NOT-MO-003 - METHOD
Postboks 6412 Etterstad
0605 Oslo
TLF +47 02694
NAVIGATION CHANNEL IN
SOUTH
OPPDRAGSNR. A058266
DOKUMENTNR. NOT – MO- 003
VERSJON 1.0
UTGIVELSESDATO 15.02.2016
UTARBEIDET Rolf Åge Vågen
KONTROLLERT Karl C. Strømsem
GODKJENT Sverre Wiborg
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement
South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 2/78
INNHOLD
1 Summary 4
2 Introduction 5
4 Pontoons 7
4.1 Pontoon dimensions 7
4.2 Construction site for pontoons 7
4.3 Construction of pontoons 9
4.4 Towing of pontoons 12
4.5 Storage of pontoons 14
5 Abutment at Flua 15
5.1 Layout 16
5.2 Temporary quay 16
5.3 Towing 18
5.4 Installation 21
6 Bridge girder 23
6.1 General 23
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement
South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 3/78
13 Progress plan 71
13.1 Overall project 71
13.2 Critical activities: 71
13.3 Non-critical activities: 72
13.4 Detailed estimation of critical activity duration: 72
14 References 75
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement
South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 4/78
1 Summary
At this stage in the project no showstoppers are identified for the construction and installation of the two
floating bridge alternatives. However, more detailing is required at later stages in order to confirm and
optimize the presented methods. The bridge design has been developed continuously throughout the
project phase. The construction and installation methods are developed in parallel with the bridge design,
but there may be cases where the method is not entirely representing the latest design. The presented
methods are considered applicable nevertheless.
As a base case, the bridge girders will be pre-fabricated in 20 m lengths and transported to a specified
quay in Norway. There the bridge girders is welded together to longer sections before the final section is
connected to the pontoons. A 20 m element weighs 200 t (each road part is taken a separate element of
the cross section) for the curved bridge and 300 t for the straight bridge. The reason for choosing 20 m
elements is that these weights can be handled using standard cranes and equipment at the assembly and
construction sites.
The pontoons are proposed constructed in a dry dock. On request from the Client, Hanøytangen is
currently used as a base case. This is an existing facility with the required dimensions. Due to the size of
the pontoons it is necessary to have 10 construction cycles to complete all pontoons in addition to the
abutment at Flua. There are however, several possible solutions that could lower the construction time,
and give more flexibility to the project as well as reduce construction time and cost, e.g. building on
submersible barges and larger production sites outside of Norway. To minimize the dry dock time it is
proposed to complete the pontoons in a floating modus.
The abutment at Flua will be started in the in the dry dock, and completed floating. The depth of the
abutment (40 m) makes it difficult to perform all work inside a dock. With the current base case, the dock
capacity is critical. It is therefore beneficial to float out the abutment as early as reasonable practical to
free up capacity for the construction of the pontoons. For previous projects for the offshore industry, a
deep-water quay has been established at Hanøytangen. The same quay is proposed established for the
floating construction phase of the abutment. The abutment will be built early in the project to avoid risk of
delay to the installation of the bridge.
The major part of the floating bridge length will be assembled by skidding the bridge girders directly onto
the pontoons. This will be done from a floating quay established using standard North Sea barges. These
barges could either be bought second hand, or rented for the duration of the assembly period. For the
transition section of the bridge (between the lower part and the stay cable bridge) a Heavy Lift Vessel will
be required to carry out four (4) lifts.
The stay cable bridge tower will be constructed using standard slip forming. For the parts of the stay
cable bridge that are suspended above the water (North of the tower) the cantilever building method will
be applied. A framework will temporarily support the parts that are above land until the stay cables are
connected.
The floating part of the bridge will for both alternatives be installed as one section. The towing operation
and positioning of the bridge will be carried out using anchor handling vessels and tugs. A guiding system
will together with winches control the motions of the bridge ends during installation. When in position, the
floating bridge will temporary be secured to Flua and the stay cable bridge by bolted connections. The
bolted connections will keep the bridge parts together until the permanent connection (welding) is
established. For the straight bridge it is possible to use the pre-installed mooring lines during installation
to provide additional guidance and support.
Estimates of expected delay are calculated by computer simulation of the weather sensitive operations.
The following operations are investigated: Towing of pontoons, towing of the abutment for Flua,
installation of the abutment, assembly using HLV (Heavy Lift Vessel) and installation of the complete
floating bridge. The simulations show that some delay may be expected, however due to the relatively
short duration of the operations it is possible to get a weather window for most operations throughout the
whole year. The basis for these simulations is time series of wind received from the Client.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 5/78
2 Introduction
This report covers the methods for construction and installation of the bridge over Bjørnafjorden. Both the
curved bridge and the straight bridge are included in the report. However, as a basis the method is
explained using the curved bridge, as this alternative is seen as most challenging in the installation
phases due to its size and layout. Any special considerations for the straight bridge are mentioned
throughout the report if deemed necessary.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 6/78
- Permissions for proposed locations are in place, and the facilities have the required capacity.
Most of the vessels are taken from the spot market. There are however operations that requires
that vessels are reserved in due time before the operations. This is particularly relevant for parts
of the assembly operation using Heavy Lift Vessels (HLV) and the towing and installation
operations (large number of towing vessels required).
- Building of pontoons and abutment at Flua is carried out at Hanøytangen Askøy, Norway.
- Assembly of floating bridge is carried out in Eikelandsfjorden. In this fjord, a storage location and
an assembly quay will be established.
- The bridge girder is ordered in 20 m lengths, and delivered to assembly quays and to the stay
cable bridge building location as required. I.e. no storage location for steelwork is planned for at
this stage.
- Pontoons are stored in a fjord close to Eikelandsfjorden between construction and assembly.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 7/78
4 Pontoons
An illustration of the pontoons together with the main dimensions are shown in Figure 4-1 below.
It is not many alternatives when it comes to existing facilities in Norway. The only dry dock that is large
enough for several pontoons is Hanøytangen outside of Bergen (there are dry docks that can facilitate
one pontoon, but these are disregarded in this report). The dimensions of the dry dock is 125 m x 125 m,
with a depth of 17 m. Throughout this report Hanøytangen is used as a base case, but some alternative
constructions facilities are discussed below.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 8/78
Lutelandet is a possible location, with an area that is already included in a zoning plan. The industrial site
3-4 hours north of Bergen has future plans for a dock with the dimensions 362 m x 132 m, and with a
depth of 21 m. As per now, no definite plans for building of the dock is in place. Figure 4-2 illustrates the
future plans for the Lutelandet industrial area.
Another alternative is to build the pontoons on a semisubmersible barge. With the current dimensions of
the pontoons (and especially the breadth of 38 m) there are a limited number of barges that are large
enough to facilitate the pontoons. In Figure 4-3 an example of a semisubmersible barge from BOA with a
width of 38 m is shown. This barge would be able to facilitate two pontoons in one construction cycle.
Using a barge could be a good complementary solution if the building time of the pontoons shows to be
important.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 9/78
There are areas that historically have been used for construction of large concrete Gravity Based
Structures (GBS) for the offshore industry. An example of such an area is Åndalsnes, which was used to
build two GBS platforms in the 1970s. This location is basically a shallow area that are enclosed from the
sea using a filling, and further drained. A challenge with the Bjørnafjord project compared to the GBS
projects is that the construction cycle off the pontoons will be repeated many times, due to the number of
pontoons. It is therefore beneficial to have a relatively standardized system, which make the filling and
discharging time as short as possible. The alternative of using a shallow non-established area with a
filling is therefore disregarded in this report.
Figure 4-4: Construction of GBS platform Frigg in Åndalsnes. Photo: Norsk Oljemuseum.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 10/78
The construction phases of the pontoons are illustrated in Figure 4-7. The first phase is to cast the bottom
plate. Then the inner and outer walls are made. These two phases are carried out inside the dock before
the dock is flooded and the pontoons moved outside.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 11/78
Outside of the dock, the pontoons will be moored to a quay and the top plate is cast. Hanøytangen has
two quays with depths of 17 m and 20m that can facilitate one pontoon each.
The last operation for the pontoons is to mount the columns. These are lifted in place by a shore-based
crane for lifts below 400 t.
For lifts that are above 400 t, a floating crane will be used. This only applies for the straight bridge.
A suggested layout for the mooring of the pontoon while along the quay side is shown in Figure 4-8.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 12/78
The towing resistance for towing of one pontoon can be obtained in a simplified way by calculating the
drag force on the submerged projected area;
1
𝐹𝐷 = ∗ 𝐶 ∗ 𝐴 ∗ 𝜌 ∗ 𝑣2
2 𝐷
Where;
𝑚
𝑣 = 𝑇𝑜𝑤𝑖𝑛𝑔 𝑠𝑝𝑒𝑒𝑑 [ ]
𝑠
For a towing speed of 3 knots (1.5 m/s), and a drag factor of 1.6 the drag force of the pontoon will be
approximately 50 t. A large tug (bollard pull of approximately 100 t) will have sufficient capacity for towing.
In addition, a small harbor tug with a bollard pull of <50 t is required for assistance with the mooring and
unmooring operations.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 13/78
The towing distance from Hanøytangen is approximately 165 km for the towing route illustrated in Figure
4-9 (the inshore towing route presented for the abutment in section 5.3 is also relevant). A mean towing
velocity of 3 knots gives a duration of 30 hrs.
A weather criterion for the pontoon tow is showed in table below. At this stage, the weather criteria is
based on experience from comparable operations. For the actual tow, safe havens must specified prior to
towing commencement.
By using Global Maritimes marine operation simulation software GMOPSIM, the expected weather delay
for the operation is calculated and shown in the figure and table below (the presented value indicates the
expected duration for waiting on forecasted weather window). Wind conditions at Marstein is used as
input to these simulations, ref /4/. See Figure 4-10.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 14/78
Figure 4-10: Expected monthly delay for pontoon towing (hours) due to weather from GMOPSIM.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 15/78
5 Abutment at Flua
The abutment at Flua will be built inside a dry dock and then floated out and completed when floating.
The reason for this is that there are no dry docks with sufficient depth for completing the abutment and
still be able to float it out. It is assumed that after 3 months production inside the dock, the abutment will
be floated out with a draft of approximately 10 m. The draft will increase to 18.5 m during the completion
(without top plate).
The abutment will be towed to Bjørnafjorden without the top plate, as the abutment will be permanently
ballasted after it is positioned on the shallow area Flua.
The top plate is cast including all of the connections that will make the connection between the bridge
girder and the abutment.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 16/78
5.1 Layout
Figure 5-1: The abutment at Flua (Curved bridge). Extract from drawing K92405.
The quay is established using barges that are fixed to bottom fixed tripods. The available depth at this
quay is 60-100 m, and the abutment will be connected to the barges using standard mooring equipment.
Another lay out than for the Troll platform will be used for building the abutment. This is used in order to
give access on all sides of the abutment during construction. A sketch of this layout is shown in Figure
5-4.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 17/78
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 18/78
Figure 5-4: Temporary quay using three standard North Sea barges.
A suggested mooring layout during building along the temporary quay is shown in Figure 5-5.
5.3 Towing
The abutment will be towed by using 3 x towing vessels from Hanøytangen to Bjørnafjorden. The base
case is to use 2x AHVs and one tug. See Figure 5-6.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 19/78
From Hanøytangen there are two possible towing routes to Bjørnafjorden. The first alternative is to tow
the abutment on the west side of Sotra, while the other is an inshore tow under the Sotra Bridge and
through Vatlestraumen. The two alternative routes are shown in Figure 5-7.
The first alternative is an offshore tow that requires a sufficient weather window, while the inner towing
route is sheltered. However, the inner towing route has shallow and narrow areas with occasionally
significant current that could create difficulties for maneuvering. The base case route is therefore the
offshore alternative.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 20/78
A study of the expected weather induced delay is carried out. This study show that the operation can be
carried out all year around, but with some expected delay. The building of the abutment at Flua is planned
carried out early in the project, and waiting on weather is not seen as critical for the overall project
duration or for costs.
Same towing distance (165 km) and towing speed (3 knots) as for the pontoons are used to obtain
expected delay for the towing operation. However, the abutment at Flua has a stricter weather criteria.
See table below.
By using GMOPSIM, the expected weather delay for the operation is obtained. Wind conditions at
Marstein is used for these simulations, ref /4/. See Figure 5-8.
Figure 5-8: Expected monthly delay for pontoon towing (hours) due to weather from GMOPSIM.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 21/78
5.4 Installation
The area where the abutment will be installed will have to be prepared prior to installation. For details of
the preparations, including leveling and ground works reference is made to ref. /1/. The installation of the
abutment at Flua is illustrated in Figure 5-9.
At this stage, the Flua abutment has been positioned at a location that is assumed to give as little ground
works as possible. At a later stage of the project, a study of the optimal position should be carried out.
Figure 5-9: The Flua area leveled and ready for installation of the abutment.
When the abutment is towed in position, it will be held in place by 4 vessels (same as towing vessels plus
an additional tug) before the lowering of the abutment is initiated. Seawater will be filled, using pre-
installed pumps in specified compartments to allow lowering the abutment in a controlled way. It could be
necessary to use guiding pins in order to position the abutment on the ground if the installation tolerances
are strict. The installation criteria must be decided at a later stage when more information of Flua is
available. The duration of this operation is estimated to be 12 hrs.
When the abutment is positioned within the tolerances on the ground, grouting using grouting pipes in the
abutment will be carried out.
Formwork is established and the top plate will be cast. A barge will be used to transport the concrete from
shore. The connections between the bridge girder and the abutment (shear studs) will be cast into the
abutment during the construction of the top plate.
By using GMOPSIM, the expected weather delay for the operation is calculated and shown in the figure
and table overleaf. Wind conditions at Bjørnafjorden is used for these simulations, ref. /4/. See Figure
5-10.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 22/78
Figure 5-10: Expected monthly delay for Flua installation (hours) due to weather from GMOPSIM.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 23/78
6 Bridge girder
6.1 General
The production of the steel elements should be detailed out at a later stage in the project. In a building
phase, the steel production location is most likely subject to the entrepreneur’s decision. It is therefore
difficult to cover all alternatives in this report at the present stage. The aim in this report is to identify a
possible solution that does not restrict the choice of yard and to prove feasibility. The production location
will also decide the suitable pre-fabrication length for transportation. Delivery to installation / assembly
location should be included in the production cost regardless of building location.
At this stage, it is assumed that the bridge girder is ordered in pre-defined lengths and delivered to the
stay cable building location and the floating bridge assembly location. 20 m lengths are used as base
case, as these are seen as flexible regarding type of transportation. It is also a method that is feasible for
production locations all around the world. 20 m elements are possible to handle using standard
equipment after arrival to building and assembly locations. A production close to the bridge location will
allow for pre-fabrication of larger elements as the transportation will be less complex. The bridge girder
may for this alternative be transported directly on the pontoons.
Storage is an issue that must be looked upon in relation to the production location. If the bridge girder is
pre-fabricated in the vicinity of Bjørnafjorden, most of the storage issues can be disregarded. However, if
the steel is pre-fabricated e.g. in Asia a storage location should be established as a buffer in order to
lower the impact of delay during transportation.
The weight of the steel work varies for different positions along the bridge, in order to handle the local
forces e.g. above the columns. For a full overview of the variation, reference is made to ref /5/ and ref /6/.
The weight of the bridge girder will be lower in the installation phase than in the permanent phase as
tarmac and other final outfitting will be installed after the bridge is installed. In Table 6-1 some average
values are presented in the Table 6-1.
