COAL RUNOFF REMAINING WORK TO COMPLETE PRIOR FOR SUSPENSION

S/N Description Target Date Remarks


1 A1 RAMP & EMBANKMENT
a) Road base course + CBR test Done
b) Ramp sheet stop / key trench cutting (10 nos) 17-Apr
c) Install PM+GCL+HDPE embankment to pond connection 22-Apr
d) HDPE welding joint 22-Apr
e) Sheet stop / key trench concreting @ embankment & ramp 22-Apr
f) HDPE test (pressure, vaccum & spark test) 22-Apr

2 A3 & B1 EMBANKMENT & POND


a) Installation of GCL + HDPE in pond & embankment 17-Apr in progress
b) HDPE welding joint 20-Apr
c) Sheet stop / key trench concreting @ embankment 17-Apr
d) HDPE test (pressure, vaccum & spark test) 20-Apr

3 POND AROUND A1 / C1 / B2
a) Joint surface preparation prior for welding joint 17-Apr
b) HDPE welding joint between existing and new 17-Apr
c) HDPE test (pressure, vaccum & spark test) 17-Apr

4 PUMP PIT
a) Pump pit inside cleaning prior for water proofing work (by Acset) Done
b) Scaffolding dismantling (by Acset) Done
c) Temporary shed and scaffolding platform erection (by Murinda) 15-Apr
d) Water proofing work (by Murinda) 30-Apr
e) Excavation & installation of precast pipe support (by SSP) 15-Apr in progress
f) Excavation & install road crossing pipe (by SSP) A
g) Concreting pipe encasement (by SSP) A

5 PARTIAL MCC WALKDOWN


a) Embankment A1 & A2 / Pond E & F 06-Apr Done
Punch Clearing 15-Apr
b) Embankment A3 / Pond G & K 11-Apr Done
Punch Clearing 20-Apr
c) Embankment A1, C1, B2 / Pond A & B 18-Apr
Punch Clearing 25-Apr
d) Embankment B1 & B2 / Pond I & J A
Punch Clearing A * A - Work resume after suspension
e) Embankment B1 & A3 / Pond L
A
Embankment A1 / Pond C & D
Punch Clearing A