Observation Location
ABC QC notice during the daily surveillance the duct bank #4 & 7 are used for heaving 115 KV
equipment traffic. Underground cable
route
ABC QC would like to notify construction team proactively to close the duct bank for heavy traffic
or make sure the below grade level to be complied as per standard requirements ASAP
SAES-P-104 table 2.
QC Engineer
ACTION
Signature: Date :
Confirmation of Corrective Action
Note: If the issue is pertaining after providing the inspection, remainder has to be given once again (please mention as REMAINDER
in the Ref. no column) and send that copy to Project manager and Site Engineer.
Project Manager Comments: