Activity Name Activity ID Original Remaining Schedule % Start Finish Total Float Actual Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Duration Duration Complete Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar
Total 164 166 0% 22-Jul-19 A 28-Jan-20 -1 0
164
Two Schools Project ALThory + ALNithamieh Schools Rehabilitation 166 0% 22-Jul-19 A 28-Jan-20 -1 0
Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
ALThory + ALNithamieh Schools Rehabilitation Classic Schedule Layout 01-Feb-20 14:31
Activity Name Activity ID Original Remaining Schedule % Start Finish Total Float Actual Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Duration Duration Complete Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar
Repairs for Playground Gate
A1680 2 2 0% 04-Jan-20* 05-Jan-20 6 0 Repairs for Playground Gate
Supply & Tile Interlock Bricks
A1690 5 5 0% 15-Dec-19* 19-Dec-19 12 0 Supply & Tile Interlock Bricks
Curb Stone Works A1700 5 5 0% 09-Dec-19* 14-Dec-19 12 0 Curb Stone Works
Concrete Works A1710 46 46 0% 08-Oct-19* 30-Nov-19 7 0 Concrete Works
Tench Excavation WorksA1720 2 2 0% 05-Oct-19* 06-Oct-19 8 0 Tench Excavation Works
Two Schools Project.B.C Finishing Works 4 4 0% 25-Jan-20 28-Jan-20 -1 0
Site Cleaning and preparing
A1730for Submission 2 2 0% 25-Jan-20* 26-Jan-20 0 0 Site Cleaning and preparing for Submission
Primal Submission A1740 1 1 0% 27-Jan-20* 27-Jan-20 0 0 Primal Submission
Final Submission A1750 1 1 0% 28-Jan-20* 28-Jan-20 -1 0 Final Submission
Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation