Professional Documents
Culture Documents
50614901717
BBA(G) SEC(B) SHIFT (1)
PROJECT MANAGEMNET
ASSIGNMENT
ANSWER
Ans.1 The following points highlight the four popular techniques for
measuring risk and uncertainty in different projects. The techniques
are: 1. Risk Adjusted Discount Rate Method 2. The Certainty
Equivalent Method 3. Sensitivity Analysis 4. Probability Method.
Technique # 1. Risk Adjusted Discount Rate Method:
This method calls for adjusting the discount rate to reflect the degree
of the risk and uncertainty of the project. The risk adjusted discount
rate is based on the assumption that investors expect a higher rate of
return on risky projects as compared to less risky projects. The rate
requires determination of:
(i) Risk free rate -Risk-free rate is the rate at which the future cash
inflows should be discounted. It is the borrowing rate of the investor.
(ii) Risk premium rate -Risk premium rate is the extra return
expected by the investor over the normal rate. The adjusted discount
rate is a composite discount rate. It takes into account both time and
risk factors. In this technique, the discount rate is raised by adding a
risk margin in it while calculating the NPV of a project. For example, if
the rate of discount is 10% for the project, it may be raised to 11% by
adding 1% to take account of risks and uncertainties. The increased
discount rate will reduce the discount factor, thereby lowering the
NPV. Thus the project would be judged as undesirable. This method
is used for ranking of risky projects. But the problem with this
method is that there is no ‘specified margin’ which should be added
to the free risk rate.
Technique # 2. Hillier Model
According to this method, the estimated cash flows are reduced to a
conservative level by applying a correction factor termed as certainty
equivalent coefficient. The correction factor is the ratio of riskless
cash flow to risky cash flow.
The certainty equivalent coefficient which reflects the management’s
attitude towards risk is :
Certainty Equivalent Coefficient = Riskless Cash Flow/Risky Cash
Flow. If a project is expected to generate a cash of Rs. 40,000, the
project is risky. But the management feels that it will get at least a
cash flow of Rs. 24,000. It means that the certainty equivalent
coefficient is 0.6.
Under the certainty equivalent method, the net present value is
calculated as:
Where αt = Certainty Equivalent Coefficient
At = Expected Cash Flow for year t
I = Initial outlay on the project
i = Discount rate
Decision Rule:
The PBP can be used as a decision criterion to select investment
proposal. If the PBP is less than the maximum acceptable payback
period, accept the project. If the PBP is greater than the maximum
acceptable payback period, reject the project. This technique can be
used to compare actual pay back with a standard pay back set
up by the management in terms of the maximum period during
which the initial investment must be recovered. The standard PBP is
determined by management subjectively on the basis of a number of
factors such as the type of project, the perceived risk of the project
etc. PBP can be even used for ranking mutually exclusive projects.
The projects may be ranked according to the length of PBP and the
project with the shortest PBP will be selected.
Merits:
1. It is simple both in concept and application and easy to calculate.
2. It is a cost-effective method which does not require much of the
time of finance executives as well as the use of computers.
3. It is a method for dealing with risk. It favours projects which
generates substantial cash inflows in earlier years and discriminates
against projects which brings substantial inflows in later years. Thus
PBP method is useful in weeding out risky projects.
4. This is a method of liquidity. It emphasizes selecting a project with
the early recovery of the investment.