO LRFD
HL93 design truck or tandem
All regions, specifications
plus 0.64 kip/ft uniform lane X
all spans Articles 3.6.1.2
load in all load lanes
Longitudinal
and 6.4.3
Permit load and legal loads shall be as defined by the governing agency.
A3.4.1 Wind loads for bridges computed in accordance with the AASHTO LRFD
specifications Article 3.8, and/or as defined by the governing agency.
TBD-BD
For structural design (concrete); see also AASHTO LRFD specifications Article 3.12:
Note: The AASHTO LRFD specifications Article C3.12.3 gives guidance related to the
exclusion of thermal gradient effects based on local performance experience.
For deck movements for design of bearings and expansion joints, per AASHTO LRFD
specifications Table 3.4.1-1, use 0.00 or 1.00 times the combined movements of creep,
shrinkage, and elastic shortening (bracketing the time-dependent behavior), plus 1.20
times the calculated movement due to temperature change.
Bearings accommodate motions that occur after girder erection; expansion joints
accommodate motions that occur after joint installation. Bearings and expansion joints
shall be designed to accommodate the full range of movement.
Bearings and expansion joints shall be adjusted based upon the temperature during the
time of installation.
A3.6.1 Strains are calculated in accordance with CEB/FIP Model Code for Concrete
Structures, 1978 or 1990, provisions developed by the American Concrete
Institute Committee 209; or AASHTO LRFD Section 5.4.2.3.
A3.6.2 Relative humidity: TBD-BD (see also the AASHTO LRFD specifications, Fig.
5.4.2.3.3-1)
A3.6.3 Permanent effects of creep and shrinkage shall be added to all AASHTO LRFD
specifications loading combinations with a load factor per Table 3.4.1-3.
A3.7.1 TBD-BD: Minimum construction live load CLL of 10 lb/ft2 when permanent deck
slab is in place, per AASHTO LRFD Article 5.14.2.3.2. Additionally, 50 lb/ft 2
loading across the width of the lid slabs and flanges during erection and 25
lb/ft2 across the full deck for falsework reactions has been used on previous
projects.
Apply construction equipment load CEQ for assumed weight of screed machine.
Apply CLL and CEQ as applicable per the load phases outlined in section A3.7.4.
A3.7.2 Wind loads on permanent and temporary components during construction shall
be considered. The design wind speed for evaluation of strength and stability
evaluations of temporary falsework may be reduced based on statistical
evaluations of the expected wind return period over the duration of the
construction. Wind loads during construction may be established by the owner.
b. Setting with beam self-weight (DC) 20% down (DC) of beam self-
weight for amplification of loads due to an abrupt placement.
c. Lid slab construction with beam self-weight (DC), lid slab self-weight
(DC), stay-in-place (SIP) forms between the girder webs and concrete filling
the SIP form flutes (DW) if applicable, and with construction load (CLL) over
the area of the lid slab and beam flanges.
A4. MATERIALS
A4.1 Concrete
A4.1.1 All concrete properties shall be in accordance with the specified 28-day
compressive strength f’c and initial strength f’ci suggested in Table A4.1.
A4.2.1 It is suggested that reinforcing steel conform to ASTM A615, Grade 60, unless
otherwise required.
A4.2.2 All reinforcing steel shall be black or epoxy as defined by the project contract
documents (plans and specifications) and the local governing agency.
A4.2.3 Mechanical couplers shall develop not less than 125% of the yield strength of
the bar.
A4.2.4 Headed reinforcing provided shall be in accordance with the project contract
documents (plans and specifications).
All strands are assumed to be 0.6 in. in diameter, conforming to the requirements of ASTM
A416 Grade 270 for low-relaxation strands.
Post-tensioning:
Material properties/parameters:
Tensile strength of prestressing strand fpu: 270 ksi
Yield strength of prestressing strand fpy : 243 ksi
Modulus of elasticity: 28,500 ksi
Anchor set: 3/8 in.
Allowable stresses:
Maximum jacking stress at anchorage: 0.80fpu
Maximum anchorage stress at anchorage
immediately after anchorage: 0.70fpu
Max. anchorage stress at internal locations
immediately after anchorage: 0.74fpu
All bars shall conform to the requirements of ASTM A722 Grade 150.
