Professional Documents
Culture Documents
PDMinTransit Rev Oct 09FinalManuscript PDF
PDMinTransit Rev Oct 09FinalManuscript PDF
net/publication/245298389
CITATIONS READS
32 978
4 authors, including:
Keith R. Molenaar
University of Colorado Boulder
137 PUBLICATIONS 2,488 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Construction Data Exploitation and Visualization: Improving the Earliest Cost Estimates in the Project Life Cycle View project
All content following this page was uploaded by Douglas D. Gransberg on 31 December 2014.
Ali Touran, F. ASCE, Assoc. Prof., Dept. of Civil and Env. Eng., 400SN, Northeastern
Univ., Boston, MA 02115, +1 617/373-5508, atouran@coe.neu.edu. (Corresponding Author)
Douglas D. Gransberg, M. ASCE, Professor, Construction Science Div, Univ of Oklahoma,
830 Van Vleet Oval, Rm. 162, Norman, OK 73019-6141, +1 405/325-6092,
dgransberg@ou.edu.
Keith R. Molenaar, M. ASCE, Assoc. Professor, Dept. of Civil, Envir. and Arch. Eng., 428
UCB Univ. of Colorado, Boulder, CO 80309-0428, +1 303/735-4276, +1 FAX 303 492-
7317, keith.molenaar@colorado.edu.
Kamran Ghavamifar, PhD, Former Research Asst., Dept. of Civil and Env. Eng., 400SN,
Northeastern Univ., Boston, MA 02115, ghavamifar.k@neu.edu.
Touran, A., D.D. Gransberg, K. R. Molenaar, and K. Ghavamifar, “Selection of Project Delivery
Method in Transit: Drivers and Objectives,” Journal of Management in Engineering, ASCE, Vol.
26 (4) October 2010.
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 2
ABSTRACT
This paper describes the results of a research on alternative project delivery methods in
transit projects in the United States. The research, sponsored by the Transit Cooperative
Research Program (TCRP), aimed to identify those factors that drive the decision in the
choice of project delivery method. A rigorous case study analysis based on on-site structured
interviews with the directors of several transit projects was used to identify decision drivers
and the rationale behind the delivery method selection decision in transit agencies. The nine
case studies conducted in this research represent a cross section of delivery methods,
methods have resulted in savings in schedule and cost for transit agencies. The research also
found that achieving aggressive schedule compression is the most influential factor when
selecting alternative delivery methods. Also, implementation of a formal risk analysis as part
of the project development process appears to improve the project’s chances of meeting
KEYWORDS
Project delivery method, schedule compression, cost growth, risk analysis, structured
interview.
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 3
INTRODUCTION
Several types of project delivery methods are currently available to the owners of publicly
funded transportation projects in the United States (US). “Project delivery method” is a term
used to refer to all the contractual relations, roles and responsibilities of the entities involved
in a project. The project delivery method (PDM) is the process by which a construction
project is comprehensively designed and constructed for an owner including project scope
design and construction operations, execution of design and construction, and closeout and
start-up. Thus, the different project delivery methods are distinguished by the way the
contracts between the owner, the designer, and the builder are formed and the technical
The Construction Industry Institute (CII) maintains that there are really only three
Construction Manager-at-Risk (CMR) (Project Delivery Systems, 1997). While there are a
multitude of various names for project delivery methods throughout the industry, CII is
essentially correct. Therefore, this paper will focus its information on those three categories.
Short definitions and distinguishing characteristics of the main delivery methods are given in
DBB is the traditional project delivery method in which an owner retains a designer
to furnish complete design services and then advertises and awards a separate construction
contract based on the designer’s completed construction documents. In DBB, the owner
“owns” the details of design during construction and as a result, is financially liable for the
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 4
cost of any errors or omissions encountered in construction, called the “Spearin Doctrine”
(Mitchell, 1999).
manager who will be at risk for the final cost and time of construction. The typical argument
for using CMR is to furnish professional management of all phases of a project’s life to an
owner whose organization may not have those capabilities. CMR contracts can contain
provisions for the CMR to handle some aspects of design, but generally, the owner retains
the traditional responsibility by keeping a separate design contract and furnishing the CMR
with a full set of plans and specifications upon which all construction subcontracts are based.
