ALThory + ALNithamieh Schools Rehabilitation Classic Schedule Layout 01-Feb-20 14:31

Activity Name Activity ID Original Remaining Schedule % Start Finish Total Float Actual Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Duration Duration Complete Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar
Total 164 166 0% 22-Jul-19 A 28-Jan-20 -1 0

164
Two Schools Project ALThory + ALNithamieh Schools Rehabilitation 166 0% 22-Jul-19 A 28-Jan-20 -1 0

Two Schools Project.Mobilization Mobilization 5 4 0% 22-Jul-19 A 23-Jul-19 40 0


Mobilization Works A1480 5 4 0% 22-Jul-19 A 23-Jul-19 40 0 Mobilization Works

Two Schools Project.A ALThory School 158 158 0% 24-Jul-19 23-Jan-20 0 0


Two Schools Project.A.1 Excavation, Demolishing Works 25 25 0% 24-Jul-19 21-Aug-19 40 0
Demolishing Works A1170 25 25 0% 24-Jul-19 21-Aug-19 40 0 Demolishing Works
Two Schools Project.A.2 Concrete Works 8 8 0% 04-Nov-19 12-Nov-19 37 0
Maintenance of Two Columns
A1010in B1 8 8 0% 04-Nov-19* 12-Nov-19 37 0 Maintenance of Two Columns in B1
Two Schools Project.A.3 Stone Works 30 30 0% 21-Aug-19 24-Sep-19 87 0
Cleaning & Pointing Repaires
A1020 of Stone Elevations 30 30 0% 21-Aug-19* 24-Sep-19 87 0 Cleaning & Pointing Repaires of Stone Elevations
Clean Existing Concrete A1200
Surface and Supply and install Stones 5cm 2 2 0% 05-Sep-19* 07-Sep-19 94 0 Clean Existing Concrete Surface and Supply and install Stones 5cm
Two Schools Project.A.4 Plastering 65 65 0% 07-Aug-19 21-Oct-19 52 0
External Plastering A1030 6 6 0% 07-Aug-19* 13-Aug-19 59 0 External Plastering
Internal Plastering A1180 50 50 0% 25-Aug-19* 21-Oct-19 52 0 Internal Plastering
Two Schools Project.A.5 Tiling & Marble Works 82 82 0% 26-Aug-19 28-Nov-19 23 0
Local Marble Sills A1040 3 3 0% 24-Nov-19* 26-Nov-19 25 0 Local Marble Sills
Ceramic Tilling A1210 3 3 0% 26-Nov-19* 28-Nov-19 19 0 Ceramic Tilling
Terrazzo Tilling A1220 73 73 0% 26-Aug-19* 18-Nov-19 28 0 Terrazzo Tilling
Two Schools Project.A.6 Carpentry & Joinery Works 54 54 0% 15-Oct-19 16-Dec-19 16 0
Maintenance of WoodenA1240
Doors & Pergula 45 45 0% 15-Oct-19* 05-Dec-19 43 0 Maintenance of Wooden Doors & Pergula
Classrooms Boards Installation
A1250 3 3 0% 07-Dec-19* 09-Dec-19 20 0 Classrooms Boards Installation
Classrooms Hangers & Protection
A1270 Rail 7 7 0% 09-Dec-19* 16-Dec-19 32 0 Classrooms Hangers & Protection Rail
Bottom Wooden KitchenA1280
Cabinet Installation 1 1 0% 04-Dec-19* 04-Dec-19 18 0 Bottom Wooden Kitchen Cabinet Installation
Doors Installation A1290 3 3 0% 04-Dec-19* 07-Dec-19 16 0 Doors Installation
Two Schools Project.A.7 Steel & Aluminum Works 89 89 0% 17-Aug-19 27-Nov-19 24 0
Supply & install InsulatedA1310
Metal Panels (Penalete) 6 6 0% 29-Aug-19* 04-Sep-19 95 0 Supply & install Insulated Metal Panels (Penalete)
Ceiling Steel Structure Maintenance
A1320 2 2 0% 17-Aug-19* 18-Aug-19 111 0 Ceiling Steel Structure Maintenance
Maintenance of Shed-Steel
A1330Sheets 3 3 0% 26-Sep-19* 29-Sep-19 75 0 Maintenance of Shed-Steel Sheets
Steel Doors Installation &A1350
Maintenance 3 3 0% 22-Oct-19* 24-Oct-19 10 0 Steel Doors Installation & Maintenance
Windows Maintenance A1390 3 3 0% 25-Nov-19* 27-Nov-19 24 0 Windows Maintenance
Supply and fix Sliding Aluminum
A1400 Windows 1 1 0% 24-Oct-19* 24-Oct-19 10 0 Supply and fix Sliding Aluminum Windows
Two Schools Project.A.8 Painting Works 47 47 0% 05-Nov-19 29-Dec-19 1 0
Supply & Install GypsumA1420
Boards Partition 6 6 0% 30-Nov-19* 05-Dec-19 20 0 Supply & Install Gypsum Boards Partition
Supply & Install & Maintenance
A1430 of False Ceiling 4 4 0% 30-Nov-19* 03-Dec-19 19 0 Supply & Install & Maintenance of False Ceiling
Painting Works A1470 47 47 0% 05-Nov-19* 29-Dec-19 1 0 Painting Works
Two Schools Project.A.9 Insulation & Roofing 5 5 0% 16-Sep-19 21-Sep-19 82 0
Supply & Apply Bitumen A1080
