You are on page 1of 12

Journal of Cleaner Production 203 (2018) 836e847

Contents lists available at ScienceDirect

Journal of Cleaner Production


journal homepage: www.elsevier.com/locate/jclepro

Strategy of indicator incorporation for roadway sustainability


certification
Andrew S. Chang a, Hsiao J. Chang b, Calista Y. Tsai c, *, Shih H. Yang a, Steve T. Muench d
a
Dept. of Civil Engineering, National Cheng Kung Univ., No.1 University Road, Tainan 701, Taiwan
b
Public Works Section, Taiwan Water Corporation, No.1 University Road, Tainan 701, Taiwan
c
Dept. of Hydraulic Engineering, National Cheng Kung Univ., No.1 University Road, Tainan 701, Taiwan
d
Tom and Marilyn Draeger | The Beavers Charitable Trust, Dept. of Civil and Environmental Engineering, University of Washington, 3760 E. Stevens Way NE,
Seattle, WA 98195, USA

a r t i c l e i n f o a b s t r a c t

Article history: Over the last decade, various rating systems and indicators have been proposed for evaluating or
Received 5 February 2018 certifying roadway sustainability. However, there is no systematic method for the roadway projects to
Received in revised form adopt the indicators of the rating systems to enhance sustainability for certification. This study devel-
1 August 2018
oped a strategy for adopting indicators in a roadway rating system for sustainability certification. First,
Accepted 4 August 2018
Available online 25 August 2018
the framework and rules for prioritizing the indicators were established from literature review. Then,
carbon emissions, costs, and the difficulties of employing the indicators were analyzed in a roadway case
study. Finally, the priorities for adopting the indicators were determined. The results revealed that the
Keywords:
Greenroads
indicators with higher scoreeunit ratios should have higher priorities in the project. By using the
Sustainable indicator developed framework, the simultaneous analysis of multiple dimensions enables appropriate investi-
Roadway gation into roadway sustainability problems. The scoreeunit ratio is a simple but effective metric to
Carbon emission evaluate whether a project has incorporated appropriate indicators to enhance sustainability.
Cost © 2018 Elsevier Ltd. All rights reserved.
Scoreeunit ratio

1. Introduction 2015). Organizations such as Greenroads, GreenLITES, and I-LAST


have developed rating systems to evaluate the sustainability of
After being widely used for green buildings in the construction roadways (Raja et al., 2014). These rating systems use performance
industry, sustainable development objectives have been gradually indicators and implementation levels to distinguish between the
applied to transportation infrastructure in recent years (Gonzalo levels of sustainability achieved by infrastructure projects (Gonzalo
and Fernado, 2010; Holton et al., 2010; Farzaneh et al., 2012). The and Fernado, 2010).
transport sector contributed 7 Gt of equivalent carbon dioxide Indicators often used in the roadway rating systems include
(CO2e) that is 14% of total energy-related emissions in the world in runoff, noise, materials, water quality, and aquatic habitat
2010 (IPCC, 2015). As a part of transportation infrastructure, (Eisenman, 2012). For land use, infrastructure, construction, and
Roadways utilize resources, consume energy, and generate carbon innovation design, Oswald and McNeil (2010) developed 37 in-
emissions (Jesús et al., 2013). Thus, reducing the impacts of dicators, such as stormwater management and light disaster
roadway projects on the environment has become an important reduction, for sustainability evaluation. Tsai and Chang (2012)
issue. developed 60 sustainability indicators for roadways and divided
Infrastructure projects' achievement of sustainability objectives them into 14 categories, including reduction in volume, grinding
is commonly assessed using a sustainability rating system with a stones or soft reinforcing, infiltration trenches or catch basins,
set of indicators (Oswald and McNeil, 2010; Veeravigrom et al., growing vegetation, and topsoil recycling.
These indicators are related to the sustainability issues that are
usually encountered during roadway design and construction. The
indicators can be used by project engineers for designing and
* Corresponding author.
constructing sustainable projects. In particular, the indicators are
E-mail addresses: anschang@mail.ncku.edu.tw (A.S. Chang), cecilia791122@
gmail.com (H.J. Chang), calista0523@gmail.com (C.Y. Tsai), shyang@mail.ncku.edu. useful for designers during the design phase because this phase
tw (S.H. Yang), stmuench@uw.edu (S.T. Muench). requires fast information turnaround and decision-making. The

https://doi.org/10.1016/j.jclepro.2018.08.047
0959-6526/© 2018 Elsevier Ltd. All rights reserved.
A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847 837

earlier the environmental dimension is integrated, the greater is criteriadconstruction management plan, noise mitigation control,
the potential of the indicators for reducing environmental impacts equipment and machinery efficiency, quality management, and
(Lame  et al., 2017; Krantz et al., 2017). Setting specific environ- erosion and sedimentation controldwere implemented at the
mental sustainability targets prior to designing allows designers to construction stage. These criteria are indicators that can be incor-
iteratively improve the design to reduce the impact of the con- porated by designers and contractors into their projects.
struction on the environment (Russell-Smith et al., 2015). Indicators can be established at different levels of aggregation
Some rating systems are open for projects to apply for certifi- (Abeelen et al., 2015). The four levels of measurement for sustain-
cation to evaluate their sustainability levels. One of them is ability are industry, organization, project, and process (Caiado et al.,
Greenroads Rating System who issues certification to roadway 2017). Most environmental performance indicators measure envi-
projects applying from USA, Canada, New Zealand, South African, ronmental performance by focusing on the operational-stage fac-
etc. (Pittenger, 2011; Greenroads, 2018). When a project, such as a tors such as material use and energy consumption (McBride et al.,
building or roadway, applies for sustainability certification, various 2011; Shen et al., 2011). The operational level usually means
indicators are incorporated during its design and construction lower of aggregation, and considerable data are required to
phases to earn scores. However, to achieve the scores desired for appropriately identify performance-related problems (Abeelen
the project, additional costs are incurred to meet the indicator re- et al., 2015).
quirements and difficulties may be encountered. A trade-off among Veeravigrom et al. (2015) described sustainability indicators as a
these factors is then required for prioritizing the incorporation of list of best sustainability practices. A key advantage of the indicator
the indicators. Therefore, for a roadway project applying for certi- sets of a rating system is that the diverse measurement units of
fication, a strategy must be implemented to earn higher scores and indicators can all be directly compared using a point-based system.
simultaneously reduce the cost and difficulty of using the The sustainability performance evaluation by using pre-set in-
indicators. dicators is a corporate social responsibility practice that is more
The aim of this study is to propose a strategy framework for frequently used by the companies in Brazil (Cazert et al., 2018).
indicator adoption for roadway projects that are applying for
Greenroads certification. This framework includes rules for
assigning strategy units and three evaluation dimensions, namely 2.2. Carbon emissions of roadways
carbon emissions, cost, and difficulty of using the indicators. The
scores and strategy units of the indicators are assessed using a case Muench (2010) reviewed 14 roadway construction life cycle
study. The scoreeunit ratio is used to determine the priority of assessment (LCA) studies and indicated that the majority of energy
indicators. Finally, indicator priorities for the certification are pro- consumption and emissions occurred during material production.
posed for the roadway project. Construction activities at jobsites accounted for less than 5% of the
total energy consumption and CO2 emissions. Similarly, Wang et al.
(2015) estimated the CO2 emissions generated from a highway
2. Literature review
construction and showed that more than 80% were generated
through raw material production. The onsite construction activities
This study analyzed indicator adoption, which has been
and material transportation only accounted for 10% and 3% of total
addressed by few studies. This section reviews studies related to
CO2 emissions, respectively. CO2 emissions during bridge and
the sustainability rating systems and indicators, the carbon emis-
tunnel construction were considerably higher than those during
sions of roadways, and difficulties in utilizing these indicators. The
subgrade and pavement construction.
Greenroads Rating System is also reviewed. Moreover, the scores of
To analyze the differences in the emissions contributed by
indicators are analyzed prior to the explanation of the indicator
various types of road projects, Mao et al. (2017) examined various
priority and strategy in the Section 4.
urban road construction activities in Shenzhen, China, between
2004 and 2013. The results showed that the carbon footprint
2.1. Sustainability rating systems and indicators generated from the material used for newly constructed roadways
and that for the maintenance activities of the roadways accounted
In addition to the aforementioned Greenroads, GreenLITES, and for 52.3% and 24.3% of the total carbon footprint, respectively. Liu
I-LAST systems, the Infrastructure Voluntary Evaluation Sustain- et al. (2017) applied LCA for 20 asphalt and 18 concrete roadway
ability Tool is a nonmandatory, self-evaluation tool that enables projects. The findings revealed that the average total CO2 emissions
agencies to improve the sustainability of the various phases of a per kilometer per lane were approximately 1250 and 500 tons for
transportation project (Bevan et al., 2015). The Envision Rating asphalt and concrete roadways, respectively. Emissions from off-
System contains sustainability best practices that can be applied to road machinery matched those of materials for the concrete
various types of infrastructure, including transportation infra- roadways. Therefore, in addition to controlling CO2 emissions from
structure (Shivakumar et al., 2014). CEEQUAL is a transportation the materials utilized, construction effectiveness and efficiency
sustainability rating system applicable to all types of infrastructure should be improved because it plays a crucial role in reducing CO2
(VanZerr et al., 2012). emissions.
Sustainability indicators are essentially index representations of Meng et al. (2017) evaluated the environmental sustainability of
sustainability, and they have developed in various industries and the bus rapid transit and normal bus transit systems in Xiamen city,
for different purposes. Yuan (2013) identified 30 key indicators that China. For both systems, higher energy consumption was observed
affect the overall effectiveness of construction and demolition in the material production and vehicle fuel production phases and
waste management. Kamali and Hewage (2017) identified and higher greenhouse gas emissions were observed in material pro-
validated 33 sustainability performance indicators for evaluating duction and vehicle operation phases. The material and energy
modular and conventional construction methods. Rooshdi et al. inputs are the critical factors that decrease roadway sustainability.
(2014) proposed seven sustainable design and construction The carbon emissions during construction stage are small
criteria and assessed their scores for green highways. Two criter- compared to those from material production. In this study, they are
iadcontext sensitive design and alignment selectiondwere calculated from material production, material transportation and
considered at the design stage, and the other five construction activities as explained in Section 3.1.
838 A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847

2.3. Difficulties in achieving sustainable construction this study for analysis (Greenroads, 2018).
Table 1 shows the indicators and points of the Greenroads
Waage (2007) suggested that specifications, cost, time, mate- Rating System Version 1.5 (Muench et al., 2011). The system in-
rials, techniques, market, and designer's preference and experience cludes six categories, namely project requirements (PR), environ-
limit a project's design. Selih (2007) stated 11 potential obstacles in ment and water (EW), access and equity (AE), construction
the construction industry, such as high implementation costs, lack activities (CA), materials and resources (MR), and pavement tech-
of technology and materials, and lack of governmental pressure for nology (PT). Another category, custom credit (CC), is provided for
implementing environmental management. Lam et al. (2009) projects to propose creative sustainable measures for earning extra
stated that cost, time, and techniques are the major design diffi- points. PR indicators should be achieved by every project, and no
culties when realizing a sustainable construction. Holton et al. points are assigned for these indicators. The indicators in other five
(2010) found that barriers in managing sustainable construction categories can be voluntarily pursued and are voluntary credits
in the United Kingdom included the commitment of senior man- (VC).
agement, knowledge and experience of engineers, and communi- As shown in Table 1, the PR category includes the common in-
cation with the British precast concrete companies. Anderson dicators concerning project issues and activity plans such as the
(2012) stated that the factors affecting Greenroads certification environmental review process and quality control plan. The EW
scores are budget, pavement surface layer, urban location, delivery category contains environmental indicators for the project such as
method, and sustainability focus. Lee et al. (2017) claimed that the the environmental management system and runoff flow control.
top-five noneconomic barriers to sustainability are related to the The indicators in the AE category address traffic issues such as
failure of a government to provide reliable information and safety auditing and intelligent transportation systems. The CA
incentives. category contains indicators that can reduce the impacts on the
Chang and Tsai (2015) presented nine difficulties in the reali- environment in the construction stage, such as the quality man-
zation of a sustainable roadway designdfour predesign issues, agement system and site recycling plan. The MR category contains
namely owner, policy and law, natural preconditions, budget and indicators that can reduce the impacts on the environment during
schedule, and insufficient data, and five design problems, namely material manufacturing and transportation, such as pavement
criteria and specifications, lack of experience among engineers, reuse. The PT category indicators can reduce the pollution to the
resources and techniques, constructability and maintainability, and surrounding environment during roadway construction or extend
interface coordination. In general, predesign issues cause more the pavement lifetime. The CC category provides credit for novel
difficulty than design problems. These nine difficulties were sustainability measures without using specific indicators.
adopted in the framework proposed by this study. The six categories comprise a total of 48 indicators. Apart from
the 11 PR indicators, different points are awarded for the indicators
2.4. Greenroads Rating System in each category (Table 1). The points were determined on the basis
of the impact of the indicators on the environment (Muench et al.,
Greenroads is a credit-based sustainability rating system for 2011). The indicators that have a greater impact on the environ-
roadways developed by University of Washington and CH2M Hill ment have more points.
(Pittenger, 2011). It awards points for approved sustainable prac- A total of 108 points are available for the 37 voluntary indicators
tices and can be used to certify roadway projects based on the in the five categories. A project can employ applicable indicators on
achievements of the indicators' requirements and total points the basis of its conditions. Moreover, the extra points of the CCs are
earned (Anderson and Muench, 2013). Although room exists for earned by proposing creative ideas and additional efforts for
improvement in its category and weight assignment similar to improving the sustainability. Based on the total number of points,
other rating systems (Berardi, 2012; Lew et al., 2016; Ismaeel, 2018). one of four certification levels is achieved. As shown in Fig. 1, a
Greenroads is adopted more by the roadway projects and used in project with a score between 32 and 42, or PR þ 30% of the points

Table 1
Greenroads indicators and points.

Project requirement (PR) Environment and water (EW) Pts. Access and equity (AE) Pts.

PR-1 Environmental Review Process EW-1Environmental Management System 2 AE-1 Safety Audit 1e2
PR-2 Lifecycle Cost Analysis EW-2Runoff Flow Control 1e3 AE-2 Intelligent Transportation System (ITS) 2e5
PR-3 Lifecycle Inventory EW-3Runoff Quality 1e3 AE-3 Context Sensitive Solutions 5
PR-4 Quality Control Plan EW-4Stormwater Cost Analysis 1 AE-4 Traffic Emissions Reduction 5
PR-5 Noise Mitigation Plan EW-5Site Vegetation 1e3 AE-5 Pedestrian Access 1e2
PR-6 Waste Management Plan EW-6Habitat Restoration 3 AE-6 Bicycle Access 1e2
PR-7 Pollution Prevention Plan EW-7Ecological Connectivity 1e3 AE-7 Transit & HOV Access 1e5
PR-8 Low Impact Development EW-8Light Pollution 3 AE-8 Scenic Views 1e2
PR-9 Pavement Management System Up to 21 AE-9 Cultural Outreach 1e2
PR-10 Site Maintenance Plan Up to 30
PR-11 Educational Outreach

Construction activities (CA) Pts. Materials and resources (MR) Pts. Pavement technology (PT) Pts.