Material properties/parameters:
Tensile strength of prestressing bars fpu : 150 ksi
Yield strength of prestressing bars fpy: 120 ksi
Modulus of elasticity: 29,700 ksi
Maximum jacking stress: 0.80fpu
Maximum anchorage stress: 0.70fpu
Anchor set: Zero
Friction coefficient μ: 0.30
Wobble coefficient k: 0.0002/ft
Allowable stresses:
Maximum jacking stress at anchorage: 0.80fpu
A5.2.1 Compression
Due to effective prestress, permanent loads, and transient loads. 0.60f’c (ksi or psi)
Flexural tension: Areas outside of joints with minimum bonded auxiliary 0.190∙√f’c (ksi)
reinforcement 6∙√f’c (psi)
Flexural tension: Closure joints with minimum bonded auxiliary 0.095∙√f’c (ksi)
reinforcement 3∙√f’c (psi)
0.110∙√f’c (ksi)
Principal tension: Neutral axis of web
3.5∙√f’c (psi)
0.190∙√f’c (ksi)
Excluding “other loads”
6∙√f’c (psi)
Flexural tension: All areas
0.220∙√f’c (ksi)
Including “other loads”
7∙√f’c (psi)
0.110∙√f’c (ksi)
Excluding “other loads”
3.5∙√f’c (psi)
Principal tension: Neutral axis of
web
0.126∙√f’c (ksi)
Including “other loads”
4∙√f’c (psi)
Design operating legal and permit limits (as defined by the governing agency)
* Dimensions are for plastic duct. Revise for galvanized duct if they are allowed by
governing agency.
Provisional strands are not required. Provisional strands may be provided at the discretion
of the governing agency. Alternatively, the jacking stress may be reduced to allow for
adjustment of post-tensioning.
Use same radius for pairs of girders along the length of the span.
The maximum rotation shall be defined by maintaining the maximum and minimum haunch
specified in section A6.7.
• 6 in. maximum preferred for cast-in-place haunches; larger haunches are possible with
appropriate detailing
• 1 in. minimum for cast-in-place lid slabs; 1½ in. minimum for precast concrete lid
slabs
The governing agency shall be consulted regarding the use of metal SIP forms, SIP
pretensioned concrete deck panels, or temporary forms.
A7. MISCELLANEOUS
A7.1.1 Concrete cover shown on the plans does not include placement or fabrication
tolerances unless noted as “minimum cover”.
A7.1.2 Dimensions shown on the plans from face of the concrete to reinforcing bars are the
clear distances, unless noted otherwise. Spacing of bars is center to center.
Superstructure:
Prestress U beams (interior and exterior) 2 in.
Prestress girders: girder top flange 1 in.
CIP, except top deck surface 2 in.
Top deck surface (including ½ in. sacrificial) 2½ in.
All other surfaces 2 in.
A7.2 Bearings
A7.2.2 If bearing are used, it is suggested to include provisions for jacking of the
superstructure for replacement of all bearings. Bearing replacement may be
considered with a reduced live load.
Expansion joints shall be in accordance with the project plans and specifications.
It is suggested to provide interior lighting and electrical outlets at all ingress/egress access
openings and at midspan of each span. Only a single interior light and electrical outlet are
required if these locations coincide. Alternatively, the use of battery powered portable
lighting may be anticipated. The inclusion of interior lighting and power is generally
prescribed by the governing agency.
Suggested U-beam inspection access is described below and shall comply with
A7.6.1 Provide access opening into the box through the bottom slab. Provide doors at all
bottom slab access openings.
A7.6.2 Provide access holes in diaphragms at both expansion and interior piers. Provide
doors at diaphragm access openings at expansion joints at all piers and abutments.
A7.6.3 Equip all doors at abutments and bottom flange entrances with a keyed lock and
hasp. Require that all locks on an individual bridge be keyed alike.
A7.6.5 Provide wooden ramps at diaphragms and bottom slab blisters to facilitate
inspection and equipment movement. Provide ramps that are continuous through
the access opening. Composite internal bottom flange build-ups used for haunched
girders may serve as ramps. For all other wood, meet the treatment requirements
of the project plans and specifications.
The illustrations and reinforcing details shown in this publication are samples from
constructed projects. Local practices and requirements need to be followed.
For
450A-1 Description.
Fabricate, store, transport and erect precast prestressed spliced structural U-Beam concrete
superstructure segments to the established lines and grades, in accordance with the design,
dimensions and details shown on the Plans and in accordance with this Technical Special
Provision. Spliced U-Beams shall meet the requirements of Sections 400 and 450 of the FDOT
Specifications except as appended by this Technical Special Provision.
Embedded reinforcing steel, other embedded items and all appurtenant items are included.
Additionally, concrete, reinforcing and post-tensioning in cast-in-place portions of spliced U-
Beams shall be in accordance with Sections 400, 415 and 462 of the FDOT Specifications,
respectively.
The work in this Section 450A is applicable to longitudinally post-tensioned spliced beams upon
which a concrete slab is cast-in-place.
450A-4 Definitions.
The following definitions apply to precast prestressed spliced U-Beam bridge
construction:
450A-4.1 U-Beam Segment: A modular section of the superstructure consisting of the
U-Beam cross-section shape and length as detailed in the Plans. U-Beam pier segments may have
a variable thickness bottom slab which can be cast be cast monolithically, or as a secondary pour,
as detailed in the Plans.
450A-4.2 Casting Bed: A special formwork arrangement, meeting the requirements of
Section 450-6 and 5.2.2 of the FDOT Specifications, usually consisting of movable bulkheads of
the cross-section shape with side and core forms capable of horizontal movement, designed and
assembled into an assembly for making single or multiple superstructure spliced U-Beam
segments.
450A-4.3 Lid Slab: A field cast partial depth portion of the deck slab cast between the
top flanges of a single U-Beam to provide improved torsional characteristics to the spliced U-
450A-6 Materials.
450A-6.1 General: Use materials which conform to this Section 450A and the
requirements prescribed in the FDOT Division III Specifications, Materials, for the particular
kind and type of material specified.
450A-7.3 Precast Geometry: Before commencing the casting operation, submit the
proposed method of curve layout for all girder casting operations to the EOR for review. This
submittal must include but is not necessarily limited to:
(1) All measuring equipment and procedures for layout of curved formwork
(2) Location of working points to be established on the forms for manufacturing
the girders.
450A-9 Erection.
450A-9.1 General: The work under this item consists of furnishing the design and
erection plan for the erection of the U-Beams, including the design of any necessary falsework,
shoring, bracing and cofferdams required during, or between, construction stages as detailed on
the plans, shop drawings, and Specifications.
450A-9.1.1 References: The following references apply to this work and shall be
used by the Contractor's Specialty Engineer when performing construction engineering and
designing Temporary Works:
(1) AASHTO - LRFD Bridge Design Specifications - Customary U.S. Units,
2012 with 2013 Interims.
(2) AASHTO I AWS Dl.5/Dl. 5-2010 with 2011 and 2012 Interims - Bridge Welding
Code.
(3) AASHTO - Construction Handbook for Bridge Temporary Works, 1st Edition
(1995) with 2008 Interims.
(5) AASHTO - Guide Design Specifications for Bridge Temporary Works, 1st
Edition (1995) with 2008 Interims.
(6) FDOT - Structures Design Manual effective date January 1, 2014.
450A-9.1.2 Qualifications: The Contractor's Specialty Engineer charged with
preparing the erection drawings, calculations and manuals shall have a minimum of 5-years'
experience in the design and erection of spliced precast concrete structures and shall be a
Registered Professional Engineer in the State of Florida. The Contractor shall furnish the resume
of its Specialty Engineer, which shall include a detailed description of projects worked on, the
Specialty Engineer's role in these projects and owner references, which can verify the
experience.
In addition to the above, the Specialty Engineer shall be qualified in accordance
with Rule 1 4-75 Florida Administrative Code, Work Group 4.2.3: Major Bridge Design -
Segmental.
450A-9.1.3 Construction Equipment: The Contractor shall furnish and
maintain, at its own cost and risk, all tools, apparatus and appliances, equipment, and power for
same, scaffolding, runways, ladders, temporary supports and bracing, and all other similar work
or materials necessary to ensure speed, convenience, and safety in the execution of the work. All
such items shall comply with OSHA regulations and other applicable codes and standards.
450A-10
This section has been deleted.