Typically, CMR contracts contain a provision in which the CMR stipulates a guaranteed
maximum price (GMP) above which the owner is not liable for payment. Constructability
and phasing of construction for faster delivery are the major reasons an owner would select
the CMR method. Unlike DBB, CMR brings the builder into the design process at a stage
DB is a project delivery method in which the owner procures both design and
construction services in the same contract from a single, legal entity referred to as the design-
builder. The method typically uses request for qualifications (RFQ) / request for proposal
(RFP) procedures rather than the DBB invitation for bids procedures. The DB entity is liable
for all design and construction costs and normally, must provide a firm, fixed price in its
proposal (El Wardani et al. 2006, Ibbs et al. 2003, Graham 2001). As in CMR, the builder
has early constructability input to the design process. The design-builder literally controls the
details of the design in this project delivery process. As a result, DB is the delivery method
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 5
which has the greatest ability to compress the project delivery period and as a result is often
The decision for choosing the delivery method is complicated because of the
differences between delivery methods, the unique characteristics of each project, and the
large number of parameters affecting project delivery method selection. The purpose of this
paper, which is based on a TCRP research project titled “A Guidebook for the Evaluation of
Project Delivery Methods,” (TCRP Web-Doc No. 41, 2009) is to portray the state of practice
in delivery method selection and to illustrate the findings of several interviews and case
studies conducted in the framework of this research. It starts with a brief review of decision
making systems and their characteristics. The research methodology and objectives are
explained in the next part and nine projects chosen as case studies are briefly introduced.
Then the findings, lessons learned, and the validation process used are shared with the
readers. Major factors considered by transit decision makers in selecting a delivery method
are identified and a comparison is made between these factors and another set of factors
making process. The decision should be made as early as possible in the design phase,
preferably during the project scoping. The decision will occur when the owner still has little
information about the outcome of the project and the project plans are not detailed enough to
be reliable grounds for judgment about the project. In this environment, having a framework
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 6
for decision-making is vital for the owners. An extensive literature review, conducted mainly
on the U.S. sources, showed that a few decision making frameworks have been developed for
this purpose, but none specifically for publicly funded transportation projects.
different delivery methods (i.e. DB, DBB and CMR) in 351 building projects. These criteria
are mostly objective and measurable, like cost growth, construction speed, and schedule
growth. Some criteria are also defined to incorporate the quality performance of the delivery
methods, like difficulty of facility start up, number and magnitude of call backs, and
operation and maintenance costs. Others such as Debella et al (2006) and Ibbs et al (2003)
have used a methodology similar to Konchar’s, but they have narrowed down the scope of
Gordon (1994) created a procurement method selection model that uses a flowchart
for selecting the best contracting method based on some parameters like time constraints,
preconstruction service needs, risk aversion, and availability of appropriate contractors. Ibbs
et al (2003) have compared the delivery methods based on a number of quantitative factors
like change in project cost or project schedule. Mahdi et al (2005) suggest an Analytical
Hierarchy Process (AHP) for decision making and define a set of factors for that. Cost
savings, time reduction, risk allocation, conflict of interests, and allowance of competitive
bidding are among their defined factors. Oyetunji & Anderson (2006) use a weighted matrix
approach for delivery selection. The approach utilizes a matrix consisting of 20 criteria such
Based on the literature, one can find that regardless of the decision support system
structure, there are some important parameters that affect the decisions early in the project.
Factors such as schedule compression, owner’s control, risk allocation, construction claims,
and cost growth are frequently cited by various papers and reports in the delivery selection
process. The authors of this paper have concentrated on the process of selecting a delivery
method for a transit project and interviewed several transit project directors in order to find
out the state of practice and their mindset. The next part of the paper discusses the research
Based on the results of a comprehensive literature review, the research team identified a set
of pertinent issues believed to have an impact on the choice of project delivery method. Clear
definitions were developed for each of these pertinent issues. This set was then presented to a
interviewees’ responses and discussions, 24 factors were finalized that cover all the aspects
of decision making for a transit project. In order to find the state of practice and collect
rationale for selecting a delivery method. The main objectives of the interviews were to:
• Identify the parameters affecting agencies’ project delivery method selection and to
verify the validity of the pertinent issues identified through literature search;
The team identified and analyzed nine projects from across the spectrum of project
delivery methods with a total worth of more than $3.0 billion. In some cases, the same
agency had used more than one delivery method. The depth and validity of the interviews
were enhanced by permitting the interviewers to gain information that compared and
contrasted the benefits and constraints of several delivery methods from a single source.
