Inservice Inspection (ISI)
Purpose of ISI
• From 1968 Draft Section XI
– Review of indications that show potential signs of
distress
– Relate the condition to the service requirements to
which the component is subjected.
– For the case where the review shows that no changes
have occurred, disposition would require nothing
further.
– For the case where the evaluation shows potential
signs of distress, but the condition meets the original
acceptance standards, disposition may require
nothing more than examination of an additional
number of components or like areas.
2
Purpose and Scope of Section XI
Organization of Section XI
3
Section XI, Division 1
Division 2 Rewrite
• Risk-informed Methodology
• Reactor-type Appendices
– Gas-cooled Reactors [such as Pebble Bed
Modular Reactor (PBMR)]
– Liquid-metal-cooled Reactors (such as
Monju)
– Unique Small Modular Reactors (such as
NuScale pool-type reactor)
• Country-specific Appendices
4
IWA-1000 Scope And Responsibility
Scope of Section XI
Quality, or Level of Compliance with Construction Code
Initial Compliance Technical Requirements
with Construction Service- induced Continued
Code Degradation Degradation
Restore to
Compliance with
Construction
Code
Section XI
Acceptance
Criteria
Start of Time
1st Periodic 2nd Periodic
Operation
Inspection Inspection
(Accept) (Reject and
Correct)
5
Design for ISI
Access Requirements
6
IWA-1200 Jurisdiction
7
IWA-1400 Owner’s Responsibility
8
IWA-2200 Examination Methods
• Types
– Visual
– Surface
– Volumetric
• Methods
• Techniques
• VT-1 (Cracks)
• VT-3 (General Degradation)
• VT-2 (Leakage)
• VE (Boric acid leakage detection)
• Remote Examination
• Illumination Levels
9
IWA-2220 Surface Examination
• Radiographic (RT)
• Ultrasonic (UT)
• Eddy Current (ET or ECT)
• Acoustic Emission (AE)
10
IWA-2240 Alternative Examinations
IWA-2300 Qualification of
Nondestructive Examination Personnel
• Written Practice Meeting American Society for
Nondestructive Testing (ASNT) CP-189, Standard for
Qualification and Certification of NDE Personnel
• NDE Certifications Valid Until Expiration
• Mandatory Appendix VII - Training, Qualification, and
Certification of Ultrasonic Examination (UT) Personnel
• VT-2 or VT-3 – Credit for Walkdown or
TestingExperience
• ANDE Performance-based Personnel Certification
• Other International Certification Systems
11
IWA-2320 through IWA-2380 Qualification
Examinations, Experience, and Responsibilities
12
IWA-2420 Inspection Plans and Schedules
13
IWA-2440 Application of Code Cases
14
Subsections IWB/IWC/IWD/IWE/IWF/IWL
Requirements for Class 1, 2, 3, MC, and CC
Components and Their Supports
IWB/IWC/IWD/IWE/IWF-2400
Inspection Schedule
• Inspection Interval - 120 Months/10
Years
• Inspection Period - 40 Months
• Exemptions
• Snubbers
– (Removed from Section XI in 2006)
• Concrete Vessels and Post-tensioning
Systems
15
IWB/IWC/IWD/IWE/IWF-2420
Successive Inspections
• Sequence of Component
Examinations
• Acceptance by Analytical Evaluation
(Fracture Mechanics) or Testing
(Supports)
IWB/IWC/IWD/IWE/IWF-2430
Additional Examinations
• Sample Expansion
– 2 Steps to 100%
– 5 Steps for Supports
16
IWB/IWC/IWD/IWE/IWF-2500 Examination
and Pressure Test Requirements
• Selection
– Basis
• Deterministic – Sampling
or
• Risk-informed
– Nonmandatory Appendix R
– Division 2
17
IWA-4000 Repair/Replacement
Activities
• IWA-4110 SCOPE
• Repair/replacement Activities - Repair,
Replacement, Modification, and Alteration
• Regardless of the Reason for the Activity or
the Detection Method
• Welding, Brazing, Defect Removal, and
Removing, Adding, and Modifying Items or
Systems
IWA-4120 Applicability
• Exemptions
• Inservice testing
• Nonmandatory Appendix J, Guide to
Plant Maintenance Activities and Section
XI Repair/Replacement Activities
• ANII
• Maintenance Activities
18
IWA-4130 Alternative Requirements
IWA-4143 Stamping
19
IWA-4150 Repair/Replacement Program
and Plan
• Repair/Replacement Program
– Managerial and Administrative Controls
– Section XI Edition and Addenda
• Repair/Replacement Plan
– Requirements for a Specific Repair/Replacement Activity
– Documentation of Actions Performed
– Construction Code Edition and Addenda, and Code Cases
– Owner's Requirements (Design Specification
Requirements)
– Intended Life
20
IWA-4170 Inspection
21
IWA-4300 Design
IWA-4312 Rerating
22
IWA-4340 Mitigation of Defects by
Modification
23
IWA-4422 Defect Removal and
Examination
24
IWA-4451 Helical-Coil Threaded Inserts
• Materials
• Certification
• Quality Assurance Programs
25
IWA-4500 Examination and Test
26
IWA-5000 System Pressure Tests
• Periodic System Pressure Tests
– Leakage Test
– Hydrostatic Test
– Pneumatic Test
• Repair/Replacement Activities
• Holding Times
• Test Pressurization Boundaries
– Class 1
– Classes 2 and 3
27
IWA-5250 Corrective Action
• Evaluation
– Evaluation Analyses
• Regulatory Submittal
• Corrective Action
– Bolted Connections in Borated Systems
28
IWA-6300 Retention
29
November 29, 2016 ASME Section XI 59
Inservice Inspection of Nuclear Power Plants
30