Description of Deviation:
Section / Clause of Employer's Requirements
Are the examples of previous use correct?
Will further deviations be needed on other plant
components as a result of this deviation?
MATERIALS SUBMISSION COMPLIANCE CHECKLIST
Prepared by: Checked by: Reference Number :
Project title Davao City Bulk Water Supply Project Design
Monna A. San Diego Wilson R. Emano
MAT-DBW-C048
Revision No.
Client Apo Agua Infrastuctura Inc. Date of Check 31-Jul-20 Construction
A
D DETAILED COMMENTS: Itemise any issues. Ensure that Safety, Environment and Quality are considered
If there are safety issues then ensure they are transferred to the safety plan. If there are commercial issues or risk ensure they are transferred to the risk register