You are on page 1of 10

SCOSS and CROSS

Newsletter 58 | April 2020 CONTENTS

908 Failure of RAAC planks in


Editorial schools › 2

All thoughts about safety are At CROSS we look at building safety 904 
Structural issues with
concentrated on the COVID-19 and by disseminating lessons learned cladding › 3
epidemic and the threats brought from reporters and our expert panel,
to the world. It is dangerous and encourage industry to take steps to 882 Post-tensioned slab failure › 5
debilitating at the front line of medical prevent future failures and collapses.
care and we must applaud and thank Lessons are there to be learned,
886 
Unconservative design of flat
those who are protecting our lives, and whilst the context is small
slab › 6
sometimes at the cost of their own. by comparison, the safety of our
buildings and built assets is crucial to
In risk terms this overwhelms society.
906 
Missing punching shear
everything, and the implications reinforcement › 7
would have been unimaginable a Many in the construction industry are
few weeks ago except to a few fearful about their jobs, their health, 873 
Propping of post-tensioned
experts who know the dreadful and the continuity of their companies, slabs › 8
power of pandemics. Some had so structural safety will not be high
warned for years of upcoming on their agendas. Nevertheless, it 911 
Suspended ceiling replacement
threats from diseases originating in would be even more distressing if in high rise block › 9
remote corners of the animal world there were to be building failures as
and jumping species. There was a consequence of inaction. Please 915 
Crane outrigger loads
preparedness in many countries but continue to make your reports: underestimated due to misuse
as events have unfolded the lack of CROSS is ‘working from home’, and of software › 9
awareness and of sufficiently robust just as busy and focussed as ever.
contingency planning has become 889 
Dangerous substitution of lintels
evident. Following the Hackitt Report and on domestic projects › 10
the proposed new Building Safety
Many lessons will emerge, and it legislation, a project was started
will be incumbent on national and in January for MHCLG (Ministry of
international leaders to put in place Housing Communities and Local
the necessary actions to learn Government) to enhance CROSS and HOW TO REPORT
from them. These will be medical, develop a new confidential reporting For more information, please
financial, and above all societal, so system for fire safety. Thanks are visit the How to Report> page.
that the world can recover and is due to those who responded to a
better prepared for the inevitable survey about this and the results If you have experienced a safety
next pandemic. Only the date will are encouraging and helpful. Work
issue that you can share with CROSS,
be unknown. To ensure safety, the will continue for the next 12 months
advice of experts is critical and must in addition to our usual activities
please Submit a CROSS Report>.
be adopted. and updates will be given in the
Newsletters. If you want to submit a report by post,
In the construction and building please send an email to
management sectors there will The reports in this edition fall into cross@structural-safety.org>
be lessons to learn too. See the the categories of either inadequate asking for instructions.
information box on page 2. In these design methods, or inadequate
circumstances what are the new supervision and control on site, and
risks, be they to workers, operatives, there are lessons to be learned for all.
KEY
building managers or occupiers?
We must design and pre-plan for
structural robustness whatever the
R CROSS Report
world brings to us. C CROSS Panel Comments
N News
CROSS I Information
VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org >  > Denotes a hyperlink

