You are on page 1of 4

Detection of Earth Faults in LV Systems - Part II

In the last issue of L&T Current Trends


we had learnt about different methods of
detecting the earth fault in TPN system.
In the following issue we will discuss
the problems related to it and their
respective solutions.

III) CT on trafo neutral & earthing at trafo


end:-

In this scheme, earthing is done at transformer end &


CT is mounted as shown in (Fig 7).

Fault current on bus section flows back to trafo neutral


point through trafo neutral CT causing the relay to trip.

Unbalance current does not flow through the CT &


hence no nuisance tripping in unbalance.

However as shown in (Fig 8), if buscoupler is


TPN type, earth fault on Bus-A has 2 paths.
First path is through neutral CT of trafo-1
back to trafo-1 neutral. Another path is through Fig.7
the neutral CT of Trafo-2 & neutral of buscoupler

WE WISH ALL OUR READERS A VERY HAPPY NEW YEAR


During the earth fault on the bus
section, current flows through trafo
end neutral CT back to trafo neutral
point,causing the relay to trip.

If system is having unbalance


current, that current will flow back
to trafo neutral point through the CT
mounted in switchboard neutral,
causing the nuisance tripping of the
relay.

If the buscoupler is TPN type, E/F


current of one bus section passes
through both the CTs of both bus
section as shown in (Fig 12). First
path is through trafo-1earth back to
trafo-1 neutral point. Another path
is through trafo#2 neutral earthing
Fig.8 – Buscoupler neutral link – trafo-1
neutral CT mounted in switch
board-back to trafo#1 neutral point.

back to neutral point of trafo-1. tion. Thus realy on incomer-2 may give
Magnitude of current passing Since relay trips on unbalance nuisance tripping for the fault on
through these paths depend on the which is a common phenomenon, bus-1 & may also cause non
impedance offered by each path. this method is not used. tripping of the relay on faulty bus
Relay on trafo-2 may start section.This problem can be
responding to faults on BUS-A, solved by using 4pole buscoupler.
causing a nuisance tripping. This V) 2: CT connection (One at
problem can be resolved by trafo earthing end & one Since this scheme trips on
providing 4 pole bus coupler. in switchboard N):- unbalance which is a common
phenomenon, it is not used.
IV) CT on neutral & earthing
towards switchboard Two CTs are mounted as shown in VI) Restricted earth
side:- (Fig.11). One CT at trafo neutral end fault protection: -
& another in switchboard neutral.
In this scheme, earthing is
done within switchboard It is usually applied for star
before the isolating link as winding of transformer. This is
shown in (Fig 9). a special type of earth fault
protection provided for a
Fault current on bus section selected zone. Special
flows back to trafo neutral protection class CTs i.e. Class
point through the CT. Relay PS CTs are employed for
mounted on the incomer achieving the protection.
senses the fault & trips the Protection works on
incomer. differential principle. As shown
in (Fig 13), if current entering
If system is having unbalance the circuit is not equal to
current, that current will also current leaving the circuit, the
flow back to neutral point difference in current flows
through the CT causing the through the relay and makes
nuisance tripping of the
the relay to operate. However
relay.
for external earth fault as
However even if the bus- shown in (Fig 14), associated
coupler is TPN type, E/F phase & neutral CT sees the
current of one bus section same fault current. Secondary
does not pass through the CT reflected current forms the
of another bus section as series connection & does not
shown in (Fig 10).Thus it does operate the relay. Depending
not give any nuisance Fig.9 upon the earthing position,
tripping under this condi- either 4 CTs or 5 CTs are
Fig.10

dition. During the unbalance the system. If fault is outside the


condition, unbalance current zone, fault current flows through
flows back through neutral CT. phase CT as well as CT mounted
Since current through neutral on trafo neutral. Current through
CT is in opposite direction as trafo neutral flows in opposite
that of phases, it avoids direction as that of phase CT. Thus
nuisance tripping of the relay blocks the nuisance tripping.
on unbalance. If this CT is not
provided, then relay may trip Case-2:
during the unbalance condi-
tion. During the earth fault If transformer earthing is as per
within the zone, current flows (Fig 16), only four (4) CTs are
back to trafo star point through required for reliable operation. In
CT on trafo neutral (T5). this case, Unbalance current flows
Thus it detects the fault & trips back through CT (T4) in the

Fig.11

used.

Case-1:

If earthing of the transformer is as


shown in (Fig 15), five (5) CTs are
required for reliable operation. CT
on neutral within switchboard (T4)
is required to avoid nuisance Fig.12
tripping during unbalance con-
Conclusion:-
In this article and in the previous
article, we have covered the
LOAD
different methods of detecting the
earth fault in TPN system.
Problems genereally encountered
& solution for that are also
discussed. Use of correct scheme,
If R location of CT's and connection of
CT's is a must to improve the
reliability of operation.

Fig.13

opposite direction as that of phase,


thus avoids nuisance tripping of
the relay during unbalance. During
earth fault within the zone, current
flows back to trafo star point through LOAD
T4. It detects the earthfault If

current & thus gives the protection

If R

Fig.14

Fig.15

against REF. For earthfault outside


the zone, fault current flows through
phase CT & T4 in opposite direction
preventing the nuisance tripping.
Thus CT (T4) performs all the three
operation.In this case, 5thCT should
Fig.16
not be provided within the switch-
board to avoid nuisance tripping.

You might also like