Concentration was needed on several aspects of project delivery and the wide
spectrum of factors affecting the delivery selection required extensive face-to-face interview
with the project owners. Because of the budgetary and schedule constraints the number of
developed questionnaire with a handful of owners was chosen as the research methodology.
Each interview was conducted at the site of the transit agency and took three to four hours.
The extensive questionnaire was sent to each interviewee two weeks ahead of the interview
so that they can prepare for the interview and collect the necessary statistics. Although few
cases can sometimes lead to unsubstantiated research conclusions based on the probability of
a typical case selections, it provides a better opportunity to examine each case in detail
without becoming too cumbersome. The sample used here represents the various project
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 9
Furthermore, conducting statistically reliable tests may not be practical for this purpose
because transit projects are usually large, complex, and relatively few in number, and it
would be difficult to collect sufficient data for projects of essentially of the same type to be
The research team used the case study method described by Yin (1994) to furnish a
rigorous methodology for collecting the data from the projects. Yin maintains that planning
the process of accessing and collecting data is essential preparation for efficiently and
select cases that can be compared directly with one another and also offer cross-sectional
diversity. The selected sample fulfills this requirement in that there are five DB projects
from four different agencies and two CMR projects from two different agencies. The
same agency. It was chosen to permit the evaluation of this DBB-hybrid technique. The
direct comparison. Nevertheless, its DB component can be reliably compared with the five
Table 1 is a summary of the case study projects that were studied in this research.
One can see that the projects span from coast to coast.
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 10
Table 1 summarizes the quantitative cost and schedule data and one can see that all
but three of the projects either completed or were on track to finish ahead of schedule. The
Hudson-Bergen project finished just two months late. The delays observed on the two
projects with significant delays were explained as being caused by external factors and not
attributable to the project delivery method. In the same vein, five of the projects experienced
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 11
cost overruns. However, on two projects (T-REX and Weber County), cost growth was
explained by the agency’s decision to add scope to the project when additional funding was
made available after award. Thus, the evaluation of the project delivery method for those two
was validated by the detailed explanation that was obtained via structured interview.
QUANTITATIVE ANALYSIS
The findings and lessons learned from the interviews and case studies are based on the
quantitative comparison of the data collected from the projects interviewed and the responses
of the interviewees to the questions regarding their decisions’ rationale. The quantitative
analysis was done on project schedule and cost performance of each delivery method. The
authors also studied the significance of risk analysis on the outcomes of the projects. The
result of the analysis regarding alternative project delivery’s impact on project schedule is
very definitive for this group of projects. Only one of the DB projects was completed behind
its original schedule. When the two-year delay incurred on the Greenbush Commuter Rail
project mostly due to wetland permits is taken into account, that project was delivered in the
three-year period originally planned. Looking at the DB projects, the five projects either
completed or were on track to finish on average of 5% ahead of schedule. If one takes the
Greenbush project out of the sample, the average is 23% ahead of schedule (Table 2). Thus,
it seems that implementing DB on large transit projects accrues a measurable benefit in terms
of compressing the project delivery period if the agency ensures that critical permitting
actions are cleared before the DB contract is awarded. The CMR projects had a similar result
in being able to compress the project delivery period, but to a more modest degree. This
would be expected in that these projects rely on cooperation between the designer and the
construction manager during the design phase and would typically not have the ability to
overlap design and construction activities to the degree of a DB project where both the
design and the construction are obtained from a single entity. These results are generally
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 12
consistent with the Konchar and Sanvido (1998) finding for project delivery schedule
performance on building projects.