1 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org > 

908: Failure of RAAC planks in schools I INFORMATION


CROSS learning from lockdown:
R REPORT
Having read the May 2019 SCOSS Alert
C COMMENTS
In a departure from our usual practice, this
structural safety hazards from
COVID-19
on Failure of RAAC Planks>, a structural report was published in advance of the
engineer has contacted CROSS to share Newsletter due to the possible urgency CROSS would welcome your reports
their experience of working on projects with of the issues. on new structural safety hazards arising
Reinforced Autoclaved Aerated Concrete from these or other consequences of the
planks. In 2017, they were asked to investigate It is one of several that was received following COVID-19 pandemic; your reports will help
an RAAC roof which had collapsed in a the publication of the SCOSS Alert on Failure us learn for the future.
school. Luckily, there was no one in the of RAAC Planks> in May 2019. These confirm
classroom at the time of the collapse. that there are considerable areas of roofing Safety hazards might be in the present
consisting of RAAC planks in use in public during lockdown, be in the future as we
According to the reporter, the cause of buildings in the UK. It appears that not all hopefully get back to normal afterwards or
the collapse was a shear failure due to of these have been identified, so structural become embedded in the built fabric and
inadequate bearing following some structural engineers and building professionals need to give problems in years to come. What are
alterations made by the school. The failure be aware of the situation and, when possible, you finding that we should learn from as a
was triggered by outfall gutters becoming check for RAAC on large flat roofs built around result of:
blocked which allowed ponding of water on the 1960s-80s.
the roof to quickly build up during a storm. • concerns about designs, checks or quality
The reporter carried out a full structural The Local Government Association, the assurance;
survey of the school and found numerous Department of Health and Social Care, and • works suspended, sites closed, structures
other signs of progressing defects similar to the Department for Education have advised left part-built;
those highlighted in the SCOSS Alert. owners to check their premises and make • revised work methods or changed
inspections to ensure that they know what supervision practice that have knock-on
In 2019, the reporter was asked to investigate they own, and if RAAC is suspected, to have effects to structural safety;
the partial failure of an RAAC plank at another structural assessments made. • consequences of 24/7 higher occupation
school. Temporary props were installed to of residential buildings during lockdown;
prevent collapse of the RAAC planks. The It is not surprising that schools do not know • consequences of vacancy of non-
reporter carried out a full structural survey of the composition of the structures in their residential buildings, or non-use of other
the school and again found numerous defects buildings. By way of explanation, a description structural assets;
in the planks, which were mainly related of RAAC is shown below. • postponement or curtailing of safety or
to historic roof leaks which caused the inspections or maintenance activity;
reinforcement in the planks to corrode and An interest group has been set up to monitor • loss of look, see, touch, feel - the intuitive
thus lose bond with the concrete. the situation and to recommend further engagement with hazard, risk and early
research into the extent and nature of the warning signs;
The reporter is now frequently encountering problems. The group will be interested to hear • other responses to this terrible crisis.
RAAC planks in school roofs and their of further experiences and anyone looking for
experience suggests that these planks are more information should contact structures@ Submit CROSS report>
becoming more defective with time. They structural-safety.org>.
have also found that many schools do not
even know that their roofs are constructed
using RAAC planks and are therefore not SUBMIT REPORT
aware of the risks.
SUBMIT FEEDBACK

I INFORMATION
What is RAAC?
 utoclaved aerated concrete (AAC) is different from normal dense concrete. It has no
A
coarse aggregate, and is made in factories using fine aggregate, chemicals to create
gas bubbles, and heat to cure the compound. It is relatively weak with a low capacity for
developing bond with embedded reinforcement.

When reinforced (Reinforced AAC: RAAC) to form structural units, the protection of the
reinforcement against corrosion is provided by a bituminous or a cement latex coating,
which is applied to the reinforcement prior to casting the planks. The reinforcement mesh is
then introduced into the formwork and the liquid AAC mix added.

2 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org >

904: Structural issues with cladding I INFORMATION


What should be reported to
R REPORT
A reporter who investigates cladding failures To overcome this issue, and as
CROSS?
 tructural failures and collapses, or safety
S
says that they are normally asked to establish recommended in relevant guidance such concerns about the design, construction or
the cause of the failure and comment on the as BS 8297:2017 (Code of practice use of structures.
roles of the designers and contractors. Issues for Design and installation of non-
they have encountered include: loadbearing precast concrete cladding)>,  ear misses, or observations relating to failures
N
the support system for panels can be or collapses (which have not been uncovered
1. Design of movement joints: the designer positioned at two points only so that the through formal investigation) are also
failing to adequately consider the panel does not act compositely with the welcomed. Reports do not have to be about
combined effect of construction tolerances floor slab and provides a predictable current activities so long as they are relevant.
with thermal and moisture movements. distribution of loads onto the supporting
This can cause the following design issues structure. Small scale events are important - they can
which may result in cladding failure: be the precursors to more major failures.
a. failure to provide movement joints, 4. Fixings for heavy cladding panels: the No concern is too small to be reported and
causing materials and fixings to become attachment of fixings into heavy panels is conversely nothing is too large.
overstressed; sometime inadequate.
b. insufficient allowances at movement Your report might relate to a specific
joints causing either the joints to close An example the reporter encountered experience or it could be based on a series
and impose stresses on the cladding and was when fixings for heavy concrete of experiences indicating a trend.
fixings, or to open excessively causing cladding panels consisted of cast-in
restraint fixings to disengage. anchors located very close to the top of Benefits of CROSS
the panels, resulting in no reinforcement • Share lessons learned to prevent future
2. Tolerances for cladding hooks: when between the cast-in anchors and the top failures
cladding fixings rely on a series of ‘hooks’ of the panel in some cases. This issue can • Spurs the development of safety
attached to the structure onto which the arise if the reinforcement for the panel improvements
cladding is hung, it is vital that the hooks is designed by a structural engineer, and • Unique source of information
and the corresponding fixing points on the then subsequently, the fixings for the panel • Improved quality of design and constructon
cladding panel are aligned so that they are are designed separately by the precast • Possible reduction in injuries and fatalities
properly attached. supplier, without review by the structural • Lower costs to the industry
engineer who originally designed the
The reporter has encountered cases where reinforcement. Supporters of CROSS
the required attachment was not properly • Association for Consultancy and
achieved. They advise that hook systems 5. D
 esign of whole cladding system: the Engineering (ACE)
like this should either be fully manufactured reporter says that every element of the • Bridge Owners Forum
off-site, or if installed on site, should be cladding system should be designed, all the • British Parking Association (BPA)
done using templates to ensure the correct way back to the structural frame. • Building Research Establishment (BRE)
location of the fixings. In both cases, they • Chartered Association of Building
say that a rigorous checking procedure An example of where this might get Engineers (CABE)
should be in place. overlooked is in the design of bespoke • Civil Engineering Contractors Association
metal cladding systems. Although the (CECA)
3. Interaction between cladding and cladding itself may be robust, the fixings • Confidential Incident Reporting and
supporting structure: the interaction can rely on lightweight aluminium sections Analysis Service (CIRAS)
between cladding panels and the concealed within the cladding and • Constructing Excellence
supporting structure is sometimes not well connected to the cladding using stainless • Construction Industry Council (CIC)
understood, says the reporter. steel screws. • Department of the Environment (DOE)
• DRD Roads Services in Northern Ireland
For example, if stiff cladding panels, The reporter has come across cases • Get It Right Initiative (GIRI)
such as precast concrete, are fixed to where the lightweight aluminium sections • Health and Safety Executive (HSE)
the edge of a concrete floor slab which were substantially under-designed, which • Highways England
spans parallel to the panels, the panels can cause the fixings to fail and cladding • Institution of Civil Engineers (ICE)
may act compositely with the slab when panels to fall. They recommend that the • Institution of Structural Engineers (IStructE)
it is under loading if the fixings provide aluminium sections, along with the screws, • Local Authority Building Control (LABC)
restraint against vertical movement. This are checked to ensure that they can resist • Ministry of Housing, Communities and
can overload the fixings and cause them the applied loads. Local Government (MHCLG)
to fail, causing panels to fall off in extreme • Network Rail
circumstances. • Royal Institute of British Architects (RIBA)
• Royal Institute of Chartered Surveyors (RICS)
• Temporary Works Forum (TWf)
• UK Bridges Board

3 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org >

6. Design of details and interfaces: an issue product performs. This has many similarities Fixings for signs can be safety critical. For
that can affect all types of cladding, but with report 911 both in terms of the risks example, there was a fatality in 2015 after
particularly bespoke systems, is a failure to associated with failure and the lack of a sign fell on to a shop worker. A report by
fully design all the details and interfaces. design control. the HSE> said an original “much lighter” sign
had been fixed to the building prior to 1980
The reporter says that this can result Several recent cladding failures have using woodscrews and a vertical stud. It is
in ad-hoc design being carried out illustrated concerns with: believed the sign was made unsafe by the
by the installers on site without a full addition “of a larger and much heavier sign”,
understanding of the engineering • inadequate design; also installed prior to 1980, but the installers
requirements. Such ad-hoc design is not • inadequate specification; relied on the fixings of the original sign.
reviewed by the original designer and is • inadequate / unsupervised installation
often not recorded on ‘as-built’ drawings. leading to missing components or
inadequate installation of fixings; SUBMIT REPORT
7. Copings on parapet walls: an often • failure of the fixings exacerbated by the
overlooked element of a cladding system use of hidden fixings which cannot be SUBMIT FEEDBACK
is the copings on the top of parapet walls. inspected, and
However, these are often subjected to the • inadequate assurance checks, where
most severe wind loading on a building. primary structure is given consideration,

The reporter has encountered issues


but secondary structural elements may
be overlooked.
N NEWS
where the design of copings on parapet CROSS-US Newsletter 1
walls was left to a specialist sub- CROSS recommend that cladding design
contractor who did not have the required and installation is given the same degree CROSS-US published their first
competence to understand the required of attention as the primary structure during Newsletter in March 2020.
load resistance or the need to provide both design and construction to improve
for thermal movements. The reporter safety, reliability and longevity. It is really Download CROSS-US Newsletter>
recommends that the design of such important that a single entity (or chartered
elements should always be reviewed by engineer) should have overall control of the You can sign-up to the CROSS-US mailing
the project’s structural engineer. design of the cladding system including its list for email updates from CROSS-US at
interfaces with the support structure and to the link below.
8. Shop signs: although not strictly cladding, assure the ability of the structure to support
the reporter states that shop signs are the applied loads. Sign-up to the CROSS-US mailing list>
often installed in an ad-hoc fashion without
any engineering input. Such signs, which
can weigh several hundred kilograms, can
be inadequately fixed and/or subject to CROSS recommend that N NEWS
deterioration of the fixings due to the use cladding design and
of unsuitable materials, which can result in installation is given the CROSS-US Director
the signs falling from buildings. same degree of attention recognised in ENR’s Top 25
as the primary structure Newsmakers 2019
during both design and
C COMMENTS
This is an interesting report highlighting a
construction to improve Glenn Bell, SEI President and Co-Director
of CROSS-US, has been recognised in
number of themes: safety, reliability and the Engineering News-Record's Top 25
longevity Newsmakers 2019 for his service to the
• The complexity in reality of what might construction industry and the public.
seem relatively straight forward items.
• The need for industry feedback on Where bespoke cladding systems are View Engineering News-Record article>
real behaviour. proposed, there are well established test
• The anticipation of modes of failure. procedures that can be used. See for example
• As always, fixings are a vital component in the work of CWCT> (Centre for Window and
any system. Cladding Technology). These test wind, water
• The need to assure that real installation and impact loads and can help to flush out
matches anticipated design. problems even if the principles are similar to
• The recurring theme of danger at the cladding used on other projects. Other sources
interfaces of responsibility. of information are the CFA> (Construction
Fixings Association) and BS8539:2012> (Code
The report highlights the trend for design of practice for the selection and installation
being split into multiple packages and of post-installed anchors in concrete and
passed down the contractual chain with no masonry).
one seemingly responsible for how the final

4 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org > 

882: Post-tensioned slab failure


R REPORT
A reporter has shared some key points
Lessons learned e) Awareness: Refresher tool-box talks
to be conducted for the concrete gang
from an investigation after the end of a slab a) Concrete concerns: The fabric of the (and on other concrete frame contractor
burst during a cable tensioning operation. slab was destroyed near a tendon ‘block’ projects) as recommended by the
An operative hit by the debris sustained arrangement which was only tensioned PT contractor.
relatively minor injuries, however the once the concrete had reached a strength
consequences could have been much worse. of 25N. Procedures were in place and
The ‘live’ end of the cable being tensioned
moved as the fixing in the concrete failed,
were used to verify the strength of
the concrete from both the concrete
C COMMENTS
This incident highlights a strong justification
exploding the slab in an area around frame contractor and PT contractors’ for CROSS reports. It appears that
1.5x1.5m. perspectives, thus the concrete should something serious happened without
not have failed. any one party being obviously negligent.
There was a range of potential causal Lessons were learned by the parties
factors including over stressing of the cable, Outcome: grout in pump lines must not be involved, but disseminating the danger and
concrete strength and structural design. discharged into the slab area and must not precautionary measures more widely ought
The contractor, the post-tensioning (PT) form part of the permanent works. to be highly valuable.
installer and the PT designer concluded
that localised under-strength concrete b) Duty of care/informal reservations: The reporter, and the organisations
was used, due to the method adopted on The PT contractor had suggested that concerned, are to be complimented on
site of grouting the mobile pump line and despite the achieved 25N strength test releasing their findings for the benefit of
discharging into the permanent works. results, that they have previously verbally others who might be faced with similar
informed the concrete frame contractors’ situations.
It is thought that this is a rare occurrence, supervision staff of their concerns
although a similar incident had occurred on regarding the concrete. Anecdotal
a previous project when heavy rain on the suggestions after an incident is normal, SUBMIT REPORT
day of a pour caused a local weakness in but in case there are serious issues,
concrete and failure at the end of a cable. concerns should be formalised at the SUBMIT FEEDBACK
time.