The Standard Specifications are hereby revised for this project to include Section 631,
Alternative Bridge design & Construction, as follows:
DESCRIPTION
631.01 (a) The intent of this Special Provision is to provide to all bidders the option to submit a
bid for the design and construction of an alternative bridge structure (“alternative bridge”), in
lieu of submitting a bid for only the construction of the two-cell steel box girder structure
shown on the Plans and referred to herein as the “default bridge”.
Bidders are not required to submit a bid for an alternative bridge; rather, that is an option, at
their sole discretion. However, bidders are hereby notified that Colorado Department of
Transportation (CDOT) will consider all submitted bids for the default bridge and for the
alternate bridge together, and that CDOT will award to the low responsible and responsive
bidder regardless of the particular type of bridge structure (default or alternative) bid by that
bidder.
(b) The only alternative bridge structure type that is acceptable to CDOT under this Special
Provision, and for which CDOT will consider a bid is Precast Post-tensioned horizontally
curved U-Girders.
No other alternative bridge types will be considered by CDOT. Any bids submitted for
alternative bridge types other than the type described above will be automatically rejected and
will not be considered.
(c) The intent of this Special Provision is to provide a specification that is applicable to an
alternative bridge. Any alternative bridge submitted by a bidder must be at least equivalent to
the default bridge. To be considered “equivalent”, the alternative bridge:
(1) Must provide all of the architectural features, live load capacity, safety features,
horizontal and vertical alignment, lateral clearance and minimum vertical
clearances, as described herein and as shown on the Plans; and
(2) Must include all work and materials to design and construct foundations, piers,
abutments, and superstructure with all appurtenances, as described herein and
as shown on the Plans.
(d) Any bid for an alternative bridge structure must strictly comply with all terms and
conditions of this Special Provision, in order to be considered “responsive” and eligible for
award.
DESIGN
631.02(a) General.
CDOT has not provided designs for the alternative bridge type described above. Therefore, if a
bidder elects to submit a bid for the alternative bridge structure, the bid must include both the
design and construction of the alternative bridge, and that bidder must provide a design for
the alternative bridge (“alternative design”).
Further, the alternative design must be completed by a Professional Engineer registered in the
State of Colorado. That Professional Engineer designer of the alternative bridge shall have
been in responsible charge of the design of the type of structure being proposed within the
past five years, and a list of successfully completed projects (which include the proposed type
of structure) shall be provided as reference.
If a bidder who elects to submit a bid for the alternative bridge is the apparent low responsible
bidder, that bidder shall submit the alternative design to the Award Officer for acceptance
within 12 calendar days of bid opening. As part of the alternative design, the bidder shall
provide to CDOT preliminary design calculations, a preliminary design and construction
schedule, and preliminary drawings for the alternative bridge structure for preliminary
approval. The preliminary drawings shall include a general layout, structure elevation, typical
section, and girder erection scheme. Two hard copies of reproducible drawings shall also be
included.
Bidders on alternative bridge should be aware that only the low bidder who gets the award
will be compensated by CDOT for the design, as part of that bid; any bidders who will have
performed design work before award, but do not get the award for any reason, will have
performed that work at their sole cost and that design work will not be reimbursed by CDOT.
Any delay in the bidder’s submittal or CDOT’s review and approval of a proposed alternative
design, or a revision thereto, shall not extend the contract time.
The Contractor shall ensure that the alternative design meets all applicable design criteria for
strength and serviceability, as described herein and as shown on the Plans. The Contractor
shall use the Plans, and the References and Guidelines in subsection 631.02(e), for the design
criteria.
Alternative designs predicated on any errors or omissions in the Contract will be rejected. If
any such error, omission or discrepancy is discovered, the Contractor shall notify the Engineer
immediately. Failure to notify the Engineer will constitute a waiver of all claims for
misunderstandings, ambiguities, or other situations resulting from error, omission, or
discrepancy.
The alternative design shall include an independent design check by an independent engineer
registered in the State of Colorado.
An alternative bridge design structure shall be identified by the same structure number as the
default bridge.
On the alternative bridge design drawings, the title block shall show the Contractor’s signature
in ink, the date signed, a business name, business address, and the note: “These drawings
(Bxxx-Byyy) which supersede drawings (Bwww-Bzzz) were approved (insert date).”