Another quantitative aspect of projects that usually plays an important role in delivery
method selection is project cost growth. Looking at the financial performance of the case
study projects, four of the nine projects finished under or within budget (the Utah and Oregon
projects) (Table 3). Two others, Weber County and T-REX, had cost growth that was
attributable to a conscious decision by the agency to add scope to a project that was going
well. The average cost growth for all the projects in the sample was a +6% with a range of –
6% to +23%. If one drops the two projects where the cost growth was due to scope additions
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 13
(T-REX and Weber County) the average is +3% cost growth. This compares very favorably
to a recent study of transit project cost growth published by the TCRP (Booz.Allen, 2005)
which found average cost growth between the Final Design and Operation phases on 28 US
transit projects completed between 1989 and 2005 to be in the order of +12.2%. It should be
noted that the TCRP study sample population included projects delivered using alternative
Risk management in relation to project delivery methods was investigated in the case
studies. The research team sought to capture each case study project’s process for
identifying, quantifying, and allocating risks. This area was the one with the clearest trend
found in this research. The two case study projects that had either no formal risk analysis
(Greenbush) or partial formal risk analysis (Silverline) were the two projects that suffered
For those that did conduct formal risk analysis, the efforts were focused on schedule
first, followed by project scope and contract risk. Three projects, Utah’s Weber County,
Portland Mall and Portland I-205 Extension, used formal risk analysis on project costs and
invested in Monte Carlo simulation-based analysis of both cost and schedule. One project,
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 15
Hudson-Bergen took the time to develop range cost estimates to supplement their
understanding of cost risk. The Oregon projects utilized the FTA mandated risk analysis
procedures. The most frequently used risk identification technique was brainstorming
followed by scenario planning and expert interviews. Those that conducted formal risk
analysis used risk registers and produced risk management and mitigation plans.
The structured interview technique was particularly well-suited for collecting valuable
information on project delivery method decision rationale. The respondents were very open
and forthright about not only sharing their rationale but also in giving the researchers the
detailed explanation behind it. The first part of this section sought to determine what
experience the interviewees had upon which to base their decision to employ the various
project delivery options. As it turned out, all the respondents (except the Silver Line) had
experience with both DBB and DB. Additionally, the Colorado, Oregon, and Utah agencies
In another part of the interview, the agencies were asked to state their reasons for
selecting a given project delivery method indicating the most important one. They were given
a list of possible reasons to which they could add any other as well. The following drivers
• Encourage innovation
all but one agency for the alternative project delivery case study projects. The Silver Line
project respondent indicated that DBB-Multi-Prime was selected because it was the only
available delivery option at the time the project was formulated. The agency did not have
authority to use DB or CMR. The T-REX project provides an excellent example of this
schedule savings. The Regional Transportation District and the Colorado Department of
Transportation estimated before the project started that DB was saving a number of years
when compared to a DBB schedule and then the DB contractor finished the project
significantly ahead of the contracted schedule for completion. This qualitative finding tracks
directly with the aforementioned quantitative finding regarding schedule compression and an
early study found in the literature (Songer and Molenaar 1996) which reported that schedule
reduction was the major reason owners selected DB. Thus, the agencies are looking to
alternative project delivery to achieve aggressive schedules and are apparently being
“Encourage innovation” was also cited by the majority of the interviewees as being a
reason why they selected the project delivery method for their given project. The literature
generally touts this aspect when discussing alternative project delivery. Follow-up questions
indicated that these agencies believed that they were successful in achieving this goal. The
Utah Transit Authority (UTA) cited a $7 million value engineering change that was adopted
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 17
based on recommendations of the CMR contractor on the Weber County Rail project.
Because the change was made as a part of the CMR’s preconstruction services during the
design phase, UTA accrued 100% of the savings. The fee for preconstruction services on this
project was $550,000. Thus, UTA realized an excellent return on their investment for
selecting a delivery method that encouraged early construction contractor involvement in the
design process. This project also cited the CMR’s innovative involvement in dealing with a
third party stakeholder, the Union Pacific Santa Fe Railroad, as key to the project’s ability to
This connects with the third most popular reason for selecting alternative project
delivery on the case study projects: “Early budget establishment” and “Early contractor
involvement.” Once again the response tracks exactly with the previously cited study by
Songer and Molenaar (1996) which found that “early budget establishment” was the second
most important reason for selecting alternative project delivery. This speaks more toward the
concept of cost certainty rather than cost savings. As was observed in the Weber County Rail
project, the agency utilized the early involvement of the construction contractor through a
CMR contract to not only establish the budget at an earlier point in time than DBB but to also
improve the project’s bottom-line by making real-time cost estimating and constructability
analysis available to the designer at a point in the design process where incorporating
Over half the interviewees also indicated that they selected a given alternative project
delivery method to facilitate “Flexibility needs during the construction phase.” The two Utah
DB projects needed to be completed before the 2002 Winter Olympics, a milestone that
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 18
carried an enormous amount of weight when compared with typical transit project
completion dates. Thus, UTA selected DB as a means to gain maximum flexibility by not
delaying early construction activities for the completion of the entire project’s design. In
fact, this flexibility allowed UTA to complete the two projects nine months ahead of
schedule and under budget. Additionally, TriMet selected CMR for its Portland Mall project
to enhance the contractor’s flexibility to deal with the City of Portland’s requirements for
traffic control during construction by allowing it to make the necessary constructability input
Given the above discussion, it appears that the major reasons for deciding to utilize
alternative project delivery methods are to compress the schedule, to encourage innovation,
to enhance project cost certainty, and to leverage the benefits of early construction contractor
momentum to expedite the design review process by essentially starting the “meter running”
and avoid endless iterations of design review comments by third party stakeholders.
The previous section described the decision drivers as described by project directors in their
factors pertinent to the delivery method selection decision after an extensive literature search.
This set of factors had been incorporated into the interview questionnaire and discussed at
some length with transit project directors during the interviews and asked how each delivery
method could cope in dealing with these factors. By analyzing the responses of the
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 19
interviewees to the questions relevant to their decision making process and combining them
with the literature and research in this field, the authors finalized a set of 24 factors for
project delivery method selection. As an example, a factor related to policy and regulation
(benefits and impacts of PDMs) was eliminated from the original list of pertinent issues
because no one thought that such factor had a large impact on the choice of delivery method..
The research team also found that "size" of the project alone does not affect the choice of
delivery method. So its definition was changed to include the complexity of the project.
Another example was the inclusion of “LEED Certification” and “sustainability” factors.
Most agencies interviewed had not used these concepts in the past but it was felt that these
factors will have to be considered in future projects. Hence, it was decided to keep them in
the set. Some effort was made to select the factors as independent from each other. In other
words, the factors do not overlap to the extent possible. These factors do not have the same
level of importance, yet they were all considered as influential by the interviewees. These
public policy/regulatory issues, 4) life cycle issues, and 5) other issues. Table 4 shows a
Based on the results of this research and other research performed in different sectors
of construction industry (e.g. Konchar and Sanvido 1998), it becomes evident that some
factors are more specific to the transit industry while other factors are important for all
sectors of construction. For example cost, schedule, and risk related issues are some of the
major factors found in almost every project and reported by all studies. However, Federal
Transit Administration (FTA) regulations, or some third party agreements (such as dealing
with local railroads and towns) are challenges specific to transit that an agency faces in a new
project. Another consideration in studying these factors is that the weight of each factor may
change from project to project based on priorities and objectives of the project owner. As an
example, in some projects, on-time project delivery is all important (for example Utah transit
projects before the Olympics). In these cases, the effect of “Schedule” will be much more
profound compared to other factors. Some agencies are more conservative in their approach
and may feel “Agency experience” with a specific delivery method should receive the most
attention. This shows that attempting to rank these factors may not be helpful in many cases.
Evaluating the validity and completeness of the set of 24 factors was a critical part of this
research. The factors were originated from a comprehensive literature review of all sorts of
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 21
reports and papers relevant to the topic. In order to assure the comprehensiveness of the set
of factors, they were checked with the transit agencies. The set “is more likely to be adequate
requisite set, Ginzberg (1978) suggests that interviews should be conducted with the future
users of those factors (i.e. current decision makers) to document their needs and also collect
and analyze the existing information and state of practice. After implementing the comments
and suggestions of the interviewees, the set was presented to the TCRP Project Panel. This
panel consists of industry professionals with vast experience in the subject matter.
Triangulating the results between the interviews (with multiple participants), the literature
(with numerous research studies), and the industry review panel showed that the proposed set
of factors cover all aspects of PDM comparison and that they can be used to build up a
decision support system for the transit industry. The process is described in detail in TCRP
Webdoc 41 (2009).