Outcome: PT contractor is to be
The contractor, the post- encouraged to properly state their N NEWS
tensioning installer and the concerns in writing on programme,
post-tensioning designer structure or safety. CROSS-AUS Newsletter 3
concluded that localised
under-strength concrete c) Bursting concern: Following the incident,
the subsequent risk potential was
CROSS-AUS published their third
Newsletter in February 2020.
was used considered, and the robust segregation
area advocated in the PT contractor’s Download CROSS-AUS Newsletter>
risk assessment was implemented and
additional coverings as ‘Blast Mats’ added You can sign-up to the CROSS-AUS
(i.e. plywood or tarpaulin). mailing list for email updates from
CROSS-AUS at the link below.
Outcome: PT contractor was asked to
review their RAMS accordingly. Sign-up to the CROSS-AUS mailing list>

d) Concrete quality assurance: Concrete


frame contractor to revise concrete
method statement to include a statement
on grout discharge. The PT contractor
is to include a statement within their PT
method statement to emphasise the
importance of good compaction and
● Figure 1
Post-tensioned slab failure ensuring homogenous concrete.

Outcome: Quality assurance checks to


include ensuring grout in pump lines and
heavy rain is not incorporated into the
permanent concrete works, especially at
the start of the pour.

5 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org > 

886: Unconservative design of flat slab


R REPORT
A reporter's organisation recently came
To avoid such an error, when creating or
checking a 3D FE model, it needs to be
Similar errors can occur when concrete
slabs are constructed from precast planks
across a design/modelling problem which ensured that any loadbearing masonry but modelled as a solid diaphragm leading
gave highly unconservative analysis results, wall that is transferred onto a slab below, to an underestimate in the loading to the
causing an under-designed RC slab to or that is not vertically continuous down supporting beams; a check of bending in
be constructed within a large domestic to foundation, is modelled as a series of the slab perpendicular to the span would
property. individual pin ended columns. This ensures have highlighted this. It is disturbing that
that they act in the vertical loadbearing such a slab can be detailed and constructed
A loadbearing blockwork wall, supported on direction only, and thus cannot act as a deep with only 50% of the required rebar without
a transfer slab, was mistakenly modelled as beam. ‘Wall’ shell elements within a 3D FE anyone in the office or on site thinking it
a concrete shell element within a 3D finite model should only be used where a vertically looked odd.
element (FE) package, as opposed to a more continuous RC concrete wall is proposed,
realistic approach of modelling such walls as as otherwise they can artificially stiffen the CROSS-US recently published their first
a series of pin ended columns. structure by acting as deep beams. Newsletter> and here is an extract from the
comments on a historic failure; the Hartford
When the transfer slab was exported to a 2D The design checker should also ensure that Coliseum roof collapse>:
FE package for reinforcement and deflection they see an 'extruded' and annotated view
checks, the 3D concrete wall element was of the 2D model, in order to verify that the Questions regarding the sufficiency of
converted to a line element of equivalent structure has been modelled correctly. computer modelling, the adequacy of
stiffness and incorporated within the 2D FE peer review, and the role of the structural
analysis. engineer in the field have been raised
C COMMENTS
There has been much disquiet expressed in
recently in the FIU bridge collapse. This
will be the topic of an upcoming CROSS-
A loadbearing blockwork engineering circles about the improper use US report. In the UK, the Standing
wall, supported on a of (or over reliance on) computer modelling
with potential for results to be divorced from
Committee on Structural Safety (SCOSS)
and CROSS have had a long-standing
transfer slab, was reality. This report is a classic illustration policy of endorsing third party checks for
mistakenly modelled as a of the kind of problems that might arise. key structures. The rationale is to assure
concrete shell element Safety demands that all model outputs are public safety. In 2016, SCOSS published a
within a 3D finite element subjected to a simplified sanity check which paper Reflective thinking> which looked
package, as opposed to a appears not to have happened. at over-reliance on computer modelling
more realistic approach of and posed a set of questions for the
modelling such walls as a designer:
series of pin ended columns Safety demands that all • Is the model capable of satisfying the
model outputs are requirements? (the validation question)
subjected to a simplified • Is the model the most appropriate in
The result of this was that the transfer slab sanity check which the context?
was artificially stiffened by the line element, appears not to have • Has the software been validated
which was effectively acting as a very stiff
beam with a depth equivalent to the height
happened and verified?
• Has the model been correctly
of the wall over. As such, both the long-term implemented? (the verification question)
deflection prediction and the reinforcement
demand was significantly underestimated. Beyond that, the description of this This is an early indication of the value of
model suggests an inappropriate level of CROSS sharing experiences between
The already constructed slab was found refinement for the essentially simple task countries by linking the Hartford collapse,
to have around 50% of the necessary of designing an RC slab supporting a wall. the FIU bridge collapse, this report,
ultimate limit state design reinforcement If, however the slab in question is complex and other CROSS reports on computer
and was about to receive a 75mm screed. with, for example, significant openings, then modelling failures. There is an overriding
Once the modelling error was discovered accurate modelling is all the more important. need in the construction industry to have
following observed excessive cracking to the sufficient checking by suitably qualified
supported masonry wall, temporary propping There were a number of opportunities to and experienced persons to uncover such
was installed. discover this mistake. For example, as the serious errors.
wall was in the model, a very quick review
A permanent strengthening solution was of the stresses in the wall would have
developed by way of a heavy steel transfer highlighted that they were inappropriate for SUBMIT REPORT
beam installed below the wall, although a masonry wall. This highlights the need to
ceilings had to be removed and services check the whole model during the design SUBMIT FEEDBACK
diverted in order to achieve this. not just the element of immediate interest.

