Professional Documents
Culture Documents
F432-005-3:2019
LEVEL 3
Copyright © DSD 2019
LEVEL 3
Preface
Standard Definition
The National Occupational Skills Standard (NOSS) is a Standard document that outlines the
minimum competencies required by a skilled worker working in Malaysia for a particular
area and level of occupational, also the path to achieve the competencies. The competencies
are based on the needs of employment, according to the career structure for the occupational
area and developed by industry experts and skilled workers.
The National Competency Standard (NCS) is a Standard document that outlines the
competencies required by a skilled worker in Malaysia.
i
F432-005-
Abbreviation
i
F432-005-
Glossary
1. Diversity factor The ratio of the sum of the maximum demands of the various part
of a system to the coincident maximum demand of the whole
system.
2. Earth Conductor Earthing connection from earth terminal at distribution board to
(EC) earth electrode.
3. Green card Registration card issued by CIDB which is compulsory for all
personnel who are involved in site construction activity, detailing
the personnel's job and degree of expertise.
4. IT electrical distribution system has no connection to earth at all, or it
has only a high impedance connection.
5. Lockout-tagout Safety procedure used in industry and research settings to ensure
(LOTO) that dangerous machines are properly shut off and not able to be
started up again prior to the completion of maintenance or repair
work.
6. Maximum Total kW that contributes the total power used in one time after
Demand applying the diversity factor based on the Total Connected Load.
7. Permit to management systems used to ensure that work is done safely and
Work (PTW) efficiently. These are used in hazardous industries and involve
procedures to request, review, authorise, document and most
importantly, de-conflict tasks to be carried out by front line
workers.
8. Proof Circuit Dead Confirm testing performed with the power disconnected from
(PCD) the circuit using relevant device.
9. Protective Earthing joints or bonds of all metal parts of an installation to earth
Conductor (PC) terminal at distribution board.
10. Safety passport Passport schemes for health and safety can be a useful way for
employers to check that somebody working on their premises, or
elsewhere doing work on their behalf, has received basic health
and safety awareness training.
11. TN-C A combined protective earth neutral (PEN) conductor fulfils the
functions of both a protective earth (PE) and a neutral (N)
conductor.
12. TN-C-S Part of the system uses a combined protective earth neutral (PEN)
conductor, which is at some point split up into separate PE and N
lines.
13. TN-S PE and N are separate conductors that are connected together only
near the power source.
i
F432-005-
14. Total Connected Mechanical and electrical load (in kW) that will be connected (or
Load (TCL) to consumed) for that particular area.
15. TT Protective earth connection for the consumer is provided by a local
earth electrode.
i
F432-005-
List of Figure
List of Table
Not Available
List of Appendix
Not Available
v
F432-005-
Acknowledgement
Director General of Department of Skills Development (DSD) would like to extend his
gratitude to the National Skills Development Council (MPKK), Standard Technical
Committee (JTS), Standard Technical Evaluation Committee (JTPS), Standard Development
Committee (JPS), and organisation and individuals who have been involved directly or
indirectly for the contribution, persistence and support in the development of this Standard
until it is completed.
The Director General of DSD also would like to express his sincere thanks to the support and
involvement of En. Harris Iskandar bin Nordin as documentor for the whole session.
v
F432-005-
STANDARD PRACTICE
LEVEL 3
1 / 95
F432-005-
1. Introduction
This reviewed NOSS titled Three Phase Electrical Installation and Maintenance specify
the competencies required to perform activities within domestic, industrial and
commercial premises. This NOSS can be used by industries as a reference and guidelines
for job description, performance appraisal and personnel development. Training centres
could also employ this document as the programme curriculum for Malaysian Skills
Certificate (Level 3) named Three Phase Electrical Installation and Maintenance.
During a local conference that was held back in 2014 in Istana Hotel, Kuala Lumpur, the
invited speaker from the Energy Commission of Malaysia (EC) has shared an important
information to the participants about the statistics on competency as at December 2013.
The statistic showed the estimated number of competent persons required based on
number and type of installations are 147,270 persons and the number of competency
certificate issued are 101,240 persons. This statistic has revealed a worrying scenario
whereby there are shortage of competent person in Malaysia by 46,033 persons. Today, it
has been 5 years after the statistic is revealed and surely the requirements of competent
persons are increasing, and it is wondered if the EC has been able to meet its target.
The Three Phase Electrical Installation and Maintenance industries are multi-million
industries which involving various sectors such as oil and gas, construction,
transportation, services, consultations and energy. Most of this industry has huge
potential and impacts for significant growth as Malaysia is actively moving towards
achieving Industrial Revolution 4.0 (IR 4.0).
The Level 3 Three Phase Electrical Installation and Maintenance personnel are
responsible for the continuous operation of electrical systems. They conducted site
visit, monitoring electrical systems condition, performed maintenance and test
electrical installation. Their invaluable experience and expertise are a huge advantage
when an electrical system is to be established in any premises.
As the demand for Three Phase Electrical Installation and Maintenance continue to
grow in Malaysia, there will be a need for highly skilled and competent workforce.
The development of highly skilled and competent workers in the industry is vital to
ensure that the need of the sectors that the electrical services industry supports is met.
Future workforce must be trained and equipped with the necessary industry specific
skills that can be achieved through competency training programmes. Hence, the
reviewed of NOSS for Three Phase Electrical Installation and Maintenance is very
timely and even
2 / 95
F432-005-
indispensable as the standard will provides a basis for formal and systematic training
as well as for certifying experienced personnel.
Consensus regarding job analysis and job matrix were obtained from the panellists
where thorough discussion and debates were conducted during several reviewing
session. Among of the outcomes from the activities are a few competencies have been
re-aligned to match and meet the current demand by the industries. This includes
competencies on building automation systems, earthing systems, relevant software's
and many more. The reviewed sessions also found out that those redundant and
repeated CU which doesn't reflect to the level's definition by the Department of Skills
Development (DSD) is amended and in fact obsolete or irrelevant competencies have
been stroked out.
In brief, this NOSS has taken into account several crucial and important points such as
the introduction of future emerging competencies, the inculcation of "green" aspects,
the incorporation of health and safety measures, the fulfilment of competent person
attributes and as well as the compliance with relevant authorities and regulatory
bodies. All of this consideration is believed to have a pivotal role towards the
successfulness of this NOSS.
