You are on page 1of 11

1 2 3 4 5 6 7 8 9

SITE IMPROVEMENTS LEGEND


150 PROPOSED MAJOR CONTOUR

BIRDSBORO POWER PROJECT


149 PROPOSED MINOR CONTOUR
CENTERLINE
CHAIN LINK FENCE
LIMITS OF GRADING A
DIRECTION OF FLOW
X 155.50 PROPOSED SPOT ELEVATION
SWALE OR DITCH FLOWLINE
CULVERT
INTEGRAL CURB & GUTTER (SPILL)

INTEGRAL CURB & GUTTER


BIRDSBORO, PENNSYLVANIA
AGGREGATE BASE COURSE

AGGREGATE SURFACE COURSE

RIPRAP
EROSION AND SEDIMENT CONTROL PLAN B

ASPHALT PAVEMENT
DRAWING INDEX
CONCRETE PAVEMENT 20019983-CE-001 EROSION & SEDIMENT CONTROL PLAN COVER SHEET
20019983-CE-002 EROSION & SEDIMENT CONTROL PLAN GENERAL NOTES
SOIL 20019983-CE-003 SENSITIVE NATURAL RESOURCE PLAN
20019983-CE-004 PHASE 1 - DEMOLITION/DDC GROUND IMPROVEMENTS
20019983-CE-005 PHASE 2 - MASS EXCAVATIONS
DEMOLISH EXISTING FEATURE 20019983-CE-006 PHASE 3 - MASS EMBANKMENT, UTILITY, AND FOUNDATION
20019983-CE-007 EROSION & SEDIMENT CONTROL PLAN DETAILS
20019983-CE-008 EROSION & SEDIMENT CONTROL PLAN DETAILS
DETECTABLE DOMES IN 20019983-CE-009 EROSION & SEDIMENT CONTROL PLAN DETAILS
SIDEWALK ADA RAMP 20019983-CE-010 EROSION & SEDIMENT CONTROL PLAN DETAILS
20019983-CE-011 EROSION & SEDIMENT CONTROL PLAN DETAILS
GRASS
L1 C1 ROAD ALIGNMENT TANGENT/ C
CURVE SEGMENTS 1
UNION TOWNSHIP/BIRDSBORO BOUNDARY LINE
PROTECTED/CONSERVED RIPARIAN BUFFER AREA
NPDES PERMIT BOUNDARY NPDES PERMIT BOUNDARY

SOIL TYPE BOUNDARY LINE (TYP) PROJECT LOCATION


LIMIT OF DISTURBANCE (LOD)
EROSION CONTROL BLANKET
DRAINAGE BOUNDARY
COMPOST FILTER SOCK D
SILT FENCE
UPDATED LEGEND
1
EXISTING CONDITIONS LEGEND M. DREHER
ISSUED FOR CONSTRUCTION
M. DREHER J. GREEN 03-01-17

0
M. DREHER M. DREHER J. GREEN 01-20-17
150 EXISTING MAJOR CONTOUR REV DESIGN BY DRAWN BY CHECKED BY DATE
149 EXISTING MINOR CONTOUR
CHAIN LINK FENCE VICINITY MAP
OVERHEAD ELECTRIC USGS 7.5 MIN TOPOGRAPHIC QUADRANGLE KIEWIT POWER CONSTRUCTORS CO.
BIRDSBORO PENNSYLVANIA (2013)
BUSH/TREE LINE NTS
WATER LINE
UNDERGROUND ELECTRIC UTILITY CONTACTS BIRDSBORO POWER LLC
UNDERGROUND TELEPHONE SERIAL NUMBER 20150470504 & 20150470505 AT THE FOLLOWING LOCATION:
LIGHT POLE COUNTY: BERKS PROJECT OWNER E
CONDUIT OR PIPE RISER MUNICIPALITY: BIRDSBORO BOROUGH BIRDSBORO POWER, LLC
POWER POLE ADDRESS: ARMORCAST ROAD
P
NEAREST INTERSECTION: NORTH FURNANCE STREET AND ARMORCAST ROAD BIRDSBORO POWER PROJECT
GUY WIRE SECOND INTERSECTION: NORTH FURNANCE STREET AND EAST MAIN STREET
UNKNOWN MANHOLE LOCATION INFORMATION: THE PROJECT INVOLVES CONSTRUCTION OF NATURAL
M
GAS COMBINE CYCLE PLANT APPROXIMATELY ON 90 ACRES
E ELECTRIC MANHOLE
HAS BEEN RESPONDED TO THROUGH PENNSYLVANIA ONE CALL SYSTEM BY THESE FACILITY
PROJECT ENGINEER
FIRE HYDRANT OPERATORS IN THE FOLLOWING MANNER: KIEWIT ENGINEERING GROUP INC
UNKNOWN PEDESTAL 9401 RENNER BLVD.
SURVEY CONTROL POINT UTILITY RESPONSE: LENEXA, KANSAS 66219
UGI UTILITIES INC PHONE: 913.928.7000
SURVEY CONTROL POINT WITH BOLLARDS PA ONE CALL REQUIRED PRIOR TO EXCAVATION, GAS
T TRANSFORMER SERVICE LINES MIGHT BE PRESENT, CONTACT: KIEWIT ENGINEERING GROUP INC.
9401 Renner Boulevard
BUSH MARY GALCZYNSKI Lenexa, Kansas 66219 Digitally signed by James J.
OPERATIONS Green, Jr.

CONIFEROUS TREE UGI UTILITIES INC Reason: I am approving this


document

HH UTILITY HAND HOLE (610) 736-5609 Date: 2018.02.05 12:12:08-06'00'

W
WATER VALVE WINDSTREAM COMMUNICATION F
MAPPING RECEIVED, SOME OVERHEAD POWER LINES PRESENT, CONTACT: EROSION & SEDIMENT CONTROL PLAN
POST LAKISHA JOHNSON COVER SHEET
GATE DAMAGE PREVENTION ENGINEER
DECIDUOUS TREE (570) 748-4433 ENGINEER/DESIGN DRAWING NUMBER
ORIGINATOR M. DREHER
BENCHMARK (PLEASE CALL 1-800-222-6470 TO HEAR NAY VOICE MESSAGE) LEAD ENG J. GREEN
U MONITORING WELLS ENG MGR N. STEWART 20019983-CE-001
CORRUGATED PLASTIC PIPE PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

