Professional Documents
Culture Documents
1 Scope..................................................................... 2
2 Conflicts and Deviations......................................... 2
3 Applicable Documents............................................ 2
4 Definitions and Acronyms....................................... 4
5 Responsibilities....................................................... 6
6 Instructions............................................................. 7
1 Scope
1.1 This engineering procedure specifies the minimum requirements for certification
review and registration of contractor welders working on In-Kingdom
construction and fabrication projects.
1.2 This engineering procedure does not apply to Manufacturer Fabrication Facilities
as defined in Section 4.
1.3 This engineering procedure does not apply to Maintenance Projects as defined in
Section 4.
2.1 Conflicts
Any conflicts between this SAEP and other applicable Mandatory Saudi Aramco
Engineering Requirement (MSAER) shall be resolved in writing by the
Company through the Chairman, Project Quality Standards Committee.
Direct and process all requests to deviate or waive the requirements of this
SAEP according to the internal company procedure SAEP-302, Instructions for
Obtaining a Waiver of a Mandatory Saudi Aramco Engineering Requirement.
3 Applicable Documents
Unless stated otherwise, all codes and standards referenced shall be the latest issue
(including Revisions and Addenda). When industry codes and standards, or Saudi
Aramco standards are required for use by project specifications, they shall become a
part of this Engineering Procedure.
Page 2 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
Page 3 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
Certified Welder: A welder that has a valid welder certification and approved agency
qualification card. A certified welder is only qualified to weld with those welding
processes, and within the essential variables, of the valid certification according to the
qualification governing code. Unless specified otherwise, the term welder shall also
mean welding operator.
Contractor Welder: A welder working directly for, and under the supervision of a
contractor.
Fabrication Shop: A facility with a controlled environment used for the fabrication
and/or assembly of equipment and structures such as pipe spools, pressure vessel, etc.
Controlled environment refers to atmospheric weather condition, established quality
system, and welder’s accessibility to welds joints. Fabrication Shop requires
pre-approval by Saudi Aramco Inspection Agency.
Fabrication Yard: A large open outdoor area used for the fabrication and/or assembly
of very large structures such as offshore platforms, etc.
Field Fabrication Shop: A temporary fabrication shop set up in the field near a
construction project by a contractor to fabricate piping, fittings and/or structural
components.
Page 4 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
in the specified project within the limits of their qualification (See Appendix II).
The JCC contains the welder’s name, symbol, photograph, limits of the qualification,
project reference (i.e., BI Number/JO Number or Work Order Number), name of
Contractor Company and Saudi Aramco Inspector’s name and signature.
Project Inspector: Refers to Saudi Aramco Project Inspection who verifies project
quality, integrity and compliance with industry and international codes/standards.
Renewal: A process of the reinstating the welder qualification certificate after the
expiration period or approval revoke.
Saudi Aramco Approved Welder Testing Agencies: Any agency approved by IEU to
qualify as an approved agency for qualifying welders/welding operators for Saudi
Aramco.
Uncertified Welder: A welder that does not have a valid welder certification from an
approved Welder Testing Agency.
Welder Certification: Certification in writing that a welder has produced a test weld
meeting a defined standard.
Page 5 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
5 Responsibilities
5.1.1 The IEU supervisor under OID is responsible for maintaining the
approved list of Welder Testing Agencies (WTA).
5.2 Contractor
Page 6 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
6 Instructions
6.1.2 WTA is not allowed to qualify their own welders and welding operators
working in the same project.
Page 7 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
The project welders in the field must carry on their original JCC cards
with PID original signatures, no scans or copies will be allowed.
6.1.5 The project inspector shall be authorized to retest or remove any welder
at any time due to unsatisfactory work or poor performance as identified
in Appendix I, Welder Performance Guidelines.
6.1.6 The Project Inspector shall regularly audit welder certifications to ensure
fabricator compliance with the Codes, standards and approved Quality
Plan.
6.1.7 All welders shall be qualified in accordance with ASME IX, AWS D1.1,
D1.6, D1.8, or API STD 1104, this SAEP as required and additional
requirements in the design code if required, for all types of welds
including tack, temporary and repair welds.
6.1.8 The first three (3) production butt welds made by each new welder,
regardless of welding process, shall be 100% examined by the applicable
NDE method. NDE acceptance shall be as specified by the applicable
Code. Decision path for evaluation of the first three (3) production welds
is illustrated in Appendix III.
6.1.9 The first three production butt welds will not be included in the project
welding statistics or weld repair rates for daily welding production
percentage. The percentage radiography requirement is as listed in the
applicable SAES-W-011, Section 17 and SAES-W-012, Section 16.
Each welder and Welding operator’s work shall be represented in the
required selection.
Commentary Note:
Page 8 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
6.1.10 For tank welding, the first three (3) production butt welds to be
radiographed shall be the first three shots of 6” length of each weld.
6.2.2 The qualification of a welder who has taken the Annex D Supplemental
Welder Qualification test is valid for 36 months, providing the D1.1
continuity requirements are also met (i.e., the process is used at least
every six months). (See D1.8, clause 5.2).
Page 9 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
6.2.5 Upon issuance of JCC, the welder shall be registered in the project’s
Welder Registration & Tracking System. Welders that have not been
properly certified and registered shall not be permitted to weld.
6.2.6 For offshore pipelines and structures, all welders shall be qualified per
applicable code and this SAEP.
6.2.7 Job Clearance Card (JCC) is only valid for the job or project it is issued
for. With approval of the project inspector, job clearance cards may be
issued per contract number of the contractor which may involve work
activities with numerous BI or JO.
6.2.8 Job Clearance Cards can be withdrawn by the Project Inspector at any
time for cause if the contractor welder is not producing work of
acceptable quality. Withdrawal of JCC shall be done through Project
Management and once withdrawn, JCC will only be reinstated upon
receipt of written proof of training, and the successful completion of a
recertification test by approved Welder Testing Agency.
6.2.9 When the welder leaves or terminated, Job Clearance Cards shall be
returned to Welder Tracking Coordinator to update the Welder
Registration and Tracking System. Welders returning to work within six
(6) months (to the same project) may be reinstated without retesting.
6.3.2 The fabricator shall maintain a welder identification system and welder
registration and tracking system acceptable to the Project Inspector
utilizing Appendix IV as minimum to follow. Welders shall carry an
identification card that includes a photo, welders name, company
identification number, and welder’s symbol.
Revision Summary
12 October 2015 Major revision to include the technical responsibility of conducting Welder Testing Agency
Assessment by Inspection Engineering Unit (IEU) to have high levels of project quality.
Page 10 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
Notes:
1. Contractor’s Welding Process Control Procedure (Company approved) shall clearly state acceptable
Welding Performance parameters for initial and weekly production.
2. Procedure shall define Linear & Joint method performance targets and these quality targets shall be
acceptable to COMPANY and approved before welding begins where Lr is the welder's total length of
repairs in one week, Lw is the welder's total length of weld radiographed in one week, Jr is total rejected
welds and Jw is the total joint welds radiographed.
3. Procedure shall detail NDT requirements of initial Welder production to determine acceptability of welder
performance, especially with new welders.
a. First three joints as a minimum shall be examined.
b. Welders shall not make additional initial production welds until their “initial performance” has been
verified and NDT results are acceptable per the procedure.
c. First three joints shall not be counted as routine daily production for project WRR.
4. Procedure states maximum number of consecutive weeks when a welder exceeds performance targets.
Severe weather or other factors beyond welder control may be considered.
5. Procedure shall state the amount of NDT up to 100% when target repair rates are exceeded or when a
welder has been removed from work.
6. Pipeline Projects using Semi-automatic / Automatic / Combination Processes may utilize even more
stringent Weld Quality Guidelines than those listed above for Manual process.
Page 11 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
Page 12 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
WBS
Photo
Project
Contractor
Note: This clearance card is for welding on the above mentioned project
only, and may be revoked if welder's performance is not satisfactory.
Card must be returned when welder is removed from this project.
PID Section
Material P-No's
Process
Electrodes/F-No's
Position/Progression
Min/Max Thickness
Diameter Range
(Backing/Inert Backing)
WPS No.
JCC-No.
Page 13 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
Page 14 of 15
Document Responsibility: Project Quality Standards Committee SAEP-324
Issue Date: 12 October 2015
Next Planned Update: 12 October 2018 Certification Review and Registration of Project Welders
(SAEP 324 Appendix IV- Sample of Welder Registration and Tracking Record)
WELDER REGISTRATION AND TRACKING RECORD
PROJECT NAME:
BI: JO: CONTRACT No.:
CONTRACTOR: LOCATION:
WELDER REGISTRATION DETAILS OF QUALIFICATIONS
Recording the
Serial No. Date of Last STATUS/REMARKS
Continuity Date of PID
OR Welder's Name Symbol ID Number Date of Test Continuity Record PID Inspector PID Signature Welding Process Material (P-No) Electrodes Position Thickness Range Diameter Range
Record (i.e. NDT Approval
JCC No. Verificied
Report No.)
Page 15 of 15