6 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org > 

906: Missing punching shear reinforcement


R REPORT C COMMENTS
A reviewer for a professional membership Issues about shear reinforcement in slabs, Designers of flat slabs
institution was concerned to note that
two candidates they recently interviewed
particularly flat slabs, have been around
for many years and were highlighted by the
should make it their
reported an experience where, as a failure of the Pipers Row Car Park>. This
business to conduct site
structural engineer monitoring the progress multi-storey structure was built in 1965 and a inspections, or have them
of their projects on site, they had observed 120-tonne section of the top floor collapsed conducted, before
the omission of design punching shear during the night of 20th March 1997. An concreting
reinforcement in a slab pour about to take initial punching shear failure developed into a
place. progressive collapse.

Given that these two candidates were from Designers should know that the critical SUBMIT REPORT
different companies with different project connection on any flat slab is the shear
experiences, the reporter feels it is worth resistance around its supports. Part of a SUBMIT FEEDBACK
reporting this in case it is a trend. One of structural engineer’s skill set is to know what
the candidates was particularly experienced to look for and to create a structure that is
having visited many sites and said that capable of being strong enough even before
omission of punching shear reinforcement is
a 'watch-it' item within their team.
starting calculations. These skills are only
acquired by practice (under supervision).
N NEWS
US SEI Structures Congress
However, as such reinforcement is a 2020
critical factor in the safety of flat slabs, the
importance of it being in place should be The Structural Engineering Institute (SEI)
known to constructors and supervisors. Structures Congress 2020 took place as
a virtual event on 07 April 2020. One of
Designers of flat slabs should make it their the special sessions was on CROSS-US,
business to conduct site inspections, or have presented by Glenn Bell, Alastair Soane
them conducted, before concreting. and Andy Herrmann.

You can view a recording of the entire


event at the link below, with the
CROSS-US session beginning at 1:15:45
into the video.

Watch recording of Structures Congress


2020>

● Figure 2
Pipers Row car park collapse
Attribution: Jonathan Wood, Pipers Row Car Park, Wolverhampton, Quantitative Study of the Causes of the Partial
Collapse on 20th March 1997

7 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org > 

873: Propping of post-tensioned slabs


R REPORT C COMMENTS
When casting in-situ concrete slabs, they are
typically propped and supported by the two
The broader lesson is the wider one of
the interactions between design and
I INFORMATION
floors below. For a concrete framed building construction. In reality, the two phases are CROSS report 866 Portal frame
a reporter was involved with, this was how intimately linked, and it is not at all uncommon design and fabrication - revised
the contractor constructed the floors. The for critical design cases to occur during the comments
slab was post-tensioned, and the contractor construction phase. It is therefore vital that
had left strips out in the slab to allow it to the design and construction teams co-  he CROSS Panel comments on report
T
be post-tensioned. Once the slab had been operate to assure that designs can be safely 866 Portal frame design and fabrication
tensioned, the small infill slab strips were to built and thereafter be safe in service. Once were revised following feedback received
be cast. a safe method of construction has been from a reader.
designed, it is essential that this method of
During the construction at one level, the construction is followed. View report 866 Portal frame design and
infill slab strip at the level below had not yet fabrication>
been poured. Therefore, the weight of the In this case, it was fortunate that the lower
slab being cast, and the weight of the floor slab was strong enough to withstand the All feedback received can be viewed on the
below was all being taken solely by the floor wrong sequence - this would not always be Structural-Safety website.
two levels below. Fortunately, this slab was the case.
designed for high superimposed and finishes View feedback page>
loads. If this had not been the case, the slab
could have failed, says the reporter. It is not at all uncommon for
critical design cases to
Lessons learnt are that the contractor needs
to ensure that post-tensioning strips are
occur during the
always cast and have achieved the required
construction phase
design strength if they are to be used to
prop the slabs above.
SUBMIT REPORT