Figure 6-1 sums up the process of combining 20 m elements into bridge sections, and the bridge sections
to the complete bridge length from the abutment in South to Flua.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 24/78
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 25/78
If more detailed environmental data is available at a later stage of the project, it could be that other
locations that are closer to the bridge location prove to be feasible for this purpose. This will shorten the
towing distance of the assembled bridge.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 26/78
Figure 7-3: Assembly of the bridge. Skidding method for the lower part, and lifting method for higher part.
The parts that are built using the skidding method will be assembled to bridge sections with lengths
varying from 600 m to 800 m at the assembly quay. Further, the bridge sections will be moved to the
storage location where they are assembled with the rest of the bridge. Figure 7-4 illustrates the different
bridge sections that will be transported and mounted together at the storage location. It should be noted
that bridge section 1 will not be transported as one element, but be put together by lifting 4 elements,
each with a length of 200 m. The method for mounting bridge section 1- 5 is described in chapter 7.3.1
and 7.3.2 .
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 27/78
Figure 7-4: Illustration of bridge section numbering with corresponding assembly method.
Figure 7-5 show the sequence of the mounting operations at the storage location.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 28/78
- 15 t stevpris/stevshark anchors
- 76 mm mooring chain (to avoid that wire or fibre rope are damaged in contact with sea bed)
- Shore bollard
- 76 mm mooring chain (to avoid that wire or fibre rope are damaged in contact with sea bed)
The top termination of the mooring system on to the bridge must be determined after the mooring system
is designed and will be dependent on the required pre-tension in the mooring system. For lower pre-
tensions, it should be possible to tension the mooring lines only using the installation vessel. If a higher
pre-tension is required it might be necessary to use tension barges or hydraulic jacks etc. At this stage, it
is assumed that tensioning using towing vessels is feasible, as the stiffness requirement in this mooring
system is believed to be low.
A typical layout for the temporary mooring system is illustrated in Figure 7-6 and Figure 7-7.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 29/78
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 30/78
The quay that will be used for this part of the operation will be established using 4 standard North Sea
barges. It is important that a stiff connection is established between the barges. This will give a quay with
a size of approximately 120 x 90 m. The benefit of using barges is that the quay will follow the tidal
variation together with the pontoon the bridge girder is resting on. The quay will be kept in place using
piles and/or mooring lines to seabed.
The bridge girder elements will be transported to the assembly quay either on a barge or on a
transportation vessel. As a base case, the elements have a length of approximately 20 m. The size of the
elements makes it possible for a standard mobile crane with approximately 200 t and 400 t capacity (for
curved bridge and straight bridge respectively) to lift each of the bridge girder elements onto the quay.
The skidding will be performed using hydraulic jacks that pushes the bridge girder from the quay and onto
the pontoons.
This method does not require a large quay area, however it is necessary to get sufficient height to be able
to skid the bridge girder on to the pontoons. This height is obtained by setting up a framework on the
barges. The required height for the framework is approximately 7.5 m. This includes all grillages, skidding
beams etc., see Figure 7-8.
The elements will be lined up and welded together before they are skidded onto the pontoon. For the
curved bridge each of the bridge girder elements will be lifted separately. When the bridge girder is
skidded onto the pontoon, there will be available space on the quay and more elements are added. This
is illustrated in Figure 7-9.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 31/78
This cycle is repeated until another pontoon is added to the assembly. The pontoon will be ballasted
down, and de-ballasted after it is positioned under the bridge girder. In order to keep control of the
cantilever during building, a mooring system will have to be pre-laid outside of the quay area and hooked
up to the bridge when the cantilever is getting longer. It is assumed that the mooring lines can be
tensioned without any special equipment. This is illustrated in step 4 in Figure 7-10.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 32/78
When a length of approximately 600 m to 800 m is welded together and floated out onto the pontoons (3-
4 pontoons), the assembled section is towed to the storage location and hooked up to the pre-laid
mooring system. Any overhang on of the bridge girder is supported by a barge, until the bridge section is
connected with the rest of the bridge. One barge can be re-used for the three sections that require
additional support (bridge section 3, 4 & 5, see Figure 7-4).
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 33/78
Using our proposed method required that the bridge girder is assembled into 200 m lengths before it is
connected on to the pontoons. See Figure 7-13. This is done in order to minimize the number of HLV lifts.
In total 4 elements will be lifted by HLV, and these elements will be assembled from 20 m lengths to 200
m lengths on a quay, or ordered in 200 m lengths from the production yard.
One proposed location for the assembly of the 200 m elements is at Eldøyane/Stord. It is beneficial to
keep this operation, separate from the skidding quay in order to make the skidding as effective as
possible. The assembly to 200 m elements and lifting in place by HLV is given large flexibility timewise in
order to have a flexible schedule when entering the heavy lift market to be able to minimize costs.
The 200 m elements can be loaded onto the barge using multiwheelers/SPMTs. The multiwheelers are
frequently used in load-out operations in the offshore industry and can be assembled as required in order
to obtain the required lifting capacity.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 34/78
The lifting of the 200 m bridge girder elements will be done using a Heavy lift vessel in one end, and
strand jacks / deck erection crane that are mounted on Bridge section 2 in the other.
The 200 m bridge girder element is transported to the storage location on a large barge. The bridge
girder, lifting vessel and deck erection crane is illustrated in Figure 7-14.
To allow for mounting of the pontoon, the bridge girder will be lifted slightly above the “in-place height”. A
small tug will be used for the positioning of the pontoon. See Figure 7-15.
The bridge girder is further lowered onto the pontoon and the pontoon is being de-ballasted in order to
carry the weight of the bridge girder. Conical guide pins will make sure the bridge girder and the column is
positioned correctly during the mounting.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 35/78
The four lifts that will be carried out for Bridge section 1 are shown below. The strand jacks will be moved
along the bridge preparing for the next lift. See Figure 7-16.
In this report we illustrate the procedure using the crane vessel Rambiz 3000 (lifting capacity 3300 t, and
lifting height of 79 m). See Figure 7-17. There are several heavy lift vessels that could be used for these
lifts. Another alternative, if the HLV market is tight, is to use a lifting tower on a barge (This method was
also used during building parts of the Sundsvall Bridge). The lifting weight of the bridge girder elements is
approximately 4600 ton (23 t/m x 200m). The weight will be divided between the strand jacks on the
bridge and the crane vessel. A capacity between 2500 t and 3000 t is therefore required (including a
margin for skewness and dynamic amplification during lifting).
On the bridge side, number of strand jacks are chosen based on the lifting weight. The capacity for each
strand jack is approximately 650 t, which means that approximately 5 strand jacks are required for the lift.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 36/78
Figure 7-17: Crane vessel Rambiz used for lifting of bridge girder on the Vasco da Gama bridge. Photo: http://www.scaldis-
smc.com/en-GB/civil-construction-works/26/
If there is a limited availability of crane vessels/lifting towers the time of building, an alternative is to split
the lifted bridge girders into smaller parts and support the overhang by a temporary pontoon. Selecting
this solution will depend on the cost of the various options available at the time of construction.
Using GMOPSIM, the expected weather delay for the operation is calculated and shown in the table and
figure overleaf. Wind conditions at Bjørnafjorden is used for these simulations, ref. /4/.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 37/78
Figure 7-18: Expected monthly delay for heavy lift operations (hrs.) due to weather from GMOPSIM
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 38/78
In order to build the section of the stay cable bridge that passes over land, a framework is set up. This
framework will mainly be standing on land, but some of the legs will be positioned in water between
Svarvhellaholmen and Reksteren. These legs will either be supported on piles or with an underwater
casting. The framework will support the bridge girder elements during assembly. An illustration of the
framework is shown in Figure 8-2.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 39/78
The bridge girder elements are lifted onto the framework using a crane vessel. An element length of 20 m
is seen as a reasonable size as it can easily be handled. An element length of 20 m, gives a lifting weight
is approximately 200 t for the curved bridge (lifting each of the bridge girder boxes for each road section
separately) and 300 t for the straight bridge. Relevant vessels to be used in this operation would be
sheerleg-lifting barges. A lifting weight of 300 t gives reasonable flexibility in selection of lifting vessel
which will keep the cost and availability under control. In this report, the Norwegian crane vessel “Uglen”
is used as an example. The lifting capacity diagram for “Uglen” is shown in Figure 8-4, as seen in the
diagram, the capacity is sufficient for the required lifting height of 55 m.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 40/78
The channel between Svarvhellaholmen and Reksteren is relatively narrow and shallow East of the
bridge, therefore in the base case we assume that lifting vessel can only approach and lifting bridge
girder elements from the West side of the bridge, as illustrated in Figure 8-5 and Figure 8-6 with skidding
of the element to the East side of the bridge.