The authors have recently completed a similar research on airport projects using the
same research methodology and have found that state of practice in that sector is not too
different from transit. While airports considered security, control over operation and flow of
passengers as influential factors specific to airport projects, the majority of pertinent issues
were similar to transit issues. In other words, airport representatives added a number of new
items to the list of pertinent issues and deleted some factors that were specific to transit,
while agreeing with the majority of the items chosen by transit agencies. Interestingly, the
items specific to each sector seem to have less importance in comparison with the core
factors repeated in both research projects. Based on the results of these two research projects,
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 22
the authors believe that the owners of construction projects select a project delivery method
based on a few important and common parameters such as potential for cost savings,
schedule compression, better risk allocation, and facilitated regulations. Other influential
issues such as sustainability or streamlined operation during the construction may not have
the power to decide the selection of delivery method individually, although the collective
effect of some of these less important issues may have an impact on the final decision. So
ignoring the less important factors affecting the delivery method may change the outcome of
the decision process. The difference in the nature of projects, governing rules and
regulations, labor union, and third party issues demand a specialized, well-structured and
CONCLUSION
A suitable project delivery method can facilitate the owner’s achievement of project goals
and objectives. A better understanding of the abilities of each delivery method provides for
rational decision making. This paper introduced some of these abilities based on the trends
found in the case studies. Several structured interviews with transit project owners after a
• The use of alternative delivery methods (DB, DBOM and CMR) seems to be driven
by the transit agency’s need to achieve aggressive delivery schedules for their projects. Their
• Alternative project delivery also appears to have a positive impact on cost certainty.
The average cost growth of the projects in this sample was below the published national
average.
• When formal risk analysis is undertaken on large transit projects, projects appear to
perform well. The projects in this sample that had substantial delays were also the ones that
Transit agencies across the United States select a project delivery method based on
innovation, early budget establishment, and early contractor involvement are among the
issues most commonly cited as deciding factors in this decision by transit agencies. These
same factors happen to be the ones used by airport agencies for the very same purpose, a
similar research for airports shows. Cost savings, schedule reduction, risk allocation, rules
and regulations, and owner’s control over the project are the main reasons why an owner of
transit project chooses an alternative project delivery method instead of traditional DBB. The
final conclusion of this paper is that every project has a different set of requirements, and that
the owner must carefully consider these requirements in the context of the projects’ legal,
environmental, and technical characteristics to decide which project delivery method is the
ACKNOWLEDGEMENT
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 24
This paper is based on the results of a research sponsored by the Transit Cooperative
Research Program under TCRP G-08: A Guidebook for the Evaluation of Project Delivery
Methods. The authors gratefully acknowledge this support. The authors have also benefited
from the generous assistance of several transit agencies who agreed to participate in this
research as interviewees.
REFERENCES
Booz Allen Hamilton Inc. (2005). “Managing Capital Costs of Major Federally Funded
Washington, D.C.
Debella, D.C. Ries ,R. (2006). “Construction Delivery Systems: A Comparative Analysis of
Management, 132(11).
Virginia.
El Wardani, M., Messner, J., Horman, M. (2006). Comparing Procurement Methods for
FHWA (2006). “Guide to Risk Assessment and Allocation for Highway Construction
Ginzberg, M.J. (1978). “Redesign of Managerial Tasks: A Requisite for Successful Decision
Support Systems”, Management Information Systems Quarterly, Vol. 2(1), pp. 39-52.
Ibbs, C.W., Kwak, Y., Odabasi, A. (2003). “Project Delivery System and Project Change: A
129(4). 382-387.
Mahdi, I.M., Alreshaid, K. (2005). “Decision Support System for Selecting the Proper
Mitchell, B.P. (1999). “The Applicability of the Spearin Doctrine: Do Owners Warrant Plans
Oyetunji, A.A, Anderson, S.D., (2006). “Relative Effectiveness of Project Delivery and
132(1), 3-13.
pp.29-48.
Touran, Gransberg, Molenaar, Ghavamifar – Final Accepted Manuscript 26
Songer, A.D., and K.R. Molenaar (1996). “Selecting Design-Build: Public and Private Sector
Walewski, J. Gibson, G., Jasper, J. (2001). “Project Delivery Methods and Contracting
Yin, R. K. (1994). Case Study Research: Design and Methods, Sage Publications.