Satnam Global Infraprojects Limited

Project: Replacement of RG Boiler and Piping


Client: TATA Chemical Limited
PLANNING SHEET FOR SHUTDOWN

ID Task Name Duration Start Finish Predecessors


Tue Mar 22 Wed Mar 23 Thu Mar 24 Fri Mar 25 Sat Mar 26 Sun Mar 27 Mon Mar 28 Tue Mar 29 Wed Mar 30 Thu Mar 31 Fri Apr 1 Sat Apr 2 Sun Apr 3 Mon Apr 4 Tue Apr 5 Wed Apr 6 Thu Apr 7 Fri
12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8 12 4 8
1
2 Shut Down 44.88 days Tue 3/22/16 Wed 4/6/16
3 Remove refractory 72 hrs Tue 3/22/16 Fri 3/25/16
4 Locking E 207 4 hrs Tue 3/22/16 Tue 3/22/16 Fitter,Rigger[5],Helper
5 Internal removal 8 hrs Tue 3/22/16 Tue 3/22/16 Fitter,Grinder,Rigger[8],Helper
6 Marking all the cut points 6 hrs Tue 3/22/16 Tue 3/22/16 Fitter[4],Rigger[8],Helper[4]
7 Marking all ref points 4 hrs Tue 3/22/16 Tue 3/22/16 Fitter[3],Helper[3],Rigger[6]
8 Cut steam outlet 2 hrs Tue 3/22/16 Tue 3/22/16 Cutter[2],Rigger[4]
9 Remove control valve & Pipe 2 hrs Tue 3/22/16 Tue 3/22/16 8 Fitter,Helper,Rigger[5],Main Crane
10 cut & remove small pipes 10 hrs Tue 3/22/16 Tue 3/22/16 Cutter[3],Helper[2],Grinder[2],Rigger[4]
11 Placements of saddles 4 hrs Tue 3/22/16 Tue 3/22/16 Fitter[2],Helper[2],Rigger[8]
12 DHT of gas outlet 5 hrs Tue 3/22/16 Tue 3/22/16 DHT Tecnician,DHT Unit
13 cut & remove gas outlet 2 hrs Tue 3/22/16 Tue 3/22/16 12 Cutter,Rigger[3],Scaffolding
14 Cutting all risers 4 hrs Tue 3/22/16 Tue 3/22/16 6FS-2 hrs Cutter[2],Helper,Rigger[4]
15 Cut & disman all downcomers 8 hrs Tue 3/22/16 Tue 3/22/16 6FS-2 hrs Cutter[6],Helper[2],Rigger[12],Main Crane,Hydra
16 Edge preparation down comers 28 hrs Tue 3/22/16 Thu 3/24/16 15 Grinder[10],Rigger[4]
17 Fitup weld spools with down comers 40 hrs Wed 3/23/16 Thu 3/24/16 16SS+6 hrs Fitter[6],Grinder[3],Helper[15],Cutter,Rigger[12],Welder[12]
18 PWHTof Riser jts 32 hrs Wed 3/23/16 Fri 3/25/16 17SS+14 hrs DHT Unit[6],DHT Tecnician[4],Helper[6]
19 dismantling platforms 6 hrs Tue 3/22/16 Tue 3/22/16 14 Cutter[4],Helper[2],Rigger[8],Main Crane,Hydra
20 Remove Steam drum 6 hrs Tue 3/22/16 Wed 3/23/16 15,14 Rigger[10],Main Crane
21 Edge preparation risers 12 hrs Wed 3/23/16 Wed 3/23/16 20 Grinder[8]
22 DHT of RGB1 12 hrs Fri 3/25/16 Fri 3/25/16 3,6 DHT Tecnician,DHT Unit
23 Cut RGB1 8 hrs Fri 3/25/16 Sat 3/26/16 22 Cutter,Rigger[3],Main Crane
24 DHT of RGB2 12 hrs Tue 3/22/16 Wed 3/23/16 5,4 DHT Tecnician,DHT Unit
25 Cut RGB2 6 hrs Fri 3/25/16 Fri 3/25/16 3,24 Cutter,Rigger
26 Remove RG Boiler 4 hrs Sat 3/26/16 Sat 3/26/16 23,22,3,25 Rigger[12],Main Crane
27 Edge preparation RGB1 30 hrs Sat 3/26/16 Sun 3/27/16 26 Grinder[2],Rigger[3]
28 Edge preparation RGB2 16 hrs Sat 3/26/16 Sun 3/27/16 26 Grinder[2],Rigger[2]
29 Erec RG boiler align & fit-up RGB1 8 hrs Sun 3/27/16 Mon 3/28/16 27FS+2 hrs Fitter[2],Helper[2],Grinder,Rigger[12]
30 Preheat & 1/2 weld RGB1 28 hrs Mon 3/28/16 Tue 3/29/16 29FS+2 hrs DHT Tecnician,DHT Unit,Welder[2],Helper[2]
31 RT of RGB1 2 hrs Tue 3/29/16 Tue 3/29/16 30FS+3 hrs
32 Full weld RGB1 20 hrs Tue 3/29/16 Wed 3/30/16 31 DHT Unit,DHT Tecnician,Welder[2],Helper[2]
33 Fix & weld refractory anchors 4 hrs Wed 3/30/16 Wed 3/30/16 32FS+1 hr Fitter,Helper,Welder
34 Fitup of RGB2 4 hrs Tue 3/29/16 Tue 3/29/16 30 Fitter,Helper,Grinder,Rigger[4]
35 Preheat & 1/2 weld RGB2 16 hrs Tue 3/29/16 Wed 3/30/16 34 DHT Unit,DHT Tecnician,Welder[2],Helper[2]
36 PWHT of RGB1 16 hrs Wed 3/30/16 Thu 3/31/16 32FS+2 hrs DHT Unit,DHT Tecnician
37 Refractory Application 72 hrs Thu 3/31/16 Sun 4/3/16 36FS+3 hrs
38 RT of RGB2 2 hrs Wed 3/30/16 Wed 3/30/16 35FS+3 hrs
39 Full weld RGB2 12 hrs Wed 3/30/16 Wed 3/30/16 38 DHT Unit,DHT Tecnician,Welder[2],Helper[2]
40 PWHT RGB2 16 hrs Wed 3/30/16 Thu 3/31/16 39 DHT Unit,DHT Tecnician
41 Internal Fitup 36 hrs Thu 3/31/16 Sat 4/2/16 40FS+2 hrs Fitter[2],Helper[2],Grinder,Rigger[5]
42 Gas outlet fitup 4 hrs Wed 3/30/16 Wed 3/30/16 32 Fitter,Helper,Rigger[5]
43 Erec steam drum 6 hrs Thu 3/31/16 Thu 3/31/16 36 Fitter[2],Rigger[12],Helper[2]
44 Fitup riser 6 hrs Thu 3/31/16 Thu 3/31/16 43FS-2 hrs Fitter[2],Helper[2],Rigger[6]
45 Fitup down comers 32 hrs Thu 3/31/16 Fri 4/1/16 36 Fitter[6],Helper[6],Grinder[4],Rigger[18]
46 Gas outlet welding 14 hrs Wed 3/30/16 Thu 3/31/16 42,32 Welder[2],Helper[2]
47 RT of above 4 hrs Thu 3/31/16 Thu 3/31/16 46FS+3 hrs
48 Gas outlet PWHT 16 hrs Thu 3/31/16 Fri 4/1/16 47FS+2 hrs DHT Unit,DHT Tecnician
49 1/2 weldof risers 26 hrs Thu 3/31/16 Fri 4/1/16 44 Welder[4],Helper[4]
50 1/2weld of down comers 46 hrs Fri 4/1/16 Sun 4/3/16 45 Welder[10],Helper[10]
51 RT of riser jts 6 hrs Fri 4/1/16 Fri 4/1/16 49
52 RT of down comers jts 16 hrs Sat 4/2/16 Sun 4/3/16 50FS-10 hrs
53 Full weld risers 24 hrs Fri 4/1/16 Sat 4/2/16 51
54 Full weld down comers 40 hrs Sun 4/3/16 Tue 4/5/16 52
55 PWHT of Risers 40 hrs Sat 4/2/16 Mon 4/4/16 53FS-8 hrs DHT Unit[5],DHT Tecnician[5]
56 PWHT of Down comers 50 hrs Mon 4/4/16 Wed 4/6/16 54FS-28 hrs DHT Unit[6],DHT Tecnician[3]
57 Fixing platforms 12 hrs Thu 3/31/16 Fri 4/1/16 44FS+6 hrs Fitter,Helper,Rigger,Main Crane
58 Steam inlet line fitup 6 hrs Fri 4/1/16 Fri 4/1/16 49 Fitter[2],Helper[2],Rigger[6]
59 1/2weld of above 8 hrs Fri 4/1/16 Sat 4/2/16 58 Welder[4],Helper[4],DHT Unit[2],DHT Tecnician
60 RT of above 10 hrs Sat 4/2/16 Sat 4/2/16 59FS+2 hrs
61 Full weld of above 8 hrs Sat 4/2/16 Sun 4/3/16 60FS+3 hrs Welder[4],Helper[4],DHT Unit[2],DHT Tecnician
62 PWHT of above 14 hrs Sun 4/3/16 Sun 4/3/16 61 DHT Unit[2],DHT Tecnician
63 Control valve fixing 4 hrs Sun 4/3/16 Sun 4/3/16 61FS+2 hrs Fitter,Helper,Rigger[4]
64 Fitup & welding small pipings 40 hrs Fri 4/1/16 Sun 4/3/16 49,45 Fitter[4],Helper[4],Welder[4],Rigger[12]
65 Removal of scraps 4 hrs Wed 4/6/16 Wed 4/6/16 56 Helper[6],Rigger[10]

Project: MSProj11 Task Progress Summary External Tasks Deadline


Date: Tue 2/9/16
Split Milestone Project Summary External Milestone