If it is seen as beneficial for cost and schedule reasons to lift larger elements, lifts may be performed from
both sides. The decision of moving in between Svarvhellaholmen and Reksteren with the crane vessel
must be agreed upon by vessel owner and the contractor. Another alternative if is to use a larger sheerleg
crane that can lift larger elements from the western side.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 41/78
Figure 8-6: Element is skidded from the West to the East side of the bridge.
As the first element is lifted onto the framework and skidded over to the eastern side of the bridge, the
transverse beams and the second bridge girder elements are lifted onto the work platform and mounted
together. The elements are only partly welded together in order to lower the period where the crane
vessel is required. Figure 8-7 illustrate the lifting of the second bridge girder element.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 42/78
Figure 8-7: Lifting of second bridge girder element onto work platform.
After the elements are mounted together, they are skidded along the framework towards the abutment.
This is done with strand jacks that are mounted onto the abutment in South. Figure 8-8 Illustrates parts of
the bridge in place, and another element that are skidded towards the abutment.
Figure 8-8: First bridge girder elements are skidded in place, another element assembled and ready for skidding.
There will be an overhang towards the sea on the North side of the tower. This section will be skidded
using wires that are routed via the tower. See Figure 8-9.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 43/78
The last element that is lifted in place, is the element above the working platform. The complete bridge
girder supported by the framework is shown in Figure 8-10.
The next phase for the construction is to erect the bridge girder on the North side of the tower. For this
phase, deck erection cranes mounted onto the bridge will be used. Bridge girder elements are lifted
directly from a barge as shown in Figure 8-11. The element length is approximately 20 m. All lifted
elements will have a transverse beam connecting the two bridge girder elements together during the lift.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 44/78
Figure 8-11: Lifting of bridge girder elements using deck erection cranes
The building sequence is further illustrated below in Figure 8-12 to Figure 8-16. For each of the elements
that are lifted in place using the deck erection cranes, the stay cable are connected to both the lifted
element and the corresponding part of the stay cable bridge on the south side of the tower. The deck
erection crane is moved after each lift.
Figure 8-12: Stay cable bridge with bridge girder supported by framework.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 45/78
Figure 8-13: First bridge girder element North of the tower lifted in and corresponding stay cables connected.
Figure 8-14: Second bridge girder element North of the tower lifted in and corresponding stay cables connected.
Figure 8-15: Third bridge girder element North of the tower lifted in and corresponding stay cables connected.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 46/78
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 47/78
9.1 Method
In order to establish the rigid connection on Flua, it is decided to install a shorter bridge element that will
be relatively easy to secure for a temporary phase. It is seen as difficult to handle the forces from the
complete bridge length and at the same time fix the bridge girder to Flua.
It is therefore decided to float in an element with a length of approximately 170 m. This length is chosen
of following reasons;
- Bending moments around the strong axis in design conditions are low at this position (see Figure
9-1). A temporary securing arrangement of the remaining complete floating bridge will therefore
be easier to handle.
- Bending moment about weak axis is as close to the in-place condition as possible (as the
connection is close to the first pontoon)
- Short overhang on the remaining floating bridge when it is installed (connection towards the
floating bridge will be close to the zero-moment position). Any overhang would have to be
supported by a barge, which again will increase the forces on the towed bridge.
Figure 9-1: Bending moments about strong axis at connection points (100 year condition), horizontal axis indicating axis
positions. Flua to the right and stay cable bridge to the left.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 48/78
This element will be floated onto the abutment on two barges. One of the barges will only be used in the
installation phase, while the other will remain and act as a temporary pontoon until the rest of the bridge is
installed.
During installation the two barges are ballasted down until the element is resting on Flua. It is also
possible to use the tidal variation in the installation phase, but a ballast system will still be required.
The element will be temporary secured on Flua, and the barge closest to Flua will be removed. The
remaining barge will be ballasted to account for tidal variation until the element is fixed on Flua. The tidal
variation is approximately +/- 1 m, which corresponds to a roughly 4000 m^3 ballast that need to be
filled/removed during a 12 hour period. This is not a critical amount of ballast to handle.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 49/78
Figure 9-4: One of the pontoons are removed, the other remains at temporary pontoon.
After the element is fixed, the element will sustain the tidal through bending of the weak axis. As
mentioned above, with the present length, this bending will for all practical purposes be similar to the in-
place condition.
If a high tide situation is experienced during installation, the floating bridge will be ballasted down until the
mean level is obtained. In order to avoid inclination on the installed bridge, at least 3 pontoons will be
ballasted down simultaneously. The ballast system will be able to keep this elevation during installation by
de-ballasting as the water level decreases. In order to ballast the pontoon 1 m, approximately 1700 m^3
of water is required.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 50/78
The bridge parts will then be connected by using the temporary connection that is defined in chapter 11.1.
Any minor inclinations will be removed by tensioning these connection points.
The barge is removed, and the cross section is permanently welded together.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 51/78
The towing route is illustrated in Figure 10-1. The total towing distance is approximately 23 km, or 12.5
nautical miles.
- Adequate speed
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 52/78
In this case the criteria for unrestricted towing and “all year” environmental data is used in the absence of
seasonal data. The operation will have a weather criteria, and will be planned carried out in the summer
season. For now however, “unrestricted towing criteria” is used due to the high uncertainty in the
operations at this stage. Using unrestricted criteria, we ensure that the bridge is safe in case the towing
and installation duration exceed a weather restricted operational time window.
The wind forces are estimated from a modified Novaframe model, wave drift forces are estimated from
Orcaflex and forces from current are calculated from drag forces (drag factor of 1.6). In this report it is
assumed that all environmental forces act in the same direction. For wind and waves this is seen as a fair
assumption as the waves in the fjord for these conditions are wind generated.
Figure 10-2 show the orientation for values tabulated in Table 10-2.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 53/78
Based on the results above, the most reasonable heading for the bridge in a storm is 0 degrees against
the environmental loads as this will minimize the wind forces. This is illustrated in Figure 10-3. Another
alternative is to tow northwards to get shelter. However at this stage, there are not available detailed
environmental data for the different areas, and a worst-case condition is therefore used to prove the
feasibility of the concept.
This layout uses 14 vessels for towing and station keeping. The heading of the vessels are 45 degrees
against the weather if a bridge heading of 0° towards the environmental forces are used.
𝐹𝑒𝑛𝑣 1237 𝑡
𝐹𝑣𝑒𝑠𝑠𝑒𝑙 = = = 125 𝑡
𝑛𝑣𝑒𝑠𝑠𝑒𝑙𝑠 ∙ cos 45° 14 ∙ cos 45°
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 54/78
This calculation show that a mean bollard pull requirement will be in the range of 125 t. For the actual tow
it is beneficial to have a variety of larger and smaller vessels. The smaller vessels can be used to control
the orientation of the bridge during tow, while the larger vessels are pulling the bridge. The smaller
vessels can also be to connect directly to the pontoons.
Figure 10-5 and Figure 10-6 illustrates the bridge at different positions along the towing route together
with the clearances to shore while towing.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 55/78
Figure 10-6: Clearance between towing vessels and shore when passing Fusa.
2 ∙ 𝐹𝑑,𝑡𝑜𝑡 𝑚
𝑉𝑇𝑜𝑤𝑖𝑛𝑔 = √ − 𝑉𝑐𝑢𝑟𝑟𝑒𝑛𝑡 = 0.57 = 1.1 𝑘𝑛𝑜𝑡𝑠
𝐴 ∙ 𝐶𝐷 ∙ 𝜌 𝑠
(Current velocity is taken as 0.5 m/s, projected area is the total submerged projected area for all pontoons
as illustrated in Figure 10-7, and a drag factor of 1.6 is used).
With a towing speed of 1.1 knots, the towing duration will be approximately 11.5 hours (towing distance
12.5 nautical miles).
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 56/78
Figure 10-7: Towing direction for pontoons during tow in narrow waters.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 57/78
At the time of the installation, the stay cable bridge is already completed and the segment at Flua is
established, ref chapter 8 and 9 respectively.
Measurements and length control of the bridge is carried out throughout the assembly phase. The bridge
girder elements will also be test-mounted prior to transport from production yard. In this way the length of
the bridge is assumed correct, and it is therefore considered possible to install the bridge with relatively
small tolerances. The bridge length will however be dependent on the temperature the day of installation.
As this is an operation that is carried out in the summer it is most likely that the bridge is longer rather
than shorter. The mean temperature (where the bridge has zero imposed stress from temperature) is +5°.
If the temperature is +15° the day of the installation (which is a realistic mean temperature in the warmest
summer month in the Bjørnafjord area), this will give an elongation of approximately 40 cm. If an extreme
temperature of +32° degrees is experienced this will elongate the bridge with approximately 1.2 m. A
method for handling this length variation is explained in the following.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 58/78
From step 6 in Figure 11-1 above, the bridge is towed towards Flua and the stay cable bridge where
winch wires are connected. This is illustrated in Figure 11-2.
Figure 11-2: Installation is done using winch wires connected to Flua and the stay cable bridge.
The best way of controlling the motion of the bridge after connection to the winches is that the installation
vessels are holding back the bridge while the winches pull on the bridge in a controlled way. The
installation vessels will in this phase apply constant tension (The vessels are omitted from the Figure 11-2
for clarity. Vessels are indicated in figures in the coming).
One of the ends (in this case indicated for the southern end) is further winched towards the stay cable
bridge, where the floating bridge is connected to the stay cable bridge using guide pin(s). The guides will
allow rotation of the bridge and make sure that the motions of the bridge is restrained as the northern end
is moved in to position. See Figure 11-3. It should be noted that the guides are not dimensioned at this
stage, but the solution is scalable and the guide pin principle is frequently used in the offshore industry.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 59/78
Figure 11-3: one end winched in towards the guide pins on the main bridge.
A proposed vessel configuration is shown in Figure 11-4. Note that the heading of the vessels will vary
throughout the installation to account for the environmental forces.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 60/78
The longitudinal motion of the bridge will initially be controlled by the installation vessels. The winches will
eventually get a better angle of attack and control the bridge onto the guide pin(s). Further, any
movements of the Northern part of the floating bridge will be damped through a bumper system. See
Figure 11-8.
The resulting moment from the opposite forces from installation vessels and winches will slightly bend the
bridge, resulting in a decreased bridge length. This bending will compensate for temperature induced
expansion and provide sufficient installation tolerances.
A hold back force of approximately 33 t on each of the AHVs will result in a deflection of approximately 7
m of the bridge arc, and shorten the bridge length with almost 3 m. The vessels have a bollard pull
capacity above this, so the vessels should have no problems delivering the necessary forces. The
resulting winch pull will be approximately 50 t. Figure 11-6 show the end deflection of the bridge with a
total applied force of 100 t vessel pull.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 61/78
Figure 11-6: Bending of bridge due to installation vessels, 1 MN = 100 t (deformation is scaled).
To obtain a controlled interaction between the floating bridge and Flua, a guiding and bumper system is
used, see Figure 11-8. The green structures will damp out the motions while the blue structures will act as
fine guiding and align the cross sections and secure them for permanent connection (welding). Figure
11-10 show the layout of the temporary connection.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 62/78
As the northern end is approaching its position a guiding and bumper system will make sure the end is
moved into the correct position. Fendering systems designed to absorb energy is common for ships,
offshore structures and quays. These systems can be utilized in the installation operation, and should be
mounted on the bumper system to absorb the kinetic energy of the bridge as it is winched in place.
Figure 11-8: Bumper system (green), installation winches and temporary securing (blue). Clearance between bridge ends is
scaled for clarity.
When the northern part of the floating bridge is rotated in place, the forces from the towing vessels can be
gradually released in order to extend the bridge longitudinal and into its position. To lower the potential
risk of uncontrolled release of energy in this operation it is advised that hydraulic jacks are used between
the installed bridge and the northern part to assist the off-loading operation. It will make the off-loading of
the bridge arc smoother and reduce the risk for the personnel working close to the connection. See
Figure 11-9.
Figure 11-9: Hydraulic jacks used to off-load the bridge arc during installation.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 63/78
When in place, the temporary connections are tightened in order to position the cross sections for
welding. A drawing of the temporary connection is shown in Figure 11-10.
Figure 11-10: Drawing of temporary securing. Top left show example of position at the end, while top right show example at
a horizontal position.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 64/78
Using GMOPSIM, the expected weather delay for both the towing and installation operation is calculated
and the results are shown in the figure and table below. Wind conditions at Bjørnafjorden is used for
these simulations, ref. /4/.
Figure 11-11: Expected monthly delay for bridge installation (days) due to weather from GMOPSIM.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 65/78
Prior to towing and installation operation is initiated, an evaluation of the defined weather window will be
done. This will be carried out for the waypoints presented in Figure 11-12 below. In addition suggested
safe locations in case of deteriorating weather is also planned. The decision procedure is described in the
flowchart in Figure 11-13
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 66/78
- The complete floating bridge will be installed in one section as for the curved bridge.
- A 170 m bridge section will be pre-installed and supported by a temporary pontoon at Flua as for
the curved bridge.
- Where the curved bridge has a fixed connection at Flua, the straight bridge has a sliding bearing.
The sliding bearing at Flua will be utilized in the installation phase to compensate for
temperature-induced expansion and give sufficient installation tolerances. Instead of bending the
bridge (as for the curved alternative), the bridge girder element at Flua is moved Northwards by
using hydraulic jacks. This will compensate for temperature induced expansion and provide
sufficient installation tolerances.
- The bridge will then be temporarily secured to the bridge girder element at Flua. The jacks are
released (controlled) and the bridge is moved towards the stay cable bridge. Once interaction to
the stay cable bridge is obtained, a temporary connection is established. The same guiding and
securing system will be used for the straight bridge as for the curved bridge.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 67/78
- The permanent mooring lines will be connected to the floating bridge during installation. These
will be connected before the floating bridge is in position and help positioning the bridge during
installation. Pre-installation and connection of the mooring system is covered in chapter 12.
- The permanent mooring lines give straight bridge alternative more flexibility in the installation
phase. If required, the bridge can be installed in shorter sections. The mooring lines can then be
used to keep the cantilever bridge girder in place in the temporary phase.
At this stage, the knowledge of seabed conditions is quite limited and it is therefore difficult to decide the
best anchor types and positions. The bridge concept is however flexible regarding anchor types and
positions as the pre-tension values can easily be adjusted to obtain required horizontal stiffness at each
pontoon. Relevant anchor types are gravity anchors (combination of steel and rock ballast), suction
anchors (steel), Drag embedded vertical load anchors and piling anchors.
- Installation of anchors (including ballasting for gravity anchors using fall pipe vessel)
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 68/78
If gravity anchors is used they will require a heavy lift vessel for installation. The total anchor weight of
these anchors, including ballast, is approximately 2200 t. The ballasting will be carried out after the
anchor is positioned on the seabed and a lifting weight of approximately 500 t is required at this stage.
The principle for the anchor installation is shown in Figure 12-2.
Figure 12-2: Installation of anchor by using HLV and anchor handling tug.
When the anchor is positioned correctly on the sea bed, the mooring line is lowered onto the ground and
either laid down with a ROV pick-up system (the case if the installation is carried out long before bridge
installation) or buoyed off to the surface using a pick-up pennant and a surface buoy. In case the mooring
lines are laid down on the bottom, these are picked up by some of the anchor handling vessels used for
towing of the bridge prior to installation operation. This is a standard operation that is carried out
frequently in the North Sea.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 69/78
Figure 12-3: Buoyed- off mooring line ready for bridge installation.
When the bridge arrives Bjørnafjorden, the vessels used for towing will pick up the mooring line using the
subsurface buoy and connect to the mooring line end on the bridge.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 70/78
After the bridge is installed at Bjørnafjorden, the mooring line system will stay passive. Some re-
tensioning will be required in relation to inspections and planned maintenance. Adjustment may also be
necessary in case the mooring lines are elongated over time due to the permanent pre-loading in the
mooring lines. Permanent winches on board the pontoons are not an alternative due to the required
inspection regime related to these. The main focus for the top termination is therefore to transfer the
loading from the bridge to the mooring lines in the most proper way, and with the possibility to do minor
adjustments during installation and for maintenance.
The most obvious alternative at this stage is to use fairlead stoppers on top of the pontoons. There are
different suppliers for this type of equipment, but in this study Scana Offshore’s fairlead stopper is used
as example. The chain stoppers are designed in order to lower the out of plane bending (that can be
experienced when the chain runs through a fairlead wheel) in order to extend the fatigue life. The fairlead
stoppers are equipped with load cells that gives continuous monitoring of the mooring line loads. The
mooring chain is tensioned to the pre-defined tension using a removable hydraulic jack that are moved
between the mooring lines as required. Number of chain jacks should be optimized to make the
installation operation as effective as possible. An illustration of the concept is shown in Figure 12-5 below.
The removable hydraulic jack is shown at the left-most chain stopper.
Figure 12-5: Fairlead stopper and removable hydraulic jack from Scana Offshore. Photo: Scana Offshore.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 71/78
13 Progress plan
- Steel work
- Production of pontoons and Flua
- Groundworks and installation of Flua
- Building of stay cable bridge
- Assembly of floating bridge
- Pre-installation of permanent mooring (straight bridge)
- Installation of floating bridge
- Finalization
Figure 13-1 shows a suggested progress plan for the overall project. Several of the activities have high
flexibility in start-up time and the presented plan only shows one iteration prior to cost/time optimization.
The overall duration of the project is in this report estimated to 41,6 months (roughly 3,5 years). However,
the progress plan is currently high level and a building time of approximately 4 years is probably more
realistic.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 72/78
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 73/78
Pontoon production:
The pontoons (and the concrete part of Flua) are partly built in parallel as it is possible to complete the
structures floating (casting of top plate), see Figure 13-3. Each production cycle is assumed to last 5
months (7 months for the batch where the concrete part of Flua is cast), all batches requires 3 months in
dock. This gives a total duration of 32 months. Flua is set to be built at the beginning of the production
cycles to allow for a maximum time window for groundworks and installation. This however, may change
when more detailed planning is carried on as it may be found that it is necessary to have pontoons
available earlier to start producing and skidding the final bridge elements on to the pontoons. However,
none of this will change the overall schedule.
Assembly of bridge
The assembly of the 5 bridge sections from 20m elements is divided between two quays. Quay 1 for
assembly through skidding of section 2-5, while section 1 (incline section of the bridge) is partly
assembled (to 200m lengths) at quay 2. A heavy lift vessel (HLV) is required for the final 4 lifts (4x 200m)
in the assembly of bridge section 1. These lifts can be done as soon as bridge section 2 (which is the
connection point of section 1) and the 4x 200 m lengths of bridge section 1 are ready. Each lift is
assumed to take 1 week, which includes preparations and temporary securing.
The overall duration of the assembly operation is estimated as 26 months, in which 1 month of HLV
services are required. The lifting operations are not on a critical path, and start-up of the operation can be
adjusted to the heavy lift market situation.
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 74/78
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 75/78
14 References
/1/ NOT-GEN-017 Anslagsnotat seilingsled syd, krum bru & NOT-GEN-019 Anslagsnotat
seilingsled syd, rett bru
/2/ DNV-OS-H101 - Marine Operations, General
/3/ DNV-OS-H202 – Sea transport operations (VMO standard – Part 2-2)
/4/ E-mail from the public road administration 01.12.15 – Historically wind data for
Marstein, Bjørnafjorden and Eikelandsfjorden.
/5/ NOT-KTEKA-020 Straight Bridge_South-Summary of analyses
/6/ NOT-KTEKA-021 Curved Bridge_South-Summary of analyses
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 76/78
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
Vessel and Equipment List
Nomenclature
DP – Dynamic Positioning
ASD - Azimuth Stern Drive Tug
ATD - Azimuth Tractor Drive
AHV – Anchor Handling Vessel
AHTS – Anchor Handling Tug Supply
H – Height
R – Radius (outreach)
LC – Lifting Capacity
HLV – Heavy Lift Vessel
MLBC – Minimum Load Bearing Capacity
MBL – Minimum Breaking Load
MBF – Maximum Breaking Force
DP FFPP – Dynamically Positioned (Flexible) Fall Pipe Vessel
Vessels
Item Description
Barges
NS Barge
- DW tonnes 9.000
- LxBxH 90x27x6
- Ballast Pumps: 2 x 600 m^3/h
- Availability: > 25 in Norway (Ugland,
Boa)
UR 93
Large NS Barge
- DW tonnes > 17.000
- LxBxH > 124x31x8
- Ballast Pumps > 2 x 3.000 m^3/h
- Availability: 6 in Norway (Boa)
BOABARGE 29/30
Very Large NS Barge
- DW tonnes > 20.000
- LxBxH > 165x42x10.7
- Ballast Pumps > 2 x 3.000 m^3/h
- Availability: 2 in Europe (Heerema)
H-541/H-542 (Heerema)
Submersible barge
- DW tonnes: 30.000
- LxBxH: 152x38x9.15
- Ballast Pumps: 2 x 6.000 m^3/h
- Availability: 1 in Norway (Boa)
BOABARGE 37
Tugs
Small Tug
- ca 50 t bollard pull
- LxB ca. 30 x 10 m
- Availability > 25 in Norway (Bukser og
Berging, Boa, Østensjø)
BB Worker (ASD)
Anchor Handling Vessels (AHV)
Small HLV
- Lifting Capacity: 800-1.500 t
- Radius/Height: ca 20/70m
- Availability: 26 in Europe
Balder
Specialized Vessels
Selfunloader (Panamax)
- Cargo capacity: 75.000 m^3
- Discharge rate: 5.000 t/h
- LxB 245 x 33 m
- Bom length: 80m
- Availability in Europe >5
Boa Deep C
Drilling Barge
- For under water blasting
- Down to 35m
- Deck area: 250m^2
Trym II
Ballast Pumps
Ballast Pump 1
- Max Capacity: 2.200m^3
- Max Height: 17m
- Cap1: (1.100m^3/h, 17m)
- Cap2: (2.100m^3/h, 9m)
ALE
Ballast Pump 2
- Max Capacity: 500m^3
- Max Height: 45m
- Cap1: (125^3/h, 40m)
- Cap2: (300m^3/h, 30m)
ALE
Other Equipment
Winch 1
- 200 t WLL
- 76mm wire rope, 1830m cap
- LxBxH: 7m x 4.6m x 4.6m
- Gross Weight: 93 t
- Hydraulic
Mobile Crane
- 200t – 400t capacity
- LxBxH: 15m x 8.3m x 3.8m
-
Multi Wheeler
- Capacity: Approximately 40t per axis.
- Can be assembled by several modules
to take the required load.
Strand Jack 1
- Capacity: 300t
- No. of strands: 19
- Strands diameter: 18mm
- Weight: 2t
- Lifting speed: 7-11 m/h
- Motor size: 15-37kW
Enerpac
Strand Jack 2
- Capacity: 650t
- No. of strands: 43
- Strands diameter: 18mm
- Weight: 4t
- Lifting speed: 8-15 m/h
- Motor size: 30-55kW
Enerpac
Deck Erection Gantry 1
- For lifting of 20m bridge elements (high
bridge)
- For lifting of stay cable bridge
(cantilever method).
- Assumed must be built
- Assumed one Strand Jack 1 per crane
- Capacity per crane: 300t
Mooring System 2
- Bollard at land
- 76 mm mooring line, 200m
- Mooring wire, 300m
Mooring Lines
Mooring rope
- Used for mooring of pontoons and
abutment along quay.
- 76-90 mm diameter.
Mooring Chain
- 76/84mm diameter
- Subm. Weight: 123 kg/m
- MLBC: 7.2 MN
BarLatch (Bardex)
Chain Jacks
Chain Jack
- For tensioning of permanent mooring
system.
- Stall Load: 500 t
- MBL: 1.100 t
Mooring Wire 2
- Up to 152 mm
- 97 kg/m (152mm)
- MBL: 1.300 t
- Grade: 1508 kN/mm^2
KTL Offshore
Mooring Rope 1
- Diameter: 62 - 194 mm
- MBL: 200 – 2.000 t
- Subm. Weight: 0.03-0.28 kg/m
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
For details regarding the
differnet items, reference is
made to Appendix A
B91.1 Marine Operasjoner (Høybru)
Item Total hire days
North Sea Barge 213
Small Tug 213
Large Tug 213
Small HLV 22
B91.2 Marine Operasjoner (Flytebru)
Item Total hire days
North Sea Barge 3 020
Very Large North Sea Barge 38
Small Tug 128
Large Tug 748
Small AHV 67
Medium HLV 36
Ballast Pump 1 2 046
Winch 1 32
Skidding System 598
Hydraulic Power Unit 598
Small Mobile Crane 598
Multi Wheeler 208
Strand Jack 2 144
Deck Erection Crane 2 72
Mooring System 1 27 372
Mooring System 2 27 372
Mooring Rope 6 840
Temporary Steel 1 300 mT
B91.3 Marine Operasjoner (Flua)
Item Total hire days
North Sea Barge 578
Small Tug 34
Large Tug 97
Large AHV 10
Self ‐ unloader 8
Ballast Pump 1 38
Ballast Pump 2 38
Mooring Rope 2 100
Temporary Steel 100 mT
B91.4 Marine Operasjoner (Forankring rett bru)
Item Total hire days
North Sea Barge 18
Small Tug 18
Large AHV 18
Small HLV 18
Rock dumper (fall pipe) 6
Assumptions
Temp storage of 20m bridge elements not included
Temp storage of 4 bridge spans not included
Personnel of vessels assumed included in dayrate
Towing of abutment
Large AHV 2 1 3 3 6 Main towing vessels
Large Tug 1 1 3 3 3 Assisting towing vessel
Installation Flua
Large AHV 2 1 2 2 4 Stationkeeping of abutment
Large Tug 2 1 2 2 4 Stationkeeping of abutment
Ballast Pump 2 6 1 2 2 12 Ballasting of abutment for installation
Self ‐ unloader 1 2 4 8 8 Filling Permanent ballast
Ballast Pump 2 2 1 10 10 20 For filling of water to compensate for hydrostatic pressure
North Sea Barge 1 1 45 45 45 Transport of concrete (top plate)
Large Tug 1 1 45 45 45 Transport of concrete (top plate)
North Sea Barge 1 1 45 45 45 Transport of equipment (reinforcement, etc.)
Large Tug 1 1 45 45 45 Transport of equipment (reinforcement, etc.)
Installation of bridge girder on Flua
Small Tug 4 1 8 8 32 Installation of segment at Flua
North Sea Barge 1 1 8 8 8 Only installation
North Sea Barge 1 1 30 30 30 Temporary pontoon and installation
Ballast Pump 1 1 1 8 8 8 Ballasting of installation barge
Ballast Pump 1 1 1 30 30 30 Ballasting of temporary barge
Temporary Steel Assumed 50 t. (temporary connection) 50
B91.1 Marine Operasjoner (Høybru)
Small HLV 1 11 2 22 22 Lifting bridge elements (20m), HLV
North Sea Barge 1 12 2 24 24 Deliver bridge elements (20m), HLV lift
Large Tug 1 12 2 24 24 Deliver bridge elements (20m), HLV lift
Small Tug 1 12 2 24 24 Deliver bridge elements (20m), HLV lift
North Sea Barge 1 21 9 189 189 Deliver bridge elements (20m), Strand Jacks lift
Large Tug 1 21 9 189 189 Deliver bridge elements (20m), Strand Jacks lift
Small Tug 1 21 9 189 189 Deliver bridge elements (20m), Strand Jacks lift
B91.2 Marine Operasjoner (Flytebru)
Building of pontoons outside dock
Small Tug 2 10 1 10 20 Moving pontoons out of dock
Mooring rope 6 19 60 1140 6 840 Mooring during final building of pontoons
Towing of pontoons from building yard
Large Tug 1 19 2 38 38 Towing of pontoons (tour, detour)
Small Tug 1 19 2 38 38 Towing of pontoons (tour, detour)
Storage of pontoons
Small AHV 1 6 3 18 18 Installation of mooring, storage location (all bridge sections)
Mooring System 1 38 1 500 500 19 000 Mooring of pontoons before and after assembly of bridge sections
Mooring System 2 38 1 500 500 19 000 Mooring of pontoons before and after assembly of bridge sections
Towing of 20m bridge elements
Large Tug 1 1 568 568 568 Towing of bridge girder elements, 20m (tour, detour)
North Sea Barge 1 1 568 568 568 Towing of bridge girder elements, 20m (tour, detour)
Delivery of bridge spans for section 1
Large Tug 1 1 38 38 38 Towing and stationkeeping of bridge spans for sec 1
Small Tug 1 1 38 38 38 Towing and stationkeeping of bridge spans for sec 1
Very Large North Sea Barge 1 1 38 38 38 Towing and stationkeeping of bridge spans for sec 1
Temporary Steel 1 400 t grillage for transport (10% of weight) 400
Establishment of assembly quay
North Sea Barge 4 1 598 598 2 392 Establish temporary quay
Small AHV 1 1 3 3 3 Installation of mooring, assembly quay
Small AHV 1 2 3 6 6 Installation of mooring, assembly site (for skidded part)
Mooring System 1 6 1 598 598 3 588 Mooring of assembly quay
Mooring System 2 6 1 598 598 3 588 Mooring of assembly quay
Mooring System 1 8 1 598 598 4 784 Mooring of pontoons during assembly
Mooring System 2 8 1 598 598 4 784 Mooring of pontoons during assembly
Small Mobile Crane 1 1 598 598 598 Lifting of birdge girder elements, 20m (xx tonnes)
Skidding System 1 1 598 598 598 Skidding at assembly quay
Temporary Steel 1 Assumed 500 t for assembly period 500
Hydraulic Power Unit 1 1 598 598 598 Power supply to skidding system
Ballast Pump 1 3 1 598 598 1 794 Ballasting pontoons, assembly quay
Towing to storage location
North Sea Barge 1 3 20 60 60 Temporary support of assembled bridge sections
Ballast Pump 1 3 3 20 60 180 Ballasting pontoons after tow, section 3‐5
Large Tug 3 4 4 16 48 Towing of bridge sectios to storage location
Small Tug 2 4 4 16 32 Towing of bridge sectios to storage location
Assembly of bridge spans for Section 1
Multi Wheeler 1 1 208 208 208 Joining 20 m elements to 200 m
Assembly of Section 1
Medium HLV 1 4 9 36 36 Lifting of bridge spans for bridge section 1, HLV
Ballast Pump 1 2 4 9 36 72 Ballasting pontoons during lifting
Strand Jack 2 4 4 9 36 144 Lifting of bridge spans for bridge section 1, Crane
Deck Erection Crane 2 2 4 9 36 72 Lifting of bridge spans for bridge section 1, Crane
Temporary Steel Assumed 200 t. (50 t on each connection) 200
Installation Floating Bridge
Small AHV 7 1 4 4 28 Towing of floating bridge
Large Tug 7 1 4 4 28 Towing of floating bridge
Small AHV 3 1 4 4 12 Installation process, pos mid on floating bridge
Large Tug 7 1 4 4 28 Installation process, pos end on floating bridge
Winch 1 4 1 8 8 32 Installation winches 2 on each side
Temporary Steel 1 Assumed 200 t. (100 t each side) 200
B91.4 Marine Operasjoner (Forankring rett bru)
Straight bridge ‐Installation of mooring system at Bjørnafjorden
Large AHV 1 6 3 18 18 Assist during installation (with mooring line)
Small HLV 1 6 3 18 18 Lifting anchor to sea bed
North Sea Barge 1 6 3 18 18 Transport of anchors for installation
Small Tug 1 6 3 18 18 Transport of anchors for installation
Rock dumper (fall pipe) 1 2 3 6 6 Ballasting anchor after installation
NOT-MO-003 – METHOD STATEMENT, NAVIGATION CHANNEL IN SOUTH 78/78
K:\03 PROJECTS\0880-0001 COWI Design Bjornafjorden\02 Project Folder\Engineering\Fabrication and Installation\Marine operations\Bridge Main bridge South\Delivered report\Method statement South_maindoc.docx
Brief stability calculations are carried out for the pontoons to ensure that the stability is
sufficient in the temporary phases. No complete stability calculations are presented in
this report. For more details of the pontoon design criteria, reference is made to HYDA-
reports for the straight and curved bridge.
Part 1 of this appendix includes calculations of the metacentric height for different weight
scenarios for the final pontoon design. The different weight scenarios is as follows;
Part 2 include calculations performed for a previous study where the main bridge was
positioned in the center of Bjørnafjorden. The pontoons had different dimensions, but
indicates the stability performance of the pontoon design.
Appendix C - Part 1 – Metacentric height calculations for final pontoon design
Straight bridge stability check for temporary phases
General input:
kg
ρw 1025 Density seawater
3
m
kg
ρa 1.02
3 Density air
m
Input pontoon:
3
Δ 18300 10 kg Displacement pontoon
Δ 4 3
Vp 1.785 10 m Volume displacement pontoon
ρw
Input columns:
Hc 43 m Height columns
kg
wc 19000 Unit weight columns
m
Hc
VCG c Hp 36 m Vertical centre of gravity for column
2
B p Lp
3 4 2
Bp π B 2 1 Lp 4 Bp 5 4
I44 2 0.110 p 5.722 10 m
12 2 4 2 2 3π 2
Definition of axis and hence motions (roll / pitch) is decided based on the bridge
coordinate system.
Metacentric height for pontoon in pitch;
Only pontoons (without columns and bridge girder):
Dp
KB 5.25 m
2
KGpontoon VCG p 6.3 m
I55
BM55 5.788 m
Vp
KGcolumns
Δ VCG p wc Hc VCG c
7.569 m
Δ wc Hc
GMTcolumns KB BM55 KGcolumns 3.469 m
Stability in "pitch" including the bridge girder weight is not applicable as the pontoon will be
supported by adjacent pontoons in this direction if the bridge girder is installed.
Metacentric height for pontoon with columns and bridge girder in the
"roll" direction of pontoon:
I44
BM44 32.048 m
Vp
The stability in the longitudinal direction of pontoon (roll) is only checked with the weight
of the bridge girder. The included weight represent 200 m of bridge girder.
Hb
VCG bridge Hp Hc 60.75 m
2
KGbridge
Δ VCGp wc Hc VCGc wb Lb VCGbridge 19.618 m
Δ wc Hc wb Lb
9
C44 ρw g Vp KB KGbridge ρw g I44 3.173 10 N m Rotational stiffness in
roll for pontoon, column
and bridge
1 2 5
Fw ρa Cdb Hb Lb Vw 8.878 10 N Wind force on bridge girder
2
aw VCG bridge KGbridge 41.132 m Moment arm for wind
7
M w Fw aw 3.652 10 N m Moment from wind
The pontoon will have limited rotation from wind even when moment from towing line is included.
Appendix C - Part 2 – GZ curves for pontoons for design with main bridge in south
NOT-MO-002 MARINE OPERATIONS - METHOD STATEMENT 44/68
Further, the two towers will be mounted together to the complete high bridge
section. This section will be towed to Bjørnafjorden from the assembly location.
This is illustrated in Figure 25
The objective of the study is to ensure that the bridge installation is accomplished
with a safe and positive stability.
For the main 70t pontoon three different stages including transport and bridge
assembly have been studied in addition to a damage case. These stages and
damage case are described in Figure 26 and Table 5.
Stage Objective
The stability of the main pontoon 70t alone is sufficient during both stage 1 and 2.
The righting arm (GZ) curves for stages 1-3 and damage case can be found in
Appendix A.
The free surface moment of the ballast water in the main pontoon 70t have been
included in all calculations assuming that all compartments are slack (i.e. not
empty, and not full). This is a conservative assumption.
In order to obtain sufficient stability during stage 3 it is found that two barges must
be connected to the main pontoon 70t. Two standard North Sea barges
[L*B*D=91.44m*27.4m*6.1m] have been used in this study, and they will be
connected to the main pontoon 70t with an overlaying beam.
The stability analyses have been performed with the barges positioned with 1m
clearance between the barge and the pontoon. If larger clearance between the
barges and the pontoon is required this will increase the stability.
During stage 3 the water ballast of the main pontoon 70t is pumped out to maintain
a constant freeboard of 3m. The barges will be ballasted to a draft of 3.1m in order
to maintain a similar freeboard as the main pontoon 70t.
The worst damage case is assumed to be loss of the outermost bridge element on
one side of the bridge. Since this element has the largest distance to the bridge
centre this will generate largest heeling moment compared to other damage cases.
The loss of the outermost bridge on one side of the bridge results in an equilibrium
condition where the main pontoon 70t and barges are heeling 1.39 degrees
towards the undamaged side of the bridge when wind is included. (Dynamics are
not checked at this stage).
A preliminary overview of the different bridge weights and COG used in the stability
analysis for main pontoon 70t are shown in Table 6 when all bridge girder elements
on each side of the tower are installed.
Margin - - 19794 -
A simplified wind model have been created with Global Maritime’s in-house
software Hydwind, ref /9/. This model have been tuned to match the wind moments
provided by COWI, ref /7/ and is shown in Appendix A. The wind moments are
shown in Table 7. These wind moments are included in the calculation of the
righting arm in stage 3 and during the damage case.
Longitudinal 43323
Transverse 16004
A stability analysis for the main pontoon 50t have also been performed. The
stability is sufficient for the pontoon before and after assembly of the column
between the pontoon and the bridge road. These two conditions are shown in
Figure 27.
The main pontoon 50t shall maintain a constant freeboard of 3m before and during
assembly of the column. This requires the pontoon to be ballasted to a draft of
24m.
The righting arm curves for the main pontoon 50t before and after assembly of the
column can be found in Appendix A.
For the stability analysis, simple hydrostatic models of the main pontoons 70t, 50t
and barges have been created with Global Maritime’s in house software HydroGM
ref /8/. These models are shown in Appendix A.
4 Stability
4.1 Stability calculations and GZ-curves stage 1-3 and damage case
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 20/34
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 21/34
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 22/34
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 23/34
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 24/34
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 25/34
Below is the hydrostatic model used for the main pontoon 50t.
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 29/34
The simplified wind model is shown in the figure below seen from the front.
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 31/34
In the figure below the ballast calculations for the barges are shown.
BILAG A – PRELIMINARY CALCULATIONS FOR TEMPORARY PHASES MARINE OPERATIONS – METHOD STATEMENT . 32/34
In the figure below the ballast plan for the barges are shown.