The Occupational Structure and Occupational Area Structure for Three Phase
Electrical Installation and Maintenance are illustrated in Figure 1 and Figure 2
respectively. Electrical installation components can be categorised into mechanical,
electrical, and electronic and instrumentation sub-groups. Three Phase Electrical
Installation and Maintenance operations include servicing of all these three sub-
groups of components. This NOSS covers the servicing of all these three categories of
components. Level 3 comprises both technical competencies to perform Three Phase
Electrical Installation and Maintenance operations and functions. The NOSS title for
Level 3 Three Phase Electrical Installation and Maintenance is as highlighted.
3 / 95
F432-005-
The minimum entry requirements for Three Phase Electrical Installation and
Maintenance (Level 2) for an accredited Training Institute are:
4 / 95
F432-005-
5 / 95
F432-005-
The NOSS is developed for various occupational areas. Below is a guideline of each
NOSS Level as defined by the Department of Skills Development, Ministry of Human
Resources, Malaysia.
6 / 95
F432-005-
5. Award of Certificate
The Director General may award, to any person upon conforming to the Standards the
following skills qualifications as stipulated under the National Skills Development Act
2006 (Act 652):
6. Occupational Competencies
The Three Phase Electrical Installation and Maintenance Level 3 personnel are competent
in performing the following core competencies:
7. Work Conditions
8. Employment Prospects
Due to the demand of Electrical supervisor in Malaysia and internationally, there is a need
for a highly skilled and competent workforce. Electrical supervisor can be employed by
electrical contractor companies, electrical services contractor companies, building
maintenance companies, factories and other companies involved in the field of electric
power requirements.
7 / 95
F432-005-
9. Up Skilling Opportunities
There are many job opportunities for Electrical Supervisor. With advanced training and
experience in specialized disciplinary priorities, they may be promoted to technical
experts in any sub-group of mechanical, electrical and / or electronic & instrumentation.
They can also conduct training in specialized equipment and electrical management.
8 / 95
F432-005-
e) Tenaga Nasional
Berhad No 129, Jalan
Bangsar 59200 Kuala
Lumpur Tel: 603 2296
5566
Website: www.tnb.com.my
9 / 95
F432-005-
10 /
F432-005-
11 /
F432-005-
LEVEL 3
12 /
F432-005-
FACILITATOR
1. Mohd Shahrol @ Shukor bin Assistant Director
Salleh Department of Skills Development
(DSD)
2. Faizal bin Abdul Majid Assistant Director
Department of Skills Development
(DSD)
13 /
F432-005-
STANDARD CONTENT
LEVEL 3
14 /
F432-005-
ELECTRICAL
THREE PHASE ELECTRICAL
BUILDING
WIRING TESTING INSTALLATION &
AUTOMATION
AND MAINTENANCE
SYSTEM
COMMISSIONING SUPERVISORY
INSTALLATION
15 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
1. Three Phase Three Phase Drawing describes the 1. Prepare three phase 1.1. Site location, logistic requirement,
Drawing competency to calculate current drawing requirements. site layout/site sketch, marking
diversity value and produce three point and authorization
F432-005- phase schematic diagram and requirement inspected and verified
3:2019-C01 layout plan. to acquire actual site information
according to technical site
The person who is competent in specification requirement.
this CU should be able to prepare 1.2. Current and voltage determined to
three phase drawing requirements, ensure exact drawing information
perform three phase drawing and according to relevant regulatory
propose three phase drawing body.
paperwork. 1.3. Current diversity value calculated
to ensure estimated load current,
The outcome of this CU is a three cable size, protection device rating
phase drawing consisting of layout and main switch rating according
plan that shows installation to diversity factor schedule.
location and a three phase 1.4. Maximum demand determined
schematic diagram that shows according to estimated load
information regarding wiring current.
installation that is required by
wireman according to MS IEC
16 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
60364, MS 1979:2007, MS 2. Perform three 2.1. Layout plan prepared to determine
1936:2006, Electricity Supply Act phase drawing. load location point, total point and
1990 (Act 447), Electricity to ensure efficient wiring work
Regulation 1994, The Electricity according to technical specification
Ordinance- Chapter 50 (Revised requirement.
2003), Electricity Rules 1999, 2.2. Final circuit distribution
Electricity (State Grid Code) Rules determined according to load
2003 and relevant regulatory body. balancing method.
2.3. Three line schematic diagram
prepared to determine cable size,
protection device rating and as a
guideline for maintenance work
according to technical specification
requirement.
17 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
The person who is competent in 1.2. Wiring tools and equipment and
this CU should be able to prepare materials prepared according to
three phase wiring requirements, project requirement.
perform three phase wiring 1.3. Location of wiring route
activities and install three phase determined according to layout
distribution board. plan.
The outcome of this CU is 2. Perform three phase 2.1. Safe working area prepared and
installation of three phase wiring wiring activities. ensured free from hazard according
with proper installation according to Occupational Safety and Health
to schematic diagram, layout plan, Act 1994 requirements.
Standard and Industrial Research 2.2. Framework materials such as
Institute of Malaysia (SIRIM) and conduit pipe, trunking, cable tray,
Energy Commission, MS IEC cable ladder, ducting, casing,
60364, MS 1979:2007, MS flexible conduit etc. installed
1936:2006, Electricity Supply Act according to site technical
1990 (Act 447), Electricity specification.
Regulation 1994, The Electricity 2.3. Wiring cable size and polarity
Ordinance- Chapter 50 (Revised confirmed according to schematic
2003), Electricity Rules 1999, plan.
Electricity (State Grid Code) Rules 2.4. Wiring cable laid to the correct
2003 and relevant regulatory body. point and marked with labelling
material according to schematic
plan requirements.
2.5. Wiring cables and accessories
terminated.
2.6. Wiring cables and accessories
connected to earthing.
18 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
2.7. Earthing location suitability
determined according to layout
plan and location condition.
2.8. Protective conductor, earth
conductor, earth electrode, earth
chamber, earthing accessories
installed to implement proper
earthing and accessories
installation according to technical
specification.
2.9. Resistance reading obtained (< 10
ohm) according to relevant code of
practice.
2.10. Wiring system continuity test and
polarity test executed to ensure safe
wiring to end user according to
relevant code of practice.
2.11. Wiring and accessories finishing
visually checked for proper
installation.
2.12. Housekeeping activities carried out
for finishing work.
2.13. Scheduled waste disposed
according to Environmental
Quality Act 1974 - ACT 127.
19 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
3. Carry out three phase 3.1. Distribution board installation
distribution board marked according to layout plan.
installation. 3.2. Distribution board installed using
conceal method or wall mounted
method according to layout plan.
3.3. Protection device such main
switch, residual current device
(RCD), miniature circuit breaker
(MCB) etc. installed on distribution
board according to schematic
diagram.
3.4. Wiring cable and earthing cable
terminated onto distribution board
according to schematic drawing.
3.5. Insulation resistance test carried
out to avoid current leakage
between phase to phase, phase to
neutral, earth to phase and earth to
neutral according to relevant code
of practice.
3.6. Housekeeping activities carried out
for finishing work.
3.7. Scheduled waste disposed
according to Environmental
Quality Act 1974 - ACT 127.
3.8. Three phase wiring and testing
work recorded and submitted to
superior.
20 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
3. Three Phase Three Phase System Maintenance 1. Prepare maintenance 1.1. Three phase maintenance
System describes the competency to work requirement. requirements such as work
Maintenance maintain three phase electrical schedule, work permit, safety
system reliability and to repair or passport and PPE prepared
F432-005- replace any faulty. according to work specification,
3:2019-C03 authorized bodies requirement and
The person who is competent in regulation requirement.
this CU should be able to prepare 1.2. Maintenance tools and equipment
maintenance work requirement, prepared according to technical
perform maintenance work and specification requirement.
prepare maintenance work report. 1.3. Location of maintenance
determined according to layout
The outcome of this CU is a plan.
maintenance work of three phase
wiring system in order to minimize 2. Perform maintenance 2.1. System functionality and condition
the downtime possible in the most work. inspected for faulty or defect
optimum operation according to according to maintenance manual
MS IEC 60364, MS 1979:2007, and operation manual
MS 1936:2006, Electricity Supply recommended by manufacturer.
Act 1990 (Act 447), Electricity 2.2. System faulty identified using
Regulation 1994, The Electricity testing tools and equipment
Ordinance- Chapter 50 (Revised according to work order.
2003), Electricity Rules 1999, 2.3. System faulty confirmed according
Electricity (State Grid Code) Rules to inspection result.
2003, Solid Waste and Public 2.4. Classification of faulty either
Cleansing Management Act 2007 minor or major determined
(Act 672) and relevant regulatory according to service
body. troubleshooting report.
21 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
2.5. Faulty rectified and tested
according to types of faulty
determined.
2.6. Troubleshooting result reported to
superior.
4. Three Phase Three Phase Motor System 1. Prepare three phase motor 1.1. Three phase motor system
Motor System Installation describes the system installation installation requirements such as
Installation competency to setup a three phase requirements. work permit, safety passport and
motor system to suit the end user PPE prepared according to work
F432-005- needs according to authority specification, authorized bodies
3:2019-C04 bodies and regulation requirement. requirement and regulation
requirement.
The person who is competent in 1.2. Motor system installation tools,
this CU should be able to prepare equipment and materials prepared
three phase motor system according to job requirement.
22 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
installation requirements, carry out 1.3. Motor system testing equipment
three phase motor installation and prepared according to testing
termination, carry out three phase procedure.
motor control installation and test 1.4. Location of motor system
three phase motor and motor installation determined according
control functionalities. to layout plan.
The outcome of this CU is 2. Carry out three phase 2.1. Safe working area prepared and
installation of a three phase motor motor installation and ensured free from hazard according
system including motor and motor termination. to Occupational Safety and Health
control to be ready for end user Act 1994 requirements.
and complied with safety standard 2.2. Motor installation location marked
requirement according to MS IEC according to layout plan.
60364, MS 1979:2007, MS 2.3. Motor installed to intended
1936:2006, Electricity Supply Act location according to layout plan
1990 (Act 447), Electricity and motor installation procedure.
Regulation 1994, The Electricity 2.4. Impedance test carried out to
Ordinance- Chapter 50 (Revised determine motor winding in good
2003), Electricity Rules 1999, condition.
Electricity (State Grid Code) Rules 2.5. Insulation resistance test carried
2003, Solid Waste and Public out to avoid current leakage
Cleansing Management Act 2007 between phase to phase and phase
(Act 672) and relevant regulatory to earth according to testing
body. procedure.
2.6. Motor termination carried out and
frame earthing cable securely
tightened according to schematic
diagram.
23 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
2.7. Scheduled waste disposed
according to Environmental
Quality Act 1974 - ACT 127.
3. Carry out three phase 3.1. Wiring cable size and polarity
motor control installation. confirmed according to motor
control circuit.
3.2. Motor control accessories installed
and fixed according to technical
specification.
3.3. Motor control circuit wired and
marked with labelling material
according to schematic diagram.
3.4. Motor control continuity test
executed to ensure circuit
functionality according to motor
control circuit.
3.5. Motor control termination carried
out and earthing cable securely
tightened according to motor
control circuit.
3.6. Housekeeping activities carried out
for finishing work.
3.7. Motor system installation work
recorded and submitted to
immediate superior.
3.8. Scheduled waste disposed
according to Environmental
Quality Act 1974 - ACT 127.
24 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
4. Test three phase motor 4.1. Motor circuit functionality test
and motor control performed to determine succession
functionalities. of wiring circuit work according
to motor circuit diagram.
4.2. On load and off load motor
performance tested and
analysed according to readings
of starting current, running
current and Rotation Per Minute
(RPM).
4.3. Test result interpreted and recorded
into logbook according to
recordkeeping procedure.
5. Three Phase Three Phase Wiring Testing and 1. Prepare three phase 1.1. Work area access permission for
Wiring Testing Commissioning describes the electrical system testing safety assurance obtained from
and competency to confirm the system and commissioning client
Commissioning is fully functional safely in requirements. 1.2. Permit to Work (PTW) obtained
accordance with as built drawing, from Competent Person (CP)
F432-005- authority bodies and regulation according to work procedure.
3:2019-C05 requirement. 1.3. System shutdown, Non-Standard
Lock (NSL), safety notice, main
The person who is competent in earthing, work area, Personal
this CU should be able to prepare Protective Equipment (PPE)
three phase electrical system information obtained from safety
testing and commissioning briefing.
requirements, perform three phase 1.4. Acceptance from Competent
electrical system testing and Person (CP) obtained.
perform three phase electrical 1.5. Testing and commissioning tools
system commissioning. and equipment prepared according
to testing procedure.
25 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
The outcome of this CU is an 2. Perform three phase 2.1 Safe working area prepared and
execution of testing and electrical system testing. ensured free from hazard according
commissioning procedure to detect to Occupational Safety and Health
any faulty in the three phase Act 1994 requirements.
electrical system according to MS 2.2 Three phase system continuity test,
IEC 60364, MS 1979:2007, MS polarity test, insulation resistance
1936:2006, Electricity Supply Act test, earthing resistance test and
1990 (Act 447), Electricity Residual Current Device (RCD)
Regulation 1994, The Electricity test executed to ensure safe
Ordinance- Chapter 50 (Revised electrical system to end user
2003), Electricity Rules 1999, according to testing procedure.
Electricity (State Grid Code) Rules 2.3 Permit to Work (PTW) closed and
2003, Solid Waste and Public returned to authorized person to
Cleansing Management Act 2007 finalize testing work.
(Act 672) and relevant regulatory
body. 3. Perform three phase 3.1. Safe working area prepared and
electrical system ensured free from hazard according
commissioning. to Occupational Safety and Health
Act 1994 requirements.
3.2. Inspection check sheet updated,
and test results compiled.
3.3. Test result compared with
acceptable range according to
electrical installation guideline.
3.4. Competent personnel endorsement
and owner acceptance obtained.
3.5. Permit to Work (PTW) closed and
returned to authorized person to
finalize commissioning work.
26 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
6. Electrical Electrical Building Automation 1. Prepare electrical BAS 1.1. Wiring schematic drawing
Building System Installation describes the installation requirement. interpreted to determine electrical
Automation installation of an automated symbols, cable size, fuse rating,
System control and monitoring system breaker rating and load.
Installation within a building. 1.2. Layout plan interpreted to
determine accessories and
F432-005- The person who is competent in Distribution Board installation
3:2019-C06 this CU should be able to prepare location.
electrical BAS installation 1.3. Site location, logistic requirement,
requirement, produce electrical site layout/site sketch, marking
BAS schematic drawing, install point and authorization
electrical BAS system, program requirement inspected and verified
electrical BAS device and perform to acquire actual site information
electrical BAS system testing and according to technical
commissioning. specification.
1.4. BAS device specification
The outcome of this CU is an determined according to wiring
installation of a smart building schematic drawing and layout
system using Building Automation plan.
System (BAS) according to 2. Produce electrical BAS 2.1. Line segment, area and several
ISO/IEC 14543-3. schematic drawing. areas arranged using BAS topology
to prevent data delay according to
ISO/IEC 14543-3.
2.2. BAS devices assigned with unique
identification address to identify
the device and describes the device
location within BAS topology.
2.3. BAS cable wiring, BAS devices
symbol and load connection drawn
27 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
according to wiring schematic
drawing and layout plan
28 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
3.9. BAS cables termination carried out
according to ISO/IEC 14543-3.
3.10. Wiring system continuity test and
polarity test executed to ensure safe
wiring to end user according to
testing procedure.
3.11. BAS termination polarity, BAS
cable continuity and permitted
BAS cable length inspected
according to installation checklist.
3.12. Scheduled waste disposed
according to Environmental
Quality Act 1974 - ACT 127.
29 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
5. Perform electrical BAS 5.1. BAS software and BAS system
system testing and connected using interface device to
commissioning. ensure connection established.
5.2. Individual address, group address,
parameter setting, and
configuration transferred to BAS
devices to execute the program.
5.3. BAS program functionality testing
and commissioning carried out to
ensure the program run reliably.
7. Electrical Electrical Installation & 1. Prepare project costing. 1.1. Consumables, tools and
Installation & Maintenance Supervisory machineries and labour cost
Maintenance describes the competency to requirement identified according
Supervisory ensure work activities are carried to job scope.
out according to Standard 1.2. Project cost calculated according
F432-005- Operating Procedure (SOP) and to Standard of Rates (SOR).
3:2019-C07 work schedule. 1.3. Project costing estimation proposed
to superior for approval.
The person who is competent in
this CU should be able to prepare 2. Supervise safety and 2.1 Regulatory body acts and
project costing, supervise safety health practice. guidelines related to working
and health practice and supervise environment quality and safety are
work progress. referred to.
2.2 Company safety and health
The outcome of this CU is an procedures interpreted.
application of effective and 2.3 Sufficient PPE prepared
efficient work supervision that will according to regulatory body
ensure execution of electrical work requirements.
comply with authority bodies and 2.4 Subordinate briefed on safety
regulation requirement. and health practises.
30 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
2.5 Safety and health practises
monitored according to company
and regulatory body requirements.
2.6 Safety and health practises reported
to related department.
31 /
F432-005-
CU TITLE & CU
CU DESCRIPTOR WORK ACTIVITIES PERFORMANCE CRITERIA
CODE
3.9. Final project report submitted to
management and filed for future
reference according to
company’s operating procedure.
32 /
F432-005-3:2019
LEVEL 3
33 /
F432-005-
34 /
F432-005-
35 /
F432-005-
36 /
F432-005-
2. Perform 2.1. Relevant 2.1. Draw layout plan. ATTITUDE 2.1. Relevant drawing guideline
three phase drawing 2.2. Determine final 2.1. Attention to details explained.
drawing. guideline. circuit distribution. when dealing with 2.2. Three phase blueprints
2.2. Three phase 2.3. Draw three line specifications and explained.
blueprints. schematic data. 2.3. Layout plan elements
2.3. Layout plan diagram. explained.
elements which SAFETY 2.4. Three line schematic
include: 2.1. Adhere to specific diagram elements explained.
Symbols. situational safety 2.5. Circuit connection technique
Loads. requirements. explained.
Accessories. 2.2. Apply safe working 2.6. Accessories fittings
Legends. culture. explained.
2.4. Three line 2.7. Building structure explained.
schematic ENVIRONMENT 2.8. Layout drawing elements
diagram Not Available. such as standard symbol,
cable size, drawing scale,
current value, sensitivity
37 /
F432-005-
38 /
F432-005-
ENVIRONMENT
Not Available.
Employability Skills
Core Abilities
Please refer NCS- Core Abilities latest edition.