SUBMIT FEEDBACK

Normal good practice - load spread over 2 floors

Infill post-tensioned
strip not yet cast

This slab takes


weight of 2 floors

Propping as installed - lower floor taking all of the load


● Figure 3
Propping of post-tensioned slabs

8 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org > 

911: Suspended ceiling replacement in high rise block


R REPORT
A reporter is involved with replacing MDF
When the reporter has queried in the past
with quantity surveyors about what they
be consulted for advice on fixings. Other
sources of information are the CFA>
ceilings (15mm thick heavy panels) on a need to do with CDPs, for example CDP for (Construction Fixings Association) and
30+ storey UK tower block. The work was steel connection design, they are told to do BS8539:2012> (Code of practice for the
triggered by fears following a few loose nothing, seemingly because when a CDP is selection and installation of post-installed
panel falls, in one case resulting in a minor identified in a Joint Contracts Tribunal (JCT) anchors in concrete and masonry).
injury. What emerges says the reporter is: contract, it is a way of packaging up design
development/cost/risk. The JCT/CDP seems This report has similarities with cladding
1. Ceiling detailed design is typically a to ignore a designer’s legal duties defined in report 904 when design is passed down the
contractor/installer designed portion (CDP). their agreement. chain, standard designs may be modified
2. Typical generic manufacturers’ details  on site, and no one is responsible to check
need modifying to suit a given building.
3. There is effectively no structural engineer
C COMMENTS
Ceilings may appear to be minor items
that the final solution meets the required
standards.
involvement, with the architect being that can just be delegated to ‘installation’.
expected to define the characteristics and However, CROSS has published numerous
the sub-contractor expected to complete reports of heavy ceiling cascade failures SUBMIT REPORT
the design and installation. The checking which represent a credible safety hazard. To
duties of the architect of the CDP find these go to the www.structural-safety. SUBMIT FEEDBACK
are unclear. org> website and enter “ceiling” in the Quick
4. Services access panels can be removed search Keyword box. Over forty reports will
and not reinstalled properly (there can be shown.
be landlord's common area services and
leaseholder flat owners who have different There is generic hazard with any suspended
companies doing maintenance). structure. The SCOSS Alert Tension
systems and post-drilled fixings> may

915: Crane outrigger loads underestimated due to misuse of software


R REPORT
A reporter would like to raise awareness of an
C COMMENTS
There are some similarities between this (CIG) published CPA 1801 Good Practice
issue they have experienced with incorrect report and report 904. In both cases, there Guide - Requirements for Mobile Cranes
outrigger loads for mobile cranes. They work are significant structural engineering issues Alongside Railways Controlled by
as an in-house temporary works design in design areas that will be unfamiliar to Network Rail>.
engineer for a main contractor and regularly many engineers (no matter how much
deal with designing the foundations for crane general experience they have). Not everyone It is sensible for all crane bases to be
outriggers. This requires knowing the accurate will be familiar enough with the operation checked and in the first instance basic hand
loads in the outriggers to check the ground of mobile cranes to be able to identify calculations and rule-of thumb methods
and any surrounding structures or slopes. configurations that give worst case outrigger will give an indication of foundation loads,
loads. including outrigger loads. As always, key
For a particular crane lift, computer calculations operations on site need to be under the
had been provided to give the outrigger loads A lesson is to beware when taking on control of qualified competent staff who
but these were not for the crane boom in the anything novel and indeed this is integral work to procedures provided by crane
worst-case position and had to be corrected. with the ethics codes of professional suppliers. Correct procedures for erection
With large mobile cranes with different rig institutions and the Royal Academy of and dismantling must be followed.
configurations, it may not be possible to Engineering’s Statement of Ethical
adequately check the outrigger loads without Principles>, one of which is ”perform
in-depth working knowledge of the crane. services only in areas of current SUBMIT REPORT
competence”.
This is not an isolated case, continues the SUBMIT FEEDBACK
reporter, and due to incorrect use of software, The risk associated with a crane collapse
it seems to be becoming more common. may be to adjacent infrastructure with
The consequence of being supplied with disproportionate consequences, such
the incorrect outrigger loads can be severe. as equipment falling onto a railway track
Lifts regularly take place close to retaining in the path of a train. In the UK, this was
walls, tunnels and underground services. examined in the 2011 HSE report Preventing
The reporter feels that this issue needs catastrophic events in construction>. In
addressing before it becomes a contributing December 2018, the Crane Interest Group
factor in a serious incident.

9 CROSS Newsletter 58 | April 2020


Structural-Safety | SCOSS and CROSS

VISIT: www.structural-safety.org > EMAIL: newsletters@structural-safety.org > 

889: Dangerous substitution of lintels on domestic projects


R REPORT
New lintels were being installed as part of This situation has left the reporter
C COMMENTS
The topic of inappropriate substitution has
a home extension project. The structural concerned because: been raised in other published reports.
engineer had specified the concrete lintels. A common case is substitution without
However, during construction, the contractor 1. T
 he contractor and their supplier’s lack reference to the design team, which runs
informed the engineer of their intent to of understanding means that several the risk of undermining design intent. If
substitute the specified lintel with an understrength lintels have been installed anything went wrong, and no reference to
alternative lintel from the same supplier. on other projects, eroding safety factors the design team had been made, the person
and significantly increasing the risk of or organisation making the change might be
It was the contractor’s understanding that failure; liable.
the structural properties of the two lintels 2. The lack of identifying marks on the lintels
were identical because the geometry means that it is not possible to determine No changes should be made without design
was identical. The engineer disputed this the capacity of proprietary lintels post- team verification. In this case, lintels might
claim and used span/load tables to show installation, and be considered minor items, but in any wider
the contractor that, for the required span, 3. T he fact that the contractor could study of disasters, it will be found that
the capacity of the alternative lintel was install understrength lintels for several ‘unauthorised design change’ is a common
approximately 0.7 times the capacity of the years without challenge highlights a heading for disaster cause.
specified lintel. The contractor admitted that systematic error in the control of product
they were unaware of this and had been substitutions in domestic projects. A second issue is the very common one
substituting these lintels for several years on of being able to verify that what was built
the recommendation of the supplier. matches design intent. Sometimes this
cannot be done because items are covered
The engineer later learned that the supplier The contractor and their up. Sometimes without markings (or
spray painted the end of one type of lintel to supplier’s lack of paperwork), verification is equally impossible.
allow it to be identified from the other type, understanding means that All this points to the need for a proper quality
but the reporter points out that this does not several understrength assurance and inspection regime.
assist with identification of the type of lintel lintels have been installed
after it has been installed.
on other projects, eroding SUBMIT REPORT
safety factors and
significantly increasing the SUBMIT FEEDBACK
risk of failure

PARTICIPATION CPD PRESENTATIONS FOLLOW STRUCTURAL-SAFETY


The success of the CROSS scheme Structural-Safety are giving online
depends on receiving reports, and presentations to organisations who are @Structural-Safety
individuals and firms are encouraged to interested in learning more about the work
participate by sending reports on safety that Structural-Safety (CROSS and SCOSS)
issues in confidence to CROSS>. do, including sharing examples of safety @structsafe
issues to learn from.
FEEDBACK
If you have any comments or questions For more information contact EMAIL UPDATES
regarding this CROSS Newsletter, please events@structural-safety.org>. Sign-up> to our mailing list for email updates
Submit Feedback>. from Structural-Safety, including the latest
CROSS Newsletters and SCOSS Alerts.

Whilst CROSS and Structural-Safety has taken every care in compiling this Newsletter, it does not constitute
commercial or professional advice. Readers should seek appropriate professional advice before acting (or not acting)
in reliance on any information contained in or accessed through this Newsletter. So far as permissible by law, neither
CROSS nor Structural-Safety will accept any liability to any person relating to the use of any such information.

10 CROSS Newsletter 58 | April 2020

You might also like