CA-1 Quality Management System 2 MR-1 Lifecycle Assessment 2 PT-1 Long-Life Pavement 5
CA-2 Environmental Training 1 MR-2 Pavement Reuse 1e5 PT-2 Permeable Pavement 3
CA-3 Site Recycling Plan 1 MR-3 Earthwork Balance 1 PT-3 Warm Mix Asphalt 3
CA-4 Fossil Fuel Reduction 1e2 MR-4 Recycled Materials 1e5 PT-4 Cool Pavement 5
CA-5 Equipment Emission Reduction 1e2 MR-5 Regional Materials 1e5 PT-5 Quiet Pavement 2e3
CA-6 Paving Emission Reduction 1 MR-6 Energy Efficiency 1e5 PT-6 Pavement Performance Tracking 1
CA-7 Water Use Tracking 2 Up to 23 Up to 20
CA-8 Contractor Warranty 3
Up to 14
A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847 839

32–42 scores 43–54 scores 55–63 scores 64+ scores


PR + 30% VC PR + 40% VC PR + 50% VC PR + 60% VC
Fig. 1. Greenroads certification levels.
(Source: Muench et al., 2011).

earned from VC indicators, is granted the certified level. A project GWP when incorporating an indicator into a project. Cost was
with a score higher than 64 obtains the highest evergreen certifi- another evaluation dimension. Knowledge of the cost required for
cation level. individual indicators helps clients decide which indicators should
be incorporated. Difficulty was also included as a dimension,
3. Methods because knowledge of the difficulties of incorporating indicators
enables the project participants to identify the order of preference
In this study, a strategy was developed for adopting Greenroads for indicators.
indicators, and a roadway project was utilized to demonstrate the Greenroads was chosen because the case project was applying
application of the strategy. Moreover, a framework involving three for its certification. This study used the indicators from Version 1.5
dimensionsdcarbon emission, cost, and difficulty of using the because the data from the case project were collected against the
indicatorsdwas established. The framework also incorporated indicators under Version 1.5.
their strategy for assigning rules. The applicable indicators for the A roadway construction project in Taiwan was used as the case
case project were analyzed to assess whether the project adhered study. This roadway has a length of 9513 m and consists of bridges
to the Greenroads indicator requirements for estimating potential (3265 m), embankments, cuttings, and tunnels (175 m) with in-
scores. The carbon emissions, costs, and difficulties of employing terchanges and service roads. The roadway construction involved
the indicators were also calculated. Finally, the indicator priority various types of bridges, tunnels, pavements, landscapes and
was determined on the basis of the derived scoreeunit ratios. ecologies, transportation pathways, geotechnical areas, drainages,
Because emissions, cost, difficulty, and requirements were analyzed soil and water conservation channels, and accessory works.
for the indicators, indicators were the unit of analysis in this study. The carbon emissions, costs, and difficulties for the Greenroads
Here, CO2e was adopted as an evaluation dimension in the indicators were determined for the roadway case. The carbon
framework because it has been used as a metric to represent global emissions were calculated by the research team by using the ma-
warming potential (GWP) in many studies. Although energy effi- terial and equipment data in the bill of quantities (BOQ) and unit
ciency is also critical, various types of energy can be converted into price breakdown tables of the project documents. The carbon
CO2e through characterization factors. The CO2e involved in an emission coefficients were adopted from government publications,
indicator was calculated to represent the GWP. This information relevant studies, and databases.
assists designers and contractors in understanding the effect of The costs and difficulties of employing individual indicators
were obtained mainly by interviewing the project participants,
especially the designers. First, the indicator tables (similar to
Table 2 Table 3) with the last four cost and difficulty column titles were
Strategy units and combinations. provided to designers. These tables were completed by eight design
Strategy unit Combination type engineers who were involved in the project. Then, individual de-
0 0 þ 0
signers were interviewed separately to discuss the requirements of
1 0 þ 1 the indicators, ensure that they were interpreted correctly, and
2 1 þ 1, 2 þ 0 confirm the estimated costs and difficulty levels. The contractor
3 2 þ 1, 3 þ 0 engineers were also interviewed, mainly to clarify the values
4 3 þ 1, 2 þ 2
specified by the designers. The interviewees were involved in the
5 3 þ 2
6 3 þ 3 certification of the project and all had more than 15 years of

Table 3
CO2e, cost, and difficulty of EW indicators.

Indicator Max. point Score CO2e (T) Cost ($1000) Cost per point ($1000) Difficulty reason Level of difficulty

EW-1 2 2 0 68 34 6 2
EW-2 3 1 10,967 10,205 10,205 0
EW-3 3 0 0 0 e 1, 4 2.2
EW-4 1 1 0 1 1 0
EW-5 3 2 9 1,110 555 2, 1 1
EW-6 3 N/A e e e e N/A
EW-7 3 0 0 38 e 4, 6 2.8
EW-8 3 1 215 994 994 1, 5, 3 2.6

Total 21 7 11,191 12,416 1,774 1.5


840 A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847

experience. The quantification methods of the three dimensions are X


described as follows. EH  UF  CF (3)

Where EH: Operation hours of equipment, UF: Unit fuel or energy


consumption of equipment, CF: Carbon emission coefficient of fuel
3.1. Carbon emission or electricity.

The carbon emissions of individual indicators were calculated as 3.2. Cost


follows: carbon emissions ¼ activity data  carbon emission coef-
ficient. The activity includes the materials and equipment that Costs related to the indicators included design, construction,
generate carbon emissions. Activity data for the project were ob- and maintenance costs. Design cost was calculated according to the
tained from the work items in the BOQ and the materials and hours employed by the designers and their fee. The hourly rate of
equipment listed in the unit price breakdown tables of the project. the designers was US$31. The construction cost for the contract
Coefficients from databases such as SimaPro and Gabi are often with a value of US$155 million is displayed in the case project's
adopted by researchers to calculate energy consumption and BOQ. The maintenance cost was estimated on the basis of the
emissions (Gowri, 2004). Because the coefficients were adopted payment records of a roadway agency's maintenance work.
from recognized data sources, the calculated carbon emissions These costs included conventional project costs that are unre-
were recorded as CO2e, which includes the contributions of other lated to sustainability (e.g., preparing design reports and pouring
greenhouse gases. concrete) and the costs related to the sustainability indicators (e.g.,
For a roadway project, carbon emissions are mainly generated the costs of ecological connectivity). Some work items in the BOQ
from material manufacturing, material transportation, and con- were related to both the conventional and sustainability costs (e.g.,
struction activities (Jeong et al., 2017). Therefore, the carbon drainage and the intelligent transportation system). However, some
emissions were calculated from these three sources by using the regular work items in conventional roadway projects are related to
commonly used formulas provided below. The carbon emissions sustainability (e.g., landscape design). These costs provided by the
were not calculated if the materials or equipment were not used interviewees were allocated to applicable indicators for the case
after incorporating the indicators. For example, no carbon emis- study.
sions were incurred for the indicators of the PR2 life cycle cost The indicators were classified into four levels on the basis of the
analysis or CA1 quality management system. cost involved: none (approximately US$0), low (<US$100,000),
medium (US$100,000eUS$300,000), and high (>US$300,000).
(1) Material manufacturing
3.3. Difficulty
This study calculated the carbon emissions of five major
manufacturing materials used in the roadway case project- First, the requirements of the indicators were analyzed to
dcrushed stones for base and sub-base, steel reinforcement, con- identify the difficulties that can be encountered when employing
crete, asphalt concrete, and prestressed steel. These five materials them. Then, related documents provided by the designers and
accounted for 74% of the total carbon emissions of the project contractors were examined, including the design concept, mate-
(Chang, 2015). The calculation formula is as follows: rials, construction plan, and construction equipment. Finally, the
designers and contractors involved with the project were inter-
X
ðWM  CMÞ (1) viewed, and the difficulties of employing the indicators were
classified on the basis of the aforementioned nine difficulties
Where WM: Weights of materials used, CM: Carbon emission co- (Chang and Tsai, 2015). Each indicator was assigned a maximum of
efficient of materials. three difficulties, each with an associated level: low (1), medium
(2), or high (3). A difficulty level of 0 implied that the indicator can
(2) Material transportation be incorporated into the project without difficulty.
An indicator can have multiple difficulties. Weights were
Material transportation includes transportation of materials, assigned if an indicator had two or three difficulties. A weight of 1.0
equipment, personnel, and waste. Because the data for equipment was assigned if an indicator had a single difficulty, whereas weights
and personnel transportation were not available and waste was of 0.8 and 0.2 were applied when two difficulties were involved and
negligible, only material transportation was considered in this weights of 0.5, 0.3, and 0.2 were assigned for three difficulties. In
study. The carbon emissions of material transportation were this study, a maximum of three difficulties per indicator was
calculated according to the weights of materials, transportation assumed to prevent multiple difficulties from obscuring the con-
distance, unit fuel consumption, and vehicle loading capacities. The ditions of the indicator (Chang and Tsai, 2015). The average diffi-
calculation formula is as follows: culty level was calculated on the basis of the assumed weights. For
example, PT3 (Table A4) had three difficulties: budget and schedule
X XWM (reason 3), which was categorized under the high difficulty level;
 TD  UF  CF (2) resources and techniques (reason 7), which was categorized under
LV
the low difficulty level; and lack of experience (reason 6), which
Where WM: Weights of materials, LV: Load capacity of vehicle, was categorized under the medium difficulty level. The average
TD: Two ways of transportation distances, UF: Unit fuel consump- difficulty level of this indicator was 0.5  3 þ 0.3  1 þ 0.2  2 ¼ 2.2.
tion, CF: Carbon emission coefficient of fuels.
4. Results
(3) Construction equipment operations (construction activities)
4.1. Strategy framework and rules for strategy units
The carbon emissions from construction equipment operations
were calculated using the following equation. A three-dimensional strategy framework for incorporating
A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847 841