EROSION & SEDIMENT PLAN NOTES EROSION & SEDIMENT PLAN NOTES (CONTINUED) EROSION & SEDIMENT PLAN NOTES (CONTINUED)
1. ALL EARTH DISTURBANCES, INCLUDING CLEARING AND GRUBBING AS WELL AS CUTS AND FILLS 15. UNTIL THE SITE IS STABILIZED, ALL EROSION AND SEDIMENT BMPS SHALL BE MAINTAINED 34. CONCRETE WASH WATER SHALL BE HANDLED IN THE MANNER DESCRIBED ON THE PLAN
SHALL BE DONE IN ACCORDANCE WITH THE APPROVED E&S PLAN. A COPY OF THE APPROVED PROPERLY. MAINTENANCE SHALL INCLUDE INSPECTIONS OF ALL EROSION AND SEDIMENT DRAWINGS. IN NO CASE SHALL IT BE ALLOWED TO ENTER ANY SURFACE WATERS OR
DRAWINGS (STAMPED, SIGNEDAND DATED BY THE REVIEWING AGENCY) MUST BE BMPS AFTER EACH RUNOFF EVENT AND ON A WEEKLY BASIS. ALL PREVENTATIVE AND GROUNDWATER SYSTEMS.
AVAILABLE AT THE PROJECT SITE AT ALL TIMES. THE REVIEWING AGENCY SHALL BE NOTIFIED REMEDIAL MAINTENANCE WORK, INCLUDING CLEAN OUT, REPAIR, REPLACEMENT,
OF ANY CHANGES TO THE APPROVED PLAN PRIOR TO IMPLEMENTATION OF THOSE CHANGES. REGRADING, RESEEDING, REMULCHING AND RENETTING MUST BE PERFORMED 35. ALL CHANNELS SHALL BE KEPT FREE OF OBSTRUCTIONS INCLUDING BUT NOT LIMITED TO FILL,
THE REVIEWING AGENCY MAY REQUIRE A WRITTEN SUBMITTAL OF THOSE CHANGES FOR IMMEDIATELY. IF THE E&S BMPS FAIL TO PERFORM AS EXPECTED, REPLACEMENT BMPS, OR ROCKS, LEAVES, WOODY DEBRIS, ACCUMULATED SEDIMENT, EXCESS VEGETATION, AND A
REVIEW AND APPROVAL AT ITS DISCRETION. MODIFICATIONS OF THOSE INSTALLED WILL BE REQUIRED. CONSTRUCTION MATERIAL/WASTES.
2. AT LEAST 7 DAYS PRIOR TO STARTING ANY EARTH DISTURBANCE ACTIVITIES, INCLUDING 16. A LOG SHOWING DATES THAT E&S BMPS WERE INSPECTED AS WELL AS ANY DEFICIENCIES 36. UNDERGROUND UTILITIES CUTTING THROUGH ANY ACTIVE CHANNEL SHALL BE IMMEDIATELY
CLEARING AND GRUBBING, THE OWNER AND/OR OPERATOR SHALL INVITE ALL CONTRACTORS, FOUND AND THE DATE THEY WERE CORRECTED SHALL BE MAINTAINED ON THE SITE AND BE BACKFILLED AND THE CHANNEL RESTORED TO ITS ORIGINAL CROSS-SECTION AND PROTECTIVE
THE LANDOWNER, APPROPRIATE MUNICIPAL OFFICIALS, THE E&S PLAN PREPARER, THE PCSM MADE AVAILABLE TO REGULATORY AGENCY OFFICIALS AT THE TIME OF INSPECTION. LINING. ANY BASE FLOW WITHIN THE CHANNEL SHALL BE CONVEYED PAST THE WORK AREA
PLAN PREPARER, THE LICENSED PROFESSIONAL RESPONSIBLE FOR OVERSIGHT OF CRITICAL IN THE MANNER DESCRIBED IN THIS PLAN UNTIL SUCH RESTORATION IS COMPLETE.
STAGES OF IMPLEMENTATION OF THE PCSM PLAN, AND A REPRESENTATIVE FROM THE LOCAL 17. SEDIMENT TRACKED ONTO ANY PUBLIC ROADWAY OR SIDEWALK SHALL BE RETURNED TO THE
CONSERVATION DISTRICT TO AN ON-SITE PRECONSTRUCTION MEETING. CONSTRUCTION SITE BY THE END OF EACH WORK DAY AND DISPOSED IN THE MANNER 37. CHANNELS HAVING RIPRAP, RENO MATTRESS, OR GABION LININGS MUST BE SUFFICIENTLY
DESCRIBED IN THIS PLAN. IN NO CASE SHALL THE SEDIMENT BE WASHED, SHOVELED, OR OVER-EXCAVATED SO THAT THE DESIGN DIMENSIONS WILL BE PROVIDED AFTER PLACEMENT
3. AT LEAST 3 DAYS PRIOR TO STARTING ANY EARTH DISTURBANCE ACTIVITIES, OR EXPANDING SWEPT INTO ANY ROADSIDE DITCH, STORM SEWER, OR SURFACE WATER. OF THE PROTECTIVE LINING.
INTO AN AREA PREVIOUSLY UNMARKED, THE PENNSYLVANIA ONE CALL SYSTEM INC. SHALL BE
NOTIFIED AT 1-800-242-1776 FOR THE LOCATION OF EXISTING UNDERGROUND UTILITIES. 18. ALL SEDIMENT REMOVED FROM BMPS SHALL BE DISPOSED OF IN THE MANNER DESCRIBED ON 38. SEDIMENT BASINS AND/OR TRAPS SHALL BE KEPT FREE OF ALL CONSTRUCTION WASTE, WASH
THE PLAN DRAWINGS. WATER, AND OTHER DEBRIS HAVING POTENTIAL TO CLOG THE BASIN/TRAP OUTLET
4. ALL EARTH DISTURBANCE ACTIVITIES SHALL PROCEED IN ACCORDANCE WITH THE SEQUENCE STRUCTURES AND/OR POLLUTE THE SURFACE WATERS.
PROVIDED ON THE PLAN DRAWINGS. DEVIATION FROM THAT SEQUENCE MUST BE APPROVED 19. AREAS WHICH ARE TO BE TOPSOILED SHALL BE SCARIFIED TO A MINIMUM DEPTH OF 3 TO 5
IN WRITING FROM THE LOCAL CONSERVATION DISTRICT OR BY THE DEPARTMENT PRIOR TO INCHES — 6 TO 12 INCHES ON COMPACTED SOILS — PRIOR TO PLACEMENT OF TOPSOIL. 39. SEDIMENT BASINS SHALL BE PROTECTED FROM UNAUTHORIZED ACTS BY THIRD PARTIES.
IMPLEMENTATION. AREAS TO BE VEGETATED SHALL HAVE A MINIMUM 4 INCHES OF TOPSOIL IN PLACE PRIOR TO
SEEDING AND MULCHING. FILL OUTSLOPES SHALL HAVE A MINIMUM OF 2 INCHES OF 40. ANY DAMAGE THAT OCCURS IN WHOLE OR IN PART AS A RESULT OF BASIN OR TRAP
5. AREAS TO BE FILLED ARE TO BE CLEARED, GRUBBED, AND STRIPPED OF TOPSOIL TO REMOVE TOPSOIL. DISCHARGE SHALL BE IMMEDIATELY REPAIRED BY THE PERMITTEE IN A PERMANENT MANNER
TREES, VEGETATION, ROOTS AND OTHER OBJECTIONABLE MATERIAL. SATISFACTORY TO THE MUNICIPALITY, LOCAL CONSERVATION DISTRICT, AND THE OWNER OF B
20. ALL FILLS SHALL BE COMPACTED AS REQUIRED TO REDUCE EROSION, SLIPPAGE, SETTLEMENT, THE DAMAGED PROPERTY.
6. CLEARING, GRUBBING, AND TOPSOIL STRIPPING SHALL BE LIMITED TO THOSE AREAS SUBSIDENCE OR OTHER RELATED PROBLEMS. FILL INTENDED TO SUPPORT BUILDINGS,
DESCRIBED IN EACH STAGE OF THE CONSTRUCTION SEQUENCE. GENERAL SITE CLEARING, STRUCTURES AND CONDUITS, ETC. SHALL BE COMPACTED IN ACCORDANCE WITH LOCAL 41. UPON REQUEST, THE APPLICANT OR HIS CONTRACTOR SHALL PROVIDE AN AS-BUILT (RECORD
GRUBBING AND TOPSOIL STRIPPING MAY NOT COMMENCE IN ANY STAGE OR PHASE OF THE REQUIREMENTS OR CODES. DRAWING) FOR ANY SEDIMENT BASIN OR TRAP TO THE MUNICIPAL INSPECTOR, LOCAL
PROJECT UNTIL THE E&S BMPS SPECIFIED BY THE BMP SEQUENCE FOR THAT STAGE OR PHASE CONSERVATION DISTRICT OR THE DEPARTMENT.
HAVE BEEN INSTALLED AND ARE FUNCTIONING AS DESCRIBED IN THIS E&S PLAN. 21. ALL EARTHEN FILLS SHALL BE PLACED IN COMPACTED LAYERS NOT TO EXCEED 9 INCHES IN
THICKNESS. 42. EROSION CONTROL BLANKETING SHALL BE INSTALLED ON ALL SLOPES 3H:1V OR STEEPER
7. AT NO TIME SHALL CONSTRUCTION VEHICLES BE ALLOWED TO ENTER AREAS OUTSIDE THE WITHIN 50 FEET OF A SURFACE WATER AND ON ALL OTHER DISTURBED AREAS SPECIFIED ON
LIMIT OF DISTURBANCE BOUNDARIES SHOWN ON THE PLAN MAPS. THESE AREAS MUST BE 22. FILL MATERIALS SHALL BE FREE OF FROZEN PARTICLES, BRUSH, ROOTS, SOD, OR OTHER THE PLAN MAPS AND/OR DETAIL SHEETS.
CLEARLY MARKED AND FENCED OFF BEFORE CLEARING AND GRUBBING OPERATIONS BEGIN. FOREIGN OR OBJECTIONABLE MATERIALS THAT WOULD INTERFERE WITH OR PREVENT
CONSTRUCTION OF SATISFACTORY FILLS. 43. FILL MATERIAL FOR EMBANKMENTS SHALL BE FREE OF ROOTS, OR OTHER WOODY
8. TOPSOIL REQUIRED FOR THE ESTABLISHMENT OF VEGETATION SHALL BE STOCKPILED AT THE VEGETATION, ORGANIC MATERIAL, LARGE STONES, AND OTHER OBJECTIONABLE MATERIALS.
LOCATION(S) SHOWN ON THE PLAN MAPS(S) IN THE AMOUNT NECESSARY TO COMPLETE THE 23. FROZEN MATERIALS OR SOFT, MUCKY, OR HIGHLY COMPRESSIBLE MATERIALS SHALL NOT BE THE EMBANKMENT SHALL BE COMPACTED IN MAXIMUM 8" LAYERED LIFTS AT 90% DENSITY.
FINISH GRADING OF ALL EXPOSED AREAS THAT ARE TO BE STABILIZED BY VEGETATION. EACH INCORPORATED INTO FILLS.
STOCKPILE SHALL BE PROTECTED IN THE MANNER SHOWN ON THE PLAN DRAWINGS.
STOCKPILE HEIGHTS SHALL NOT EXCEED 35 FEET. STOCKPILE SLOPES SHALL BE 2H:1V OR 24. FILL SHALL NOT BE PLACED ON SATURATED OR FROZEN SURFACES.
FLATTER.
25. SEEPS OR SPRINGS ENCOUNTERED DURING CONSTRUCTION SHALL BE HANDLED IN 1
9. IMMEDIATELY UPON DISCOVERING UNFORESEEN CIRCUMSTANCES POSING THE POTENTIAL ACCORDANCE WITH THE STANDARD AND SPECIFICATION FOR SUBSURFACE DRAIN OR OTHER
FOR ACCELERATED EROSION AND/OR SEDIMENT POLLUTION, THE OPERATOR SHALL APPROVED METHOD. C
IMPLEMENT APPROPRIATE BEST MANAGEMENT PRACTICES TO MINIMIZE THE POTENTIAL FOR
EROSION AND SEDIMENT POLLUTION AND NOTIFY THE LOCAL CONSERVATION DISTRICT 26. ALL GRADED AREAS SHALL BE PERMANENTLY STABILIZED IMMEDIATELY UPON REACHING
AND/OR THE REGIONAL OFFICE OF THE DEPARTMENT. FINISHED GRADE. CUT SLOPES IN COMPETENT BEDROCK AND ROCK FILLS NEED NOT BE
VEGETATED. SEEDED AREAS WITHIN 50 FEET OF A SURFACE WATER, OR AS OTHERWISE
10. ALL BUILDING MATERIALS AND WASTES SHALL BE REMOVED FROM THE SITE AND RECYCLED SHOWN ON THE PLAN DRAWINGS, SHALL BE BLANKETED ACCORDING TO THE STANDARDS OF
OR DISPOSED OF IN ACCORDANCE WITH THE DEPARTMENT’S SOLID WASTE MANAGEMENT THIS PLAN.
REGULATIONS AT 25 PA. CODE 260.1 ET. SEQ. 271.1, AND 287.1 ET. SEQ. NO BUILDING
MATERIALS OR WASTES OR UNUSED BUILDING MATERIALS SHALL BE BURNED, BURIED, 27. IMMEDIATELY AFTER EARTH DISTURBANCE ACTIVITIES CEASE IN ANY AREA OR SUBAREA OF
DUMPED, OR DISCHARGED AT THE SITE. THE PROJECT, THE OPERATOR SHALL STABILIZE ALL DISTURBED AREAS. DURING
NON-GERMINATING MONTHS, MULCH OR PROTECTIVE BLANKETING SHALL BE APPLIED AS
11. ALL OFF-SITE WASTE AND BORROW AREAS MUST HAVE AN E&S PLAN APPROVED BY THE DESCRIBED IN THE PLAN. AREAS NOT AT FINISHED GRADE, WHICH WILL BE REACTIVATED
LOCAL CONSERVATION DISTRICT OR THE DEPARTMENT FULLY IMPLEMENTED PRIOR TO BEING WITHIN 1 YEAR, MAY BE STABILIZED IN ACCORDANCE WITH THE TEMPORARY STABILIZATION
ACTIVATED. SPECIFICATIONS. THOSE AREAS WHICH WILL NOT BE REACTIVATED WITHIN 1 YEAR SHALL BE
STABILIZED IN ACCORDANCE WITH THE PERMANENT STABILIZATION SPECIFICATIONS.
12. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ANY MATERIAL BROUGHT ON SITE IS
CLEAN FILL. FORM FP-001 MUST BE RETAINED BY THE PROPERTY OWNER FOR ANY FILL 28. PERMANENT STABILIZATION IS DEFINED AS A MINIMUM UNIFORM, PERENNIAL 70%
MATERIAL AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE BUT QUALIFYING VEGETATIVE COVER OR OTHER PERMANENT NON-VEGETATIVE COVER WITH A DENSITY
AS CLEAN FILL DUE TO ANALYTICAL TESTING. SUFFICIENT TO RESIST ACCELERATED EROSION. CUT AND FILL SLOPES SHALL BE CAPABLE OF
RESISTING FAILURE DUE TO SLUMPING, SLIDING, OR OTHER MOVEMENTS.
13. ALL PUMPING OF WATER FROM ANY WORK AREA SHALL BE DONE ACCORDING TO THE D
PROCEDURE DESCRIBED IN THIS PLAN, OVER UNDISTURBED VEGETATED AREAS. 29. E&S BMPS SHALL REMAIN FUNCTIONAL AS SUCH UNTIL ALL AREAS TRIBUTARY TO THEM ARE
PERMANENTLY STABILIZED OR UNTIL THEY ARE REPLACED BY ANOTHER BMP APPROVED BY
14. VEHICLES AND EQUIPMENT MAY NEITHER ENTER DIRECTLY NOR EXIT DIRECTLY FROM LOTS THE LOCAL CONSERVATION DISTRICT OR THE DEPARTMENT.
(SPECIFY LOT NUMBERS) ONTO (SPECIFY ROAD NAMES). UPDATED PERMIT PER COUNTY REVIEW COMMENTS
30. UPON COMPLETION OF ALL EARTH DISTURBANCE ACTIVITIES AND PERMANENT STABILIZATION 1
OF ALL DISTURBED AREAS, THE OWNER AND/OR OPERATOR SHALL CONTACT THE LOCAL M. DREHER M. DREHER J. GREEN 03-15-17

CONSERVATION DISTRICT FOR AN INSPECTION PRIOR TO REMOVAL/CONVERSION OF THE E&S 0


ISSUED FOR CONSTRUCTION
BMPS. M. DREHER M. DREHER J. GREEN 01-20-17
REV DESIGN BY DRAWN BY CHECKED BY DATE
31. AFTER FINAL SITE STABILIZATION HAS BEEN ACHIEVED, TEMPORARY EROSION AND SEDIMENT
BMPS MUST BE REMOVED OR CONVERTED TO PERMANENT POST CONSTRUCTION
STORMWATER MANAGEMENT BMPS. AREAS DISTURBED DURING REMOVAL OR CONVERSION KIEWIT POWER CONSTRUCTORS CO.
OF THE BMPS SHALL BE STABILIZED IMMEDIATELY. IN ORDER TO ENSURE RAPID
REVEGETATION OF DISTURBED AREAS, SUCH REMOVAL/CONVERSIONS ARE TO BE DONE ONLY
DURING THE GERMINATING SEASON.
32. UPON COMPLETION OF ALL EARTH DISTURBANCE ACTIVITIES AND PERMANENT STABILIZATION
OF ALL DISTURBED AREAS, THE OWNER AND/OR OPERATOR SHALL CONTACT THE LOCAL BIRDSBORO POWER LLC
CONSERVATION DISTRICT TO SCHEDULE A FINAL INSPECTION.
33. FAILURE TO CORRECTLY INSTALL E&S BMPS, FAILURE TO PREVENT SEDIMENT-LADEN RUNOFF E
FROM LEAVING THE CONSTRUCTION SITE, OR FAILURE TO TAKE IMMEDIATE CORRECTIVE
ACTION TO RESOLVE FAILURE OF E&S BMPS MAY RESULT IN ADMINISTRATIVE, CIVIL, AND/OR
CRIMINAL PENALTIES BEING INSTITUTED BY THE DEPARTMENT AS DEFINED IN SECTION 602 OF BIRDSBORO POWER PROJECT
THE PENNSYLVANIA CLEAN STREAMS LAW. THE CLEAN STREAMS LAW PROVIDES FOR UP TO
$10,000 PER DAY IN CIVIL PENALTIES, UP TO $10,000 IN SUMMARY CRIMINAL PENALTIES, AND
UP TO $25,000 IN MISDEMEANOR CRIMINAL PENALTIES FOR EACH VIOLATION.

KIEWIT ENGINEERING GROUP INC.


9401 Renner Boulevard
Lenexa, Kansas 66219
Digitally signed by James J. Green, Jr.
Reason: I am approving this document
Date: 2018.02.05 12:12:29-06'00'

F
EROSION & SEDIMENT CONTROL PLAN
GENERAL NOTES

ENGINEER/DESIGN DRAWING NUMBER


ORIGINATOR M. DREHER
LEAD ENG J. GREEN
ENG MGR N. STEWART 20019983-CE-002
PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

SOILS LEGEND
19 BmB - BIRDSBORO SILT LOAM, 3 TO 8 PERCENT SLOPES
PROTECTED/CONSERVED Bo - BOWMANSVILLE-KNAUERS SILT LOAMS
RIPARIAN BUFFER AREA (TYP) Gc - GIBRALTAR SILT LOAM
POI 3 LfA - LAMINGTON SILT LOAM, 0 TO 3 PERCENT SLOPES
4.20 ACRES OF CONSERVED RaB - RARITAN SILT LOAM, 3 TO 8 PERCENT SLOPES
RIPARIAN BUFFER FOR POI 3 Ua - UDORTHENTS
UgB - URBAN LAND, 0 TO 8 PERCENT SLOPES A
UxB - URBAN LAND-PENN COMPLEX, 0 TO 8 PERCENT SLOPES
SOIL INFORMATION GATHERED FROM THE NRCS WEBSOIL SURVEY WEBSITE.
160
160
100 YEAR FLOOD PLAIN AREA
IN ZONE AE
NOTES
A MAINTENANCE PROGRAM SHALL BE CONDUCTED TO PROVIDE FOR OPERATIO
3 20 AND MAINTENANCE OF ALL BMP'S TO BE INSPECTED ON A WEEKLY BASIS AND

16
16
160 0

0
EACH STORM EVENT. CONTRACTOR SHALL FILL OUT "VISUAL SITE INSPECTION
BmB 18 REPORT" FOUND ON THE E&S REPORT.

160
MINIMIZED DISTURBANCE/REDUCED GRADING

160
3.58 ACRES OF CONSERVED DRAINAGE AREA (TYP) 160 IN ADDITION TO THE AREA OF MINIMIZED DISTURBANCE/REDUCED GRADING NOTED

116600
RIPARIAN BUFFER FOR POI 2
NPDES BOUNDARY 160 THIS PLAN WITHIN DA4, ALL AREA THAT LIES BETWEEN THE NPDES PERMIT BOUNDA
AND THE LOD BOUNDARY, THAT IS NOT IDENTIFIED HEREON AS AN EXISTING RIPARIA
POI 2
RaB BUFFER OR AN EXISTING WETLAND, IS ALSO AN AREA OF MINIMIZED
DISTURBANCE/REDUCED GRADING.
                MINIMIZED DISTURBANCE/REDUCED GRADING WITHIN DA4 -   14.13 ACRES
1.54 ACRES OF CONSERVED Ua NPDES BOUNDARY
B
                MINIMIZED DISTURBANCE/REDUCED GRADING OUTSIDE LOD - 29.35 ACRES
RIPARIAN BUFFER FOR POI 2 DRAINAGE

159
DRAINAGE WETLAND DELINEATION FROM THE WETLAND PRIMARY
AREA 5 AREA 4 SURVEY AND GEOTECH BORING PLAN (QUAD3, 2016) AS
STATED IN THE PHASE 1 SITE ENVIRONMENTAL SITE
ASSESSMENT DATED APRIL 2016 (TYP)

16
0
151055 60

161
1 161 AREA IF MINIMUM DISTURBANCE/REDUCED GRADING -

165
PREDOMINATELY AREAS OF EXISTING IMPREVIOUS

160
160

165
161 16

160
160
SURFACES TO REMAIN.

160
5

160 DRAINAGE AREA (TYP) OTHER FLOOD AREA

UNION
BIRDSB
161

160
Gc

160
TOWN
ORO BO
2.98 ACRES OF CONSERVEDPOI 1 60 14.13 ACRES OF MINIMUM
1601
RIPARIAN BUFFER FOR POI 1 160 DISTURBANCE/REDUCED GRADING

SHIP
160
100 YEAR FLOOD PLAIN LINE

ROUGH
C
ELEVATION = 161'

160
STATE PLANT
PLANE NORTH

160
21
DRAINAGE
UgB AREA 2 160 17
11600 LfA
160
159
160
161 161

161
161

161

1611
16
161
DRAINAGE
AREA 1

116622
159 160
161
1 60 150 0 150 300

161
116611261126623 62 1

160
16060

163
161
1
160

161
161 SCALE IN FEET
1615

170 161 161116161

161
70

SCALE: 1" = 150'-0"

161
161
165 160160 160

16
160
160
Ua

160
1160
MINOR MOD TO EXPAND LOD FOR ADDITIONAL SITE CLEANUP
160

60
3 D
2.43 ACRES OF CONSERVED A. VICUNA M. DREHER J. GREEN 07-24-17

22 WETLAND FOR POI 3 165


160 160 DRAINAGE 2
UPDATED PERMIT - PER COUNTY REVIEW COMMENTS
A. VICUNA M. DREHER J. GREEN 03-15-17
165
165 AREA 3 UPDATED PERMIT
170
175
Ua 1
A. VICUNA M. DREHER J. GREEN 03-01-17

175
ISSUED FOR CONSTRUCTION

170
0
565550
16116
A. VICUNA M. DREHER J. GREEN 01-20-17

165
165
170 1 15617 15 0.28 ACRES OF CONSERVED REV DESIGN BY DRAWN BY CHECKED BY DATE

175 16 WETLAND FOR POI 3

5
14

17
180 KIEWIT POWER CONSTRUCTORS CO.
13

180
118801080
12

180
23
10 11 1850
18 1.14 ACRES OF CONSERVED 180 NPDES BOUNDARY
9 WETLAND FOR POI 2

180
NPDES BOUNDARY 8 BIRDSBORO POWER LLC
190
UxB

180
185
7 0.37 ACRES OF CONSERVED E
BmB WETLAND FOR POI 1
BIRDSBORO POWER PROJECT

4
5
KIEWIT ENGINEERING GROUP INC.
9401 Renner Boulevard
Lenexa, Kansas 66219
3
SOIL TYPE BOUNDARY LINE (TYP) Digitally signed by James J. Green, Jr.
Reason: I am approving this document
Date: 2018.02.05 12:12:46-06'00'

F
SENSITIVE NATURAL RESOURCE PLAN
2
1 ENGINEER/DESIGN
ORIGINATOR M. DREHER
DRAWING NUMBER

LEAD ENG J. GREEN


ENG MGR N. STEWART 20019983-CE-003
PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

NOTES
A MAINTENANCE PROGRAM SHALL BE CONDUCTED TO PROVIDE FOR OPERATIO
POI 3 AND MAINTENANCE OF ALL BMP'S TO BE INSPECTED ON A WEEKLY BASIS AND
EACH STORM EVENT. CONTRACTOR SHALL FILL OUT "VISUAL SITE INSPECTION
REPORT" FOUND ON THE E&S REPORT.

TEMPORARY STORMWATER DISCHARGE POINT:


BMP LEGEND A

OUTLET PIPE FOR SEDIMENTATION BASIN WILL NOT BE INSTALLED UNTIL INLET PROTECTION SEE DETAIL CE-009-6
OUTFALL PERMITTING IS APPROVED. IN THE INTERIM, CLEANED STORMWATER
MAY BE PUMPED FROM THE SEDIMENTATION BASIN'S TEMPORARY OUTLET
STRUCTURE TO THE EXISTING STORM SEWER SYSTEM THAT CURRENTLY PROTECTED/CONSERVED ROCK FILTER PER DETAIL CE008-1
DISCHARGES TO POI 2. DURING PERIODS OF RAINFALL, THE CONTRACTOR RIPARIAN BUFFER AREA (TYP)
MUST PROVIDE AROUND THE CLOCK MONITORING OF THIS SYSTEM TO
ENSURE UNINTERRUPTED PUMP OPERATION, THEREBY PREVENTING ANY BmB 12" OR 24" COMPOST FILTER SOCK PER DETAIL CE007-2
POSSIBLE POND OVERFLOW. DRAINAGE AREA (TYP)
PROPERTY LINE
30" SILT FENCE PER DETAIL CE011-2
LOCATION OF EXISTING STORM SEWER OUTFALL TIE-IN.
REFER TO OUTFALL PERMIT PLANS BY OTHERS FOR AREA OF CONCRETE REMOVAL & DEEP DYNAMIC
COORDINATION WITH PLANNED REHAB OF EXISTING COMPACTION
OUTFALL AND ASSOCIATED EROSION CONTROL BMPS. RIPRAP APRON PER DETAIL CE009-4 (NOTE THAT FOR ANY
PIPE DISCHARGING PERPENDICULAR TO THE CHANNEL,BTH
POI 2 RIPRAP APRON LENGTH MUST BE ADDITIONALLY EXTENDE
Ua UP THE OPPOSITE BANK TO A POINT EQUAL TO THE HEIGH
OF THE PIPE DIAMETER)
161
159 FAB SHOP EROSION CONTROL BLANKET PER DETAIL CE008-5 AND
DRAINAGE

162
TC PATH CE008-6
159
DRAINAGE DRAINAGE AREA 5
AREA 4

163
CONCRETE WASHOUT PER DETAIL CE007-3
AREA 5

163
3
158 16316
150 158 AREA OF MINIMUM DISTURBANCE/REDUCED GRADING -
PREDOMINATELY AREAS OF EXISTING IMPERVIOUS
150
EXISTING STORM SEWER EMERGENCY SPILLWAY SURFACES TO REMAIN.
155 60 INSTALL PER DETAIL CE011-1
1
162
161 STATE PLANT
160 SKIMMER INSTALL PER
DETAIL CE009-2 PLANE NORTH C
CONCRETE WASHOUT
PROPOSED INSTALL ANTI-SEEP COLLARS

0'
159

20.0
TRANSMISSION LINE PER DETAIL CE 007-5 ON SEDIMENTATION BASIN
159

0 SHEET 20019983-CE-007 100 INSTALL PER DETAIL CE009-1


159

Gc 15 .00'

UNION RO BOROUG
0'

BIRDSB
80.0
TC PATH
160

DRAINAGE AREA 2

TOWN
155

O
POI 1

16
160 INSTALL BAFFLE WALLS PER LAYDOWN

0
100 0 100 200

SHIP
116655 DETAIL 7-14 ON SHEET
20019983-CE-009
EROSION CONTROL BLANKET (TYP) SCALE IN FEET
APPROXIMATE LOCATION OF TEMPORARY BINS FOR
1650 SEGREGATION OF MATERIALS. STORAGE BINS ARE SCALE: 1" = 100'-0"
5
1155

H
159

AREA OF CONCRETE REMOVAL & LOCATED ON THE EXISTING CONCRETE SLAB AND ARE MINOR MOD TO EXPAND LOD FOR ADDITIONAL SITE CLEANUP
DEEP DYNAMIC COMPACTION CONSTRUCTED OF CONCRETE BARRIERS ON THREE SIDES 4
A. VICUNA M. DREHER J. GREEN 07-24-17
SOCK NO. 4 - SOCK NO. 1 - WITH HEAVY MIL PLASTIC SHEETING ON THE FLOOR AND MINOR MODIFICATION PER FIELD REQUEST AND PERMITTING AGENCY
12" COMPOST FILTER SOCK 24" COMPOST FILTER UP THE SIDES. THE OPEN ENDS ARE TO BE WALLED OFF 3 D
159

A. VICUNA M. DREHER J. GREEN 05-11-17


WHEN NOT IN USE TO PREVENT THE ESCAPE OF
DRAINAGE SOCK (TYP) SEDIMENT-LADEN RUNOFF DURING A RAINFALL EVENT. 2
UPDATED PERMIT - PER COUNTY REVIEW COMMENTS

UgB
159

A. VICUNA M. DREHER J. GREEN 03-15-17

NO EARTH DISTURBANCE IN
AREA 2 1
UPDATED PERMIT
A. VICUNA M. DREHER J. GREEN 03-01-17
DA1 DURING THIS PHASE 14.13 ACRES OF MINIMUM ISSUED FOR CONSTRUCTION
CONSTRUCTION ENTRANCE 0
INSTALL PER DETAIL CE007-1 DISTURBANCE/REDUCED GRADING A. VICUNA M. DREHER J. GREEN 01-20-17

161

161
161

161
161
REV DESIGN BY DRAWN BY CHECKED BY DATE

161
161
161
16 161
DRAINAGE 0 TC PATH
DRAINAGE AREA 4 KIEWIT POWER CONSTRUCTORS CO.
AREA 1 160
159
159 LAYDOWN
OFFICE TRAILERS/PARKING
151961061 161
159

160
161

161

BIRDSBORO POWER LLC


11662

TC PATH
2

DRAINAGE AREA 1 TC PATH DRAINAGE AREA 3 E


165
Ua
1

165
16

159
16
2

BIRDSBORO POWER PROJECT


163

159
DRAINAGE
160

165 AREA 3
165
Ua
KIEWIT ENGINEERING GROUP INC.
9401 Renner Boulevard
Lenexa, Kansas 66219
Digitally signed by James J. Green, Jr.
SOIL TYPE BOUNDARY LINE (TYP) Reason: I am approving this document
Date: 2018.02.05 12:12:58-06'00'

F
PHASE 1 - DEMOLITION/DDC GROUND IMPROVEMENTS

ENGINEER/DESIGN DRAWING NUMBER


ORIGINATOR M. DREHER
LEAD ENG J. GREEN

4 ENG MGR N. STEWART 20019983-CE-004


PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

DEMOLITION OF EXISTING STRUCTURE. STABILIZE GROUND POI 3


IMMEDIATELY AFTER STRUCTURE REMOVAL. USE SEED AS
STATED ON DETAIL CE010-2 & APPLY SEED PER TABLE ON
DWG CE-010 "SEED AND MULCH SPECIFICATION"
PROTECTED/CONSERVED
BMP LEGEND A

RIPARIAN BUFFER AREA (TYP) INLET PROTECTION SEE DETAIL CE-009-6


TEMPORARY STORMWATER DISCHARGE POINT:
OUTLET PIPE FOR SEDIMENTATION BASIN WILL NOT BE INSTALLED UNTIL ROCK FILTER PER DETAIL CE008-1
OUTFALL PERMITTING IS APPROVED. IN THE INTERIM, CLEANED STORMWATER
MAY BE PUMPED FROM THE SEDIMENTATION BASIN'S TEMPORARY OUTLET
STRUCTURE TO THE EXISTING STORM SEWER SYSTEM THAT CURRENTLY
DISCHARGES TO POI 2. DURING PERIODS OF RAINFALL, THE CONTRACTOR
THE END OF ANY COMPOST FILTER SOCK
OR SILT FENCE RUN MUST TURN UP-SLOPE
BmB 12" OR 24" COMPOST FILTER SOCK PER DETAIL CE007-2
MUST PROVIDE AROUND THE CLOCK MONITORING OF THIS SYSTEM TO AT A MINIMUM ANGLE OF 45° AND AT A
ENSURE UNINTERRUPTED PUMP OPERATION, THEREBY PREVENTING ANY 30" SILT FENCE PER DETAIL CE011-2
PROPERTY LINE MINIMUM LENGTH OF 8 FEET (TYPICAL)
POSSIBLE POND OVERFLOW.
DRAINAGE AREA AREA OF CONCRETE REMOVAL & DEEP DYNAMIC
STABILIZE BACKFILLED STORMSEWER TRENCH COMPACTION
INSTALL PER DETAIL CE008-5 & APPLY SEE PER RIPRAP APRON PER DETAIL CE009-4 (NOTE THAT FOR ANY
"SEED AND MULCH SPECIFICATION" ON DWG CE-010 STORM PIPE PIPE DISCHARGING PERPENDICULAR TO THE CHANNEL,BTH
SOCK NO. 3 - TO SCHUYLKILL RIPRAP APRON LENGTH MUST BE ADDITIONALLY EXTENDE
24" COMPOST RIVER UP THE OPPOSITE BANK TO A POINT EQUAL TO THE HEIGH
POI 2
FILTER SOCK Ua OF THE PIPE DIAMETER)
EROSION CONTROL BLANKET PER DETAIL CE008-5 AND
159 30" SILT FENCE CE008-6
159
FAB SHOP DRAINAGE
DRAINAGE SKIMMER INSTALL AREA 4 CONCRETE WASHOUT PER DETAIL CE007-3
AREA 5 PER DETAIL CE009-2

16
AREA OF MINIMUM DISTURBANCE/REDUCED GRADING -

161
158

0
2
EXISTING STORM
150 SEWER INSTALL ANTI-SEEP
58 COLLARS PREDOMINATELY AREAS OF EXISTING IMPERVIOUS

16
1 162

162
PER DETAIL CE 007-5 ON SURFACES TO REMAIN.
150

SHEET 20019983-CE-007 SOCK NO. 2 - 162


15560 24" COMPOST

2
1

16
FILTER SOCK (TYP)
STORM PIPE (TYP) 162 STATE PLANT
160 161 PLANE NORTH C
STABILIZE SLOPES OF
PROPOSED SEDIMENTATION BASIN
TRANSMISSION PER DETAIL CE008-5 CONCRETE WASHOUT
EMERGENCY SPILLWAY 1
15505
159

LINE

80.0 20.00'
INSTALL PER DETAIL CE011-1 SEDIMENTATION BASIN
159

INSTALL PER DETAIL CE009-1 100 0 100 200


150
9

Gc
15

APRON 100 100

0'

UNION RO BOROUG
APRON 300 - RIPRAP LENGTH MUST BE SCALE IN FEET
INLET PROTECTION (TYP) .00'

BIRDSB
POI 1 SOCK NO. 1 - APRON 200 EXTENDED UP THE OPPOSITE BANK TO A SCALE: 1" = 100'-0"
160

1
24" COMPOST FILTER 15550 DEPTH EQUAL TO THE PIPE DIAMETER

TOWN
155 SOCK

O
16
160 INSTALL BAFFLE WALLS PER RIPRAP APRON (TYP) LAYDOWN

SHIP
116655 DETAIL 7-14 ON SHEET
20019983-CE-009 ADDED PERMANENT ROCK CHECK DAMS TO ADDRESS BOROUGH REVIEW
1650
5

APPLY SEED PER TABLE ON APRON 700 A. VICUNA M. DREHER J. GREEN 10-30-17
5
1155
MINOR MOD TO EXPAND LOD FOR ADDITIONAL SITE CLEANUP

H
159

DWG CE-010 "SEED AND MULCH BUILD GRAVEL ROAD 14.13 ACRES OF MINIMUM 4
A. VICUNA M. DREHER J. GREEN 07-24-17
SPECIFICATION" FOR BOTTOM OF OVER CULVERT 1 FOR CONSTRUCTION DISTURBANCE/REDUCED GRADING MINOR MODIFICATIONS PER FIELD REQUEST AND PERMITTING AGENCY
SEDIMENTATION BASIN ACCESS. EXTEND TO REMAINING
3
A. VICUNA M. DREHER J. GREEN 05-11-17 D
SLAB TO PREVENT TRACK OUT. UPDATED PERMIT - PER COUNTY REVIEW COMMENTS
159

2
SOCK NO. 4 - DRAINAGE A. VICUNA M. DREHER J. GREEN 03-15-17
12" COMPOST
UgB
159

UPDATED PERMIT
FILTER SOCK AREA 2 EROSION CONTROL BLANKET 1
A. VICUNA M. DREHER J. GREEN 03-01-17
PER DETAIL CE008-6 (TYP) ISSUED FOR CONSTRUCTION
DEEP FOUNDATION N 5986.178 0
A. VICUNA M. DREHER J. GREEN 01-20-17
TYPICAL FILL EXCAVATION E 4409.804 N 5715.046 REV DESIGN BY DRAWN BY CHECKED BY DATE
PARKING AND OFFICE TRAILERS MATERIAL ROCK FILTER NO. 1 (PERMANENT) E 4500.101
161

161
161

161
161

161
161
SEE DETAIL CE008-1

155
155
ROCK FILTER NO. 2 (PERMANENT)

161
16 161 APRON 700 SEE DETAIL CE008-1
DRAINAGE 0 KIEWIT POWER CONSTRUCTORS CO.

AREA 1 CONSTRUCTION ENTRANCE 160


159
INSTALL PER DETAIL CE007-1 159 LAYDOWN
151961061 161
159

0 BIRDSBORO POWER LLC


16 ROCK FILTERS NO. 3 (TEMPORARY)
161

161
1162

SEE DETAIL CE008-1 E


2

165
Ua
1

165
16

159 BIRDSBORO POWER PROJECT


16

157
156 CHANNEL 1
2

163

159 156
157
DRAINAGE
160

APRON16500
5 - RIPRAP LENGTH MUST BE
EXTENDED UP THE OPPOSITE BANK TO A
AREA 3
165
DEPTH EQUAL TO THE PIPE DIAMETER
Ua
KIEWIT ENGINEERING GROUP INC.
9401 Renner Boulevard
Lenexa, Kansas 66219
Digitally signed by James J. Green, Jr.
Reason: I am approving this document
Date: 2018.02.05 12:13:09-06'00'

SOIL TYPE BOUNDARY LINE (TYP)


F
PHASE 2 - MASS EXCAVATIONS

ENGINEER/DESIGN DRAWING NUMBER


ORIGINATOR M. DREHER
LEAD ENG J. GREEN
5 ENG MGR N. STEWART 20019983-CE-005
PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

BMP LEGEND
INLET PROTECTION SEE DETAIL CE-009-6
POI 3
ROCK FILTER PER DETAIL CE008-1

12" OR 24" COMPOST FILTER SOCK PER DETAIL CE007-2A

30" SILT FENCE PER DETAIL CE011-2


PROTECTED/CONSERVED
RIPARIAN BUFFER AREA (TYP) ASPHALT

BmB RIPRAP APRON PER DETAIL CE009-4 (NOTE THAT FOR ANY
PIPE DISCHARGING PERPENDICULAR TO THE CHANNEL, THE
RIPRAP APRON LENGTH MUST BE ADDITIONALLY EXTENDE
UP THE OPPOSITE BANK TO A POINT EQUAL TO THE HEIGH
PROPERTY LINE (TYP) OF THE PIPE DIAMETER)
STABILIZE SLOPES PER DETAIL CE008-5

GRAVEL B
STORM PIPE TO SCHUYLKILL RIVER
POI 2
Ua 16
CONCRETE
162 1
DRAINAGE FAB SHOP DRAINAGE EXISTING WOODS
AREA 4

163
AREA 5
1
STORM PIPE (TYP) 116598 589 GRASS
0 160
STABILIZE SLOPES PER
160 EROSION CONTROL BLANKET PER DETAIL CE008-5 AND

16
DETAIL CE008-5 (TYP)

0
CE008-6
PROPOSED TRANSMISSION LINE
150 AREA OF MINIMUM DISTURBANCE/REDUCED GRADING -
PREDOMINATELY AREAS OF EXISTING IMPREVIOUS
115501

152 SURFACES TO REMAIN.


C
153 STATE PLANT
23 154 1598 TEMPORARY SEDIMENTATION BASIN PLANE NORTH
114445687 1 TO BE CONVERTED TO PERMANENT
15505
151150 149

DETENTION BASIN AT THE END OF


PHASE 3
Gc

160

UNION RO BOROUG
INLET PROTECTION (TYP) 150 N 5986.178

BIRDSB
164 E 4409.804 100 0 100 200
1
16505 ROCK FILTER NO. 1 (PERMANENT)

TOWN
POI 1

O
SCALE IN FEET
SEE DETAIL CE008-1 LAYDOWN SCALE: 1" = 100'-0"

SHIP
1450 RIPRAP APRON (TYP)
15 5
ADDED PERMANENT ROCK CHECK DAMS TO ADDRESS BOROUGH REVIEW
A. VICUNA M. DREHER J. GREEN 10-30-17
1550

H
164
161

MINOR MOD TO EXPAND LOD FOR ADDITIONAL SITE CLEANUP


1665
4
A. VICUNA M. DREHER J. GREEN 07-24-17
163

1 60 MINOR MODIFICATIONS PER FIELD REQUEST AND PERMITTING AGENCY


1 55 14.13 ACRES OF MINIMUM 3 D
1 DISTURBANCE/REDUCED GRADING
A. VICUNA M. DREHER J. GREEN 05-11-17
164

UPDATED PERMIT - PER COUNTY REVIEW COMMENTS


161 DRAINAGE 2

164
UgB
A. VICUNA M. DREHER J. GREEN 03-15-17
164
159

AREA 2 EROSION CONTROL BLANKET (TYP) UPDATED PERMIT


1621

155
1

155
A. VICUNA M. DREHER J. GREEN 03-01-17
TYPICAL FILL MATERIAL
LfA ISSUED FOR CONSTRUCTION

160
PARKING AND OFFICE TRAILERS N 5715.046 0

160
A. VICUNA M. DREHER J. GREEN 01-20-17
164

E 4500.101 REV DESIGN BY DRAWN BY CHECKED BY DATE

161
ROCK
16 1FILTER NO. 2 (PERMANENT)
158

SEE DETAIL CE008-1


158

DRAINAGE 158 KIEWIT POWER CONSTRUCTORS CO.


AREA 1
158

LAYDOWN
163
162 BIRDSBORO POWER LLC
161
E

Ua 160
160 162
161 157
156 CHANNEL 1 BIRDSBORO POWER PROJECT
160 156
157
162
163
1
160
161
62
16263
1 64 DRAINAGE
6
15614
3 11656
6
1167 AREA 3
16 168
166
16167
8
169
169
1
1 66998
16 NO. 3 (TEMPORARY)
Ua
1 667

ROCK FILTERS
SEE DETAIL CE008-1
168 1116166767890 KIEWIT ENGINEERING GROUP INC.
9401 Renner Boulevard
Lenexa, Kansas 66219
171
Digitally signed by James J. Green, Jr.

SOIL TYPE BOUNDARY LINE (TYP)


17 172

Reason: I am approving this document

173
Date: 2018.02.05 12:13:23-06'00'
1754

F
176
117787

PHASE 3 - MASS EMBANKMENT, UTILITY,


AND FOUNDATION IMPROVEMENTS

ENGINEER/DESIGN DRAWING NUMBER


ORIGINATOR M. DREHER
LEAD ENG J. GREEN
5 ENG MGR N. STEWART 20019983-CE-006
PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

DETAIL CE007-3
CONCRETE WASHOUT

DETAIL CE007-1
ROCK CONSTRUCTION ENTRANCE

ISSUED FOR CONSTRUCTION


0
A. VICUNA M. DREHER J. GREEN 01-20-17
REV DESIGN BY DRAWN BY CHECKED BY DATE

KIEWIT

BIRDSBORO POWER, LLC

DETAIL CE007-4
DETAIL CE007-5 BIRDSBORO POWER PROJECT
FLARED END SECTION
CONCRETE ANTI-SEEP COLLAR

Kiewit Engineering Group Inc.


