You are on page 1of 16

Channel Design

Hydromechanics VVR090

Design of Channels

• lined channels – minimizing lining material costs


• unlined channels – maximum permissible velocity and
threshold of movement (stable hydraulic section)

Concrete-lined Unlined channel


channel

1
Objectives of Channel Design

Transport water between two points in a safe and cost-effective


manner. Includes economical, safety, and esthetics aspects.
Here, mainly hydraulic aspects are considered.

General observations:

• Conveyance of a channel increases with the hydraulic radius


(wetted perimeter deceases). From Manning’s formula.
• The best hydraulic section is a semicircle (for a given area it
has the minimum wetted perimeter).
• For a specific cross section, the proportion that produce the
best hydraulic section (maximum flow) might be derived.
• The best hydraulic section might not be the best from an
economical point of view.

Best Hydraulic Cross Section I

Maximize the flow for a given cross-sectional shape and area.


From the Manning formula:

1
Q= AR 2 / 3 So1/ 2
n

Qn
= AR 2 / 3
So

⎛ Qn ⎞
Thus: max ⎜ = AR 2 / 3 ⎟ should be found for a given A
⎜ S ⎟
⎝ o ⎠

2
Best Hydraulic Cross Section II

Optimum geometries for different cross sections.


Rectangular cross section: best hydraulic cross
section when the water depth is half the channel
width.

Practical Considerations for Best Hydraulic Section

• The area needed to excavate the best hydraulic section might


be larger than the area required to achieve the flow area
• It may not be possible to construct a stable best hydraulic
section in the natural material
• The cost of excavation depends on other things than the
amount of material removed (e.g., access to the site, cost of
disposing material)
• The slope of the channel must also be considered.

3
Channel Design – General Aspects

1. The minimum permissible velocity is the lowest velocity that


will prevent sedimentation and vegetative growth (crude
estimates: 0.6 – 0.9 m/s for sedimentation and 0.75 m/s for
vegetation).

2. The side slopes depend primarily on the engineering


properties of the material through which the channel is
excavated.

3. The freeboard refers to the vertical distance between either


the top of the channel or the top of the channel lining and the
water surface (design flow at normal depth).

Side Slopes

4
Channel Freeboard I
Lined channel

Channel Freeboard II

Preliminary estimate of freeboard (unlined channel):

F = Cy

F: freeboard (ft)
y: design depth (ft)
C: coefficient (=1.5 for 20 ft3/s and 2.5 for 3000 ft3/s)

5
Flow Around a Channel Curve I

Flow Around a Channel Curve II

Rise in water surface at the outer bank:

u 2b
Δh =
gR

b: channel width
R: distance from center of curve to centerline of channel

Take into account velocity variation:

u2 ⎛R ⎞ Ri: inner radius


Δh = 2.3 log ⎜ o ⎟
g ⎝ Ri ⎠ Ro: outer radius

6
Use of Lined Channels

Lined channels may be used:


• to permit transmission of water at high velocities through
areas of deep or difficult excavation
• to permit transmission of water at a reduced construction
cost
• to decrease channel seepage
• to reduce operation and maintenance costs
• to ensure stability of the channel section

Typical Lined Channel Cross Sections

7
Design Procedure for Lined Channels

Minimize the cost of the lining material. Identical to find best


hydraulic section, if uniform thickness of the lining material is
employed.

Design procedure:
1. Estimate n
2. Compute the value of the section factor
3. For appropriate expression for A and R, compute yN
4. Compute channel properties
5. Check minimum permissible velocity and Froude number
6. Estimate height of lining above surface and freeboard
7. Summarize results with dimensioned sketch

Design for Different Lining Thickness or Material

The base of the channel and the sides of the channel might be
lined with different material of same material with different
thickness.
Design procedure involves minimizing the total cost (C) of the
lining material:

min ( C ) = min ( Cb + Cs )

Cb: material cost for channel base (per unit length)


Cs: material cost of sides (per unit length)

8
Design of Stable, Unlined, Earthen Channels

Find a stable cross section =>


One where neither scour nor deposition constitutes a problem.

