R12.

2 Upgrade Approximate Time Estimation


S.No Task Name

1 Pre Upgrade Process

2 Patching Process

3 Database Upgrade

4 Application Upgrade

5 Post Upgrade Process

6 Functional Testing

7 Custom Object Retro Fit (If any)

8 UAT Ist Iteration Release


9 TEST Instance IInd Iteration Release
10 PRODUCTION Instance - Go Live
grade Approximate Time Estimation
Sub Task No of Days Resource Type

6
Clone Prodcution and Create UAT 3 DBA
Transactions Posting and Period Closing 3 Functional
3
Patch Downloads 1 DBA
Pre Requesting Process 1 DBA
Configuration Changes 1 DBA
7 DBA
Patching Process for Database 3 DBA
Configuration Changes 3 DBA
Post Patch Process 1 DBA
12
Patching Process for Application 6 DBA
Configuration Changes 3 DBA
Post Patch Process 3 DBA
2
Sanity Checking 2 DBA
6
Forms Testing 3 Functional
Transactional Testing 3 Functional
4
Forms Bug Fixing 2 Technical
Report Retro Fit 2 Technical
Total No. Of Days 40
Total No. Of Days 18
Total No. Of Days 7