Cost
Y
High
EW5 (L,H,L)

Medium

EW8 (L,H,H) Low MR3 (M,L,0)


Carbon emission
Low
Low Medium High X
Medium
High
Difficulty Z
Fig. 2. Strategy framework for incorporating indicators.

indicators was established, as shown in Fig. 2. The three dimensions requirements. The score and unit are integrated into the scoreeunit
were carbon emission (X-axis), cost (Y-axis), and difficulty (Z-axis). ratio to determine the feasibility of incorporating the indicator.
Each dimension was divided into three zones of high, medium, and Because higher scores and fewer units are preferred, indicators
low; thus, 27 zones were obtained in total. The indicators were with higher scoreeunit ratios are assigned higher priorities.
categorized into the 27 zones on the basis of their values for carbon
emissions, cost, and difficulty.
4.2. Carbon emissions, costs, and difficulties of the indicators
This indicator categorization facilitates decision-making for the
incorporation of suitable indicators. As shown in Fig. 2, the in-
The indicators and their respective weight points are displayed
dicators located closer to the origin, which represent lower carbon
in Table 1. The carbon emissions, costs, and difficulties of individual
emissions, costs, and difficulty, can be more easily incorporated
indicators were analyzed, calculated, and summarized. The detailed
into a project. Conversely, indicators located far from the origin,
results are shown in Table 3 and described as follows by taking the
representing high barriers to incorporation, should be chosen the
EW indicators as an example. The results for other categories are
latest. If a project is assessed as worthy of receiving certification,
provided in the Appendix A.
the incorporation of the indicators would depend on the project
Table 3 lists the CO2e, cost, and difficulty for incorporating the
budget and difficulty in incorporation.
indicators in the EW category. Maximum points are assigned for
The categorization of low, medium, and high for carbon emis-
individual indicators in Greenroads. The scores were assessed for
sions, cost, and difficulty can be defined according to a project's
the roadway case study on the basis of the degree of adherence to
conditions, that is, the values in the three dimensions. Consider the
the indicator requirements. The level of difficulty indicated the
following case study as an example. For carbon emissions, emis-
average difficulty as described in Section 3.3.
sions of <1,000, 1000e10,000, and >10,000 tons are considered as
As shown in Table 3, the maximum number of points of EW2
low, medium, and high, respectively. Costs of <US$100,000,
was 3. The score of EW2 was estimated to be 1 after assessing the
US$100,000eUS$300,000, and >US$300,000 are considered as low,
design of the runoff flow control and relevant measures in the
medium, and high, respectively. Difficulty values of <1, 1e2, and >2
roadway case, which satisfied the requirements of EW2 only
are considered as low, medium, and high, respectively.
partially. The score of EW3 was 0 because the runoff quality indi-
The rules used to assign strategy units are listed as follows. Units
cator was not pursued by the project. The score of EW6 was
of 0, 1, 2, and 3, respectively, are assigned to zero, low, medium, and
recorded as N/A because the habitat restoration indicator was not
high levels for CO2e, cost, and difficulty. “Unit” is used to avoid the
applicable to the project.
confusion with “point” or “score” for the indicators.
For the eight EW indicators in Table 3, only EW2, 5 and 8
generated CO2e. Other indicators with 0 CO2e were paper work
(1) Zero CO2e, cost, or difficulty: 0 unit
such as EW1 environmental management system and EW4
(2) Low CO2e, cost, or difficulty: 1 unit
stormwater cost analysis that did not generate CO2e.
(3) Medium CO2e, cost, or difficulty: 2 units
The CO2e values in Table 3 have support. For example, CO2e for
(4) High CO2e, cost, or difficulty: 3 units
EW2 runoff flow control was 10,967 T. As presented in Table 4,
factors such as the drainage system involving concrete and steel
Table 2 lists the strategy units and possible combinations for an
reinforcement (10,542 T), material transportation (151 T), and
indicator in two dimensions. For the strategy unit of 0, two of the
equipment operation (274 T) mainly contributed to the CO2e.
three dimensions receive 0 units. For the strategy unit of 1, one
Table 4 was prepared using three tablesdmaterials, material
dimension receives 0 units and the other receives 1 unit. For the
transportation, and equipment operation. Many calculations and
strategy unit of 6, each of the two dimensions receives 3 units.
interim tables were required for preparing the three tables for the
Fewer units implies that the indicator has low carbon emissions,
selected case project that included bridges, roads, pavements, and
incurs low difficulty for incorporation, and thus is preferred.
drainages. The values for the tables were calculated from the
Conversely, indicators with more units are not preferred.
quantities and carbon coefficients by using the formulas presented
Other than the strategy unit, the indicators under assessment
in Section 3.1. Detailed calculations and tables were provided by
earn scores on the basis of the degree to which they meet the
Chang (2015).
842 A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847

Table 4
Carbon emissions of EW2.

CO2 Sources Work

Bridges Road, pave- ment Drainage system Geotech. Road lighting … Total (ton)

1.Materialst
Concrete 140 1,386 3 695 0 0 2,084
245 353 170 5,599 0 0 6,122
280 18,926 1,302 407 0 0 20,635
Steel SD280 5,368 405 2,398 43 55 8,269
SD420 36,529 0 1,443 0 0 37,972
Subtotal 10,542

2.Transportationt
Concrete 898 32 136 0.04 2 1,068
Steel 169 2 15 0.18 0.24 187
Subtotal 151

3.Equipment
Tower crane 345 0 ` 761
Excavators 3,388 1,700 36 10 5,194
Subtotal 274

After the scores and costs were acquired, the cost per point was Table 5
calculated by dividing the total cost by the score of an indicator. For Scoreeunit ratios of indicators.

example, EW1 had a cost per point of US$34,000 (68,000/2). EW2 Indicator Score Dimension Unit Score/unit Priority
had the highest cost per point ($10,205,000) among the eight in- CO2e Cost Difficulty
dicators. The cost per point became an employing criterion for an
EW1 2 0 1 2 3 0.7 2
indicator. The lower is the cost per point for an indicator, the higher
EW2 1 3 3 0 6 0.2 5
is the priority to incorporate the indicator. EW4 1 0 1 0 1 1.0 1
The nine difficulties described by Chang and Tsai (2015) and the EW5 2 1 3 1 5 0.4 5
weight assignment method explained in Section 3 were used to EW8 1 1 3 3 7 0.1 5
determine the difficulty dimension for incorporating indicators. For Subtotal 7 5 11 6 22 0.3 5
example, EW3 (runoff quality) had two difficultiesd“owner, policy, AE1 1 0 1 1 2 0.5 4
and law” and “insufficient data”dthat were marked as 1 and 4, AE2 4 1 3 2 6 0.7 2
respectively, in Table 3. The former was assessed as level 2 and the AE3 5 0 1 0 1 5.0 1
latter was assigned level 3 by the interviewees. Then, the average AE9 2 0 2 2 4 0.5 4
level of difficulty was 0.8  2 þ 0.2  3 ¼ 2.2. EW7 had the highest Subtotal 12 1 7 5 13 0.9 1
level of difficulty (2.8). CA1 2 0 3 2 5 0.4 5
At the bottom in Table 3, the eight EW indicators with a CA2 1 0 1 1 2 0.5 4
maximum of 21 points (from Table 1) were assessed, and the CA3 1 0 2 0 2 0.5 4
project could achieve 7 points. The total CO2e of the EW indicators CA7 2 0 0 1 1 2.0 1
CA8 3 0 0 3 3 1.0 1
was 11,191 T. The cost for satisfying the EW indicators was
US$12,416,000, and the cost per point was US$1,774,000 Subtotal 9 0 6 7 13 0.7 2
(12,416,000/7). The average level of difficulty was 1.5, which was MR1 2 0 1 2 3 0.7 2
categorized as medium difficulty. MR3 1 2 1 0 3 0.3 5
As shown in Fig. 2, EW5, EW8, and MR3 are located in different MR4 2 1 0 3 4 0.5 3
MR5 4 0 3 0 3 1.3 1
zones in the three-dimensional framework. The (X, Y, Z) coordinate
MR6 2 1 2 3 6 0.3 5
of EW5 was (low, high, low) due to the CO2e of 9 T, cost of
Subtotal 11 4 7 8 19 0.6 4
US$1,110,000, and difficulty level of 1 (Table 3). That of EW8 was
(low, high, high) due to the CO2e of 215 T, cost of US$994,000, and PT1 5 3 3 2 8 0.6 2
difficulty level of 2.6. MR3 was located closer to zero than EW5 and PT3 3 0 2 2 4 0.8 2

EW8 and thus should be incorporated into the design earlier than Subtotal 8 3 5 4 12 0.7 3
EW5 and EW8. The three-dimensional analysis is explained in Total 47 13 36 30 79 0.6
Appendix B.

implying that the score (1) earned is not worth the cost (3) and
4.3. Scoreeunit ratios and priority of indicators
difficulty (3) with low CO2e (1).
The priority of indicator incorporation for the certification is
Table 5 lists the scoreeunit ratios of the indicators considered in
shown in Table 6. As seen in Table 6, five priorities were offered for
the roadway case study. For example, after the assessment, EW1
the roadway case study. The five sets of indicators were determined
earned a score of 2 and received 3 units (0 þ 1 þ 2 ¼ 3). The
according to their scoreeunit ratios and marked with priority
scoreeunit ratio in Table 5 represents the assessed score and unit
numbers in Table 5. The first priority included five indica-
calculated on the basis of the CO2e, cost, and difficulty. AE3 (context
torsdEW4, AE3, CA7, CA8, and MR5dwith scoreeunit ratios of
sensitive solutions) had the highest scoreeunit ratio (5), implying
1.0, as shown in Table 5. They could yield a total score of 15
that the 5 points of this indicator could be earned with the least
(1 þ 5 þ 2 þ 3 þ 4). However, this score was insufficient for the
effort [low cost (1) and no difficulty (0)] and without CO2e (0).
certification level, which requires 32 points, as indicated in Fig. 1. In
Conversely, EW8 (light pollution) had the lowest ratio (1/7 ¼ 0.1),
A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847 843

Table 6
Priority of indicator incorporation for certification.

Priority Indicator Score Certification level

Total Accumulated

1st EW4,AE3,CA7, CA8, MR5 15 15 Not certified


2nd EW1, AE2,MR1, PT1, PT2 16 31 Not certified
3rd MR4 2 33 Certified
4th AE1,AE9, CA2,CA3 5 38 Certified
5th EW2, EW5, EW8, CA1, MR3, MR6 9 47 Silver

the second priority level, the five indicators contributed an addi- through a ranking method. The CO2e dimension is intended to
tional 16 points (2 þ 4 þ 2 þ 5 þ 13), thus increasing the score to 31. provide benefits by reducing emissions; thus, the costebenefit
However, an additional 1 point was required to reach the certified analysis is also implied in this study. Therefore, the developed
level. strategy framework is an operational tool for decision-making and
In the third priority level, MR4 (recycled materials) was selected is similar to the decision-analytical framework that can be easily
because it contributed 2 points and the cost was 0 in the case implemented for sustainable manufacturing (Stoycheva et al.,
study. Therefore, the total score was 33, and the project could 2018).
receive the first level of certification. For higher levels of certifica- Castro-Lacouture et al. (2009) mentioned that a standard
tion, the fourth and fifth priorities could be employed to increase method to select alternatives that can achieve environmental ob-
the score by 5 and 9 points, respectively, to a total of 47. Because jectives and adhere to budget and design limitations has not been
this score is higher than 43, the project could receive the silver developed. Virtanen et al. (2013) indicated that sustainability
certification. research is required to develop pragmatic tools to integrate sus-
The indicator incorporation can be determined on the basis of tainability targets with performance management. Moreover,
the project owner's target certification level. If the target level is Trianni et al. (2014) stated that researchers should explore deci-
only to obtain a certification, then the case project should incor- sion-makers’ needs and identify how different actors' involvement
porate the indicators up to the third priority, as presented in can be improved. Lew et al. (2016) recommended that the process
Table 6. If a silver certification is desired, then all the indicators of incorporating sustainability into practice by the industry should
listed in Table 6 should be adopted for the roadway case study. If the be investigated. Stoycheva et al. (2018) stated that the tradeoffs
target is higher, additional indicators that were not considered in between sustainability dimensions have rarely been examined in a
the case study's design must be adopted, such as EW6, AE4e7, sustainability framework. This study responds to these statements
CA4e6, MR2, PT2, and PT4e6. by providing the following: 1) a sustainability strategy framework
In summary, Section 4.1 presents the strategy framework and to facilitate the selection of alternatives based on the budget, 2) a
rules for the strategy units. Section 4.2 presents the calculated the pragmatic tool for integration and performance management, 3) a
carbon emissions, costs, and difficulties of incorporating the in- method to help project owners to get involved in the roadway
dicators (Table 3). Section 4.3 presents the calculated scoreeunit sustainability development process, 4) a guidance method to
ratios of the indicators (Table 5), and lists the priority sequence enable designers and contractors to incorporate sustainability into
for incorporating certain indicators into the project (Table 6). their projects, and 5) strategy units to evaluate the tradeoffs among
Tables 3, 5 and 6 are crucial when using this framework. By the CO2e, cost, and difficulty of employing the indicators.
following the steps listed in Section 4, a project can establish its The use of CO2e, cost, and difficulty in the current study is
own tables and evaluate its strategy by selecting appropriate in- supported by other studies. For example, Gscho € sser and Wallbaum
dicators for certification. (2013) and Liu et al. (2015) have stated that the most commonly
used multiobjective parameters are costs, such as construction and
5. Discussions life cycle costs, and environmental impact factors, such as carbon
footprint. Flintsh and Bryce (2014) considered level of achievement
This study analyzed indicator adoption for roadway sustain- as a third parameter to identify performance. The level of
ability certification, which has received scant attention. In partic- achievement can be partially determined by the “difficulty” of
ular, the developed framework includes unique details, such as the incorporating an indicator. Jeong et al. (2017) evaluated the CO2
scoreeunit ratio in Table 5. Related studies that have investigated emissions, cost, and productivity of building columns. Productivity
green construction, decision-making methods or tools, and is also relevant factor for difficulty because productivity will be
assessment criteria support the findings of the current study. The high if the difficulty level is low.
clarifications and extensions provided by the current study are Some issues have been clarified in the research process. The
discussed in the second half of this section. CO2e, cost, and difficulty of incorporating indicators and the
Decision-making methods for green construction include mul- derived adoption priority were determined on the basis of data
tiobjective optimization, ranking methods, index-based methods, obtained from a roadway project in Taiwan. Carbon emission co-
and costebenefit analysis (Martin et al., 2007). Among these, the efficients differ slightly between countries, and costs and diffi-
multiobjective or multicriteria method is the most suitable tool for culties also vary between projects. However, these are minor
the decision-making (Walker, 2010; Flintsh and Bryce, 2014; Sierra problems that do not affect the function of the established
et al., 2018). Criteria methods were identified as a suitable approach framework.
to overcoming the obstacles when integrating environmental Although the weights were the same for the three dimensions in
analysis into decision-making (Lame  et al., 2017). The selection of this study, they could differ. Conventional projects would empha-
the indicators on the basis of a trade-off among CO2e, cost, and size cost over the other two dimensions. However, each roadway
difficulty in this study is similar to the selection in multiobjective project has unique characteristics and considerations. Some pro-
optimization. The indicator-incorporation priority was obtained jects may emphasize the environment over cost and difficulty.
844 A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847