The Contractor shall submit complete original plans and electronic files for an alternative
design entirely in Auto-Cad 2000 format, and the Contractor shall make any changes in the
same medium.
The Contractor shall submit the final plans, the itemized quantity and cost break down, and the
bridge field package, to the Engineer in accordance with the preliminary design and
construction schedule. The final package for submittal shall include complete design
calculations, design check calculations, and the bridge rating. Final bridge geometry, including
project coordinates and dead load deflections, shall be included in the bridge field package.
For each portion of the alternative bridge, the Contractor shall submit two record sets of plans
with design notes and computations to the Engineer one week prior to starting construction of
that portion of the alternative bridge. The design notes and computations shall document the
conclusions reached during the development of the construction plans. The plans and design
computations will be reviewed by CDOT for completeness and to assure conformance with the
design requirements only. However, all details of the alternative design plans, as well as the
completeness and accuracy of those plans, are the Contractor’s sole responsibility. Designs and
computations that are not in compliance with Design Requirements, in section 631.02(d)
below, shall be corrected by the Contractor and resubmitted. The record sets shall bear the
endorsement seal and signature of the Professional Engineer in responsible charge of the
design and preparation of the plans.
The first sheet of the computations for the alternative bridge design shall contain the
endorsement seal and signature of a Professional Engineer registered in the State of Colorado.
Discrepancies between the design and the design check shall be resolved by the Contractor and
all corrections shall be reflected in the design computations.
The complete set of design computations for the alternative bridge design shall include both
substructure and superstructure and all appurtenances required. The structure shall be rated
in accordance with the CDOT Bridge Rating Manual and subsection 3.2 of the CDOT Bridge
Design Manual. The structure shall be designed for an HL-93 live load and the design shall
conform to all AASHTO requirements as amended by the CDOT Bridge Design Manual.
The foundations design shall be consistent with the recommendations provided by the CDOT
Geotechnical Section. In lieu of those recommendations, the Contractor may provide a
foundation analysis by an independent geotechnical consultant. Costs for independent
foundation analysis shall be borne by the Contractor.
The Standard Specifications shall apply to the construction of the alternative bridge.
The Contractor, in accordance with the Plans and the CDOT Bridge Design Manual, shall
provide inspection and maintenance access to the alternative bridge.
The Contractor shall provide all roadway lighting attachments for the alternative bridge at the
locations shown on the Plans.
All deck drains for the alternative bridge shall be placed by the Contractor at the locations, and
of the same or greater hydraulic capacity, than shown on the Plans.
All earthquake restraints or pintels for the alternative bridge shall be provided by the
Contractor in accordance with the CDOT Bridge Design Manual and AASHTO specifications.
The horizontal and vertical alignment for the alternative bridge shall be as shown on the Plans.
All substructure locations for the alternative bridge shall be as shown on the Plans. All
horizontal clearances to the traveled roadways for the alternative bridge shall be as shown on
the Plans. All vertical clearances for the alternative bridge shall not be less than the minimum
shown on the Plans.
All bearings, expansion devices, bridge rail and fence screening of the alternative bridge shall
be in accordance with the Contract, and CDOT Staff Bridge Design Manual and Staff Bridge
Design Worksheets.
The Contractor may use lightweight concrete for any portion of the alternative bridge only
with written approval of the Owner or Governing Agency.
The texture finish and color scheme of the alternative bridge shall be as shown on the Plans.
The pier column shape of the alternative bridge shall be as shown on the Plans. All piers shall
be the same shape.
The alternative bridge shall be constant depth, or shall provide the appearance of constant
depth. The girders of the alternative bridge shall be trapezoidal box shaped, and they shall be
continuous. The minimum deck overhang from the edge of the deck to the face of the girder at
the bottom of the deck shall be 3’-0”. The exterior webs of the boxes shall be sloped at one
The following shall be applicable to the design and construction of an alternative bridge.
Future continuity reinforcement required by the AASHTO Guide specification for Precast Post-
tensioned Segmental Bridges shall be external and shall be provided for with tendon
blockouts, deviation blocks and anchor blocks.
MATERIALS
631.04 General: All materials used in the construction of an alternative bridge structure must
meet the requirements of the applicable sections of the Standard Specifications.