39 /
F432-005-
1. Shelton, Christopher. 2006. Electrical Installation. United Kingdom: Nelson Thornes Ltd. ISBN-0748796029
2. A Manan, MD Nasir. 2007. Panduan Pendawaian Elektrik Domestik I.E.E Edisi 16 BS7671:1992 (Edisi Ketiga). Selangor, Malaysia:
ibs BUKU. ISBN-9789679501810
3. In Partnership with NJATC. 2007. Conduit Bending and Fabrication. USA: American Technical Publisher, Inc. ISBN-9780826912671
4. Hanif, Abd Samad. 2004. Pemasangan dan Penyelenggaraan Elektrik (Edisi Kedua). Kuala Lumpur, Malaysia: Dawama Sdn Bhd.
ISBN- 9836240632
5. Mullin, Ray C. 2005. Electrical Wiring Residential, Based on the 2005 National Electrical Code (15th Edition). USA: Thomson
Delmar Learning. ISBN-1401850197
40 /
F432-005-
41 /
F432-005-
42 /
F432-005-
43 /
F432-005-
44 /
F432-005-
45 /
F432-005-
46 /
F432-005-
47 /
F432-005-
3. Carry out 3.1. Types of 3.1. Mark distribution ATTITUDE 3.1. Types of electrical system
three phase electrical system board installation 3.1. Responsible in testing listed out.
distribution testing which location. handling task 3.2. Distribution board
board include: 3.2. Install distribution assigned. installation location
installation. Insulation board. 3.2. Proactive and able to marked.
resistance 3.3. Install protection anticipate and 3.3. Distribution board
test. device in overcome potential installed.
Polarity test. distribution board. problems. 3.4. Protection device installed
Continuity 3.4. Connect wiring in distribution board.
test. cable and earthing SAFETY 3.5. Wiring cable and earthing
cable onto 3.1. Apply safe working cable connected onto
distribution board. procedure. distribution board.
3.5. Execute insulation 3.6. Insulation resistance
resistance test on test executed on wiring
wiring system. system.
48 /
F432-005-
Employability Skills
Core Abilities
Please refer NCS- Core Abilities latest edition.
49 /
F432-005-
1. Shelton, Christopher. 2006. Electrical Installation. United Kingdom: Nelson Thornes Ltd. ISBN-0748796029
2. A Manan, MD Nasir. 2007. Panduan Pendawaian Elektrik Domestik I.E.E Edisi 16 BS7671:1992 (Edisi Ketiga). Selangor, Malaysia:
ibs BUKU. ISBN-9789679501810
3. In Partnership with NJATC. 2007. Conduit Bending and Fabrication. USA: American Technical Publisher, Inc. ISBN-9780826912671
4. Hanif, Abd Samad. 2004. Pemasangan dan Penyelenggaraan Elektrik (Edisi Kedua). Kuala Lumpur, Malaysia: Dawama Sdn Bhd.
ISBN- 9836240632
5. Mullin, Ray C. 2005. Electrical Wiring Residential, Based on the 2005 National Electrical Code (15th Edition). United
Kingdom: Thomson Delmar Learning. ISBN-1401850197
6. L Smith, Robert and J Herman, Stephen. 2008. Electrical Wiring Industrial, Based on the 2008 National Electrical Code (13th
Edition). United Kingdom: Delmar Cengage Learning. ISBN-9781418063986
50 /
F432-005-
51 /
F432-005-
52 /
F432-005-
2. Perform 2.1. Troubleshooting 2.1. Inspect system ATTITUDE 2.1. Troubleshooting procedure
maintenance procedure. functionality and 2.1. Responsible in explained.
work. 2.2. Maintenance condition. handling task 2.2. Maintenance technique
technique which 2.2. Execute parts assigned. explained.
include: maintenance. 2.2. Proactive and able to 2.3. Types of faulty explained.
Service. 2.3. Identify parts faulty anticipate and 2.4. Functionality test
Repair. 2.4. Rectify faulty parts. overcome potential explained.
Replace. 2.5. Utilise testing tools problems. 2.5. System functionality and
2.3. Types of faulty and equipment. condition inspected.
which include: SAFETY 2.6. Parts maintenance
Electrical 2.1. Apply safe working performed according to
fault. procedure. maintenance procedure.
Mechanical 2.7. Parts faulty identified
fault. ENVIRONMENT according to maintenance
procedure.
53 /
F432-005-
54 /
F432-005-
Employability Skills
Core Abilities
Please refer NCS- Core Abilities latest edition.
1. Sekar, Sekar. 2007. Electrical & Electronics Engineering. Selangor, Malaysia: ibs BUKU. ISBN-978967950249X
2. Balakrishnan, A and Balakrishnan, T Vasantha. 2008. Electrical Machines - 1. Selangor, Malaysia: ibs BUKU. ISBN-9789679502541
3. Keljik, Jeff. 2006. Electricity 4 AC/DC Motors, Controls and Maintenance (8th Edition). Canada: Thomson Delmar Learning.
ISBN- 9781401897239
4. Camille L. Wainwright. [et al] 2006. Science Explorer: Electricity and Magnetism. USA: Prentice Hall. ISBN-013054101X
5. Shelton, Christopher. 2006. Electrical Installation. United Kingdom: Nelson Thornes Ltd. ISBN-0748796029
6. A Manan, MD Nasir. 2007. Panduan Pendawaian Elektrik Domestik I.E.E Edisi 16 BS7671:1992 (Edisi Ketiga). Selangor, Malaysia:
ibs BUKU. ISBN-9789679501810
7. In Partnership with NJATC. 2007. Conduit Bending and Fabrication. USA: American Technical Publisher, Inc. ISBN-9780826912671
8. Hanif, Abd Samad. 2004. Pemasangan dan Penyelenggaraan Elektrik (Edisi Kedua). Kuala Lumpur, Malaysia: Dawama Sdn Bhd.
ISBN- 9836240632
9. Mullin, Ray C. 2005. Electrical Wiring Residential, Based on the 2005 National Electrical Code (15th Edition). United
Kingdom: Thomson Delmar Learning. ISBN-1401850197
10. L Smith, Robert and J Herman, Stephen. 2008. Electrical Wiring Industrial, Based on the 2008 National Electrical Code (13th
Edition). United Kingdom: Delmar Cengage Learning. ISBN-9781418063986
55 /
F432-005-
56 /
F432-005-
57 /
F432-005-
58 /
F432-005-
59 /
F432-005-
2. Carry out 2.1. Motor securing 2.1. Setup safe ATTITUDE 2.1. Motor securing factor
three phase factor: working area. 2.1. Responsible in explained.
motor Alignment. 2.2. Mark motor handling task 2.2. Motor winding resistance
installation Mounting. installation assigned. test procedure explained.
and 2.2. Motor winding location. 2.2. Thorough in 2.3. Motor insulation
termination. resistance test 2.3. Install motor. addressing work resistance test procedure
procedure. 2.4. Execute motor schedule explained.
winding resistance requirements. 2.4. Earth continuity conductor
test. (ECC) explained.
60 /
F432-005-
61 /
F432-005-
62 /
F432-005-
4. Test three 4.1. Types of dead 4.1. Execute dead ATTITUDE 4.1. Types of dead circuit
phase motor circuit testing: circuit test 4.1. Responsible in testing listed out and
and motor Insulation. (insulation, handling task explained.
control Continuity. continuity, assigned. 4.2. Motor test run explained.
functionalities. Polarity. polarity). 4.2. Thorough in 4.3. Test result analysis
4.2. Motor test run: 4.2. Execute live addressing work explained.
On load. circuit test (on schedule 4.4. Test record format/form
Off load. load and off load, requirements. explained.
Rotation rotation direction). 4.3. Proactive and able 4.5. Dead circuit test executed
direction. 4.3. Analyse test result. to anticipate and according to testing
4.3. Test result 4.4. Record test data. overcome potential procedure (insulation,
analysis: problems. continuity, polarity).
Speed - 4.6. Live circuit test executed
SAFETY according to testing
Rotation Per
4.1. Adhere to procedure (on load and off
Minute
components safety load, rotation direction).
(RPM).
standards and 4.7. Test result analysed
Current.
requirements. according to testing
Voltage.
procedure.
63 /
F432-005-
Employability Skills
Core Abilities
Please refer NCS- Core Abilities latest edition.
1. Sekar, Sekar. 2007. Electrical & Electronics Engineering. Selangor, Malaysia: ibs BUKU. ISBN-978967950249X
2. Balakrishnan, A and Balakrishnan, T Vasantha. 2008. Electrical Machines - 1. Selangor, Malaysia: ibs BUKU. ISBN-9789679502541
3. Keljik, Jeff. 2006. Electricity 4 AC/DC Motors, Controls and Maintenance (8th Edition). Canada: Thomson Delmar Learning.
ISBN- 9781401897239
4. Camille L. Wainwright. [et al] 2006. Science Explorer: Electricity and Magnetism. USA: Prentice Hall. ISBN-013054101X
5. L Smith, Robert and J Herman, Stephen. 2008. Electrical Wiring Industrial, Based on the 2008 National Electrical Code (13th
Edition). United Kingdom: Delmar Cengage Learning. ISBN-9781418063986
64 /
F432-005-
65 /
F432-005-
66 /
F432-005-
2. Perform three 2.1. Testing guideline 2.1. Prepare safe ATTITUDE 2.1. Testing guideline and
phase electrical and regulations: working area 2.1. Responsible in regulations explained.
system testing. Visual (Notice, PTW, handling task 2.2. Process to acquire notice
inspection. shutdown, LOTO, assigned. and PTW explained.
Dead circuit PCD, CME). 2.2. Proactive and able 2.3. Application on testing safety
test. 2.2. Execute to anticipate and procedure explained.
Live circuit continuity test. overcome potential 2.4. Application on various type
test. 2.3. Execute polarity problems. of testing procedure
2.2. Process to test. explained.
acquire notice 2.4. Execute SAFETY 2.5. Analysis of testing
and PTW. insulation 2.1. Apply safe working result explained.
2.3. Application on resistance test. procedure. 2.6. Safe working area prepared.
testing safety 2.5. Execute phase 2.7. Continuity test executed
procedure: sequence test. ENVIRONMENT according to test procedure.
PTW 2.6. Execute earthing 2.1. Maintain workplace 2.8. Polarity test executed
issuance. resistance test. safety, cleanliness according to test procedure.
and tidiness.
67 /
F432-005-
68 /
F432-005-
3. Perform three 3.1. Application on 3.1. Prepare safe ATTITUDE 3.1. Application on
phase electrical commissioning working area 3.1. Responsible in commissioning safety
system safety procedure (Notice, PTW, handling task procedure explained.
commissioning. which include: shutdown, LOTO, assigned. 3.2. Testing and commissioning
PTW PCD, CME). 3.2. Proactive and able checklist and report format
issuance. 3.2. Update inspection to anticipate and explained.
Power check sheet. overcome potential 3.3. Safe working area prepared
shutdown. 3.3. Compile testing problems. (Notice, PTW, shutdown,
LOTO result. LOTO, PCD, CME).
tagging. 3.4. Compare test SAFETY 3.4. Inspection check
Proof Circuit result (electrical 3.1. Apply safe working sheet updated.
Dead (PCD). installation procedure. 3.5. Testing results compiled.
guideline).
69 /
F432-005-
Employability Skills
Core Abilities
Please refer NCS- Core Abilities latest edition.
70 /
F432-005-
1. A Manan, MD Nasir. 2007. Panduan Pendawaian Elektrik Domestik I.E.E Edisi 16 BS7671:1992 (Edisi Ketiga). Selangor, Malaysia:
ibs BUKU. ISBN-9789679501810
2. In Partnership with NJATC. 2007. Conduit Bending And Fabrication. USA: American Technical Publisher, Inc. ISBN-9780826912671
3. Hanif, Abd Samad. 2004. Pemasangan dan Penyelenggaraan Elektrik (Edisi Kedua). Kuala Lumpur, Malaysia: Dawama Sdn Bhd.
ISBN- 9836240632
4. Mullin, Ray C. 2005. Electrical Wiring Residential, Based on the 2005 National Electrical Code (15th Edition). United
Kingdom: Thomson Delmar Learning. ISBN-1401850197
5. L Smith, Robert and J Herman, Stephen. 2008. Electrical Wiring Industrial, Based on the 2008 National Electrical Code (13th
Edition). United Kingdom: Delmar Cengage Learning. ISBN-9781418063986
71 /
F432-005-
72 /
F432-005-
73 /
F432-005-
2. Produce 2.1. Relevant 2.1. Interpret BAS ATTITUDE 2.1. Layout plan elements
electrical BAS drawing blueprint. 2.1. Meticulous when explained.
schematic guideline. 2.2. Plan BAS topology. dealing with 2.2. BAS schematic diagram
drawing. 2.2. BAS blueprint 2.3. Address BAS specifications and elements explained.
interpretation. device. data. 2.3. BAS topology prepared.
2.3. Layout plan 2.4. Produce electrical 2.2. Precise and neat in 2.4. BAS device address
elements which BAS schematic drawing BAS defined.
include: drawing. schematic diagram. 2.5. BAS schematic diagram
Symbols. produced.
Loads. SAFETY
Accessories. 2.1. Apply safe working
Legends. culture.
2.4. BAS schematic
diagram ENVIRONMENT
elements which 2.1. Maintain workplace
include: safety, cleanliness
Symbols and tidiness.
74 /
F432-005-
3. Install 3.1. Electrical BAS 3.1. Setup safe working ATTITUDE 3.1. Electrical BAS wiring tools
electrical BAS wiring tools area. 3.1. Ensure no wastage and equipment listed out
system. and equipment: 3.2. Determine location of cable. and explained.
Hand tools. for BAS device 3.2. Tools and equipment usage
Power tools. installation. SAFETY technique explained.
Test and 3.3. Conduct BAS 3.1. Use appropriate 3.3. Framework installation
measurement framework PPE during wiring technique listed out and
equipment. installation activities. explained.
Sundry (hacking, drilling, 3.2. Ensure safety 3.4. Cable laying procedure
items. levelling, plastering tools & equipment explained.
3.2. Tools and and painting). in proper order. 3.5. Electrical fitting and
equipment usage 3.4. Lay and mark AC termination explained.
technique. load cable. ENVIRONMENT 3.6. Types of BAS devices
3.3. Framework 3.5. Lay BAS cable. 3.1. Maintain workplace listed out and explained.
installation 3.6. Interpret BAS safety, cleanliness 3.7. BAS wiring inspection
technique: devices technical and tidiness. explained.
Conceal manual. 3.8. Safe working area set up.
wiring.
75 /
F432-005-
76 /
F432-005-
4. Perform 4.1. BAS system 4.1. Import BAS device ATTITUDE 4.1. BAS system software
electrical BAS software. database. 4.1. Ensure appropriate explained.
device 4.2. BAS devices 4.2. Create BAS project. BAS devices 4.2. BAS devices database
programming. database. 4.3. Identify device database. explained.
4.3. BAS devices functionality. 4.3. BAS devices
parameter. 4.4. Assign group SAFETY parameter explained.
4.4. BAS project: address. 4.1. Apply safe working 4.4. BAS project explained.
Building culture. 4.5. BAS device functionality
view explained.
(building ENVIRONMENT 4.6. Appropriate BAS devices
structure, 4.1. Maintain workplace database imported
BAS device). safety, cleanliness according to BAS system
Group and tidiness. software procedure.
address view
77 /
F432-005-
78 /
F432-005-
79 /
F432-005-
Employability Skills
Core Abilities
Please refer NCS- Core Abilities latest edition.
1. Herman Merz, Thomas Hansemann, Christof Hűbner (2018) Building Automation: Communication systems with EIB/KNX, LON
and BACnet Signals and Communication Tehcnology, Springer, ISBN 3319732234, 9783319732237
2. Shelton, Christopher. 2006. Electrical Installation. United Kingdom: Nelson Thornes Ltd. ISBN-0748796029
3. A Manan, MD Nasir. 2007. Panduan Pendawaian Elektrik Domestik I.E.E Edisi 16 BS7671:1992 (Edisi Ketiga). Selangor, Malaysia:
ibs BUKU. ISBN-9789679501810
4. In Partnership with NJATC. 2007. Conduit Bending And Fabrication. USA: American Technical Publisher, Inc. ISBN-9780826912671
5. Hanif, Abd Samad. 2004. Pemasangan dan Penyelenggaraan Elektrik (Edisi Kedua). Kuala Lumpur, Malaysia: Dawama Sdn Bhd.
ISBN- 9836240632
6. Mullin, Ray C. 2005. Electrical Wiring Residential, Based on the 2005 National Electrical Code (15th Edition). United
Kingdom: Thomson Delmar Learning. ISBN-1401850197
7. L Smith, Robert and J Herman, Stephen. 2008. Electrical Wiring Industrial, Based on the 2008 National Electrical Code (13th
Edition). United Kingdom: Delmar Cengage Learning. ISBN-9781418063986
80 /
F432-005-
81 /
F432-005-
82 /
F432-005-
2. Supervise 2.1. Safety and 2.1. Conduct safety and ATTITUDE 2.1. Safety and health briefing
safety and health briefing: health briefing. 2.1. Responsible in explained.
health Safety. 2.2. Convey information handling task 2.2. Personal Protective
practice. Scope of to staff. assigned. Equipment (PPE) listed out
work. 2.3. Monitor PPE usage 2.2. Proactive and able to and explained.
Standard among workers. anticipate and 2.3. Electrical Act & Regulation
Operating 2.4. Conform working overcome potential and Standard explained.
Procedure process to Standard problems. 2.4. Occupational Safety &
(SOP). Operating Procedure Health Act 514 (OSHA)
2.2. Personal (SOP). SAFETY 1994 explained.
Protective 2.1. Apply safe working 2.5. Environmental Quality Act
Equipment procedure. 1974 explained.
(PPE): 2.6. Safety and health briefing
Safety ENVIRONMENT conducted.
helmet. 2.1. Maintain workplace 2.7. PPE usage monitored.
Goggle. safety, cleanliness 2.8. Working process conformed
Ear and tidiness. with Standard Operating
plug/muff. 2.2. Scheduled waste Procedure (SOP).
disposed according
Rubber
to Environmental
glove.
Quality Act 1974 -
Safety
ACT 127.
harness.
Safety vest.
Safety boot.
83 /
F432-005-
84 /
F432-005-
3. Supervise 3.1. Briefing topic: 3.1. Conduct project ATTITUDE 3.1. Briefing topic explained.
work Scope of briefing. 3.1. Responsible in 3.2. Manpower planning
progress. work. 3.2. Convey information handling task requirement explained.
Work to staff. assigned. 3.3. Project report format
schedule. 3.3. Determine work 3.2. Proactive and able to explained.
3.2. Manpower completion date. anticipate and 3.4. Communication skill
planning 3.4. Arrange manpower overcome potential explained.
requirement: requirement. problems. 3.5. Presentation technique
Numbers of 3.5. Check work explained.
workers. performance against SAFETY 3.6. Slide preparation explained.
Worker’s work schedule. 3.1. Apply safe working 3.7. Project briefing conducted.
competency. 3.6. Compile procedure. 3.8. Manpower requirement
3.3. Project project progress arranged.
report and ENVIRONMENT 3.9. Work performance checked
format. commissioning 3.1. Maintain workplace against work schedule.
3.4. Communication report. safety, cleanliness 3.10. Progress report presented.
skill. 3.7. Recommend and tidiness.
3.5. Presentation improvement for the 3.2. Scheduled waste
technique. project disposed according
3.6. Slide 3.8. Present to Environmental
preparation. progress report.
85 /
F432-005-
Employability Skills
Core Abilities
Please refer NCS- Core Abilities latest edition.
1. Asgar, J. 2008 The Organizational Role of Supervisors. Universal Publishers. ISBN-13: 978-1-59942-969-4
2. Brette, A., Sember, W., Sember, & Sember, T.J. 2007 The Essential Supervisor's Handbook: A Quick and Handy Guide for Any
Manager or Business Owner. Career Press. ISBN: 9781564148933
3. Chek Mat. 2001.Penyeliaan Berkesan. Utusan Publications. Kuala Lumpur. ISBN -9789676111975
4. J. Maxwell Towers, 2016, Role-Playing for Supervisors: The Commonwealth and International Library: Supervisory Studies,
Elsevier, ISBN 1483159701, 9781483159706
5. Carl Heyel, 2012, The Foreman/Supervisor’s Handbook, Springer Science & Business Media, ISBN 1468465996, 9781468465990
86 /
F432-005-
KNOWLEDGE SKILL
Lecture
Demonstration
Group discussion
Simulation
E-learning, self-paced
Project
E-learning, facilitate
Scenario based training (SBT)
Case study or Problem based learning (PBL)
Role play
Self-paced learning, non-electronic
Coaching
One-on-one tutorial
Observation
Shop talk
Mentoring
Seminar
Skills training and skills assessment of trainees should be implemented in accordance with TEM requirements and actual situation.
87 /
F432-005-
LEVEL 3
* Items listed refer to TEM’s minimum requirement for skills delivery only.
88 /
F432-005-
89 /
F432-005-
90 /
F432-005-
The following table shows the percentage of training priorities based on consensus made by the Standard Development Committee (SDC).
LEVEL 3
COMPETENCY WORK
CU CODE COMPETENCY UNIT TITLE UNIT WORK ACTIVITIES ACTIVITIES
WEIGHTAGE WEIGHTAGE
1. Prepare three phase drawing
15%
requirements.
F432-005-
Three Phase Drawing 10% 2. Perform three phase drawing. 70%
3:2019-C01
3. Propose three phase drawing
15%
paperwork.
1. Prepare three phase wiring
15%
requirements.
F432-005- 2. Perform three phase wiring
Three Phase Wiring 30% 70%
3:2019-C02 activities.
3. Carry out three phase distribution
15%
board installation.
1. Prepare maintenance work
15%
F432-005- Three Phase System requirement.
10% 2. Perform maintenance work. 70%
3:2019-C03 Maintenance
3. Prepare maintenance work report. 15%
1. Prepare three phase motor system
10%
installation requirements.
F432-005- Three Phase Motor System 2. Carry out three phase motor
15% 15%
3:2019-C04 Installation installation and termination.
3. Carry out three phase motor control
60%
installation.
91 /
F432-005-
92 /
F432-005-
The following table shows the nominal training hours based on recommendations made by the Standard Development Committee (SDC).
For purpose of Malaysian Skills Certification through accredited centre training, the program duration is subject to Malaysian Skills
Certification System.
LEVEL 3
WORK ACTIVITY
TRAINING
COMPETENCY TRAINING DURATION SKILLS
CU CODE WORK ACTIVITY (HOURS) DURATION
UNIT TITLE CREDIT
KNOWLEDGE SKILLS (HOURS)
1. Prepare three phase
drawing 3 8
F432-005- requirements.
Three Phase
3:2019- 2. Perform three phase 70 7
Drawing 14 34
C01 drawing.
3. Propose three phase
3 8
drawing paperwork.
1. Prepare three phase
10 23
wiring requirements.
F432-005- 2. Perform three phase
Three Phase 46 108
3:2019- wiring activities. 220 22
Wiring
C02 3. Carry out three
phase distribution 10 23
board installation.
1. Prepare maintenance
F432-005- Three Phase 3 8
work requirement.
3:2019- System 70 7
2. Perform
C03 Maintenance 14 34
maintenance work.
93 /
F432-005-
3. Prepare maintenance
3 8
work report.
1. Prepare three phase
motor system
4 10
installation
requirements.
2. Carry out three
phase motor
F432- 6 15
Three Phase installation and
005- termination.
Motor System 140 14
3:2019-
Installation 3. Carry out three
C04
phase motor control 24 60
installation.
4. Test three phase
motor and motor
6 15
control
functionalities.
1. Prepare three phase
electrical system
testing and 2 5
commissioning
Three Phase
F432-005- requirements.
Wiring Testing
3:2019- 2. Perform three phase 70 7
and
C05 electrical system 15 34
Commissioning
testing.
3. Perform three phase
electrical system 4 10
commissioning.
Electrical 1. Prepare electrical
F432-
Building BAS installation 5 8 110 11
005-
Automation requirement.
94 /
F432-005-
3:2019- System 2.
Produce electrical
C06 Installation BAS schematic 5 8
drawing.
3. Install electrical
10 20
BAS system.
4. Perform electrical
BAS device 12 30
programming.
5. Perform electrical
BAS system testing 4 8
and commissioning.
1. Prepare project
5 9
F432- Electrical costing.
005- Installation & 2. Supervise safety and
4 9 40 4
3:2019- Maintenance health practice.
C07 Supervisory 3. Supervise work
4 9
progress.
TOTAL HOURS (CORE COMPETENCY) 216 504 720 72
TOTAL HOURS OF COMPETENCY UNIT 720
TOTAL HOURS OF CORE ABILITIES 80
TOTAL HOURS TRAINING DURATION 800
The sample calculations performed are based on table in section 18 for delivery of level 3 training program at 720 hours excluding delivery
of core abilities.
95 /