Therefore, assigning weights to the three dimensions by consid- priorities. This simple quantitative ratio is a powerful metric that
ering the actual conditions of individual projects can be considered can be used to evaluate whether a project has incorporated
in future research. appropriate sustainable indicators. Furthermore, the proposed
Realization of sustainable projects is often limited by budget, strategy framework supplements prior research in indicator
manpower, and difficulty. The incorporation of Greenroads in- employment methods for roadway designing and construction.
dicators into the case project presented similar problems. Hence, Sustainability is an emerging factor in the construction industry.
some indicators were not considered in the case study. The strategy Many engineers aim toward this goal but lack suitable methods or
framework can be used systematically to incorporate appropriate tools. The strategy framework developed in this study is a tool to
indicators into roadway projects. After more data are collected by examine sustainability and arrange the indicators related to the
using the framework, barriers will become clear and benchmarks design and construction work on the basis of their priorities.
can be identified with which designers can compare their projects Tables 3, 5 and 6 are crucial when using this framework. By
(Lew et al., 2016; Lame  et al., 2017). following the steps in Section 4, a project can prepare its own tables
Finally, the strategy framework can be further used to compare and evaluate its strategy in by selecting appropriate indicators for
sustainability among various disciplines and projects. As presented obtaining the certification.
in Table 5, the scoreeunit ratios of various categories can be Carbon emissions have been researched and calculated in
compared to determine the category that should be considered numerous studies in recent years. However, such calculations are
first. For example, AE had a subtotal ratio of 0.9, the highest among not ends in themselves. The calculation results should be used in
the five categories. Hence, AE indicators were selected under the other applications that warrant further research. In this study, the
first priority level, as stated in Section 4.3. A project team that ex- calculated CO2e was integrated with the cost and difficulty of
cels in certain disciplines could target related indicators to earn incorporating an indicator. Multiple dimensions can be analyzed
higher scores. Furthermore, the total score, unit, and scoreeunit together to better understand the sustainability challenges faced by
ratio of the case study were 47, 79, and 0.6, respectively. These engineering projects.
values can be compared with those of other projects to identify the When clients are approached for building a sustainable project,
projects with high chances of receiving certification. they often ask questions concerning the related cost, difficulty, and
effects. Cost refers to the cost of incorporating the indicators, and
6. Conclusions difficulty reflects experiences using the indicators. Moreover, the
effects can involve carbon emissions caused by the infrastructure
This study developed a strategy framework for indicator adop- and its use. These three questions can be answered individually or
tion in roadway projects for obtaining the Greenroads Rating Sys- together by using the values presented in the proposed framework
tem certification. The carbon emissions, costs, and difficulties of and tables.
employing the indicators were categorized into three levels and
converted into strategy units. Because the certification is awarded Appendix A. CO2e, Cost, and Difficulty of Indicators in Other
on the basis of the scores, the indicator requirements were Four Categories
analyzed to assess the scores earned for the case project. The scores
and units were combined to form scoreeunit ratios. The indicators
with higher scoreeunit ratios were assigned higher incorporation

Table A1
CO2e, cost, and difficulty of AE indicators

Indicator Point Score CO2e (T) Cost ($1000) Cost per point ($1000) Difficulty reason Level of difficulty

AE-1 2 1 0 5 5 6 1
AE-2 5 4 221 1,710 428 1 2
AE-3 5 5 0 51 10 0
AE-4 5 N/A e e e N/A
AE-5 2 N/A e e e N/A
AE-6 2 N/A e e e N/A
AE-7 5 N/A e e e N/A
AE-8 2 0 0 0 e 2 3
AE-9 2 2 0 248 124 1、3 1.8

Total 30 12 221 2,014 168 1.6

Table A2
CO2e, cost and difficulty of CA indicators

Indicator Point Score CO2e (T) Cost ($1000) Cost per point (US$1000) Difficulty reason Level of difficulty

CA-1 2 2 0 544 272 6 2


CA-2 1 1 0 14 14 7 1
CA-3 1 1 0 244 244 0
CA-4 2 N/A e e e N/A
CA-5 2 N/A e e e N/A
CA-6 1 N/A e e e N/A
CA-7 2 2 0 0 0 6 1
CA-8 3 3 0 0 0 3 3

Total 14 9 0 802 89 1.4


A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847 845

Table A3
CO2e, cost and difficulty of MR indicators

Indicator Point Score CO2e (T) Cost ($1000) Cost per point ($1000) Difficulty reason Level of difficulty

MR-1 2 2 0 35 18 4、6 1.8


MR-2 5 N/A e e e N/A
MR-3 1 1 4,630 41 41 0
MR-4 5 2 822 544 272 1、5 2.8
MR-5 5 4 120,301 61,631 15,408 0
MR-6 5 2 37 192 96 1、3、7 2.5
Total 23 11 125,790 61,355 5,578 1.4

Table A4
CO2e, cost, and difficulty of PT indicators

Indicator Point Score CO2e (T) Cost ($1000) Cost per point ($1000) Difficulty reason Level of difficulty

PT-1 5 5 9,824 561 112 1 2


PT-2 3 N/A e e e N/A
PT-3 3 3 230 197 66 3、7、6 2.2
PT-4 5 N/A e e e N/A
PT-5 3 N/A e e e N/A
PT-6 1 N/A e e e N/A
Total 20 8 9,594 758 95 2.0

Appendix B. Three-Dimensional Analysis impact to the environment. MR5 (regional materials) was placed
here because it reduced CO2e due to material transportation. The
The priority for incorporating indicators was evaluated using a zone of zero carbon emissions and low cost included six indicators.
three-dimensional analysis. However, two dimensions can be used Therefore, several indicators, such as EW1 (environmental man-
to approximate the idea of the priority. Table B1 lists the indicators agement system), incurred low cost. For the zone of low carbon
in the carbon and cost dimensions in the EW, AE, CA, MR, and PT emissions and zero cost, incorporating a “cheaper” indicator, such
categories. Sixteen zones exist for the zero, low, medium, and high as MR4 (recycled materials), could reduce the cost. For the zone of
levels. For carbon emissions and costs, the integral numbers such as high carbon emissions and high cost, EW2 (runoff flow control) and
PT1 (long-life pavement), should be assigned the lowest priority.

Table B1
Carbon emissions and costs of indicators in two dimensions

Cost CO2e

Zero (approximately zero or CO2e reduced) Low ˂1,000T Medium 1,000T High S10,000T
e10,000T

Zero (almost zero or cost reduced) CA7 Water use tracking MR4 Recycled materials (cost reduced)
CA8 Contractor warranty
Low ˂ $100,000 EW1 Environmental management system MR3 Earthwork balance
EW4Stormwatercost analysis
AE1Safetyaudit
AE3 Context sensitive solutions
CA2 Environmental training
MR1Lifecycle assessment
Medium AE9 Cultural outreach MR6 Energy efficiency
$100,000~$300,000 CA3Site recycling plan
PT3Warm mix asphalt (CO2e reduced)
High S$300,000 CA1 Quality management system EW5 Site vegetation EW2 Runoff flow control
MR5 Regional materials (CO2e reduced) EW8 Light pollution PT1Long-life pavement
AE2 Intelligent transportation
system

1,000T and $100,000 were used to divide the ranges because the The strategy units of indicators and the indicator-incorporation
values calculated from the case project data distinguished the in- priority are explained by taking EW1 as an example. According to
dicators well into the zones. Zero was also used because many in- Table 3, EW1 generated a CO2e of 0 T, costed US$68,000, and had a
dicators such as CA7 water use tracking did not generate emissions difficulty level of 2; thus, it was classified into the (zero, low, me-
or incur expenditure. The ranges can be determined based on the dium) zone according to the definitions in Section 4.1. On the basis
conditions of a roadway project. of the prior rules, the strategy units for the CO2e, cost, and difficulty
In Table B1, the zone of zero carbon emissions included 13 out of of EW1 are 0, 1, and 2, respectively. Then, in the X (CO2e)eY (cost)
the 21 applicable indicators for the case project. Therefore, many of dimensions, as shown in Table B1, the combination type for EW1
the indicators, such as CA7 (water use tracking), would cause no was 0 þ 1 ¼ 1 unit. Thus, EW1 belongs to the second priority
846 A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847

category, as shown in Table 2. Kamali, M., Hewage, K., 2017. Development of performance criteria for sustain-
ability evaluation of modular versus conventional construction methods.
The other two dimensions indicated the following results. In the
J. Clean. Prod. 142, 3592e3606.
Y (cost)eZ (difficulty) dimensions, the combination type of EW1 Krantz, J., Lu, W., Johansson, T., Olofsson, T., 2017. Analysis of alternative road
was 1 þ 2 ¼ 3 units. In the X (CO2e)eZ (difficulty) dimensions, the construction staging approaches to reduce carbon dioxide emissions. J. Clean.
combination type was 0 þ 2 ¼ 2 units. The combination type can be Prod. 143, 980e988.
Lam, P.T.I., Chan, E.H.W., Chau, C.K., Poon, C.S., Chun, K.P., 2009. Integrating green
analyzed according to the XeY, YeZ, or XeZ dimensions as per the specifications in construction and overcoming barriers in their Use. J. Prof. Is-
requirements. If only the budget and difficulty for the project are sues Eng. Educ. Pract. 135 (4), 142e152.
Lame , G., Leroy, Y., Yannou, B., 2017. Ecodesign tools in the construction sector:
considered, the results from the YeZ dimensions can be referred to
analyzing usage inadequacies with designers' needs. J. Clean. Prod. 148, 60e72.
for incorporating appropriate indicators. Lee, C.T., Hashim, H., Ho, C.S., Fan, Y.W., 2017. Sustaining the low-carbon emission
Three-dimensional strategy analysis provides a method to development in Asia and beyond: sustainable energy, water, transportation and
consider CO2e, cost, and difficulty concurrently for the indicators. low-carbon emission technology. J. Clean. Prod. 146, 1e13.
Lew, J.B., Anderson, J.L., Muench, S.T., 2016. Informing roadway sustainability
However, the strategy excludes the PR indicators, the indicators practices by using a Greenroads certified project data. J. Transport. Res. Board
marked as N/A (e.g., EW6 in Table 3) and the indicators with a score 2589, 1e13.
of 0 (e.g., EW3 and EW7 in Table 3). Liu, R., Smartz, B.W., Descheneaux, B., 2015. LCCA and environmental LCA for
highway pavement selection in Colorado. Int. J. Sustain. Eng. 8 (2), 102e110.
Liu, Y., Wang, Y., Li, D., 2017. Estimation and uncertainty analysis on carbon dioxide
References emissions from construction phase of real highway projects in China. J. Clean.
Prod. 144, 337e346.
Abeelen, C., Harmsen, R., Worrell, E., 2015. Counting project savings-an alternative Mao, R., Duan, H., Dong, D., Zuo, J., Song, Q., Liu, G., Hu, M., Zhu, J., Dong, B., 2017.
way to monitor the results of a voluntary agreement on industrial energy Quantification of carbon footprint of urban roads via life cycle assessment: case
saving. Energy Effic. 9 (3), 755e770. study of a megacity-Shenzhen, China. J. Clean. Prod. 166, 40e48.
Anderson, J.L., 2012. Measuring sustainability in Civil engineering: development, Martin, C., Ruperd, Y., Legret, M., 2007. Urban stormwater drainage management:
testing and implementation of the Greenroads™ rating system. PhD thesis. In: the development of multi-criteria decision aid approach for best management
Civil and Environmental Engineering Department. University of Washington. practices. Eur. J. Oper. Res. 181, 338e349.
Anderson, J.L., Muench, S.T., 2013. Sustainability trends measured by the Green- McBride, A.C., Dale, V.H., Baskaran, L.M., Downing, M.E., Eaton, L.M.,
roads rating system. J. Transport. Res. Board 2357, 24e32. Efroymson, R.A., Garten Jr., C.T., Kline, K.L., Jager, H.I., Mulholland, P.J.,
Berardi, U., 2012. Sustainability assessment in the construction sector: rating sys- Parish, E.S., Schweizer, P.E., Storey, J.M., 2011. Indicators to support environ-
tems and rated buildings. Sustain. Dev. 20, 411e424. mental sustainability of bioenergy system. Ecol. Indicat. 11, 1277e1289.
Bevan, T., Reid, L., Davis, A., Neuman, T., Penney, K., Seskin, S., VanZerr, M., Meng, F., Liu, G., Yang, Z., Casazza, M., Cui, S., Ulgiati, S., 2017. Energy efficiency of
Anderson, J., Muench, S., Weiland, C., Ramani, T., Zietsman, J., Crossett, J., urban transportation system in Xiamen, China. An integrated approach. Appl.
Crocker, C., Schulz, J., 2015. INVEST Economic, Social, Environmental Sustainable Energy 186, 234e248.
Highways Self-evaluation Tool v1.2. Federal Highway Administration (FHWA). Muench, S.T., 2010. Roadway construction sustainability impacts: review of life-
http://www.sustainablehighways.org/. cycle assessments. J. Transport. Res. Board 2151, 36e45.
Caiado, R.G.G., Dias, R. d. F., Mattos, L.V., Quelhas, O.L.G., Filho, W.L., 2017. Towards Muench, S.T., Anderson, J.L., Hatfield, J.P., Koester, J.R., Soderlund, M., 2011. In:
sustainable development through the perspective of eco-efficiency- A system- Anderson, J.L., Weiland, C.D., Muench, S.T. (Eds.), Greenroads manual v1.5.
atic literature review. J. Clean. Prod. 165, 890e904. University of Washington, Seattle, WA.
Castro-Lacouture, D., Sefair, A., Florez, L., Medaglia, L., 2009. Optimization model for Oswald, M.R., McNeil, S., 2010. Rating sustainability: transportation investments in
the selection of material using a LEED-based green building rating system in urban corridors as a case study. J. Urban Plann. Dev. 136, 177e185.
Colombia. J. Build. Environ. 44 (6), 1162e1170. Pittenger, D.M., 2011. Evaluating sustainability of selected airport pavement treat-
Cazert, G.T., Anholon, R., Silva, D. d., Ordonez, R.E.C., Quelhas, O.L.G., Filho, W.L., ments with life-cycle cost, raw material consumption, and Greenroads stan-
Santo-Eulalia, L. A. d., 2018. An assessment of the integration between corporate dards. J. Transport. Res. Board 2206, 61e68.
social responsibility practices and management systems in Brazil aiming at Raja, R.R.M.R., Nurizan, A.R., Nazurah, Z.U.B., MuhdZaimi, M., Faridah, I., 2014. An
sustainability in enterprises. J. Clean. Prod. 182, 746e754. evaluation of sustainable design and construction criteria for green highway. In:
Chang, A.S., Tsai, C.Y., 2015. Difficulty and reasons for sustainable roadway design- 4th International Conference on Sustainable Future for Human Security, Sustain
the case from Taiwan. J. Civ. Eng. Manag. 21 (3), 395e406. 2013, Procedia Environmental Sciences, vol. 20, pp. 180e186.
Chang, H.J., 2015. Roadway project CO2 emissions analysis and green strategies for Rooshdi, R.R.R.M., Rahman, N.A., Baki, N.Z.U., Majid, M.Z.A.M., Ismail, F., 2014. An
Greenroads indicators. Master thesis. In: Civil Engineering Department. Na- evaluation of sustainable design and construction criteria for green highway.
tional Cheng Kung University, Tainan, Taiwan (Chinese). Procedia Environ. Sci. 20, 180e186.
Eisenman, A.P.A., 2012. Sustainable streets and highways: an analysis of green roads Russell-Smith, S.V., Lepech, M.D., Fruchter, R., Meyer, Y.B., 2015. Sustainable target
rating systems. Master thesis. In: Civil Engineering. University of Georgia value design: integrating life cycle assessment and target value design to
Institute of Technology. improve building energy and environmental performance. J. Clean. Prod. 88,
Farzaneh, R., Ramani, T., Krishnan, A., Zietsman, J., 2012. Performance Measures for 43e51.
Sustainable Freight Movement. University Transportation Centre for Mobility Selih, J., 2007. Environmental management systems and construction SMES: a case
and Department of Transportation Research and Innovative Technology study for Slovenia. J. Civ. Eng. Manag. 13 (3), 217e226.
Administration. UTCM 09-37-15. Shen, L., Wu, Y., Zhang, X., 2011. Key assessment indicators for the sustainability of
Flintsh, G., Bryce, J., 2014. Sustainable pavement management. In: infrastructure projects. J. Construct. Eng. Manag. ASCE 137 (6), 441e451.
Gopalakrishnan, K., Steyn, W.J., Harvey, J. (Eds.), Climate Change, Energy, Sus- Shivakumar, S., Pedersen, T., Wilkins, S., Schuster, S., 2014. EnvisionTM e a measure
tainability and Pavements. Springer, New York. of infrastructure sustainability. Pipelines 2249e2256.
Gonzalo, F., Fernado, R., 2010. A methodology to identify sustainability indicators in Sierra, L.A., Yepes, V., Pellicer, E., 2018. A review of multi-criteria assessment of the
construction project management-Application to infrastructure projects in social sustainability of infrastructures. J. Clean. Prod. 187, 496e513.
Spain. J. Ecol. Indicat. 10 (6), 1193e1201. Stoycheva, S., Marchese, D., Paul, C., Padoan, S., Juhmani, A., Linkov, I., 2018. Multi-
Gowri, K., 2004. Green building rating systems: an overview. ASHRAE J. 46 (11), criteria decision analysis framework for sustainable manufacturing in auto-
56e60. motive industry. J. Clean. Prod. 187, 257e272.
Greenroads, 2018. https://www.greenroads.org/ratingsystem, assessed on July 30, Trianni, A., Cagno, E., De Donatis, A., 2014. A framework to characterize energy
2018. efficiency measures. Appl. Energy 118, 207e220.
Gscho€sser, F., Wallbaum, H., 2013. Life cycle assessment of representative Swiss Tsai, C.Y., Chang, A.S., 2012. Framework for developing construction sustainability
road pavements for national roads with and accompanying life cycle cost items: the example of highway design. J. Clean. Prod. 20, 127e136.
analysis. Environ. Sci. Technol. 47, 8453e8461. VanZerr, M., Connolly, S., Sowerby, C., Harmer, C., Folkeson, L., Gudmundsson, H., de
Holton, I., Glass, J., Price, A.D.F., 2010. Managing for sustainability: findings from Vos-Effting, S., Leegwater, G., 2012. Best Practices in Sustainability Rating Sys-
four company case studies in the UK precast concrete industry. J. Clean. Prod. 18, tems. SUNRA, Deliverable D3.1, Road ERA Net.
152e160. Veeravigrom, M., Muench, S.T., Kosonen, H., 2015. Global framework for sustainable
Intergovernmental Panel on Climate Change, 2015. Climate Change 2014: Mitiga- roadway rating systems. In: Presented at the 94th Annual Meeting of the
tion of Climate Change, vol. 3. Cambridge University Press. Transportation Research Board, 11e15 January 2015, Washington, D.C.
Ismaeel, W.S.E., 2018. Midpoint and endpoint impact categories in Green building Virtanen, T., Tuomaala, M., Pentti, E., 2013. Energy efficiency complexities: a tech-
rating systems. J. Clean. Prod. 182, 783e793. nical and managerial investigation. Manag. Account. Res. 24, 401e416.
Jeong, J., Hong, T., Ji, C., Kim, J., Lee, M., Jeong, K., Lee, S., 2017. An integrated eval- Waage, S.A., 2007. Re-considering product design: a practical road-map for inte-
uation of productivity, cost, and CO2 emission between prefabricated and gration of sustainability issues. J. Clean. Prod. 15, 638e649.
conventional columns. J. Clean. Prod. 142, 2393e2406. Walker, G., 2010. Environmental justice, impact assessment and politics of knowl-

