You are on page 1of 1

How to Analyse for Whole Life Superior Approach: The Principle

Assessment of Whole Life Assessment


A better approach to whole-life assessment
Trade-offs between Initial Emissions and looks beyond the ‘payback period’, taking
Service Life Emissions account of CO2 emissions over the whole-life
Whole-life assessment is normally used to of the project or a study period of, say, 20 to
compare alternative designs or specifications. 30 years. All values in the data stream are
If one alternative has lower initial CO2 aggregated, to give whole-life emissions.
emissions and lower service life CO2 When comparing alternatives, the one with
emissions than the others, it can be selected the lowest whole-life emissions is preferred.
without the need for further analysis; and an The simplest way of aggregating initial and
alternative with higher initial CO2 emissions service life CO2 emissions is to add them all
and higher service life CO2 emissions can together, giving a cumulative value that rises
similarly be rejected. year by year. This can be plotted on a graph,
The situation is more interesting when (see Figure 11) with a line for each alternative
comparing alternatives with low construction being compared. Each line starts at Year 0 (the
CO2 emissions and high service life CO2 year when construction is completed) at a
emissions, against others with high value equal to the embodied CO2 emissions
construction CO2 emissions and low service of construction, and then rises year by year
life CO2 emissions. It is then necessary to during the service life. The steepness of the
analyse the trade-off between construction line corresponds to the annual CO2 emissions
and service life CO2 emissions using a whole- (mainly operational emissions). The lines often
life assessment methodology. have vertical steps, when components are
replaced (mainly embodied emissions).
Rudimentary Approach: The ‘Simple The interesting thing is whether the lines on
Payback’ Method the cumulative emissions graph (Figure 10)
Whole-life assessment is often used to cross. When this happens, it means that a
compare a ‘base’ case with enhanced design alternative that had higher construction
specification alternatives that have higher emissions ends up with lower whole-life
Figure 11 Cumulative graph replacement or refurbishment. construction CO2 emissions and lower service emissions. The alternative with the higher
for three alternatives. If two lines cross, the higher
Typical form of a whole-life initial investment is more than life CO2 emissions. initial CO2 emissions is preferred.
assessment of three outweighed by lower
alternatives, represented emissions during the service
The task is to establish whether the benefits The graph also indicates how long it takes
on a cumulative graph. life; if they don’t cross, the from the enhanced specification alternatives before the lines cross – equivalent to the
The starting points of the alternative with the lower
lines correspond to the initial investment cost also
are sufficient to justify the extra investment ‘payback period’. The more distant the
investment in the alternatives performs better over the and, if there are several alternatives, which of crossover point, the less convincing is the
– the embodied CO2 study period. In this example,
emissions in construction. alternative A represents
them performs best from a whole-life case for the alternative with higher
The gradients indicate the under-investment; C is over- perspective. construction CO2 emissions, due to increasing
rate of CO2 emissions during investment; and B is efficient
the service life, with vertical A simple but rudimentary method is to divide uncertainty in estimates of future emissions.
‘steps’ indicating component
the extra construction CO2 emissions by the The lines on the cumulative graph that start
annual savings in service life CO2 emissions. low and end up high represent under-
Cumulative CO2 emissions

7 This gives a ‘payback period’ in years: short investment; and lines that start off high and
‘payback periods’ are preferred. stay high represent over-investment. The line
C Alternatives with a ‘payback period’ that is that ends up with the lowest whole-life
longer than the component’s service life ‘emissions cost’ represents efficient
should normally be avoided. investment.

One problem with this method is that it The same exercise can be carried out using
B money-based costs, as in whole-life costing.
doesn’t look beyond the end of the ‘payback
period’. An alternative with a five year Cumulative graphs for CO2 emissions, money
‘payback’ and a six year service life would costs, and CO2-adjusted money costs are
A be rated ahead of a component with a six compared in Figure 12 for four house types: a
year ‘payback’ and a 20 year service life. ‘base’ design corresponding to mainstream
Now Study period
practice, and three low- CO2 alternatives, the
Time The ‘simple payback’ method is useful as a
‘low’, ‘medium’ and ‘ambitious’ types. The
Over-investment preliminary guide, but it ignores important
graphs shows the contrast between money-
factors and can be misleading.
Efficient investment based and CO2 emissions-based assessment.
Under-investment

Figure 11

11

You might also like