CONSTRUCTION
631.07
(a) General. Construction of the alternative bridge shall strictly conform to the
applicable sections of the Standard Specifications.
(b) Survey. Construction survey for the alternative bridge shall be in accordance with
Section 625, as revised for this project.
(c) Traffic Control. Traffic control for the alternative bridge shall conform to the Traffic
Control Plan included in the Contract.
(d) Construction Oversight and Inspection. Cost of quality assurance inspections will be
the responsibility of CDOT. The Contractor shall be responsible for quality control
inspections for the alternative bridge. The Contractor’s Engineer of Record shall
check and approve all construction details, and records of post-tensioning and
geometric control, for the alternative bridge.
The designer of a shored structure shall review and approve shoring and falsework details for
construction of the proposed alternative bridge.
(e) Engineer’s Certification. The Contractor’s registered Engineer shall provide a letter
certifying that the alternative bridge structure was constructed in accordance with the
Contract, and that it meets all requirements of the design.
The presence of the Engineer of Record on the project shall in no way act to relieve the
Contractor of the full responsibility for: conformance of the work to the requirements of the
contract documents; the structural adequacy of the erection scheme he chooses; or the safety
of workmen or the general public.
(f) As-constructed Plans. The Contractor shall provide copies of the as-constructed plans,
shop drawings, and working drawings for the alternative bridge for informational purposes
and for future maintenance. Complete as-constructed plans and electronic files for an
The bottom slab and webs shall be placed monolithically. A construction joint between the
bottom slab and web will not be allowed.
631.10 The alternative bridge design and construction will not be measured, but will be paid
for on a lump sum basis, which basis will include all work and materials required to design and
construct an alternative bridge.
The work will include, without limitation, the design, the independent design check, bridge
rating, preparation of plans, details, and drawings required to fabricate and construct the
alternative bridge, and the construction of the superstructure, foundations, abutments, railings
and appurtenances. All discrepancies in quantities for the alternative bridge design will be the
Contractor’s sole responsibility and will not be adjusted.
The completed structure shall include the following items, which will not be measured
separately, but will be included in the bid price for Item 631, Alternative Bridge Design
Construction:
Structure Excavation, Structure Backfill (Class 1), Structure Backfill (Class 2), Mechanical
Reinforcement of Soil, Shoring, Drilled Caissons, Concrete Slope and Ditch Paving, Structural
Steel, Bearing Devices, Bridge Drains, Concrete Sealer, Bridge Expansion Devices, Concrete Class D
(Bridge), Structural Concrete Coating, Bridge Deck Finish (sawed Grooves), Reinforcing Steel,
Reinforcing Steel (Epoxy Coated), Bridge Rail Type 7, Fence Chain Link (Special) (36 Inch), 1 Inch
Electrical Conduit, 2 Inch Electrical Conduit, Prestressing Steel Wire or Strand, Prestressed
Concrete Slab (Depth Less Than 6 Inches), Precast Concrete U Girder (Post-Tensioned),
Mobilization and all other work and materials to complete the structure.
By submitting a bid for Alternative Bridge Design and Construction, the Contractor agrees to
accept the amount of that bid, as a lump sum basis, for the complete and satisfactory
performance of the work.
BASIS OF PAYMENT
The Engineer will determine partial payment for the construction of the alternative bridge and
include the partial payment on the monthly pay estimate.
Partial Payment and Price Reduction: The Contractor shall furnish an itemized quantity and
cost break down of the Lump Sum bid to the Engineer prior to commencement of construction.
The Contractor’s itemized quantity and cost break down shall reference the CDOT item
numbers as provided in the CDOT Cost Estimates Item Book.
The Engineer will review the Contractor’s itemized quantity and cost break down to determine
its trueness and reasonableness by using CDOT cost estimate data. The Contractor’s approved
itemized quantity and cost break shall be used as a basis for calculating monthly partial
payments and price adjustments for materials that do not meet specifications.
No adjustment will be made for differences in preliminary estimated quantities and final
quantities.
D.6 CAMBER
The information presented on these questionnaires was collected from available plan sets and
may not represent the actual as-built condition of the structure. For bridges with multiple
units, only the unit containing the controlling span was recorded.
8770 W. Bryn Mawr Ave. | Suite 1150 | Chicago, IL 60631-3517 | 312-786-0300 | www.pci.org