Jesús, M.B., Gonzalo, F.S., Alvaro, B., Juan, A.D., Francisco, J.A., 2013. Applying life edge: the implications of assessing the social distribution of environmental
cycle thinking to reduce greenhouse gas emissions from road projects. J. Clean. outcomes. Environ. Impact Assess. Rev. 30, 312e318.
Prod. 57, 79e91. Wang, X., Duan, Z., Wu, L., Yang, D., 2015. Estimation of carbon dioxide emission in
A.S. Chang et al. / Journal of Cleaner Production 203 (2018) 836e847 847

highway construction: a case study in southwest region of China. J. Clean. Prod. Calista Y. Tsai is an assistant professor at Dept. of Hydraulic Engineering, National
103, 705e714. Cheng Kung Univ. in Taiwan. She got her PhD from Civil Engineering Department of
Yuan, H., 2013. Key indicators for assessing the effectiveness of waste management National Cheng Kung University. She has 15 years of construction management and
in construction projects. Ecol. Indicat. 24, 476e484. project scheduling experience. Her current research focuses on infrastructure sus-
tainability evaluation.

Andrew S. Chang is a professor of Civil Engineering Department of National Cheng


Kung University in Taiwan. He got his PhD degree from the University of California at Shih H. Yang is an assistant professor of Civil Engineering Department of National
Berkeley and used to work in the construction industry for 10 years. His current Cheng Kung University in Taiwan. He got his PhD degree from University of Illinois at
research is in sustainable design and management. Urbana Champaign. He has extensive experience in roadway engineering, pavement
materials, and infrastructure management.

Hsiao J. Chang is an Engineer of Taiwan Water Corporation. She got the Master degree
from Civil Engineering Department of National Cheng Kung University in Taiwan. Her Steve T. Muench is an associate professor of University of Washington in the USA.
thesis analyzed roadway project CO2 emissions and green strategies. Since 2011, Dr. Muench has been the holder of the Tom and Marilyn Draeger | The
Beavers Charitable Trust professorship. He has research interest in transportation
infrastructure. Current sustainability efforts include Greenroads, a sustainability rating
system for roadway design and construction.

You might also like