Sl. No.

Description of works Amount


1 Fixing & Providing temporary supports for
existing damaged structure till the 9000
completion of work
2 Removing existing damaged floor tile &
2000
floor concrete
3 Earthwork excavation for new column
foundation including the cost of removal
3000
of existing damaged foundation & plinth
beam
4 Dewatering system for new foundation 1000
5 PCC 1:4:8 below new foundation 2000
6 M30 grade RCC foundation for new
column including the cost of side 16000
shuttering & cost of reinforcement
7 Stub Column upto plinth beam level
including the cost of shuttering & 3000
reinforcement
8 Earthwork in filling with selected earth
above new foundation & below floor 2500
concrete
9 Casting of Plinth beam using M30 grade
concrete including the cost of shuttering 7000
& reinforcement
10 Casting of new column with M30 grade
concrete including the cost of shuttering, 15000
centering & reinforcement
11 Chipping of existing damaged roof beam 4000
12 Fixing of reinforcement for roof beam 5000
13 Casting of roof beam with M30 grade
micro concrete including the cost of 27000
centering & shuttering
14 PCC 1:4:8 for floor concrete 4000
15 Plastering of Column & roof beam with
5000
cement mortar 1:4
16 Decorative work for Column 5000
17 Floor tile for damaged portion 5000
18 Painting works 4000
19 Shifting & Relaying of existing damaged
8200
Plumbing line
20 Structural Consultancy charges 17700
Total 145400