Professional Documents
Culture Documents
1zcl000005tsg Process Tests and Control Points For Power Transformers Presentation PDF
1zcl000005tsg Process Tests and Control Points For Power Transformers Presentation PDF
Quality Manager
Francisco J. Ramos S.
John Alejandro Jairo Suárez S. Heiber Varón Juan C. Vélez Carlos Ossa
Ramírez
Julio Patiño
Winding Operators
Uriel Madrid
Assembly Operators
1. Core Manufacture
1. Core Cutting
2. Core Clamps
TESTS
T1. After raising the core
but before glue or asecond
is applied, an insulation test
is carried out
1ZBA 461 003-5
3. Winding
TESTS
CONTROL POINTS
TESTS
CONTROL POINTS
3. Transportation
TESTS ROOM
PLANNING
CUSTOMER: SAMSUNG
POWER: 40/50 MVA
VOLTAGE: 66.0 / 12.0 KV
PROJECT NUMBER: 127010
Test’s schedule for the transformers in reference.