Three types of unstable sections:


1. Scouring occur but no deposition
2. Deposition occur but no scouring
3. Both scour and deposition occur

Maximum Permissible Velocities

9
Theoretical Approach to Stable Cross Section I

Bed shear stress (balance between gravity and force due


to flow resistance):

τo = ρgRSo

For a wide channel, R ≈ y N , giving:

τo = ρgy N So

The shear stress is not uniformly distributed along the


perimeter. Complex problem to determine correct distribution,
but for trapezoidal cross section the following applies:

τomax = ρgy N So maximum along bottom


τ max
o = 0.76ρgy N So maximum along side slopes

Maximum Unit Tractive Force

Channel side

Channel bottom

(in terms of ρgy N So )

10
Theoretical Approach to Stable Cross Section II

Study a particle in equilibrium, just before mobilization.


Employ a balance between the shear force mobilizing the
sediment and the resisting force depending on the material.
Balance for particles along the bed:

τ L Ae = Ws tan α

Ws
τL = tan α
Ae

Ae: effective area


Ws: submerged particle weight
a: angle of friction (= angle of repose)

Angle of Respose

The angle to the horizontal at which


grains start to roll on a flat bed of
sediment that is gradually tilted
from the horizontal.

A representative value on the angle of


repose is 32 deg.

11
Theoretical Approach to Stable Cross Section III

Balance for particles on the side slopes:

( τS Ae ) + (Ws sin Γ ) = Ws cos Γ tan α


2 2

Ws tan 2 Γ
τS = cos Γ tan α 1 −
Ae tan 2 α

Tractive force ratio:

τS tan 2 Γ sin 2 Γ
K= = cos Γ 1 − = 1 −
τL tan 2 α sin 2 α

Angle of Repose

tana

12
Maximum Unit Tractive Force for
Different Materials

non-cohesive cohesive

Typical Channel Cross Sections

13
Design Procedure for Unlined Channels

Find a stable cross section. Design procedure:

1. Estimate n
2. Estimate angle of repose for channel material
3. ...

Consult French for the procedure.

Example 14.265: Water Surface Profile


Upstream an Obstruction

Water flowing at the normal depth in a rectangular concrete


channel that is 12 m wide encounters an obstruction (see figure),
causing the water level to rise above the normal depth at the
obstruction and for some distance upstream. The water discharge
is 126 m3/s and the channel bottom slope is 0.00086. The depth of
water just upstream from the obstruction is 4.55 m. Find the
distance upstream to the point where the surface is at the normal
depth.

14
Normal water depth:

1
Q= AR 2 / 3 S 1/ 2
n

2/3
1 ⎛ 12 y N ⎞
126 = 12 y N ⎜ ⎟ 0.000861/ 2
0.013 ⎝ 12 + 2 y N ⎠

2/3
⎛ 12 y N ⎞ 10.5
2.256 ⋅ ⎜ ⎟ − =0
⎝ 12 + 2 y N ⎠ yN

y N = 2.95 m (by trial and error)

Critical water depth:

1/ 3
⎛ 1 ⎛ 126 ⎞ 2 ⎞
1/ 3
⎛ q2 ⎞
ycr = ⎜ ⎟ =⎜ = 2.24 m
⎝ g ⎠ ⎜ 9.81 ⎜⎝ 12 ⎟⎠ ⎟⎟
⎝ ⎠

yN > ycr => subcritical flow at normal water depth

Start at obstruction and calculate upstream through the step


method.

Δxi =
(y+u 2
/ 2g )
i +1
− ( y + u2 / 2g )
i

So − ( n u / R2 2 4/3
) i +1/ 2

15
Table for Step Calculation

16

You might also like