Professional Documents
Culture Documents
STREAM 1
STREAM 2
STREAM 3
18
Key Principles Of Erosion and
Sediment Control
Objective:
19
Key Principle Of Erosion and
Sediment Control
Principle 1.1
Developments should aim to utilise the existing topography to
minimize the need for extensive land reshaping and surfaces
modifications
20
Conventional design
21
1) Development to Fit Site
Before
(Plot 34)
After
(Plot 34)
Before
(Plot 23)
After
(Plot 23)
Before
(Plot 38)
After
(Plot 38)
Key Principle Of Erosion and
Sediment Control
25
Principle 2.2
Identify high-risk areas and high-risk construction activities during site planning
26
Slope Map of the Project Site
Principle 3.1
Appropriately amend the adopted erosion and sediment control
measures, and where appropriate revise the ESCP, if the
implemented works fail to achieve the “objective” of the
ESCP, the required performance standard or the State’s
environmental protection requirement.
30
Green
Ma(ress
Silt
Fence
Hydroseed
Swale
VIGROLOG
This application is limited to
stream which has low flow
rate and medium velocity
otherwise it would be washed
away during storm.
Key Principle Of Erosion and
Sediment Control
4. Minimise the extent and duration of soil
disturbance
Principle 4.1
Construction schedules should aim to minimise the extent to witch and
duration that any and all areas of soil are exposed to the erosive
effects of wind, rain and flowing water
Principle 4.2
Wherever reasonable and practicable, land clearing and site
rehabilitation must be appropriately staged to minimise the duration
of soil exposure and the area of exposure at any given instant
34
Key Principle Of Erosion and
Sediment Control
Principle 4.3
As long as the risk of rainfall or strong winds exist on a site, land disturbance should be
restricted to those areas required for the current stage of works.
Principle 4.4
Wherever reasonable and practicable, major land disturbance should be scheduled for the
least erosive periods of the year
Principle 4.5
Disturbance to high and extreme erosion risk areas should be minimised, if not totally avoided
especially during the most erosive periods of the year.
Principle 4.6
Wherever reasonable and practicable, the disturbance of dispersive or potential acid sulfate
soils should be minimised, if not totally avoided.
35
Key Principle Of Erosion and
Sediment Control
Principle 4.7
Disturbance to the existing ground cover should be delayed as long as possible
Principle 4.8
Construction procedure should aim to minimise the extent of unnecessary soil disturbance
including any disturbance outside the designated work area.
36
Work Done Stages
Months May June July August September October November December January February March
Activity
Wash
Trough
Plot
11
Plot
20
Plot
13
Plot
14
Plot
34
Plot
38
Plot
37
Plot
36
Plot
32
Plot
31
Plot
30
Plot
18
Plot
50
Plot
17
Plot
20
Plot
16
Pond
4
Pond
2
Road
12
Road
18
Road
17
Key Principle Of Erosion and
Sediment Control
5. Control water movement through the site
Principle 5.1
To the maximum degree reasonable and practicable “clean” water needs to be diverted
around sediment traps in a manner that maximise the sediment trapping efficiency of
the sediment trap
Principle 5.2
On disturbance exceeding 1500m2 construction drainage plan need to be prepared for
each stage of earth works
38
Principle 5.3
The construction schedule an ESCP installation sequence should allow for the
installation of the temporary drainage system and preferably the permanent storm
water drainage system as soon a practicable
Principle 5.4
Long slopes of disturbed or otherwise unstable soils should be divide into small,
manageable drainage area to prevent or minimise soil erosion.
39
Principle 5.5
In region containing dispersive soils, construction detail of drainage systems and bank stabilisation works
need to be demonstrate how to these soils are to be stabilised and/or buried under a layer of non-
dispersive soil.
Principle 5.6
Appropriate outlet scour protection needs to be placed on all stormwater outlet, chutes, spillways and
slope drain to dissipate flow energy and minimise the risk of soil erosion.
40
6. Minimise Soil Erosion
Principle 6.1
Priority to preventing or minimising soil erosion rather than allowing to
occur erosion and try to trap the resulting sediment.
Principle 6.2
Standard erosion control need to be appropriate for the given soils
properties to environmental harm from turbid runoff
42
Key Principle Of Erosion and
Sediment Control
7. Promptly stabilize disturbed area
Principle 7.1
The ESCP installation sequence need to ensure that soil stabilisation
procedurs, including site preparation and revegetation are commenced
as soon as practicable after each stage of earthworks is complete.
Principle 7.2
Manage top soil appropriately to preserve long term values
Principle 7.3
Plant species need for the site conditions, including compatibility with
local environmental values and anticipated erosive forces
44
Stabilised Disturbed Area
45
HYRDROSEEDING
Key Principle Of Erosion and
Sediment Control
8. Maximize sediment retention on the site
Principle 8.1
All reasonable and practicable measures need to be taken to project adjacent properties and
downstream environments from the adverse effect of sediment and sediment laden water displaced
from the site.
Principle 8.2
Work sites must not realy solely on the application of sediment control measures to provide
adequate environmental protection.
Principle 8.3
Sediment control measures need to be appropriate for the given properties expected weather
conditions, required treatment standard and the type, cost and scope of the works.
47
CATCHMENT 1
CATCHMENT 2
Location of
Retention Ponds
POND 4
POND 2
Key Principle Of Erosion and
Sediment Control
53
Key Principle Of Erosion and
Sediment Control
10. Monitor the site and adjust ESC practices to maintain the
required performance standard.
SAMPLING
POINT RP2
SAMPLING
POINT RP4
Sampling Dates and Results
High TSS level in Sept 09 due to land opening of Plot 30. Minimal ESC measures implemented & large area of land opening.
Sampling Dates and Results
High TSS level in Sept 09 due to land opening of Plot 30. Minimal ESC measures implemented & large area of land opening.
Total Suspended Solids
Bill of Quantities for Environmental Items/ESCP
Total
earthworks &
ESC value:
RM 8.68 Mil.
Conclusion