Escription: Factory Acceptance Test of SAFE Module
Escription: Factory Acceptance Test of SAFE Module
1. DESCRIPTION
Factory Acceptance Test of SAFE module
2. DETAILS OF INSTALLATION
...................9220.0082.02.A..............................
............................................................................
............................................................................
............................................................................
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
2
FACTORY ACCEPTANCE TEST
CERN PROJECT
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
3
FACTORY ACCEPTANCE TEST
CERN PROJECT
Contents
1. Description ......................................................................................................................................................................................................................................................................................................................................1
2. Details of installation .......................................................................................................................................................................................................................................................................................................................1
3. People present for FAT.....................................................................................................................................................................................................................................................................................................................2
4. Visual inspection of equipment ........................................................................................................................................................................................................................................................................................................4
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
4
FACTORY ACCEPTANCE TEST
CERN PROJECT
4.1.2 Inspection of all doors in SAFE module, check good opening of door with cylinder & knob
(inside).
• Main entrance door (cylinder, no door handle, handle on the inside)
• Emergency doors (no cylinder & door handle on the outside, handle on the
inside)
• Presence off door closer & storm chain
4.1.3 Inspection of cyberhandlers area, ladder, grids, railing Not applicable, cyberhandlers will be shipped directly to CERN
• AHU 1 SAT test will be done once installed on site
• AHU 2
• AHU 3
• AHU 4
4.1.4 Water supply connection to all cyberhandlers Not applicable, cyberhandlers will be shipped directly to CERN
SAT test will be done once installed on site
4.1.5 Fresh air louver opening
4.1.7 Other/Remarks:
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
5
FACTORY ACCEPTANCE TEST
CERN PROJECT
4.2.2 Ensure all racks, cabinets, fixtures and fittings are firmly secured
• MDBs
o A-feed
o B-feed
o UPS feed
o Common
• AHU control box
• Junction Box (JB1)
• IT racks
• PDU systems
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
6
FACTORY ACCEPTANCE TEST
CERN PROJECT
• Roxtec 1 configuration
14 x RM60 filler
3 x RM40 filler
3 x RM40 -> capacity for 3 cables
with diameter 9,5mm – 32,5mm
24 x RM20W40 -> capacity for 48
cables with diameter 3,5mm –
16,5mm
• Roxtec 2 configuration
8 x RM60 filler
6 x RM20 filler
3 x RM40 filler
36 x RM20w40 -> capacity for 72
cables with diameter 3,5mm –
16,5mm
• Roxtec 3 configuration
•
8 x RM60 filler
6 x RM40 filler
42 x RM20w40 -> capacity for 84
cables with diameter 3,5mm –
16,5mm
16 x RM30 -> capacity for 16 cables
with diameter 20-25mm
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
7
FACTORY ACCEPTANCE TEST
CERN PROJECT
4.2.7 Other/remarks:
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
8
FACTORY ACCEPTANCE TEST
CERN PROJECT
5. ELECTRICAL
REF. DESCRIPTION PASS/FAIL COMMENTS
5.1 MDB A – FEED: Overall check of installation & connections of all cabling l
(Separate FAT already done in factory of panel builder)
5.2 Check good functioning of all MDBs Good functioning will be proven during SAT test on site after
MDB A- FEED: installation
MDB B- FEED:
MDB COMMON:
Check the values on the power meter
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
9
FACTORY ACCEPTANCE TEST
CERN PROJECT
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
10
FACTORY ACCEPTANCE TEST
CERN PROJECT
6. COOLING
6.1. AHU 1
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
11
FACTORY ACCEPTANCE TEST
CERN PROJECT
6.2. AHU 2
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
12
FACTORY ACCEPTANCE TEST
CERN PROJECT
6.3. AHU 3
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
13
FACTORY ACCEPTANCE TEST
CERN PROJECT
6.4. AHU 4
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
14
FACTORY ACCEPTANCE TEST
CERN PROJECT
7.4. Others/Remarks:
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
15
FACTORY ACCEPTANCE TEST
CERN PROJECT
8.2 Others/Remarks:
Not in our scope of works, Automation has foreseen 1 x 230Vac on the designated spot where the system will be installed.
9.2 Check presence of alarm contacts & mechanical locks in all emergency doors
• ASSA ABLOY LOCK 35MM
• DC107 Door contact
• Check functioning of door contact with Ohm meter
9.2. Others/Remarks:
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
16
FACTORY ACCEPTANCE TEST
CERN PROJECT
10.LOAD TEST
Not applicable, load test will be done on site after installation @ CERN during SAT
10.6 Re-connect main power on A-Feed and wait until all returns to
normal
10.8 Re-connect main power on B-Feed and wait until all returns to
normal
10.9 Failure of random AHU unit, contact to reduce IT load with 25%
Other AHU units will go into emergency mode
10.10
10.11.
10.12
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
17
FACTORY ACCEPTANCE TEST
CERN PROJECT
11.RESULTS LOADTEST
Not applicable, will be done after installation on site @ CERN
© All rights reserved, this information is the exclusive property of Automation NV (B-1502 Halle) and is confidential information. It may not be reproduced or communicated or used, in any form, without prior written permission of Automation NV.
18
FACTORY ACCEPTANCE TEST
CERN PROJECT
12.CONCLUSIONS
REF.
12.1.