9401 Renner Boulevard
’ Lenexa, Kansas 66219
Digitally signed by James J. Green, Jr.
Reason: I am approving this document
Date: 2018.02.05 12:13:36-06'00'


F
EROSION & SEDIMENT CONTROL PLAN DETAILS

DETAIL CE007-2 ENGINEER/DESIGN DRAWING NUMBER


COMPOST FILTER SOCK ORIGINATOR M. DREHER
LEAD ENG J. GREEN
ENG MGR N. STEWART 20019983-CE-007
PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

DETAIL CE008-1
ROCK FILTER

DETAIL CE008-6
VEGETATED CHANNEL

DETAIL CE008-4
EROSION CONTROL BLANKET STAPLE PATTERN

D
UPDATED ROCK FILTER DETAIL TO ADDRESS BOROUGH REVIEW
2
A. VICUNA M. DREHER J. GREEN 11-06-17
UPDATED ROCK FILTER DETAIL TO ADDRESS BOROUGH REVIEW
1
DETAIL CE008-2 A. VICUNA M. DREHER J. GREEN 10-30-17
ACCESS ROAD ISSUED FOR CONSTRUCTION
0
A. VICUNA M. DREHER J. GREEN 01-20-17
REV DESIGN BY DRAWN BY CHECKED BY DATE

KIEWIT POWER CONSTRUCTORS CO.

BIRDSBORO POWER LLC

BIRDSBORO POWER PROJECT

KIEWIT ENGINEERING GROUP INC.


9401 Renner Boulevard
Lenexa, Kansas 66219
Digitally signed by James J. Green, Jr.
Reason: I am approving this document
Date: 2018.02.05 12:13:49-06'00'

F
EROSION & SEDIMENT CONTROL PLAN DETAILS

ENGINEER/DESIGN DRAWING NUMBER


DETAIL CE008-3 ORIGINATOR M. DREHER
DETAIL CE008-5
LEAD ENG J. GREEN
SOIL STOCKPILE SLOPE STABILIZATION ENG MGR N. STEWART 20019983-CE-008
PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

DETAIL CE009-3
TEMPORARY OUTLET STRUCTURE

DETAIL CE009-2
DETAIL CE009-1 SKIMMER
SEDIMENT BASIN

BAG DEPTH TO
TOP OF PIPE
INLET GRATE DROP INLET

D
2 UPDATED NOTE FOR RIPRAP APRON DETAIL
2
"SILT SACK" DUMP A. VICUNA M. DREHER J. GREEN 05-12-17
SEDIMENT STRAP UPDATED PERMIT PER COUNTY REVIEW COMMENTS
CONTROL BAG 1
A. VICUNA M. DREHER J. GREEN 03-15-17
(SEE NOTE 3)

DEPTH
ISSUED FOR CONSTRUCTION
STORM DRAIN PIPE 0
A. VICUNA M. DREHER J. GREEN 01-20-17
INSTALLATION DETAIL REV DESIGN BY DRAWN BY CHECKED BY DATE

DETAIL CE009-4 LEN


GTH TH
RIPRAP APRON
WID EXPANSION RESTRAINT KIEWIT POWER CONSTRUCTORS CO.
CORD (1/4" NYLON ROPE, 2 EACH
2" FLAT WASHERS) DUMP STRAPS
DROP INLET BIRDSBORO POWER LLC

E
STORM DRAIN PIPE
ISOMETRIC SILT SACK DETAIL BIRDSBORO POWER PROJECT
DETAIL CE009-6
DROP INLET PROTECTION - SILT SACK
NTS
NOTES:
1. INSTALL SILT SACK PER MANUFACTURER'S PRINTED INSTRUCTIONS. EMPTY OR REMOVE SEDIMENT FROM SILT
SACK WHEN RESTRAINT CORD IS NO LONGER VISIBLE. CLEAN, RINSE AND REPLACE SILT SACK AS NEEDED.
2. THE CONTRACTOR SHALL MEASURE CATCH BASIN AND INLET DIMENSIONS IN THE FIELD AND ORDER THE
APPROPRIATE SIZE SILT SACK FOR EACH STRUCTURE. KIEWIT ENGINEERING GROUP INC.
9401 Renner Boulevard
Lenexa, Kansas 66219
3. THE SILT SACK SHALL BE OF HIGH FLOW DESIGN (200 GAL/MIN/FT), AS MANUFACTURED BY ACF
ENVIRONMENTAL, INC. OR ENGINEER-APPROVED SUBSTITUTE. Digitally signed by James J. Green, Jr.
Reason: I am approving this document
Date: 2017.05.12 12:36:28-05'00'

4. THE SILT SACK SHALL BE INSPECTED AND MAINTAINED WITHIN 48 HOURS FOLLOWING A STORM EVENT. THE
FILTER SHALL BE CLEANED IN A MANNER WHICH ENSURES THAT ALL SEDIMENT REMAINS ON SITE. F
EROSION & SEDIMENT CONTROL PLAN DETAILS
5. SUBSTITUTION OF A SHEET OF FILTER FABRIC PLACED OVER THE OPENING F THE INLET IN LIEU OF PROVIDING A
SILT SACK IS NOT ACCEPTABLE.
DETAIL CE009-5 6. THE FILTER SHALL BE REPLACED OR CLEANED WHEN THE BAG BECOMES HALF FULL. ENGINEER/DESIGN
ORIGINATOR M. DREHER
DRAWING NUMBER

TRASH RACK AND ANTI-VORTEX DEVICE 7. SILT SACK SHALL BE REMOVED FROM INLET ONCE FINAL SURFACE STABILIZATION IS IN PLACE. LEAD ENG J. GREEN
ENG MGR N. STEWART 20019983-CE-009
PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

DETAIL CE010-1
PUMPED WATER FILTER BAG

ISSUED FOR CONSTRUCTION


0
A. VICUNA M. DREHER J. GREEN 01-20-17
REV DESIGN BY DRAWN BY CHECKED BY DATE

KIEWIT

BIRDSBORO POWER, LLC

BIRDSBORO POWER PROJECT

DETAIL CE010-2
Kiewit Engineering Group Inc.
SITE RESTORATION SEED AND MULCH 9401 Renner Boulevard
Lenexa, Kansas 66219
Digitally signed by James J. Green, Jr.
Reason: I am approving this document
Date: 2018.02.05 12:14:19-06'00'

F
EROSION & SEDIMENT CONTROL PLAN DETAILS

ENGINEER/DESIGN DRAWING NUMBER


ORIGINATOR M. DREHER
LEAD ENG J. GREEN
ENG MGR N. STEWART 20019983-CE-010
PROJ MGR G. ROUSH
1 2 3 4 5 6 7 8 9

DETAIL CE011-3 3
CONSTRUCTION SEQUENCE

UPDATED CONSTRUCTION SEQUENCE


3 D
A. VICUNA M. DREHER J. GREEN 10-30-17
UPDATED CONSTRUCTION SEQUENCE
2
A. VICUNA M. DREHER J. GREEN 05-12-17
UPDATED PERMIT PER COUNTY REVIEW COMMENTS
1
A. VICUNA M. DREHER J. GREEN 03-15-17
ISSUED FOR CONSTRUCTION
0
A. VICUNA M. DREHER J. GREEN 01-20-17
REV DESIGN BY DRAWN BY CHECKED BY DATE

KIEWIT POWER CONSTRUCTORS CO.

BIRDSBORO POWER LLC

DETAIL CE011-1 BIRDSBORO POWER PROJECT


EMERGENCY SPILLWAY WITH RIPRAP

KIEWIT ENGINEERING GROUP INC.


9401 Renner Boulevard
Lenexa, Kansas 66219
Digitally signed by James J. Green, Jr.
Reason: I am approving this document
Date: 2018.02.05 12:14:32-06'00'

F
EROSION & SEDIMENT CONTROL PLAN DETAILS
30" SILT FENCE
SUPER SILT FENCE
ENGINEER/DESIGN DRAWING NUMBER
ORIGINATOR M. DREHER
DETAIL CE011-2
· LEAD ENG J. GREEN
SILT FENCE
· ENG MGR N. STEWART 20019983-CE-011
PROJ MGR G. ROUSH

You might also like