rolls Membrane 1 1 0% 21-Sep-19* 21-Sep-19 82 0 Supply & Apply Bitumen rolls Membrane
Casting Sloping Screed A1120 2 2 0% 16-Sep-19* 17-Sep-19 86 0 Casting Sloping Screed
Two Schools Project.A.10 Electrical Works 98 98 0% 02-Oct-19 23-Jan-20 0 0
Electrical Works A1090 98 98 0% 02-Oct-19* 23-Jan-20 0 0 Electrical Works
Two Schools Project.A.11 Mechanical Works 42 42 0% 15-Oct-19 02-Dec-19 16 0
Mechanical Works A1100 42 42 0% 15-Oct-19* 02-Dec-19 16 0 Mechanical Works
Two Schools Project.A.12 External Works 98 98 0% 03-Sep-19 25-Dec-19 0 0
Maintenance of Water Trenches
A1160 in PlayGround 2 2 0% 03-Dec-19* 04-Dec-19 18 0 Maintenance of Water Trenches in PlayGround
Main Entrance Steel Gate
A1190 1 1 0% 10-Dec-19* 10-Dec-19 7 0 Main Entrance Steel Gate
Supply & Install Galvanized
A1230
Steel Mech Fence 2 2 0% 24-Dec-19* 25-Dec-19 0 0 Supply & Install Galvanized Steel Mech Fence
Cement & Sand Plastering
A1260 7 7 0% 03-Dec-19* 10-Dec-19 23 0 Cement & Sand Plastering
Concrete & Slab on Grade
A1300
Works 66 66 0% 15-Sep-19* 30-Nov-19 21 0 Concrete & Slab on Grade Works
Trench Excavation A1340 10 10 0% 03-Sep-19* 14-Sep-19 30 0 Trench Excavation
Handrails & Railing Installation
A1360 3 3 0% 11-Dec-19* 14-Dec-19 7 0 Handrails & Railing Installation
Anti-Slip Sticker Installation
A1370 1 1 0% 07-Dec-19* 07-Dec-19 16 0 Anti-Slip Sticker Installation
Stone Tiling, Coping & Stairs
A1380Installation and Reparing Works 3 3 0% 02-Dec-19* 04-Dec-19 19 0 Stone Tiling, Coping & Stairs Installation and Reparing Works
Supply & Install Prefabricated
A1410Steel Canopy 3 3 0% 15-Dec-19* 17-Dec-19 7 0 Supply & Install Prefabricated Steel Canopy
Maintenance of Steel Handrails
A1440 1 1 0% 15-Dec-19* 15-Dec-19 9 0 Maintenance of Steel Handrails
External Demolishing Works
A1450 25 25 0% 09-Sep-19 07-Oct-19 68 0 External Demolishing Works
Two Schools Project.B ALNithamieh School 110 110 0% 23-Sep-19 28-Jan-20 -1 0
Two Schools Project.B.1 Excavation & Demolishing Works 2 2 0% 23-Sep-19 24-Sep-19 48 0
Demolishing Works A1490 2 2 0% 23-Sep-19* 24-Sep-19 48 0 Demolishing Works
Two Schools Project.B.2 TIling & Marble Works 4 4 0% 03-Dec-19 07-Dec-19 16 0
Local Marble Works A1500 1 1 0% 03-Dec-19* 03-Dec-19 19 0 Local Marble Works
Ceramic Tilling Works A1510 4 4 0% 03-Dec-19* 07-Dec-19 16 0 Ceramic Tilling Works
Two Schools Project.B.3 Carpentry & Joinery Works 11 11 0% 20-Nov-19 02-Dec-19 20 0
Kitchen Cabinet Installation
A1550
Works 1 1 0% 20-Nov-19* 20-Nov-19 30 0 Kitchen Cabinet Installation Works
Finger Protection Works A1560 1 1 0% 02-Dec-19* 02-Dec-19 20 0 Finger Protection Works
Two Schools Project.B.4 Steel & Aluminum Works 27 27 0% 26-Oct-19 25-Nov-19 26 0
Supply & Install Steel Doors
A1600 5 5 0% 20-Nov-19* 25-Nov-19 26 0 Supply & Install Steel Doors
Maintenance of Windows
A1610
& Windows Steel Protection 5 5 0% 26-Oct-19* 30-Oct-19 48 0 Maintenance of Windows & Windows Steel Protection
Two Schools Project.B.5 Insulation & Roofing 1 1 0% 05-Dec-19 05-Dec-19 17 0
Supply & Apply High Build
A1620
Rubber (Bitumen Emulsion) 1 1 0% 05-Dec-19* 05-Dec-19 17 0 Supply & Apply High Build Rubber (Bitumen Emulsion)
Two Schools Project.B.6 Electrical Works 15 15 0% 18-Dec-19 04-Jan-20 4 0
Electrical Works A1630 15 15 0% 18-Dec-19* 04-Jan-20 4 0 Electrical Works
Two Schools Project.B.7 Mechanical Works 30 30 0% 31-Oct-19 04-Dec-19 17 0
Mechanical Works A1640 30 30 0% 31-Oct-19* 04-Dec-19 17 0 Mechanical Works
Two Schools Project.B.8 External Works 80 80 0% 05-Oct-19 05-Jan-20 6 0
Playground Works A1650 9 9 0% 21-Dec-19* 30-Dec-19 13 0 Playground Works
Supercryl External Waterproofing
A1660 Painting 3 3 0% 04-Dec-19* 07-Dec-19 16 0 Supercryl External Waterproofing Painting
Supply & Install Galvanized
A1670
Steel Mesh Fence 15 15 0% 03-Dec-19* 19-Dec-19 7 0 Supply & Install Galvanized Steel Mesh Fence

Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
ALThory + ALNithamieh Schools Rehabilitation Classic Schedule Layout 01-Feb-20 14:31
Activity Name Activity ID Original Remaining Schedule % Start Finish Total Float Actual Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020
Duration Duration Complete Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar
Repairs for Playground Gate
A1680 2 2 0% 04-Jan-20* 05-Jan-20 6 0 Repairs for Playground Gate
Supply & Tile Interlock Bricks
A1690 5 5 0% 15-Dec-19* 19-Dec-19 12 0 Supply & Tile Interlock Bricks
Curb Stone Works A1700 5 5 0% 09-Dec-19* 14-Dec-19 12 0 Curb Stone Works
Concrete Works A1710 46 46 0% 08-Oct-19* 30-Nov-19 7 0 Concrete Works
Tench Excavation WorksA1720 2 2 0% 05-Oct-19* 06-Oct-19 8 0 Tench Excavation Works
Two Schools Project.B.C Finishing Works 4 4 0% 25-Jan-20 28-Jan-20 -1 0
Site Cleaning and preparing
A1730for Submission 2 2 0% 25-Jan-20* 26-Jan-20 0 0 Site Cleaning and preparing for Submission
Primal Submission A1740 1 1 0% 27-Jan-20* 27-Jan-20 0 0 Primal Submission
Final Submission A1750 1 1 0% 28-Jan-20* 28-Jan-20 -1 0 Final Submission

Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation