Cost per day $ 470 $ 470 $ 200 $ 200 $ 200 $ 200 $ 270 $ 270
Cumulative Cost $ 470 $ 940 $ 1,140 $ 1,340 $ 1,540 $ 1,740 $ 2,010 $ 2,280
*Assumption: Resources are not paid double if they are working on same tasks simultaneously
Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18
Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18
$ 270
$ 200 $ 200 $ 200 $ 200 $ 200 $ 200 $ 200 $ 200 $ 200
$ 270 $ 200 $ 200 $ 200 $ 200 $ 200 $ 200 $ 200 $ 200 $ 200
$ 2,550 $ 2,750 $ 2,950 $ 3,150 $ 3,350 $ 3,550 $ 3,750 $ 3,950 $ 4,150 $ 4,350
Day 19 Day 20 Day 21 Day 22 Day 23 Day 24 Day 25 Day 26
$ 200
$ 270 $ 270
$ 200 $ 200 $ 200 $ 200 $ 200
$ 270 $ 270
$ 1,000 $ 1,000
$ 1,800
$ 1,050 $ 1,050
$ 1,000 $ 1,000
$ 1,800
$ 1,000 $ 1,000
Week 13 Week 14
$ 1,000 $ 1,000
$ 1,000 $ 1,000
$ 35,700 $ 36,700
Resource $/hour Hours/week
Ann 60 30
Becky 35 30
Clive 50 20
Activity
1.1 Operational definition Resource No of weeks Cost per activity Cost per week
1.1.1 Research literature Becky 3 $ 3,150 $ 1,050
1.1.2. Identify and define terms Ann 1 $ 1,800 $ 1,800
1.1.3. Obtain approval of definition Clive 2 $ 2,000 $ 1,000
1.2 Target selection
1.2.1 Solicit partners for pilot Ann 2 $ 3,600 $ 1,800
1.2.2 Hold brainstorming meeting Becky 2 $ 2,100 $ 1,050
1.2.3 Identify characteristics of targets Ann 1 $ 1,800 $ 1,800
1.2.4 Obtain approval of partners Clive 1 $ 1,000 $ 1,000
1.3 Question set
1.3.1 Identify process group members Clive 2 $ 2,000 $ 1,000
1.3.2 Develop question set Ann 4 $ 7,200 $ 1,800